9.1
Major site activities for the coming reporting month will include:
Marine
Portion
¡P
Installation of cat ladders at pile cap walls;
and
¡P
Dismantling NSS access platforms
Land
Portion
¡P
Reinstatement of South Perimeter Road
9.2
The tentative environmental monitoring schedule for the next month is
shown in Appendix D.
9.3
A tentative construction programme is provided
in Appendix A.