1.
This is the 2nd Quarterly Environmental Monitoring and Audit
(EM&A) Report prepared by Cinotech Consultants
Limited for the project “Contract No. HY/2011/09 – Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road – Section between
HKSAR Boundary and Scenic Hill” (hereinafter called the “Contract”). This report documents the findings of EM&A Works performed in the
period between June and August 2013.
Environmental Monitoring and Audit Progress
2.
A summary of the monitoring activities in this reporting period is
listed in Table I below:
Table I Summary Table for Monitoring Activities in the Reporting Period
Parameter(s) |
Monitoring Date(s) |
1-hr TSP Monitoring |
3rd, 7th,
13th, 19th, 25th and 28th June
2013 4th, 10th,
16th, 22th and 26th July 2013 1st, 7th,
13th, 19th, 23rd and 29th August
2013 |
24-hr TSP Monitoring |
|
Noise Monitoring |
4th, 10th,
20th and 26th June 2013 2nd, 8th,
17th , 23rd and 29th July 2013 8th, 15th
, 20th and 26th August 2013 |
Water Quality Monitoring |
3rd, 5th,
7th, 10th, 13th, 15th, 17th,
19th, 21st, 24th, 26th and 28th
June 2013 2nd, 4th,
6th, 8th, 10th, 12th, 15th,
17th, 19th, 22th, 24th, 26th,
29th and 31st July 2013 3rd, 5th,
7th, 9th, 12th, 16th, 19th,
21st, 23rd, 26th, 28th and 31st August 2013 |
6th and 17th
June 2013 5th and 10th
July 2013 21st and 26th
August 2013 |
|
(1)(2) Construction-phase underwater Noise Monitoring |
11th, 12th,
15th, 16th, 17th, 18th, 19th,
22nd, 23rd and 24th July 2013 |
(1) (2) Dolphin Behaviour
Monitoring |
8th, 9th,
10th, 11th, 12th, 13th, 15th,
17th, 18th, 19th, 23rd, 24th
and 29th July 2013 |
(1)(2)Land-based Dolphin Behaviour
and Movement Monitoring |
9th, 11th,
12th, 15th, 16th, 17th, 18th,
22nd, 23rd, 24th, 25th and 26th
July 2013 |
Environmental Site Inspection |
4th, 11th,
18th and 28th June 2013 2nd, 9th,
16th, 23th and 30th July 2013 6th, 13th,
20th and 29th August 2013 |
Archaeological Site Inspection |
18th June 2013 |
Remark: (1) Dolphin-related monitoring
was conducted in the reporting period. According to the EM&A Manual for
HKLR, the dolphin-related monitoring was conducted during the bored piling
activities (e.g. installation of permanent casting for bored piling activities)
which presented in Appendix A.
(2)30days of
construction-phase underwater noise monitoring, dolphin behavior monitoring and
land-based dolphin behavior and movement monitoring have been completed in July
2013 according to EM&A Manual for HKLR. No additional Land-based Dolphin Behaviour and Movement Monitoring was
conducted in August 2013.
Breaches of Action and Limit Levels
3.
Summary of the environmental exceedances of
the reporting period is tabulated in Table
II.
Table II Summary Table for Events Recorded in the Reporting Period
Environmental Monitoring |
Parameter |
No. of Exceedance |
No.
of Exceedance related to the Construction Activities
of this Contract |
||
Action
Level |
Limit
Level |
Action
Level |
Limit
Level |
||
Air Quality |
1-hr TSP |
0 |
0 |
0 |
0 |
24-hr TSP |
0 |
0 |
0 |
0 |
|
Noise |
Leq(30min) |
0 |
0 |
0 |
0 |
Water Quality |
Dissolved Oxygen (DO)
(Surface & Middle) |
0 |
0 |
0 |
0 |
Dissolved Oxygen (DO)
(Bottom) |
0 |
0 |
0 |
0 |
|
Turbidity |
0 |
0 |
0 |
0 |
|
Suspended Solids (SS) |
4 |
3 |
0 |
0 |
|
Underwater Noise |
RMS sound
pressure level re 1µPa |
0 |
0 |
0 |
0 |
Dolphin Monitoring |
Line-transect Vessel
Surveys |
0 |
0 |
0 |
0 |
4.
Environmental monitoring works were performed in the reporting period
and all monitoring results were checked and reviewed. The details of each exceedance
were attached in the Monthly EM&A Reports.
Complaint Log
5.
Summary of the environmental complaints of the reporting period is
tabulated in Table III.
Table III Summary Table for Complaints Recorded in the Reporting Period
Complaint Log Ref. |
Location |
Received Date |
Nature of Complaint |
Com-2013-07-001 |
Southeast Quay of Chek Lap Kok near the junction
of Chek Lap Kok South
Road and Scenic Road |
17 July 2013 |
Noise |
Notification of Summons and Successful Prosecutions
6.
No notification of summons and successful prosecution was received in
the reporting period.
7.
This report has been developed in compliance with the reporting
requirements for the quarterly EM&A Summary Report
as required by the EM&A Manual for Hong Kong Link Road (EM&A Manual).
8.
Major site activities for
the coming reporting month will include:
WA4
Fabrication
of rebar cages
Fabrication
of temporary piling platforms
WA7
Fabrication
of rebar cages
Loading and
Unloading
Land
Viaduct (P85 to P114)
Set up of
water treatment system
Set up of
piling platforms
Set up of
barriers
Site
clearance
Forming of
site access
Marine
landing access establishment work
Land piling
Slewing the
tele-communication cable and AA’s COM cable
Tree
felling/transplant
Drainage and
water main diversion
Pre-drilling
work
Marine
Viaduct (P0 to P84)
Piling
works for temporary jetty
Installation
of piling jacket
Installation
of permanent casings
Installation
of temporary casings
Pile
excavation by Reverse Circulation Drilling (RCD)
method
Pile
excavation by Kelly method
Pre-drilling
Work
Setting up
of silt-curtain
Platform
installation for pre-drilling works and bored piling works