7           ENVIRONMENTAL site inspection

Site Audits

7.1         Site audits were carried out by ET on weekly basis to monitor the timely implementation of proper environmental management practices and mitigation measures in the Contract site.  The summaries of site audits are attached in Appendix M.

7.2         Site audits were conducted on 3rd, 10th, 17th, 24th and 31st July 2018 by ET after the commencement of construction works for the Contract. A joint site audit with the representative with IEC, SOR, the Contractor and the ET was carried out on 24th July 2018. The details of observations during site audit can refer to Table 7.1.

7.3         According to EP condition 4.7 and EM&A Manual, periodic monitoring (every three months) of construction works shall be conducted to ensure the avoidance of any impacts on Sha Lo Wan (West) Archaeological Site. Access to Sha Lo Wan (West) Archaeological site for works areas and storage of construction equipment is not allowed. The 19th inspection to the Sha Lo Wan (West) Archaeological Site was conducted on 19th June 2018 and next inspection will be conducted in September 2018.

Implementation Status of Environmental Mitigation Measures

 

7.4         According to the EIA Study Report, Environmental Permit and the EM&A Manual, the mitigation measures detailed in the documents are recommended to be implemented during the construction phase. An updated summary of the EMIS is provided in Appendix N.

7.5         Regular marine travel route for marine vessels were implemented properly in accordance with the submitted plan and relevant records were kept properly.

7.6         Acoustic decoupling measures for the stationary equipment (generators, winch generators and air compressors) mounted on boards were adopted according to EP Condition 3.7 and EM&A Manual, Section 10.2.18.

7.7         Dolphin exclusion zone and dolphin watching plan according to EM&A Manual, Section 10.2.12 and EP Condition 3.5 was implemented by DCVJV’s trained dolphin watcher.

7.8         Spill kits and booms are ready on site for the event of accidental spillage of oil or other hazardous chemicals from construction activities including vessels operating for the Contract.

7.9         During site inspections in the reporting month, no non-conformance was identified. The observations and recommendations made during the audit sessions are summarized in Table 7.1.


Table 7.1       Observations and Recommendations of Site Audit

Parameters

Date

Observations and Recommendations

Follow-up

Water Quality

10/7/2018

Ponding water should be avoided at WA4.

Rectification/improvement was observed during the follow-up audit session on 17 July 2018.

Ecology

N/A(1)

N/A(1)

N/A(1)

Air Quality

24/7/2018

NRMM labels should be provided for the generator and the air compressor at P56.

Rectification/improvement was observed during the follow-up audit session on 31 July 2018.

Noise

N/A(1)

 N/A(1)

N/A(1)

Waste / Chemical Management

03/7/2018

To provide drip tray for the chemical containers at near P82.

Rectification/improvement was observed during the follow-up audit session on 10 July 2018.

03/7/2018

To clear the damaged traffic barriers at near P82 and Portion C.

Rectification/improvement was observed during the follow-up audit session on 10 July 2018.

10/7/2018

To clear the accumulated waste on the sheet pile at WA4.

Rectification/improvement was observed during the follow-up audit session on 17 July 2018.

17/7/2018

Housekeeping should be enhanced at Portion C.

Rectification/improvement was observed during the follow-up audit session on 24 July 2018.

24/7/2018

Oil stains at P56 should be properly cleared as chemical waste.

Rectification/improvement was observed during the follow-up audit session on 31 July 2018.

24/7/2018

To clear the construction waste and set up a proper tree protection zone at near P82.

Rectification/improvement was observed during the follow-up audit session on 31 July 2018.

31/7/2018

To provide a drip tray for the chemical containers at Portion C.

Rectification/improvement was observed during the follow-up audit session on 7 August 2018.

Landscape & Visual Impact

N/A(1)

N/A(1)

N/A(1)

Permits/Licences

N/A(1)

N/A(1)

N/A(1)

Other

N/A(1)

N/A(1)

N/A(1)

Cultural Heritage

(Sha Lo Wan (West) Archaeological Site)

19/6/2018

N/A(1)

N/A(1)

Remark:       N/A(1) - No major environmental deficiency was identified during the site inspection in the reporting month.

Advice on the Solid and Liquid Waste Management Status

7.10     According to the Contractor, 52 m3 inert C&D materials were generated during the reporting month. 

 

 

7.11     The Contractor was advised to minimize the wastes generated through the recycling or reusing. All mitigation measures stipulated in approved waste management plan shall be fully implemented.

7.12     The amount of wastes generated by the activities of the Contract during the reporting month is shown in Appendix O.