Table 7.1 Observations and
Recommendations of Site Audit
Parameters |
Date |
Observations and Recommendations |
Follow-up |
Water
Quality |
06/02/2018 |
Silt curtain at
P68 should be surrounded properly around P68 during dismantling works. |
Rectification/improvement
was observed during the follow-up audit session on 13 February 2018. |
Ecology |
N/A(1) |
N/A(1) |
N/A(1) |
Air
Quality |
N/A(1) |
N/A(1) |
N/A(1) |
Noise |
N/A(1) |
N/A(1) |
N/A(1) |
Waste / Chemical Management |
06/02/2018 |
Drip tray at P70 should be plugged. |
Rectification/improvement
was observed during the follow-up audit session on 13 February 2018. |
13/02/2018 |
Housekeeping should be enhanced at P52. |
Rectification/improvement
was observed during the follow-up audit session on 27 February 2018. |
|
20/02/2018 |
Chemical at P56 should be stored in proper
chemical container with chemical label and drip tray. |
Rectification/improvement
was observed during the follow-up audit session on 27 February 2018. |
|
20/02/2018 |
Housekeeping at P113 should be enhanced. |
Rectification/improvement
was observed during the follow-up audit session on 27 February 2018. |
|
27/02/2018 |
Housekeeping should be enhanced at P84 (Portion
A) and accumulation of waste nearby sea should be avoided. |
Rectification/improvement
was observed during the follow-up audit session on 6 March 2018. |
|
Landscape & Visual Impact |
N/A(1) |
N/A(1) |
N/A(1) |
Permits/Licences |
N/A(1) |
N/A(1) |
N/A(1) |
Other |
N/A(1) |
N/A(1) |
N/A(1) |
Cultural Heritage (Sha Lo Wan (West) Archaeological Site) |
12/12/2017 |
N/A(1) |
N/A(1) |
Remark:
N/A(1) - No major environmental
deficiency was identified during the site inspection in the reporting month.