EXECUTIVE SUMMARY

Introduction

1.              This is the 3rd Quarterly Environmental Monitoring and Audit (EM&A) Report prepared by Cinotech Consultants Limited for the project “Contract No. HY/2011/09 – Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road – Section between HKSAR Boundary and Scenic Hill” (hereinafter called the “Contract”). This report documents the findings of EM&A Works performed in the period between September and November 2013.

Environmental Monitoring and Audit Progress

2.              A summary of the monitoring activities in this reporting period is listed in Table I below:

Table I            Summary Table for Monitoring Activities in the Reporting Period

 

Parameter(s)

Monitoring Date(s)

1-hr TSP Monitoring

4th, 10th, 16th, 21st and 27th September 2013

3rd, 9th, 15th, 21st, 25th and 31st October 2013

6th, 12th, 18th, 22nd and 28th November 2013

24-hr TSP Monitoring

Noise Monitoring

5th, 11th , 17th, 23rd and 30th September 2013

10th, 16th , 22nd  and 28th October 2013

7th, 13th , 19th  and 25th November 2013

Water Quality Monitoring

2nd, 4th, 6th, 9th, 11th, 14th, 16th, 18th, 21st, 23rd, 25th , 28th and 30th September 2013

2nd, 4th, 7th, 9th, 11th, 15th, 17th, 19th, 21st, 23rd, 25th , 28th and 30th October 2013

1st, 4th, 6th, 8th, 11th, 13th, 15th, 18th, 20th, 22nd, 26th , 28th and 30th November 2013

Dolphin Monitoring (Line-transect Vessel Surveys)

11th and 19th September 2013

9th and 18th October 2013

6th and 15th November 2013

(1)(2)Land-based Dolphin Behaviour and Movement Monitoring

28th and 30th September 2013

Environmental Site Inspection

3rd, 10th, 17th and 27th September 2013

2nd, 7th, 16th, 22nd and 29th October 2013

5th, 12th, 19th  and 29th November 2013

Archaeological Site Inspection

10th  September 2013

Remark:    (1) Detailed monitoring methodology and results will be provided in a separate report after the completion of full set of additional land-based dolphin behavior and movement monitoring.

(2) No additional land-based dolphin behavior and movement monitoring was conducted in October and November 2013. In view of the construction activities have no significant change, the monitoring in October, November and December 2013 will be considered/reviewed in the monthly EM&A report for November and December 2013 respectively.

Breaches of Action and Limit Levels

3.              Summary of the environmental exceedances of the reporting period is tabulated in Table II.

Table II          Summary Table for Events Recorded in the Reporting Period

 

Environmental Monitoring

Parameter

No. of Exceedance

No. of Exceedance related to the Construction Activities of this Contract

Action Level

Limit Level

Action Level

Limit Level

Air Quality

1-hr TSP

0

1

0

0

24-hr TSP

0

0

0

0

Noise

Leq(30min)

0

0

0

0

Water Quality

Dissolved Oxygen (DO) (Surface & Middle)

0

0

0

0

Dissolved Oxygen (DO) (Bottom)

0

0

0

0

Turbidity

1

0

0

0

Suspended Solids (SS)

15

10

0

0

Dolphin Monitoring

Line-transect Vessel Surveys

0

0

0

0

 

4.              Environmental monitoring works were performed in the reporting period and all monitoring results were checked and reviewed.  The details of each exceedance were attached in the Monthly EM&A Reports.

Complaint Log

 

5.              Summary of the environmental complaints of the reporting period is tabulated in Table III.

Table III         Summary Table for Complaints Recorded in the Reporting Period

Complaint Log Ref.

Location

Received Date

Nature of Complaint

Com-2013-11-001

Chek Lap Kok (CLK) South Road

16 November 2013

Air Quality

Notification of Summons and Successful Prosecutions

 

6.              No notification of summons and successful prosecution was received in the reporting period.

Reporting Changes

 

7.              This report has been developed in compliance with the reporting requirements for the quarterly EM&A Summary Report as required by the EM&A Manual for Hong Kong Link Road (EM&A Manual).

Future Key Issues

8.              Major site activities for the coming reporting month will include:

WA4

Ÿ   Fabrication of rebar cages

Ÿ   Fabrication of temporary piling platforms

WA7

Ÿ   Fabrication of rebar cages

Ÿ   Loading and Unloading of rebar materials

Marine Viaduct (P0 to P84)

Ÿ   Piling works for the temporary jetty

Ÿ   Beams and deck installation for jetty

Ÿ   Installation of temporary casings, jackets and permanent casings

Ÿ   Dismantling of jacket

Ÿ   Pile excavation by Reverse Circulation Drill (RCD) method

Ÿ   Pile excavation by Kelly method

Ÿ   Inter-face Coring Test and Sonic Test

Ÿ   Installation of temporary piles, platform and permanent casing

Ÿ   Predrilling works

Ÿ   Operation of floating concrete batching plants

Ÿ   Casting of precast shell for pile cap

 

Land Viaduct (P85 to P114)

Ÿ   Land piling and concreting works

Ÿ   Formation of piling platform along seawall

Ÿ   Kicker pour for column

Ÿ   Rebar threading for coupler

Ÿ   Marine landing access establishment work

Ÿ   Construction of ingress and egresses

Ÿ   Trial trenches for pile cap

Ÿ   Drainage and water main diversion

Ÿ   Tree felling/transplant work

Ÿ   Pile head excavation / trimming

Ÿ   Pile cap and column construction

Ÿ   Predrilling works

Ÿ   Construction of cofferdam for pilcaps