2.1
The
proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong
Link Road (HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao
Bridge (HZMB) at the HKSAR Boundary with the Hong Kong Boundary Crossing
Facilities (HKBCF) situated at the north eastern waters of the Hong Kong
International Airport, opening a new and direct connection route between Hong
Kong, Macao and the Western Pearl River Delta.
2.2
The
HKLR comprises a 9.4km long viaduct section from the HKSAR boundary to Scenic
Hill on the Airport Island; a 1km tunnel section to the reclamation formed
along the east coast of the Airport Island and a 1.6km long at-grade road
section on the reclamation connecting to the HKBCF. The tunnel section of HKLR
will pass under Scenic Hill, Airport Road and Airport Railway to minimize the
environmental and visual impacts to Tung Chung residents.
2.3
An
application (No ESB-110/2003) for an Environmental Impact Assessment (EIA)
Study Brief under Section 5(1) of the Environmental Impact Assessment Ordinance
(EIAO) was submitted by Highways Department (the Project Proponent) on 8
October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection has subsequently been renamed as
HKLR. EPD issued an EIA Study Brief
(No: ESB-110/2003) in November 2003 to the Project Proponent to carry out an
EIA study.
2.4
An EIA
Study (Reg. No. AEIAR-144/2009) has been undertaken to provide information on
nature and extent of environmental impacts arising from the construction and
operation of HKLR. The Environmental Permit was issued on 4 November 2009
(Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the Director of
Environmental Protection amends the Environmental Permit (No. EP-352/2009)
based on the Application No. VEP-339/2011 and the environmental Permit (Permit
No. EP-352/2009/A) was issue on 9 November 2011 for HKLR to the Highways
Department as the Permit Holder. Subsequently, the Director of Environmental
Protection amends the Environmental Permit (No. EP-352/2009/A) based on the
Application No. VEP-409/2013 and the environmental Permit (Permit No.
EP-352/2009/B) was issue on 1 August 2013.
2.5
Figure 1a-d
shows the layout of the Contract and the scope of the Contract works comprises the following major items:
·
a dual 3-lane
carriageway in the form of viaduct from the HKSAR boundary (connecting with the
HZMB Main Bridge) to the Scenic Hill (connecting with the tunnel under separate
Contract No. HY/2011/03), of approximately 9.4km in length with a hard shoulder
for each bound of carriageway and a utilities trough on the outer edge of each
bound of viaducts;
·
a
grade-separated turnaround facility located near San Shek
Wan, composed of sliproads in the form of viaduct
with single-lane carriageway bifurcated from the HKLR mainline with an elevated
junction above the mainline;
·
provision
of ancillary facilities including, but not limited to, meteorological
enhancement measures including the provisioning of anemometers and modification
of the wind profiler station at hillside of Sha Lo
Wan, provisioning of a compensatory marine radar, and provisioning of security
systems; and
·
associated
civil, structural, geotechnical, marine, environmental protection, landscaping,
drainage and highways electrical and mechanical (E&M) works, street
lightings, traffic aids and sign gantries, marine navigational aids, ship
impact protection system, water mains and fire hydrants, lightning protection
system, structural health monitoring and maintenance management system
(SHM&MMS), supervisory control and data acquisition (SCADA) system, as well
as operation and maintenance provisions of viaducts, provisioning of facilities
for installation of traffic control and surveillance system (TCSS),
provisioning of facilities for installation of telecommunication
cables/equipments and reprovisioning works of
affected existing facilities/utilities.
2.6
Different
parties with different levels of involvement in the Contract organization
include:
Supervising
Officer’s Representative (SOR) – Ove Arup &
Partners Hong Kong Limited (ARUP)
Contractor
–Dragages -China Harbour-VSL
JV (DCVJV)
Environmental
Team (ET) – Cinotech Consultants Ltd. (Cinotech)
2.7
The
proposed project organization and lines of communication with respect to the
on-site environmental management structure are shown in Figure 2. The key personnel contact names and numbers are
summarized in Table 2.1.
Table 2.1 Key Contacts of the Contract
Party |
Position |
Name |
Phone No. |
Fax No. |
SOR (ARUP) |
CRE |
Mr. Michael Chan |
3767 5803 |
3767 5922 |
Mr. Colin Meadows |
3767 5801 |
|||
ENPO/IEC (Environ) |
Environmental Project Office Leader |
Mr. Y. H Hui |
3465 2888 |
3465 2899 |
Independent Environmental Checker |
Mr. Antony Wong |
3465 2888 |
3465 2899 |
|
Contractor (DCVJV) |
Deputy Project Director |
Mr. W.K Poon |
3121 6638 |
3121 6688 |
Environmental Officer |
Mr. CHU Chung Sing |
3121 6672 |
||
24-hour Hotline |
-- |
6898 6161 |
-- |
|
ET (Cinotech) |
Environmental Team Leader |
Dr. H.F Chan |
2151 2088 |
3107 1388 |
2.8
ENVIRON
Hong Kong Ltd. (Environ) is employed by the Highways Department as the
Independent Environmental Checker (IEC) and Environmental Project Office (ENPO)
for the Project.
2.9
A copy of Contractor’s
construction programme is provided in Appendix A.
Summary of Construction Works Undertaken During Reporting Period
2.10 The major site activities undertaken in the reporting period included:
June 2013:
(a) Diversion to existing 1350mm drainage
pipe and the 600mm water main for construction of piling works of P106 to P108
is ready but still pending for tree felling permit and works permit from AA;
(b) 2
nos. wheel washing bays in Portion C were completed and are in operation;
(c) Installation
of water-filled barrier and site clearance in Portion A along seawall was
commenced with 60% completed. Forming of site access along the crest of the
existing seawall are in progress;
(d) Land
piling for P109, P110, P111 and P112 are in progress with 1 pile at P110
concreted in June. Mobilization the 2nd set of piling machine to P112 is in
progress;
(e) CCTV
inspection for existing condition of drainage started but was stopped by
blockage at several manhole locations;
(f) Piling
Jacket and permanent casing were installed at P71, P72 & P73;
(g) Pile
excavation by RCD method at P71, P72 & P73 commenced and 7 nos. concreted
in June;
(h) Piling
works for the temporary jetty at P69 - P70 commenced and remains in progress
(15% of piling completed);
(i) Installation of permanent
casing at P74 & P78;
(j) Pile
excavation by Kelly method at P74 & P78 commenced with 2 nos. pile at P74
and 2 no. of pile at P78 were concreted in June;
(k) Fabrication
of piling platforms in PRC: all CP1 and CP4 were completed;
(l) Installation
of temporary casings for the piling platform at P19, P46 and P47 are in
progress;
(m) Piling
platform were installed at P20 and in progress at P19;
(n) Pile
excavation down to rockhead continued at P50 &
P52 in early May butrock socket excavation in Western
Water was suspended during the peak dolphin calving season;
(o) Assembly
of the 3rd BG40 completed in June and the 4th BG40 arrived site before end
June;
(p) Spoil
disposal at Tuen Mun Area
38; mud disposal to East Sha Chau
and Cheung Chau South.
(q) Rebar
cages prefabrication for piles is in progress at WA4 and WA7 remains in
progress;
(r) Set
up of the floating concrete batching plants was completed and awaiting the
approval of the VEP and operating license from Maine Department. Floating
concrete batching plant 1602 was mobilized to Hong Kong and moored off WA4 on
17 May 2013;
(s) Pre-assembly
of launching girder LG1 and the segment unloading gantry elements into 11m
sections at Portion C was completed.
July 2013:
(a) Land piling works are
in progress with 5
piles concreted in
Portion C in
this reporting period;
(b) Piling
equipment was started mobilizing to seawall in Portion A. Water treatment
system is on site;
(c) Installation of
piling platform along seawall is
in progress and
4 nos. of platforms will
be completed in this reporting period;
(d) First
batch of formworks for column of land viaduct was delivered to Portion C. Trial
panel will be fabricated;
(e) Diversion
to existing 1350mm drainage pipe and
the 600mm water main for construction of piling works of P106
to P108 is ready but still pending for tree felling permit and works permit
from AA;
(f) Installation
of water-filled barrier and site clearance in Portion A along seawall was
commenced with 70% completed. Forming of site access along the top of the existing
seawall are in progress;
(g) One wheel washing bay
for hual road at
Portion A (near SE
Quay) was completed and in
use;
(h) Tracing
of AA COM cables alignment and terminals was completed. A report will be
submitted;
(i) Marine landing access
establishment work near P82 was commenced;
(j) Piling
works for the temporary jetty at P69 - P70 continued and 32% of piling completed;
(n) Pile
excavation by RCD method at P53 was commenced and down to rockhead
continued at P50, P72 & P73 in July;
(o) 14
nos. piles excavation by RCD method were concreted in July 13;
(p) Pile
excavation by Kelly method at P74, P78, P0 and P20. 3 nos. pile
at P74, 5 no. of pile at P78 and 1 no. of pile at P0 were cast in July;
(q) Temporary
piles for P46, P47 were extracted;
(r) Installation
of temporary casings for the piling platform at P43 and P45 are in progress;
(s) Piling
platform at P19 was installed;
(t) 4th
BG arrived and installation at P20 was completed.
August 2013:
Land Viaduct (P84 to Eastern Abutment) and
Preparation Works
(a) Land
piling works are in progress with 5 and 1 no of pile concreted in Portion C and
Portion A respectively.
(b) Formation
of piling platform along seawall is in progress. 10 nos. of platform (P98 to
P107) were completed in this reporting period. Three other platforms (P95 to
P97) were being filled up to level of +3mPD.
(c) First
two batches of steel formworks for column of land viaduct were delivered to
Portion C.
(d) Setting
up of water-filled barrier along edge of carriageway at Portion A was
completed. Site clearance was also completed except for areas pending for tree
felling. Formation of site access along the top of the existing seawall is in
progress.
(e) Telecommunication
cable slewing (near P113) was completed. Concrete surround will be completed.
(f) Tracing
of AA COM cables alignment and terminals was completed with report submitted.
Cable terminals were also checked in the survey.
(g) Marine
landing access establishment work near P82 is in progress.
(h) Diversion
to existing 1350mm drainage pipe and the 600mm water main for construction of
piling works of P106 to P108 is ready but still pending for tree felling permit
with the Works Permit from AA received.
Marine Viaduct (P0 - P84)
(i) Piling works for the
temporary jetty at P69 - P70 continued and remains in progress (57% of piling
completed); Steel structure erection was started (6% completed);
(j) Installation
of temporary casings at P47R, P71L & P54R is in progress.
(k) Piling
Jacket were installed at P47L & P71L;
(l) Permanent
casing were installed at P47R, P54R, P71L & P53R;
(m) Pile excavation by RCD method at P47, P50, P53,
P54 and P71 in this reporting period with 11 piles concreted;
(n) 11
nos. piles using RCD method were concreted in this reporting period;
(o) Finished
dismantle jacket at P52 & P50;
(p) Sonic
Test carried out at P50L;
(q) Installation
of piling platform at P43 and P45 were completed
(r) Installation
of permanent casing at P43 was completed and is on-going at P19 & P45;
(s) Installation
of temporary piles for piling platform at P16 was completed and is on-going at
P40;
(t) Piling
platforms at P74 and P78 were removed;
(u) Pile
excavation by Kelly method at P0, P20, P43, P48 and P49 in this reporting
period with 15 piles concreted;
(v) Progress of pile construction at P0 was
affected by difficult ground conditions encountered, further investigation is
required;
(w) Sonic
test for the completed piles at P78 had been carried out.
2.11
The
valid environmental licenses and permits were attached in the Monthly EM&A
Reports.