EXECUTIVE SUMMARY

Introduction

1.              This is the 4th Quarterly Environmental Monitoring and Audit (EM&A) Report prepared by Cinotech Consultants Limited for the project “Contract No. HY/2011/09 – Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road – Section between HKSAR Boundary and Scenic Hill” (hereinafter called the “Contract”). This report documents the findings of EM&A Works performed in the period between December 2013 and February 2014.

Environmental Monitoring and Audit Progress

2.              A summary of the monitoring activities in this reporting period is listed in Table I below:

Table I            Summary Table for Monitoring Activities in the Reporting Period

 

Parameter(s)

Monitoring Date(s)

1-hr TSP Monitoring

4th, 10th, 16th, 21st and 27th December 2013

2nd, 8th, 14th, 20th, 24th and 30th January 2014

5th, 11th, 17th, 21st and 27th February 2014

24-hr TSP Monitoring

Noise Monitoring

5th, 11th , 17th , 23rd  and 30th December 2013

9th, 15th , 21st  and 27th January 2014

6th, 12th , 18st  and 24th February 2014

Water Quality Monitoring

2nd, 4th, 6th, 9th, 11th, 13th, 16th, 18th, 20th, 24th, 26th , 28th and 30th December 2013

2nd, 4th, 6th, 8th, 10th, 13th, 15th, 17th, 20th, 22th, 24th , 28th and 30th January 2014

1st, 4th, 6th, 8th, 11th, 13th, 15th, 17th, 19th, 21st, 25th  and 27th February 2014

Dolphin Monitoring (Line-transect Vessel Surveys)

3rd and 20th December 2013

3rd and 24th January 2014

24th  and 26th February 2014

(1)(2)(3) Additional Land-based Dolphin Behaviour and Movement Monitoring

22nd and 27th January 2014

Environmental Site Inspection

3rd, 10th, 17th , 24th and 31st December 2013

7th, 14th , 21st and 28th January 2014

5th, 11th , 18th and 28th February 2014

Archaeological Site Inspection

30th December 2013

Remark:    (1) In view of the construction activities have no significant change in December 2013, no additional land-based dolphin behavior and movement monitoring was conducted in December 2013.

                            (2) Detailed monitoring methodology and results in January 2014 will be provided in a separate report after the completion of full set of additional land-based dolphin behavior and movement monitoring.

(3) Due to the short notice given to Dolphin Specialist, additional land-based dolphin behaviour and movement monitoring could not be arranged on 27 and 28 February 2014.

Breaches of Action and Limit Levels

3.              Summary of the environmental exceedances of the reporting period is tabulated in Table II.

Table II          Summary Table for Events Recorded in the Reporting Period

 

Environmental Monitoring

Parameter

No. of Exceedance

No. of Exceedance related to the Construction Activities of this Contract

Action Level

Limit Level

Action Level

Limit Level

Air Quality

1-hr TSP

0

0

0

0

24-hr TSP

4

0

0

0

Noise

Leq(30min)

0

0

0

0

Water Quality

Dissolved Oxygen (DO) (Surface & Middle)

0

0

0

0

Dissolved Oxygen (DO) (Bottom)

0

0

0

0

Turbidity

10

18

0

0

Suspended Solids (SS)

40

27

0

0

Dolphin Monitoring

Line-transect Vessel Surveys

0

0

0

0

 

4.              Environmental monitoring works were performed in the reporting period and all monitoring results were checked and reviewed.  The details of each exceedance were attached in the Monthly EM&A Reports.

Complaint Log

 

5.              Summary of the environmental complaints of the reporting period is tabulated in Table III.

Table III         Summary Table for Complaints Recorded in the Reporting Period

Complaint Log Ref.

Location

Received Date

Nature of Complaint

Com-2014-01-001

Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road – Section between HKSAR Boundary and Scenic Hill (Contract No. HY/2011/09

3 January 2014

Noise

Com-2014-01-002

Hong Kong-Zhuhai-Macao Bridge

16 January 2014

Air Quality

Notification of Summons and Successful Prosecutions

 

6.              No notification of summons and successful prosecution was received in the reporting period.

Reporting Changes

 

7.              This report has been developed in compliance with the reporting requirements for the quarterly EM&A Summary Report as required by the EM&A Manual for Hong Kong Link Road (EM&A Manual).

Future Key Issues

8.              Major site activities for the coming reporting month will include:

WA4

Ÿ   Fabrication of rebar cages

Ÿ   Fabrication of temporary piling platforms

WA7

Ÿ   Fabrication of rebar cages

Ÿ   Loading and Unloading of rebar materials

 

Marine Viaduct (P0 to P84)

Ÿ   Construction of the temporary jetty

Ÿ   Installation of temporary casings, piling jackets, temporary piles, platform and permanent casings

Ÿ   Dismantling of piling jacket

Ÿ   Pile excavation by Reverse Circulation Drill (RCD) method

Ÿ   Pile excavation by Kelly method

Ÿ   Inter-face coring test, full depth coring test and sonic test

Ÿ   Pre-drilling works

Ÿ   Operation of floating concrete batching plants

Ÿ   Trimming of pile head

Ÿ   Grouting works

Ÿ   Driving of sheet piling

Ÿ   Trial water cracking and trial shaft grouting

Ÿ   Precast shells waterproofing works

Ÿ   Advanced concrete breaking works inside the permanent steel casing

 

Land Viaduct (P85 to P114)

Ÿ   Land piling and concreting works

Ÿ   Rebar threading for coupler

Ÿ   Drainage and water main diversion works

Ÿ   Backfilling

Ÿ   Tree transplant and maintenance works

Ÿ   Installation of portal beam

Ÿ   Excavation works and Earth Lateral Support (ELS)

Ÿ   Pouring of pile cap and pile head breaking

Ÿ   Formation works

Ÿ   Pours of column

Ÿ   Erection of side formwork for the portal and kickers

Ÿ   Road diversion works

Ÿ   Pre-drilling works, pile cap, column and portal construction