10         CONCLUSIONS AND RECOMMENDATIONS

Conclusions

10.1     The Environmental Monitoring and Audit (EM&A) Report presents the EM&A works undertaken in October 2018 in accordance with EM&A Manual. 

10.2     No Action/Limit Level exceedance was recorded for construction noise.

10.3     All 1-hour TSP monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedances were recorded.

 

10.4     All 24-hour TSP monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedances were recorded.

 

10.5     All water quality monitoring was conducted as scheduled in the reporting month. No Action/Limit Level exceedance for dissolved oxygen, turbidity and suspended solids were recorded.

 

10.6     Dolphin transect survey was carried out on 2nd and 9th October 2018. No adverse impact on Chinese White Dolphins was noticeable from general observations.

 

10.7     Environmental site inspection was conducted on 2nd, 9th, 16th and 23rd October 2018 by ET in the reporting month. All deficiencies identified during the site inspection have already rectified / improved during the follow-up audit session.

 

10.8     The inspection to the Sha Lo Wan (West) Archaeological Site was conducted on 18th September 2018. No access to Sha Lo Wan (West) Archaeological site for works areas and storage of construction equipment was observed.

 

10.9     There was no environmental complaints, no notification of summons and successful prosecution received in the reporting month.

 

10.10 Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road (HKLR) has been commissioned on 24 October 2018. All Construction Phase EM&A Programme under HY/2011/09 have been terminated starting from the commissioning date for HKLR.

 


Recommendations

 

10.11 According to the environmental audit performed in the reporting month, the following recommendations were made:

 

Air Quality Impact

 

¡P  To regularly maintain the quality of machinery and vehicles on site.

¡P  To implement dust suppression measures on all haul roads, stockpiles, dry surfaces and excavation works.

¡P  To provide hoarding along the entire length of that portion of the site boundary.

 

Noise Impact

 

¡P  To inspect the noise sources inside the site.

¡P  To space out noisy equipment and position the equipment as far away as possible from sensitive receivers.

¡P  To provide temporary noise barriers for operations of noisy equipment near the noise sensitive receivers, if necessary.

 

Water Impact

 

¡P     To prevent any surface runoff discharge into any stream course and sea.

¡P     To review and implement temporary drainage system.

¡P     To identify any wastewater discharges from site.

¡P     To ensure properly maintenance for de-silting facilities.

¡P     To clear the silt and sediment in the sedimentation tanks.

¡P     To review the capacity of de-silting facilities for discharge.

¡P     To divert all the water generated from construction site to de-silting facilities with enough handling capacity before discharge.

¡P     To avoid accumulation of stagnant and ponding water on site.

 

Ecology Impact

 

¡P     To implement Spill Response Plan in the event of accidental spillage of or other hazardous chemicals.

¡P     To implement Dolphin Exclusion Zone during the installation of bored pile casing located in the waters to the west of Airport.

¡P     To implement Dolphin Watching Plan after the bored piling casing is installed.

¡P     To ensure the acoustically-decoupled measures were implemented for air compressors and other noisy equipment mounted on construction vessels according to acoustic decoupling measures plan. 

 

 

Waste/Chemical Management

 

¡P          To check for any accumulation of waste materials or rubbish on site.

¡P          To ensure the performance of sorting of C&D materials at source (during generation);

¡P          To carry out inspection of dump truck at site exit to ensure inert and non-inert C&D materials are properly segregated before removing off site.

¡P          To avoid any discharge or accidental spillage of chemical waste or oil directly from the site.

¡P          To avoid improper handling or storage of oil drum on site.