9               FUTURE KEY ISSUEs

Key Issues in the Coming Month

 

9.1         Major site activities for the coming reporting month will include:

WA4

¡P             Operation of Asphalt Plant

 

Ancillary and Associated Facilities

¡P             Breaking off the concrete footings for reinstatement of slope underneath the deck

¡P             Reinstatement of sloping seawall

¡P             Installation of precast parapet facial panel

¡P             Construction of median and side barriers

¡P             Construction of longitudinal stitching

¡P             Sealing of deck openings and preparation deck surface for waterproofing

¡P             Installation of fire hydrants and fire main

¡P             Installation of utility trough covers

¡P             Erection of sign gantry

¡P             Installation of the additional pier number and information signs

¡P             Installation of the headroom sign and vessel length restriction sign

¡P             Installation of the height restriction sign

¡P             Site clearance / formation work to reinstatement of SPR

¡P             Construction of concrete carriageway for Chek Lap Kok South Road realignment*

¡P             Installation of carrier drains

¡P             Installation of watermain

¡P             Laying of asphalt pavement

¡P             Fill slope and road works for Chek Lap Kok South Road realignment*

 

Note:

*Minor Modification Works:-

¡PShifting the bus stop location;

¡PShifting the old alignment near P109 southward; and

¡PRe-instating the underground drainage with the new alignment due to the minor modification works above.

 

E&M Works

¡P             E&M ducting installation

¡P             E&M works inside SHT building

¡P             Street light cables and poles installation

¡P             Cable hanger installation

¡P             LV and HV cable laying works

¡P             Cable tray installation of SMS system

¡P             Cable laying works for HKPF

¡P             GPS pole installation

¡P             Installation of electrical sliding barrier

¡P             Installation of pile cap lighting

¡P             Installation of radar at radar platform

 

Removal of Temporary works at P68 - P70

Deck Erection

¡P             Movement joints installation

 

Turnaround Facilities

¡P             Casting of wingslab

¡P             Casting of roof finishing and ground level finish of mobile telecom equipment room

¡P             Apply waterproof membrane for mobile telecom equipment room

¡P             Dismantling of sling platform, box girder support tower and extended platform

¡P             Installation of Type K1 Kerb for traffic island

¡P             Parapet installation

 

10m at P0

¡P             Construction of central barrier and side barriers

¡P             Construction of the utility trough       

¡P              

 

Monitoring Schedule for the Next Month

9.2         The tentative environmental monitoring schedule for the next month is shown in Appendix D.

Construction Programme for the Next Month

 

9.3         A tentative construction programme is provided in Appendix A.