2               Contract INFORMATION

Background

2.1         The proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road (HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao Bridge (HZMB) at the HKSAR Boundary with the Hong Kong Boundary Crossing Facilities (HKBCF) situated at the north eastern waters of the Hong Kong International Airport, opening a new and direct connection route between Hong Kong, Macao and the Western Pearl River Delta. 

2.2         The HKLR comprises a 9.4km long viaduct section from the HKSAR boundary to Scenic Hill on the Airport Island; a 1km tunnel section to the reclamation formed along the east coast of the Airport Island and a 1.6km long at-grade road section on the reclamation connecting to the HKBCF. The tunnel section of HKLR will pass under Scenic Hill, Airport Road and Airport Railway to minimize the environmental and visual impacts to Tung Chung residents.

2.3         An application (No ESB-110/2003) for an Environmental Impact Assessment (EIA) Study Brief under Section 5(1) of the Environmental Impact Assessment Ordinance (EIAO) was submitted by Highways Department (the Project Proponent) on 8 October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection has subsequently been renamed as HKLR.  EPD issued an EIA Study Brief (No: ESB-110/2003) in November 2003 to the Project Proponent to carry out an EIA study.

2.4         An EIA Study (Reg. No. AEIAR-144/2009) has been undertaken to provide information on nature and extent of environmental impacts arising from the construction and operation of HKLR. The Environmental Permit was issued on 4 November 2009 (Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the Director of Environmental Protection amends the Environmental Permit (No. EP-352/2009) based on the Application No. VEP-339/2011 and the environmental Permit (Permit No. EP-352/2009/A) was issue on 9 November 2011 for HKLR to the Highways Department as the Permit Holder.

2.5         Figure 1a-d  shows the layout of the Contract and the scope of the Contract works comprises the following major items:

 

·           a dual 3-lane carriageway in the form of viaduct from the HKSAR boundary (connecting with the HZMB Main Bridge) to the Scenic Hill (connecting with the tunnel under separate Contract No. HY/2011/03), of approximately 9.4km in length with a hard shoulder for each bound of carriageway and a utilities trough on the outer edge of each bound of viaducts;

·           a grade-separated turnaround facility located near San Shek Wan, composed of sliproads in the form of viaduct with single-lane carriageway bifurcated from the HKLR mainline with an elevated junction above the mainline;

·           provision of ancillary facilities including, but not limited to, meteorological enhancement measures including the provisioning of anemometers and modification of the wind profiler station at hillside of Sha Lo Wan, provisioning of a compensatory marine radar, and provisioning of security systems; and

·           associated civil, structural, geotechnical, marine, environmental protection, landscaping, drainage and highways electrical and mechanical (E&M) works, street lightings, traffic aids and sign gantries, marine navigational aids, ship impact protection system, water mains and fire hydrants, lightning protection system, structural health monitoring and maintenance management system (SHM&MMS), supervisory control and data acquisition (SCADA) system, as well as operation and maintenance provisions of viaducts, provisioning of facilities for installation of traffic control and surveillance system (TCSS), provisioning of facilities for installation of telecommunication cables/equipments and reprovisioning works of affected existing facilities/utilities.

Contract Organisation

2.6         Different parties with different levels of involvement in the Contract organization include:

Ÿ   Supervising Officer’s Representative (SOR) – Ove Arup & Partners Hong Kong Limited (ARUP)

Ÿ   Contractor –Dragages -China Harbour-VSL JV   (DCVJV)

Ÿ   Environmental Team (ET) – Cinotech Consultants Ltd. (Cinotech)

 

2.7         The proposed project organization and lines of communication with respect to the on-site environmental management structure are shown in Figure 2. The key personnel contact names and numbers are summarized in Table 2.1.

Table 2.1        Key Contacts of the Contract

Party

Position

Name

Phone No.

Fax No.

SOR (ARUP)

CRE

Mr. Michael Chan

3767 5803

3767 5922

Mr. Colin Meadows

3767 5801

ENPO/IEC

(Environ)

Environmental Project Office Leader

Mr. Y. H Hui

3465 2888

3465 2899

Independent Environmental Checker

Mr. Antony Wong

3465 2888

3465 2899

Contractor (DCVJV)

Deputy Project Director

Mr. W.K Poon

3121 6638

3121 6688

Environmental Officer

Mr. CHU Chung Sing

3121 6672

24-hour Hotline

--

6898 6161

--

ET

(Cinotech)

Environmental Team Leader

Dr. H.F Chan

2151 2088

3107 1388

 

2.8         ENVIRON Hong Kong Ltd. (Environ) is employed by the Highways Department as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) for the Project.

Construction Programme

 

2.9         A copy of Contractor’s construction programme is provided in Appendix A.

 

Summary of Construction Works Undertaken During Reporting Period

2.10     The major site activities undertaken in the reporting period  included:

February 2013:

(a)  Pre-drilling works at WA3;

(b)  Setting up of bentonite slurry barges and assembly of 2 nos. of BG40 piling rigs and fabrication of piling platforms at WA4;

(c)   Plant mobilization at WA7;

(d) Trial pit excavation, Utilities diversion and erection of hoarding & fence and site office area at Portion C;

(e)  Pre-drilling works at P20, P51, P69, P71, P75, P82, P83, P101 & P103;

(f)   Installation of temporary casings for the piling platform at P48 and P0.

March 2013:

(a)   Predrilling works are in progress with marine jack-up rigs, land rigs on micro platforms and timber scaffoldings along sloping seawall at P14, P15, P53, P72, P94 & P104;

(b)   Trial pit excavation to locate the fuel pipes is completed with protection works in progress;

(c)   Slewing of existing 132KV CLP cable into newly built cable trough near the area of P113 and P108 was completed. Backfilling works to P113 area was commenced and to be completed before mid April 2013. Outstanding set of 11KV cable at P108 is to be completed before 3 April 2013;

(d)  Tele-communication cable man-holes for slewing were inspected. Meeting was conducted with relevant parties. It has been confirmed that slewing is feasible with method statement submitted to SO and parties. Workshop will be arranged for further discussion;

(e)   Erection of hoarding & fence and site office area set up in Portion C in are progress with decoration to follow;

(f)   Fabrication of 2 nos. piling platforms at WA4 was completed and the remaining platforms in progress at yard in the mainland;

(g)   Installation of temporary casings for the piling platform was completed at P0 and P49 and in progress at P20;

(h)   Installation of piling jackets at P52 and prefabrication of 2 nos. piling jackets for P50 were completed;

(i)    Piling platform was completed at P48 and the permanent pile casings have been installed;

(j)    Installation of 8 nos. permanent casing at P52 is in progress;

(k)   Rebar cages prefabrication at WA4 and WA7 for piles is in progress;

(l)    Earth Auger (Model: BG40) has been loaded onto Ro-Ro barge ready for transfer to P48 on 27 March 2013;

(m)  Progress of the precast concrete segment casting yard in Zhongshan are as follows:

-                                                           Backfilling works were completed

-                                                           Access roads work are in progress

-                                                           11 piling rigs are working on site (approx. 2800 piles completed)

-                                                           Batch plant installation was completed and trial mixing initial has commenced

-                                                           Gantry rail beams are also in progress (with 4400m completed)

-                                                           Permanent power was energised and water were connected

-                                                           75% of dredging works for the loading jetty were completed

(n) Set up of the floating concrete batching plants was completed and awaiting the confirmation of the VEP and operating license from Marine Department;

(o)   Sub-contractor for piling of land section has been finalized. The company profile of the subcontractor, Bachy, has been submitted to SO for approval.  Setting up works would be commenced as soon as the permit of site establishment is issued by AA;

(p)   Delivery of launching girder and lifting gantry from abroad with containers was commenced on 22 February 2013 for further assembling on site;

(q)   EBS monitoring with witness from SOR’s staff started on 24 January 2013 and report submitted to SO on bi-weekly basis;

(r)   Diversion to existing 1350 drainage pipe and the 600mm water main for facilitating the construction of piling works to pier 106 to 108 pending for permit of tree felling.

April 2013:

(a)   Trial pit excavation to locate the fuel pipes is completed with protection works and settlement markers;

(b)   Slewing of existing 11kV and 132kV CLP cable into newly built cable trough near the area of P108 and P113 including backfilling works was completed;

(c)   Tele-communication and AA COM cables man-holes for slewing were inspected. The cable slags have been checked with sufficient length for slewing. Another meeting with AA & tele-communication providers are scheduled in 1st week of May;

(d)  Diversion to existing 1350mm  drainage pipe and the 600mm water main for the construction of piling works of P106 to P108 is ready but pending for permit of tree felling and works permit from AA;

(e)   Fabrication of piling platforms in PRC: CP1 - 1 was delivered, CP2 and CP4 are in progress;

(f)   P0 - Installation of permanent casings completed and BG40 mobilized on 27 April, pile excavation is in progress;

(g)   P19 and P20 - Installation of temporary casings for the piling platform is in progress;

(h)   P48 - 1st pile concreting was completed on 25 April 2013;

(i)    P49 - Piling platform was installed with IDC certificate on 25 April 2013;

(j)    P50 - 1 no. pile at P50 was casted, 1 no. pile excavation was completed, 2 nos. piles are under excavation, the remaining 4 piles has not been started;

 (k)  P52 - 2 nos. piles at P52 were casted, the remaining 6 piles are under excavation;

(l)    P71 to P73 - 1 no. piling jacket fabrication is in progress;

(m)  Rebar cages prefabrication for piles is in progress at WA4 and WA7;

(n)   Land piling machine from Bachy is pending to be mobilized to site awaiting for the AA’s works permit;

(o)   Set up of the floating concrete batching plants was completed and awaiting the approval of the VEP and operating license from Maine Department;

(p)   Delivery of launching girder for landside (LG1) and lifting gantry from abroad was completed. All containers arrived on site. The components are being handled and put within the site area in Portion C and WA3. Pre-assembly of elements into 11m sections has commenced at Portion C;

(q)   Continue or commence the following works (subject to permits and/or approval): trench excavation for the tele-communication cable and AA’s COM cable, satellite site office set-up in Portion C, site mobilization for piling work in Portion C, site clearance and setting up of barriers along Portion A, drainage and water main diversion near P108 and P109, pre-drilling work at Western Water, along sloping seawall and at Portion C, installation of piling platform, installation of permanent casing, bored piling works, fabrication of reinforcement cage and piling jacket,  set up casting yard  and pre-assembly of 11m elements for launching gantries.

May 2013:

(a)   Diversion to existing 1350mm drainage pipe and the 600mm water main for construction of piling works of P106 to P108 is ready but still pending for tree felling permit and works permit from AA;

(b)   Erection of hoarding & fence and site office area set up in Portion C were completed;

(c)   Installation of decorative hoarding in Portion C was completed;

(d)  2 nos. wheel washing bays in Portion C were completed and are in operation;

(e)   Installation of water-filled barrier and site clearance  in Portion A along seawall was commenced;

(f)   Land piling Sub-Contractor (Bachy) completed mobilization in Portion C;

(g)   Piling Jacket and permanent casing were installed at P71, P72 & P73;

(h)   Pile excavation for P71, P72 & P73 was commenced;

(i)    Fabrication of piling platforms in PRC: all CP1 were completed, CP4 are in progress;

(j)    Installation of temporary casings for the piling platform at P19, P20, P74 and P78 carried out and P20, P74 and P78 complete;  

(k)   Piling platform were installed at P49 and P74;

(l)    Installation of permanent casing at P74;

(m)  1 no. pile at P48 and 1 no. of pile at P0 were casted in May;

(n)   2 nos. pile at P52 and 2 nos. piles at P50 were casted in May;

(o)   Pile excavation down to rockhead continued at P50 & P52 in early May but rock socket excavation in Western Water was suspended during the peak dolphin calving season;

 (p)  Installation of permanent casing at P0 was resumed; 

(q)   Spoil disposal at Tuen Mun Area 38;

(r)   Rebar cages prefabrication for piles is in progress at WA4 and WA7 remains in progress;

(s)   Set up of the floating concrete batching plants was completed and awaiting the approval of the VEP and operating license from Maine Department. Floating concrete batching plant 1602 was mobilized to Hong Kong and moored off WA4 on 17 May 2013;

(t)   Pre-assembly of launching girder LG1 and the segment unloading gantry elements into 11m sections at Portion C are in progress.

Status of Environmental Licences, Notification and Permits

 

2.11     The valid environmental licenses and permits were attached in the Monthly EM&A Reports.