2               Contract INFORMATION

Background

2.1         The proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road (HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao Bridge (HZMB) at the HKSAR Boundary with the Hong Kong Boundary Crossing Facilities (HKBCF) situated at the north eastern waters of the Hong Kong International Airport, opening a new and direct connection route between Hong Kong, Macao and the Western Pearl River Delta. 

2.2         The HKLR comprises a 9.4km long viaduct section from the HKSAR boundary to Scenic Hill on the Airport Island; a 1km tunnel section to the reclamation formed along the east coast of the Airport Island and a 1.6km long at-grade road section on the reclamation connecting to the HKBCF. The tunnel section of HKLR will pass under Scenic Hill, Airport Road and Airport Railway to minimize the environmental and visual impacts to Tung Chung residents.

2.3         An application (No ESB-110/2003) for an Environmental Impact Assessment (EIA) Study Brief under Section 5(1) of the Environmental Impact Assessment Ordinance (EIAO) was submitted by Highways Department (the Project Proponent) on 8 October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection has subsequently been renamed as HKLR.  EPD issued an EIA Study Brief (No: ESB-110/2003) in November 2003 to the Project Proponent to carry out an EIA study.

2.4         An EIA Study (Reg. No. AEIAR-144/2009) has been undertaken to provide information on nature and extent of environmental impacts arising from the construction and operation of HKLR. The Environmental Permit was issued on 4 November 2009 (Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the Director of Environmental Protection amends the Environmental Permit (No. EP-352/2009) based on the Application No. VEP-339/2011 and the environmental Permit (Permit No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the Highways Department as the Permit Holder. Subsequently, the Director of Environmental Protection amends the Environmental Permits (No. EP-352/2009/A and EP-352/2009/B) based on the Application No. VEP-409/2013 and VEP-411/2013 respectively. The environmental Permit (Permit No. EP-352/2009/C) was then issued on 5 September 2013.

2.5         Figure 1a-d  shows the layout of the Contract and the scope of the Contract works comprises the following major items:

 

·           a dual 3-lane carriageway in the form of viaduct from the HKSAR boundary (connecting with the HZMB Main Bridge) to the Scenic Hill (connecting with the tunnel under separate Contract No. HY/2011/03), of approximately 9.4km in length with a hard shoulder for each bound of carriageway and a utilities trough on the outer edge of each bound of viaducts;

·           a grade-separated turnaround facility located near San Shek Wan, composed of sliproads in the form of viaduct with single-lane carriageway bifurcated from the HKLR mainline with an elevated junction above the mainline;

·           provision of ancillary facilities including, but not limited to, meteorological enhancement measures including the provisioning of anemometers and modification of the wind profiler station at hillside of Sha Lo Wan, provisioning of a compensatory marine radar, and provisioning of security systems; and

·           associated civil, structural, geotechnical, marine, environmental protection, landscaping, drainage and highways electrical and mechanical (E&M) works, street lightings, traffic aids and sign gantries, marine navigational aids, ship impact protection system, water mains and fire hydrants, lightning protection system, structural health monitoring and maintenance management system (SHM&MMS), supervisory control and data acquisition (SCADA) system, as well as operation and maintenance provisions of viaducts, provisioning of facilities for installation of traffic control and surveillance system (TCSS), provisioning of facilities for installation of telecommunication cables/equipments and reprovisioning works of affected existing facilities/utilities.

Contract Organisation

2.6         Different parties with different levels of involvement in the Contract organization include:

Ÿ   Supervising Officer’s Representative (SOR) – Ove Arup & Partners Hong Kong Limited (ARUP)

Ÿ   Contractor –Dragages -China Harbour-VSL JV   (DCVJV)

Ÿ   Environmental Team (ET) – Cinotech Consultants Ltd. (Cinotech)

 

2.7         The proposed project organization and lines of communication with respect to the on-site environmental management structure are shown in Figure 2. The key personnel contact names and numbers are summarized in Table 2.1.

Table 2.1        Key Contacts of the Contract

Party

Position

Name

Phone No.

Fax No.

SOR (ARUP)

CRE

Mr. Michael Chan

3767 5803

3767 5922

Mr. Colin Meadows

3767 5801

ENPO/IEC

(Environ)

Environmental Project Office Leader

Mr. Y. H Hui

3465 2888

3465 2899

Independent Environmental Checker

Mr. Antony Wong

3465 2888

3465 2899

Contractor (DCVJV)

Deputy Project Director

Mr. W.K Poon

3121 6638

3121 6688

Environmental Officer

Mr. CHU Chung Sing

3121 6672

24-hour Hotline

--

6898 6161

--

ET

(Cinotech)

Environmental Team Leader

Dr. H.F Chan

2151 2088

3107 1388

 

2.8         ENVIRON Hong Kong Ltd. (Environ) is employed by the Highways Department as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) for the Project.

Construction Programme

 

2.9         A copy of Contractor’s construction programme is provided in Appendix A.

Summary of Construction Works Undertaken During Reporting Period

2.10     The major site activities undertaken in the reporting period  included:

September 2013:

Land Viaduct (P84 to Eastern Abutment) and Preparation Works

(a)   Land piling works are in progress with total 14 and3 no of pile concreted in Portion C and Portion A respectively. 6 piles were concreted in this reporting period.

(b)   Formation of piling platform along seawall is in progress. 10 nos. of platform (P98 to P107) were completed in this reporting period. Three other platforms (P94 to P97) were being filled up to level of +3mPD.

(c)   Two kicker pour for column of land viaduct (P109L &P109R) were poured.

(d)  Tree felling started in Portion A & C and continue in progress.

(e)   Telecommunication cable slewing and concrete surround (near P113) was completed. Piling work in the vicinity started.  

(f)   Tracing of AA COM cables alignment and terminals was completed with report submitted. Cable terminals were also checked in the survey pending for AAHK’s confirmation to finalize method statement.

(g)   Marine landing access establishment work near P82 was completed.

(h)   Diversion to existing 1350mm drainage pipe and the  600mm water main for construction  of  piling  works  of  P106  to  P108  is  ready  but  still  pending  for Works Permit from AA.

Marine Viaduct (P0 - P84)

(i)  Piling  works  for  the  temporary  jetty  at  P69  -  P70  continued  and  remains  in progress (80% of piling completed);

(j)  Beams and deck installation for jetty at P69-P70 isin progress (50% of beams & 10% of deck installed);

(k)  Installation of temporary casings at P53L, P54L & P73L is in progress;

(l)  Piling Jacket were installed at P46, P54L & P53L;

(m)  Permanent casing were installed at P46 & P53L;

(n)  Pile  excavation  by  RCD  method  at  P53L  was  commenced and  down  to rockhead at P46, P72R & P73R;

(o)  11 nos.  piles  excavated  using  RCD  method  were  concreted  in  this  reporting period;

(p)  Finish dismantle jacket at P71, P54R & P53R;

(q)  Sonic Test has been carried out at P53R;

(r)  22  visas  out  of  50  requested  by  Sambo  were  granted  this  month.  A 4th working front will start in October2013;

(s)  Installation of piling platform at P44, P16 and P40were completed;

(t)  Installation  of  permanent  casing  at  P44  and  P19  were  completed  and  ongoing at P40 & P16;

(u)  Installation  of  temporary  piles  for  piling  platform at  P40  and  P41  was completed and on-going at P18 and P42;

(v)  Piling  platforms  at  P48  and  P49  were  removed  and  transferred  to  P16  and P40;

(w)  Pile  excavation  by  Kelly  method  at  P0,  P19,  P20,  P43  and  P45  with  16  piles concreted in this reporting period;

(x)  Progress at P0 was affected by results of interfacecoring;

(y)  Sonic test for the completed piles at P0, P48 had been carried out;

(z)  Interface coring was done at P0, P48 and P49.

 

October 2013:

 

Land Viaduct (P84 to Eastern Abutment at SHT) and Preparation Works

(a)   Land piling works are in progress with total 15 and 6 no. of pile concreted in Portion C and Portion A respectively. 4 piles were concreted in this reporting period. All land piling machines are now carrying out piling works at Portion A due to existing drainage/watermain diversion and the COM cable of AA inside Portion C still to be diverted;

(b)   Formation of piling platform along seawall continues in progress. 6 nos. of platform (in between P92 to P107) were completed in this reporting period. Four other platforms (in between P84 to P91) were being filled up to level of +3mPD;

(c)   Three kickers at column P108L, P110L & P110R were poured and two column stem sections (P109L & P109R) were poured in this reporting period;

(d)  Rebar threading for coupler started on site in Portion C;

(e)   Tree felling in Portion A & C and continues in progress;  

(f)   Tracing of AA COM cables alignment and terminals was completed with report submitted. Cable terminals were also checked in the survey and now slewing works pending for AAHK’s works permit. Revised method statement was submitted;

(g)   Marine landing access near P82 commenced operation  on 10 October followed a joint inspection with AA on 3 October;

(h)   Drainage diversion work permit was received and excavation works and ELS installation started in this reporting period;

 (i)  Construction of ingresses & egresses along Portion A are in progress; 

(j)  Trial trenches for pile cap construction at P111 started but disrupted due to uncharted cable was found obstructing the pile cap.

Marine Viaduct (P0 to P84)

(k)  Beams and deck installation for jetty at P69-P70 in progress (100% of piling completed, 60% of beams & 45% of deck installed);

(l)  Installation of temporary casings, jackets and permanent casings carried outat P51L&R, P54L & P65 carried out in this reporting period;

(m)  Dismantling of jacket at P47 was finished;

(n)  Pile excavation by RCD method at P46, P51, P53, P54, P65 and P73 carried out in this reporting period with 17 piles concreted;

(o) The remaining visas requested by Sambo were granted this month. A 5th working front will start in November 2013;

(p)  Installation of temporary piles, platforms and permanent casings for Kelly method carried out at P18, P38, P39, P40, P41, P42 and P44 in this reporting period;

(q)  Piling platform at P43 and P45 were removed in this reporting period;

(r)  Pile excavation by Kelly method at P19, P20, P40, P43, P44 and P45 carried out in this reporting period with 20 piles concreted;

(s)  Progress at P0 was affected by the interface concrete issues at exceptional depth;

(t)  Inter-face Coring Test and Sonic Testing were carried out to completed piles at P0, P43, P47 and P53 in this reporting period.

 

November 2013:

Land Viaduct (P84 to Eastern Abutment at SHT) and Preparation Works

(a)  Land piling works are in progress with total 15 and 13 no. of pile concreted in Portion C and Portion A respectively. 7 piles were concreted in this reporting period. All land piling machines are carrying out piling works in Portion A due to pending of existing drainage, watermain and Communication Cable (COM cable) of Airport Authority (AA) division in Portion C;

(b)  Stage 1 formations of piling platform along seawall (P92 to P107) were completed in this reporting period. 8 other platforms (P84 to P91) were filled up to level of +3mPD;

(c)  12 pours of column were completed with 5 pours in this reporting period;

(d)  Rebar threading for coupler continues in Portion C;

(e)  Tree felling in Portion A & C was completed for areas currently having site works. Further approved tree felling will be carried out as required in nextstage;

(f)  Hong Kong Airport Authority’s permit for AA COM cables slewing still pending;

(g)  Drainage diversion work remains in progress with approximately 30m of 1200mm diameter pipe and 10m of 1350mm diameter pipe laid in November. Excavation works and Earth Lateral Support (ELS) continues;

(h)  Construction of ingresses & egresses along Portion A was completed and in operation;

(i)  ELS for pile cap construction at P111L was completed. Pile head breaking is in progress. ELS for P111R & P112L are also in progress;

Marine Viaduct (P0 to P84)

(j)  Jetty works at P69-P70 were completed;

(k)  Installation of temporary casings at P57 is in progress;

(l)  Piling Jacket were installed at P14, P22, P55, P56 & P66;

(m)  Permanent casing were installed at P14L, P22R, P55R, P56R & P66;

(n)  Pile excavation by RCD method in progress at P14, P22, P51, P54, P55, P56, P65 & P66 with 17 piles concreted in this reporting period;

(o)  Jackets were dismantled at P46, P51, P54L & P65;

(p)  Inter-face Coring Tests were carried out at P46, P53, P54 & P71;

(q)  Sonic Tests were carried out at P71L;

(r)  All barges moved out from Airport Channel on 7 November 2013 due to expiry of permit;

(s)  Installation of temporary piles, platforms and permanent casings for Kelly method carried out at P16, P17, P18, P38 and P39;

(t)  Piling platform at P0, P16, P40 and P44 were removed;

(u)  Pile excavation by Kelly method in progress at P19, P20, P38, P40, P41 and P42 carried out with 12 piles concreted in this reporting period;

(v)  Remedial works to piles at P0 completed and erection of temporary supports for receiving the precast shells in progress;

(w)  Inter-face Coring Test and Sonic Testing were carried out to completed piles at P20, P44 and P74;

Casting Yard / Floating Batching Plant

(x)  Progress of the precast concrete segment casting yard:

-     Construction of the two load-out jetties completed; Test and commissioning to be conducted in December.

-    All gantries (18 nos.) erected; 7 nos. tested and commissioned; 11 nos. to be tested and commissioned in December.

-   Mould fabrications are on-going with 1 no. “Type “B”, 8 nos. “Type A” (including 2 no. SOP’s) and 2 nos. Type D moulds assembled; “Type CH” (long spans) and “Type CP” mould fabrication continues at casting yard with first CH2 type fabricated.

-     Rebar jigs fabrication and installation continues with 18 of 30 nos. completed

-     Rebar and Prestress Tendon (PT) material delivery continues

-    A total of 41 segments concreted in this reporting period and up to end of the reporting period total 86 segments casted;

(y)  The floating concrete batching plant 1602 is in operation with 7 piles concreted;

(z)  Barge 1601 commenced its operation on 14 November with total 3 piles concreted.

Status of Environmental Licences, Notification and Permits

 

2.11     The valid environmental licenses and permits were attached in the Monthly EM&A Reports.