2.1
The
proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong
Link Road (HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao
Bridge (HZMB) at the HKSAR Boundary with the Hong Kong Boundary Crossing
Facilities (HKBCF) situated at the north eastern waters of the Hong Kong
International Airport, opening a new and direct connection route between Hong
Kong, Macao and the Western Pearl River Delta.
2.2
The
HKLR comprises a 9.4km long viaduct section from the HKSAR boundary to Scenic
Hill on the Airport Island; a 1km tunnel section to the reclamation formed
along the east coast of the Airport Island and a 1.6km long at-grade road
section on the reclamation connecting to the HKBCF. The tunnel section of HKLR
will pass under Scenic Hill, Airport Road and Airport Railway to minimize the
environmental and visual impacts to Tung Chung residents.
2.3
An
application (No ESB-110/2003) for an Environmental Impact Assessment (EIA)
Study Brief under Section 5(1) of the Environmental Impact Assessment Ordinance
(EIAO) was submitted by Highways Department (the Project Proponent) on 8
October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection has subsequently been renamed as
HKLR. EPD issued an EIA Study Brief
(No: ESB-110/2003) in November 2003 to the Project Proponent to carry out an
EIA study.
2.4
An EIA
Study (Reg. No. AEIAR-144/2009) has been undertaken to provide information on
nature and extent of environmental impacts arising from the construction and
operation of HKLR. The Environmental Permit was issued on 4 November 2009
(Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the Director of
Environmental Protection amends the Environmental Permit (No. EP-352/2009)
based on the Application No. VEP-339/2011 and the environmental Permit (Permit
No. EP-352/2009/A) was issue on 9 November 2011 for HKLR to the Highways
Department as the Permit Holder.
2.5
Figure 1a-d
shows the layout of the Contract and the scope of the Contract works comprises the following major items:
·
a dual 3-lane
carriageway in the form of viaduct from the HKSAR boundary (connecting with the
HZMB Main Bridge) to the Scenic Hill (connecting with the tunnel under separate
Contract No. HY/2011/03), of approximately 9.4km in length with a hard shoulder
for each bound of carriageway and a utilities trough on the outer edge of each
bound of viaducts;
·
a
grade-separated turnaround facility located near San Shek
Wan, composed of sliproads in the form of viaduct
with single-lane carriageway bifurcated from the HKLR mainline with an elevated
junction above the mainline;
·
provision
of ancillary facilities including, but not limited to, meteorological
enhancement measures including the provisioning of anemometers and modification
of the wind profiler station at hillside of Sha Lo
Wan, provisioning of a compensatory marine radar, and provisioning of security
systems; and
·
associated
civil, structural, geotechnical, marine, environmental protection, landscaping,
drainage and highways electrical and mechanical (E&M) works, street
lightings, traffic aids and sign gantries, marine navigational aids, ship
impact protection system, water mains and fire hydrants, lightning protection system,
structural health monitoring and maintenance management system (SHM&MMS),
supervisory control and data acquisition (SCADA) system, as well as operation
and maintenance provisions of viaducts, provisioning of facilities for
installation of traffic control and surveillance system (TCSS), provisioning of
facilities for installation of telecommunication cables/equipments and reprovisioning works of affected existing
facilities/utilities.
2.6
Different
parties with different levels of involvement in the Contract organization
include:
Supervising
Officer’s Representative (SOR) – Ove Arup &
Partners Hong Kong Limited (ARUP)
Contractor
–Dragages -China Harbour-VSL
JV (DCVJV)
Environmental
Team (ET) – Cinotech Consultants Ltd. (Cinotech)
2.7
The
proposed project organization and lines of communication with respect to the
on-site environmental management structure are shown in Figure 2. The key personnel contact names and numbers are
summarized in Table 2.1.
Table 2.1 Key
Contacts of the Contract
Party |
Position |
Name |
Phone No. |
Fax No. |
SOR (ARUP) |
CRE |
Mr. Michael Chan |
3767 5803 |
3767 5922 |
Mr. Colin Meadows |
3767 5801 |
|||
ENPO/IEC (Environ) |
Environmental Project Office Leader |
Mr. Y. H Hui |
3465 2888 |
3465 2899 |
Independent Environmental Checker |
Mr. Antony Wong |
3465 2888 |
3465 2899 |
|
Contractor (DCVJV) |
Deputy Project Director |
Mr. W.K Poon |
3121 6638 |
3121 6688 |
Environmental Officer |
Mr. CHU Chung Sing |
3121 6672 |
||
24-hour Hotline |
-- |
6898 6161 |
-- |
|
ET (Cinotech) |
Environmental Team Leader |
Dr. H.F Chan |
2151 2088 |
3107 1388 |
2.8
ENVIRON
Hong Kong Ltd. (Environ) is employed by the Highways Department as the
Independent Environmental Checker (IEC) and Environmental Project Office (ENPO)
for the Project.
2.9
A copy of Contractor’s
construction programme is provided in Appendix A.
Summary of Construction Works Undertaken During Reporting Period
2.10 The major site activities undertaken in the reporting period included:
February 2013:
(a) Pre-drilling
works at WA3;
(b) Setting
up of bentonite slurry barges and assembly of 2 nos.
of BG40 piling rigs and fabrication of piling platforms at WA4;
(c) Plant mobilization at WA7;
(d) Trial pit excavation, Utilities diversion and erection
of hoarding & fence and site office area at Portion C;
(e) Pre-drilling
works at P20, P51, P69, P71, P75, P82, P83, P101 &
P103;
(f) Installation of temporary casings for the
piling platform at P48 and P0.
March 2013:
(a) Predrilling works are in progress with marine jack-up rigs,
land rigs on micro platforms and timber scaffoldings along sloping seawall at P14,
P15, P53, P72, P94 & P104;
(b) Trial
pit excavation to locate the fuel pipes is completed with protection works in
progress;
(c) Slewing
of existing 132KV CLP cable into newly built cable trough near the area of P113
and P108 was completed. Backfilling works to P113 area was commenced and to be
completed before mid April 2013. Outstanding set of 11KV cable at P108 is to be
completed before 3 April 2013;
(d) Tele-communication
cable man-holes for slewing were inspected. Meeting was conducted with relevant
parties. It has been confirmed that slewing is feasible with method statement
submitted to SO and parties. Workshop will be arranged for further discussion;
(e) Erection
of hoarding & fence and site office area set up in Portion C in are
progress with decoration to follow;
(f) Fabrication
of 2 nos. piling platforms at WA4 was completed and the remaining platforms in
progress at yard in the mainland;
(g) Installation
of temporary casings for the piling platform was completed at P0 and P49 and in
progress at P20;
(h) Installation
of piling jackets at P52 and prefabrication of 2 nos. piling jackets for P50
were completed;
(i) Piling platform was completed
at P48 and the permanent pile casings have been installed;
(j) Installation
of 8 nos. permanent casing at P52 is in progress;
(k) Rebar
cages prefabrication at WA4 and WA7 for piles is in progress;
(l) Earth
Auger (Model: BG40) has been loaded onto Ro-Ro barge ready for transfer to P48
on 27 March 2013;
(m) Progress
of the precast concrete segment casting yard in Zhongshan
are as follows:
-
Backfilling works were completed
-
Access roads work are in progress
-
11 piling rigs are working on site (approx. 2800
piles completed)
-
Batch plant installation was completed and trial
mixing initial has commenced
-
Gantry rail beams are also in progress (with 4400m
completed)
-
Permanent power was energised
and water were connected
-
75% of dredging works for the loading jetty were
completed
(n) Set up of the floating concrete batching plants
was completed and awaiting the confirmation of the VEP and operating license
from Marine Department;
(o) Sub-contractor
for piling of land section has been finalized. The company profile of the
subcontractor, Bachy, has been submitted to SO for
approval. Setting up works would be
commenced as soon as the permit of site establishment is issued by AA;
(p) Delivery
of launching girder and lifting gantry from abroad with containers was
commenced on 22 February 2013 for further assembling on site;
(q) EBS
monitoring with witness from SOR’s staff started on 24 January 2013 and report
submitted to SO on bi-weekly basis;
(r) Diversion
to existing 1350 drainage pipe and the 600mm water main for facilitating the
construction of piling works to pier 106 to 108 pending for permit of tree
felling.
April 2013:
(a) Trial
pit excavation to locate the fuel pipes is completed with protection works and settlement
markers;
(b) Slewing
of existing 11kV and 132kV CLP cable into newly built cable trough near the
area of P108 and P113 including backfilling works was completed;
(c) Tele-communication
and AA COM cables man-holes for slewing were inspected. The cable slags have been checked with sufficient length for slewing.
Another meeting with AA & tele-communication
providers are scheduled in 1st week of May;
(d) Diversion
to existing 1350mm drainage pipe
and the 600mm water main for the construction of piling works of P106 to P108
is ready but pending for permit of tree felling and works permit from AA;
(e) Fabrication
of piling platforms in PRC: CP1 - 1 was delivered, CP2 and CP4 are in progress;
(f) P0
- Installation of permanent casings completed and BG40 mobilized on 27 April,
pile excavation is in progress;
(g) P19
and P20 - Installation of temporary casings for the piling platform is in
progress;
(h) P48
- 1st pile concreting was completed on 25 April 2013;
(i) P49 - Piling platform was
installed with IDC certificate on 25 April 2013;
(j) P50
- 1 no. pile at P50 was casted, 1 no. pile excavation was completed, 2 nos.
piles are under excavation, the remaining 4 piles has not been started;
(k) P52 - 2 nos. piles at P52 were casted,
the remaining 6 piles are under excavation;
(l) P71
to P73 - 1 no. piling jacket fabrication is in progress;
(m) Rebar
cages prefabrication for piles is in progress at WA4 and WA7;
(n) Land
piling machine from Bachy is pending to be mobilized
to site awaiting for the AA’s works permit;
(o) Set
up of the floating concrete batching plants was completed and awaiting the
approval of the VEP and operating license from Maine Department;
(p) Delivery
of launching girder for landside (LG1) and lifting gantry from abroad was completed.
All containers arrived on site. The components are being handled and put within
the site area in Portion C and WA3. Pre-assembly of elements into 11m sections
has commenced at Portion C;
(q) Continue
or commence the following works (subject to permits and/or approval): trench
excavation for the tele-communication cable and AA’s
COM cable, satellite site office set-up in Portion C, site mobilization for
piling work in Portion C, site clearance and setting up of barriers along
Portion A, drainage and water main diversion near P108 and P109, pre-drilling
work at Western Water, along sloping seawall and at Portion C, installation of
piling platform, installation of permanent casing, bored piling works,
fabrication of reinforcement cage and piling jacket, set up casting yard and pre-assembly of 11m elements for
launching gantries.
May 2013:
(b) Erection of
hoarding & fence and site office area set up in Portion C were completed;
(c) Installation of
decorative hoarding in Portion C was completed;
(d) 2 nos. wheel washing bays
in Portion C were completed and are in operation;
(e) Installation of
water-filled barrier and site clearance in Portion A along seawall was
commenced;
(f) Land piling Sub-Contractor
(Bachy) completed mobilization in Portion C;
(g) Piling Jacket and
permanent casing were installed at P71, P72 & P73;
(h) Pile excavation for P71, P72 &
P73 was commenced;
(i) Fabrication
of piling platforms in PRC: all CP1 were completed, CP4 are in progress;
(j) Installation
of temporary casings for the piling platform at P19, P20, P74 and P78 carried
out and P20, P74 and P78 complete;
(k) Piling platform were installed at P49 and P74;
(l) Installation
of permanent casing at P74;
(m) 1 no. pile at P48 and 1 no. of pile at P0
were casted in May;
(n) 2 nos. pile at P52 and 2 nos. piles
at P50 were casted in May;
(o) Pile excavation
down to rockhead continued at P50 & P52 in early
May but rock socket excavation in Western Water was suspended during the peak dolphin
calving season;
(p) Installation of permanent casing at P0 was resumed;
(q) Spoil disposal at Tuen Mun Area 38;
(r) Rebar cages
prefabrication for piles is in progress at WA4 and WA7 remains in progress;
(s) Set up of the floating
concrete batching plants was completed and awaiting the approval of the VEP and
operating license from Maine Department. Floating concrete batching plant 1602
was mobilized to Hong Kong and moored off WA4 on 17 May 2013;
(t) Pre-assembly of
launching girder LG1 and the segment unloading gantry elements into 11m
sections at Portion C are in progress.
2.11
The
valid environmental licenses and permits were attached in the Monthly EM&A
Reports.