EXECUTIVE SUMMARY

Introduction

1.              This is the 2nd Quarterly Environmental Monitoring and Audit (EM&A) Report prepared by Cinotech Consultants Limited for the project “Contract No. HY/2011/09 – Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road – Section between HKSAR Boundary and Scenic Hill” (hereinafter called the “Contract”). This report documents the findings of EM&A Works performed in the period between June and August 2013.

Environmental Monitoring and Audit Progress

2.              A summary of the monitoring activities in this reporting period is listed in Table I below:

Table I            Summary Table for Monitoring Activities in the Reporting Period

Parameter(s)

Monitoring Date(s)

1-hr TSP Monitoring

3rd, 7th, 13th, 19th, 25th and 28th June 2013

4th, 10th, 16th, 22th and 26th July 2013

1st, 7th, 13th, 19th, 23rd and 29th August 2013

24-hr TSP Monitoring

Noise Monitoring

4th, 10th, 20th and 26th June 2013

2nd, 8th, 17th , 23rd and 29th July 2013

8th, 15th , 20th and 26th August 2013

Water Quality Monitoring

3rd, 5th, 7th, 10th, 13th, 15th, 17th, 19th, 21st, 24th, 26th and 28th June 2013

2nd, 4th, 6th, 8th, 10th, 12th, 15th, 17th, 19th, 22th, 24th, 26th, 29th and 31st July 2013

3rd, 5th, 7th, 9th, 12th, 16th, 19th, 21st, 23rd, 26th, 28th  and 31st August 2013

Dolphin Monitoring (Line-transect Vessel Surveys)

6th and 17th June 2013

5th and 10th July 2013

21st and 26th August 2013

(1)(2) Construction-phase underwater Noise Monitoring

11th, 12th, 15th, 16th, 17th, 18th, 19th, 22nd, 23rd and 24th July 2013

(1) (2) Dolphin Behaviour Monitoring

8th, 9th, 10th, 11th, 12th, 13th, 15th, 17th, 18th, 19th, 23rd, 24th and 29th July 2013

(1)(2)Land-based Dolphin Behaviour and Movement Monitoring

9th, 11th, 12th, 15th, 16th, 17th, 18th, 22nd, 23rd, 24th, 25th and 26th July 2013

Environmental Site Inspection

4th, 11th, 18th and 28th June 2013

2nd, 9th, 16th, 23th and 30th July 2013

6th, 13th, 20th and 29th August 2013

Archaeological Site Inspection

18th June 2013

Remark:     (1) Dolphin-related monitoring was conducted in the reporting period. According to the EM&A Manual for HKLR, the dolphin-related monitoring was conducted during the bored piling activities (e.g. installation of permanent casting for bored piling activities) which presented in Appendix A. 

 (2)30days of construction-phase underwater noise monitoring, dolphin behavior monitoring and land-based dolphin behavior and movement monitoring have been completed in July 2013 according to EM&A Manual for HKLR. No additional Land-based Dolphin Behaviour and Movement Monitoring was conducted in August 2013.

Breaches of Action and Limit Levels

3.              Summary of the environmental exceedances of the reporting period is tabulated in Table II.

Table II          Summary Table for Events Recorded in the Reporting Period

 

Environmental Monitoring

Parameter

No. of Exceedance

No. of Exceedance related to the Construction Activities of this Contract

Action Level

Limit Level

Action Level

Limit Level

Air Quality

1-hr TSP

0

0

0

0

24-hr TSP

0

0

0

0

Noise

Leq(30min)

0

0

0

0

Water Quality

Dissolved Oxygen (DO) (Surface & Middle)

0

0

0

0

Dissolved Oxygen (DO) (Bottom)

0

0

0

0

Turbidity

0

0

0

0

Suspended Solids (SS)

4

3

0

0

Underwater Noise

RMS sound pressure level re 1µPa

0

0

0

0

Dolphin Monitoring

Line-transect Vessel Surveys

0

0

0

0

 

4.              Environmental monitoring works were performed in the reporting period and all monitoring results were checked and reviewed.  The details of each exceedance were attached in the Monthly EM&A Reports.

 

Complaint Log

 

5.              Summary of the environmental complaints of the reporting period is tabulated in Table III.

Table III         Summary Table for Complaints Recorded in the Reporting Period

Complaint Log Ref.

Location

Received Date

Nature of Complaint

Com-2013-07-001

Southeast Quay of Chek Lap Kok near the junction of Chek Lap Kok South Road and Scenic Road

17 July 2013

Noise

Notification of Summons and Successful Prosecutions

 

6.              No notification of summons and successful prosecution was received in the reporting period.

Reporting Changes

 

7.              This report has been developed in compliance with the reporting requirements for the quarterly EM&A Summary Report as required by the EM&A Manual for Hong Kong Link Road (EM&A Manual).

Future Key Issues

8.              Major site activities for the coming reporting month will include:

WA4

Ÿ   Fabrication of rebar cages

Ÿ   Fabrication of temporary piling platforms

 

WA7

Ÿ   Fabrication of rebar cages

Ÿ   Loading and Unloading

 

Land Viaduct (P85 to P114)

Ÿ   Set up of water treatment system

Ÿ   Set up of piling platforms

Ÿ   Set up of barriers

Ÿ   Site clearance

Ÿ   Forming of site access

Ÿ   Marine landing access establishment work

Ÿ   Land piling

Ÿ   Slewing  the  tele-communication cable and AA’s COM cable

Ÿ   Tree felling/transplant

Ÿ   Drainage  and  water  main diversion

Ÿ   Pre-drilling work

 

Marine Viaduct (P0 to P84)

Ÿ   Piling works for temporary jetty

Ÿ   Installation of piling jacket

Ÿ   Installation of permanent casings

Ÿ   Installation of temporary casings

Ÿ   Pile excavation by Reverse Circulation Drilling (RCD) method

Ÿ   Pile excavation by Kelly method

Ÿ   Pre-drilling Work

Ÿ   Setting up of silt-curtain

Ÿ   Platform installation for pre-drilling works and bored piling works