2.1
The proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road
(HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao Bridge (HZMB) at the
HKSAR Boundary with the Hong Kong Boundary Crossing Facilities (HKBCF) situated
at the north eastern waters of the Hong Kong International Airport, opening a new
and direct connection route between Hong Kong, Macao and the Western Pearl
River Delta.
2.2
The HKLR comprises a 9.4km long viaduct section from the HKSAR boundary
to Scenic Hill on the Airport Island; a 1km tunnel section to the reclamation
formed along the east coast of the Airport Island and a 1.6km long at-grade
road section on the reclamation connecting to the HKBCF. The tunnel section of
HKLR will pass under Scenic Hill, Airport Road and Airport Railway to minimize
the environmental and visual impacts to Tung Chung residents.
2.3
An application (No ESB-110/2003) for an Environmental Impact Assessment
(EIA) Study Brief under Section 5(1) of the Environmental Impact Assessment
Ordinance (EIAO) was submitted by Highways Department (the Project Proponent)
on 8 October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong
Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway
Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North
Lantau Highway Connection has subsequently been renamed as HKLR. EPD issued an EIA Study Brief (No:
ESB-110/2003) in November 2003 to the Project Proponent to carry out an EIA
study.
2.4
An EIA Study (Reg. No. AEIAR-144/2009) has been undertaken to provide
information on nature and extent of environmental impacts arising from the
construction and operation of HKLR. The Environmental Permit was issued on 4
November 2009 (Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the
Director of Environmental Protection amends the Environmental Permit (No.
EP-352/2009) based on the Application No. VEP-339/2011 and the environmental
Permit (Permit No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the
Highways Department as the Permit Holder. Subsequently, the Director of
Environmental Protection amends the Environmental Permits (No. EP-352/2009/A, EP-352/2009/B,
EP-352/2009/C) based on the Application No. VEP-409/2013, VEP-411/2013 and VEP-459/2014
respectively. The environmental Permit (Permit No. EP-352/2009/D) was then issued
on 22 December 2014.
2.5
Figure 1a-d shows the layout of the Contract
and the scope of the Contract works comprises the following major items:
¡P
a dual 3-lane carriageway in the form of viaduct from the HKSAR boundary
(connecting with the HZMB Main Bridge) to the Scenic Hill (connecting with the
tunnel under separate Contract No. HY/2011/03), of approximately 9.4km in
length with a hard shoulder for each bound of carriageway and a utilities
trough on the outer edge of each bound of viaducts;
¡P
a grade-separated turnaround facility located near San Shek Wan,
composed of sliproads in the form of viaduct with single-lane carriageway
bifurcated from the HKLR mainline with an elevated junction above the mainline;
¡P
provision of ancillary facilities including, but not limited to,
meteorological enhancement measures including the provisioning of anemometers
and modification of the wind profiler station at hillside of Sha Lo Wan,
provisioning of a compensatory marine radar, and provisioning of security
systems; and
¡P
associated civil, structural, geotechnical, marine, environmental
protection, landscaping, drainage and highways electrical and mechanical
(E&M) works, street lightings, traffic aids and sign gantries, marine
navigational aids, ship impact protection system, water mains and fire
hydrants, lightning protection system, structural health monitoring and
maintenance management system (SHM&MMS), supervisory control and data
acquisition (SCADA) system, as well as operation and maintenance provisions of
viaducts, provisioning of facilities for installation of traffic control and
surveillance system (TCSS), provisioning of facilities for installation of
telecommunication cables/equipments and reprovisioning works of affected
existing facilities/utilities.
2.6
Different parties with different levels of involvement in the Contract
organization include:
Supervising Officer¡¦s Representative (SOR) ¡V
Ove Arup & Partners Hong Kong Limited (ARUP)
Contractor ¡VDragages -China Harbour-VSL
JV (DCVJV)
Environmental Team (ET) ¡V Cinotech Consultants
Ltd. (Cinotech)
2.7
The proposed project organization and lines of communication with
respect to the on-site environmental management structure are shown in Figure 2. The key personnel contact
names and numbers are summarized in Table
2.1.
Table 2.1 Key
Contacts of the Contract
Party |
Position |
Position |
Phone
No. |
Fax
No. |
SOR (ARUP) |
CRE |
Mr. Michael Chan |
3767 5803 |
3767 5922 |
Mr. Dennis Leung |
3767 5801 |
|||
ENPO/IEC (Ramboll Hong
Kong Limited) |
Environmental Project Office Leader |
Mr. Y. H Hui |
3465 2888 |
3465 2899 |
Independent Environmental Checker |
Mr. Antony Wong |
3465 2888 |
3465 2899 |
|
Contractor
(DCVJV) |
Project Director |
Mr. W.K Poon |
3121 6638 |
3121 6688 |
Environmental Officer |
Mr. CHU Chung Sing |
3121 6672 |
||
24-hour Hotline |
-- |
6898 6161 |
-- |
|
ET (Cinotech) |
Environmental Team Leader |
Dr. Priscilla Choy |
2151 2089 |
3107 1388 |
2.8
Ramboll Hong Kong Limited is employed by the Highways
Department as the Independent Environmental Checker (IEC) and Environmental
Project Office (ENPO) for the Project.
2.9
A copy of Contractor¡¦s
construction programme is provided in Appendix A.
1.4. Summary of Construction Works Undertaken During
Reporting Month
2.10
The major site
activities undertaken in the reporting month included:
Ancillary and Associated Facilities
(a)
P115
& P114 interface area - Reinstatement of slope underneath the deck is in
progress;
(b)
Hydroseeding
at Portion A after reinstatement of the sloping seawall and the crest is in
progress;
(c)
Installation
of the remaining outstanding end panel utility trough covers at high mast and
valve chambers locations completed in June;
(d)
Installation
of stainless steel covers at P115 movement joint location was completed;
(e)
Installation
of stainless steel hoppers and uPVC drainage pipes at movement joint locations
is in progress;
(f)
Kiosks
fabrication and construction of civil provision for the additional LEAs
requirement at Turnaround;
(g)
Construction
of U-channels at Turnaround;
(h)
Rehabilitation
works for existing drains and sewerage at South Perimeter Road between P81 to
P84 continues;
(i)
Site
clearance/formation works to the reinstatement of South Perimeter Road between
P84 to P81 are in progress;
(j)
Road
lighting installation at Scenic Road in progress;
(k)
Road
lighting installation at EVA of Ngong Ping 360 in progress.
E&M Works
(a)
Lightning
installation in deck void from P0 to P113 substantially complete and minor
touching up continues;
(b)
Deck
void lighting installation at slip road of ML8 substantially complete;
(c)
Cable
laying for power to the additional kiosks at turnaround in progress.
Temporary Works/ Works at P68
(a)
P68
Works - Removal of the temporary rock fill platform was completed.
(b)
P71,
P72 & P77 Works -Removal of the temporary working platforms under LSSOP is
in progress.
Stainless Steel Maintenance Platform
Installation
of platforms was completed, minor modification and general cleaning works are
in progress.
2.11 A summary
of the relevant permits, licences, and/or notifications on environmental
protection for this Contract is presented in Table 2.2.
Table 2.2 Status
of Environmental Licences, Notification and Permits
Permit
/ License No. |
Valid
Period |
Status |
|
From |
To |
||
Environmental Permit (EP) |
|||
EP-352/2009/D |
22/12/2014 |
N/A |
Valid |
Consruction Noise Permit
(CNP) |
|||
P0-P115: GW-RS0366-18 |
04/05/2018 (19:00) |
03/11/2018 (23:00) |
Valid |
WA4: GW-RW0202-18 |
31/05/2018 (00:00) |
30/11/2018 (24:00) |
Valid |
Notification pursuant to Air Pollution
Control (Construction Dust) Regulation |
|||
345773 |
04/06/2012 |
N/A |
Receipt acknowledged by EPD |
Billing Account for Construction Waste
Disposal |
|||
A/C# 7015341 (Construction Site) |
11/06/2012 |
N/A |
Valid |
Registration of Chemical Waste Producer |
|||
WPN
5213-951-D2499-01 |
18/07/2012 |
N/A |
Valid |
Effluent Discharge License under Water
Pollution Control Ordinance |
|||
WA6A (DCVJV
site office): WT00028521-2017 |
18/07/2017 |
30/09/2022 |
Valid |
WA6B (SOR site office): WT00028841-2017 |
03/08/2017 |
31/10/2022 |
Valid |
Portion C: WT00023624-2016 |
17/02/2016 |
28/02/2018 |
|
Portion A: WT00031351-2018 |
20/06/2018 |
31/05/2023 |
Valid |
WA4B:
WT00014750-2012 |
12/08/2013 |
31/08/2018 |
Valid |
P114: WT00018631-2014 |
31/03/2014 |
31/03/2019 |
Valid |
P81-P83: WT00023608-2016 |
01/04/2016 |
31/07/2020 |
Valid |
Specific Process License
(SP license) for conduct Tar and Bitumen Works |
|||
WA4: Licence No. L-15-038(1) |
31/05/2017 |
30/05/2020 |
Valid* |
*The license holder is the supplier, ASL.
[IT1]Please
check with DCVJV if any update for Portion C discharge license