1.
This is the 1st Quarterly Environmental Monitoring and Audit
(EM&A) Report prepared by Cinotech Consultants
Limited for the project “Contract No. HY/2011/09 – Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road – Section between
HKSAR Boundary and Scenic Hill” (hereinafter called the “Contract”). This report documents the findings of EM&A Works performed in the
period between 22nd February and 31st May 2013.
Environmental Monitoring and Audit Progress
2.
A summary of the monitoring activities in this reporting period is
listed in Table I below:
Table I Summary
Table for Monitoring Activities in the Reporting Period
Parameter(s) |
Monitoring Date(s) |
1-hr TSP Monitoring |
22nd and 28th
February 2013 6th, 12th,
18th, 22nd and 27th March 2013 2nd, 8th,
12th, 18th, 24th and 30th April
2013 6th, 10th,
16th, 22nd and 28th May 2013 |
24-hr TSP Monitoring |
|
Noise Monitoring |
23rd February
2013 1st, 7th,
13th, 19th, 23rd and 28th March
2013 3rd, 9th,
15th and 25th April 2013 2nd, 7th,
13th, 23rd and 29th May 2013 |
Water Quality Monitoring |
22nd, 25th
and 27th February 2013 1st, 4th,
6th, 8th, 11th, 13th, 15th,
18th, 20th, 23rd, 25th, 27th
and 29th March 2013 1st, 3rd,
5th, 8th, 10th, 12th, 15th,
17th, 19th, 22th, 24th, 26th
and 29th April 2013 2nd, 4th,
6th, 8th, 10th, 13th, 15th,
18th, 20th, 22th, 24th, 27th,
29th and 31st
May 2013 |
19th and 25th
February 2013 8th and 22th
March 2013 9th and 17th
April 2013 6th and 14th
May 2013 |
|
(1)Construction-phase underwater Noise Monitoring |
With
Bored Piling Activities: 18th, 19th,
20th, 21st, 22nd, 23rd, 25th,
27th, 28th March 2013 2nd, 3rd,
5th, 8th, 9th, 10th, 25th,
26th, 27th, 29th and 30th April 2013 Without
Bored Piling Activities: 13th, 14th,
15th and 26th March 2013 11th April
2013 |
(1) Dolphin Behaviour
Monitoring |
With
Bored Piling Activities: 18th, 19th,
20th, 21st, 22nd, 23rd, 25th,
27th, 28th and 29th March 2013 1st, 2nd,
3rd, 5th, 7th, 8th, 10th
and 11th April 2013 Without
Bored Piling Activities: 6th, 7th,
8th, 9th, 11th to 17th, 24th
and 30th March 2013 |
(1)Land-based Dolphin Behaviour
and Movement Monitoring |
With
Bored Piling Activities: 18th, 19th,
20th, 21st, 22nd, 23rd, 25th,
27th, 28th March 2013 1st, 2nd,
4th, 5th, 7th, 8th, 9th,
10th and 11th April 2013 Without
Bored Piling Activities: 6th, 7th,
9th to 17th, 24th and 30th March
2013 |
Environmental Site Inspection |
26th February
2013 5th, 12th,
19th and 26th March 2013 2nd, 9th,
16th, 26th and 30th April 2013 7th, 14th,
21st and 31st May 2013 |
Archaeological Site Inspection |
25th March
2013 |
Remark: (1) Dolphin-related monitoring
was conducted in the reporting period. According to the EM&A Manual for
HKLR, the dolphin-related monitoring was conducted during the bored piling
activities (e.g. installation of permanent casting for bored piling activities)
which presented in Appendix A. The dolphin-related monitoring conducted
without bored piling activities are for reference only. In addition, no monitoring was conducted
in May 2013 as no underwater sockets into rock can be carried out for marine
bored piles in West Lantau in May and June in accordance
with EP Condition 3.1.
Breaches of Action and Limit Levels
3.
Summary of the environmental exceedances of
the reporting period is tabulated in Table
II.
Table II Summary
Table for Events Recorded in the Reporting Period
Environmental Monitoring |
Parameter |
No. of Exceedance |
No.
of Exceedance related to the Construction Activities
of this Contract |
||
Action
Level |
Limit
Level |
Action
Level |
Limit
Level |
||
Air Quality |
1-hr TSP |
0 |
0 |
0 |
0 |
24-hr TSP |
0 |
0 |
0 |
0 |
|
Noise |
Leq(30min) |
1 |
0 |
1 |
0 |
Water Quality |
Dissolved Oxygen (DO)
(Surface & Middle) |
7 |
6 |
0 |
0 |
Dissolved Oxygen (DO)
(Bottom) |
10 |
0 |
0 |
0 |
|
Turbidity |
30 |
101 |
0 |
0 |
|
Suspended Solids (SS) |
22 |
92 |
0 |
0 |
|
Underwater Noise |
RMS sound
pressure level re 1µPa |
0 |
0 |
0 |
0 |
Dolphin Monitoring |
Line-transect Vessel
Surveys |
0 |
0 |
0 |
0 |
4.
Environmental monitoring works were performed in the reporting period
and all monitoring results were checked and reviewed. The details of each exceedance
were attached in the Monthly EM&A Reports.
Complaint Log
5.
Summary of the environmental complaints of the reporting period is
tabulated in Table III.
Table III Summary
Table for Complaints Recorded in the Reporting Period
Complaint Log Ref. |
Location |
Received Date |
Nature of Complaint |
Com-2013-04-001 |
Near Tung Chung New Development
Pier |
8 April 2013 |
Water Quality |
Com-2013-05-001 |
WA6 |
2 May 2013 |
Noise |
Com-2013-05-002 |
WA6 |
18 May 2013 |
Noise |
Com-2013-05-003 |
Near Tung Chung New Development
Pier |
18 May 2013 |
Water Quality |
Notification of Summons and Successful
Prosecutions
6.
No notification of summons and successful prosecution was received in
the reporting period.
7.
This report has been developed in compliance with the reporting
requirements for the quarterly EM&A Summary Report
as required by the EM&A Manual for Hong Kong Link Road (EM&A Manual).
8.
Major site activities for
the coming reporting month will include:
WA4
Fabrication
of rebar cages
Loading and
unloading
Setup of
casting yard
WA7
Preparation
for bored piling
Fabrication
of rebar cages
Loading and
Unloading
Portion A (Land Section)
Site
clearance and formation
Timber
Scaffolding
Pre-drilling
work
Set-up
facilities for marine delivery of concrete from land plants
Slewing of the
tele‐communication & AA COM cables
Portion C
Satellite
site office set up
Pre-drilling
work
Protection
work to the fuel pipes
Fabrication of reinforcement cage and
piling jacket, setting up
for land piling work
Western
Water
Pre-drilling
Work
Loading and
Unloading
Setting up
of silt-curtain
Platform
installation for pre‐drilling works
Installation
of temporary casings for the piling platform
Installation
of permanent casing
Bored piling
works