9               FUTURE KEY ISSUEs

Key Issues in the Coming Month

 

9.1         Major site activities for the coming reporting month will include:

Marine Portion

¡P             Installation of cat ladders at pile cap walls; and

¡P             Dismantling NSS access platforms

Land Portion

¡P             Reinstatement of South Perimeter Road

Monitoring Schedule for the Next Month

9.2         The tentative environmental monitoring schedule for the next month is shown in Appendix D.

Construction Programme for the Next Month

 

9.3         A tentative construction programme is provided in Appendix A.