9              FUTURE KEY ISSUEs

Key Issues in the Coming Month

 

9.1         Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road (HKLR) has been commissioned on 24 October 2018. As the Construction Phase EM&A Programme under HY/2011/09 have been terminated since 24th October 2018 as per EPD¡¦s letter to SOR (EPD¡¦s ref.: ¡§( ) in AX(2) to EP771/E1/099¡¨ dated 30 November 2018), no impact monitoring (air quality, construction noise, water quality and dolphin) and weekly site audit will be carried out in the coming month.

 

9.2         Major site activities for the coming reporting month will include:

Portion A

¡P             Reinstatement of South Perimeter Road (P81-P83)

 

Portion C

¡P             Reinstatement Works

 

Pier 115 & Pier 114 Interface Area

¡P             Reinstatement of Slope and drainage works

Construction Programme for the Next Month

 

9.3         A tentative construction programme is provided in Appendix A.