Table I                 Summary Table for Monitoring Activities in the Reporting Month

 

Parameter(s)

Date(s)

1-hr TSP Monitoring

4th, 10th, 16th and 22nd October 2018

24-hr TSP Monitoring

[1]2nd, 4th, 10th, 16th and 22nd October 2018

Noise Monitoring

5th, 11th, 18th and 23rd October 2018

Water Quality Monitoring

[2]2nd, 4th, 6th, 8th, 10th, 12th, [2]15th, 18th, 20th and 23rd October 2018

Dolphin Monitoring (Line-transect Vessel Surveys)

2nd and 9th October 2018

Environmental Site Inspection

2nd, 9th, 16th and 23rd October 2018

[1] 24 hr TSP at AMS1 on 28th September 2018 was cancelled due to the power supply and rescheduled to 2 October 2018.

[2] Water quality monitoring (Mid-Ebb) on 2nd and 15th October 2018 were cancelled due to safety reason. The reasons for no alternative include:

a) The tidal ranges of the alternative is less than 0.5m
b) Two sets of monitoring are not less than 36 hours