Table 7.1     Observations and Recommendations of Site Audit

Parameters

Date

Observations and Recommendations

Follow-up

Water Quality

N/A(1)

N/A(1)

N/A(1)

Ecology

N/A(1)

N/A(1)

N/A(1)

Air Quality

2/10/2018

To provide mitigation measure (e.g. watering) to the dusty material at near P81 for dust suppression.

Rectification/improvement was observed during the follow-up audit session on 9 October 2018.

Noise

N/A(1)

 N/A(1)

N/A(1)

Waste / Chemical Management

2/10/2018

To provide drip tray for the chemical containers at Portion C.

Rectification/improvement was observed during the follow-up audit session on 9 October 2018.

9/10/2018

To provide drip tray for the chemical containers at near P81.

Rectification/improvement was observed during the follow-up audit session on 16 October 2018.

16/10/2018

Accumulated construction waste were observed at Portion C. The contractor was reminded to clear them regularly.

Rectification/improvement was observed during the follow-up audit session on 23 October 2018.

23/10/2018

To clear the accumulated waste at near P81.

Rectification/improvement was observed during the follow-up audit session on 30 October 2018.

Landscape & Visual Impact

N/A(1)

N/A(1)

N/A(1)

Permits/Licences

N/A(1)

N/A(1)

N/A(1)

Other

N/A(1)

N/A(1)

N/A(1)

Cultural Heritage

(Sha Lo Wan (West) Archaeological Site)

19/9/2018

N/A(1)

N/A(1)

Remark:      N/A(1) - No major environmental deficiency was identified during the site inspection in the reporting month.