2               Contract INFORMATION

Background

2.1         The proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road (HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao Bridge (HZMB) at the HKSAR Boundary with the Hong Kong Boundary Crossing Facilities (HKBCF) situated at the north eastern waters of the Hong Kong International Airport, opening a new and direct connection route between Hong Kong, Macao and the Western Pearl River Delta. 

2.2         The HKLR comprises a 9.4km long viaduct section from the HKSAR boundary to Scenic Hill on the Airport Island; a 1km tunnel section to the reclamation formed along the east coast of the Airport Island and a 1.6km long at-grade road section on the reclamation connecting to the HKBCF. The tunnel section of HKLR will pass under Scenic Hill, Airport Road and Airport Railway to minimize the environmental and visual impacts to Tung Chung residents.

2.3         An application (No ESB-110/2003) for an Environmental Impact Assessment (EIA) Study Brief under Section 5(1) of the Environmental Impact Assessment Ordinance (EIAO) was submitted by Highways Department (the Project Proponent) on 8 October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection has subsequently been renamed as HKLR.  EPD issued an EIA Study Brief (No: ESB-110/2003) in November 2003 to the Project Proponent to carry out an EIA study.

2.4         An EIA Study (Reg. No. AEIAR-144/2009) has been undertaken to provide information on nature and extent of environmental impacts arising from the construction and operation of HKLR. The Environmental Permit was issued on 4 November 2009 (Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the Director of Environmental Protection amends the Environmental Permit (No. EP-352/2009) based on the Application No. VEP-339/2011 and the environmental Permit (Permit No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the Highways Department as the Permit Holder. Subsequently, the Director of Environmental Protection amends the Environmental Permits (No. EP-352/2009/A and EP-352/2009/B) based on the Application No. VEP-409/2013 and VEP-411/2013 respectively. The environmental Permit (Permit No. EP-352/2009/C) was then issued on 5 September 2013.

2.5         Figure 1a-d  shows the layout of the Contract and the scope of the Contract works comprises the following major items:

 

·           a dual 3-lane carriageway in the form of viaduct from the HKSAR boundary (connecting with the HZMB Main Bridge) to the Scenic Hill (connecting with the tunnel under separate Contract No. HY/2011/03), of approximately 9.4km in length with a hard shoulder for each bound of carriageway and a utilities trough on the outer edge of each bound of viaducts;

·           a grade-separated turnaround facility located near San Shek Wan, composed of sliproads in the form of viaduct with single-lane carriageway bifurcated from the HKLR mainline with an elevated junction above the mainline;

·           provision of ancillary facilities including, but not limited to, meteorological enhancement measures including the provisioning of anemometers and modification of the wind profiler station at hillside of Sha Lo Wan, provisioning of a compensatory marine radar, and provisioning of security systems; and

·           associated civil, structural, geotechnical, marine, environmental protection, landscaping, drainage and highways electrical and mechanical (E&M) works, street lightings, traffic aids and sign gantries, marine navigational aids, ship impact protection system, water mains and fire hydrants, lightning protection system, structural health monitoring and maintenance management system (SHM&MMS), supervisory control and data acquisition (SCADA) system, as well as operation and maintenance provisions of viaducts, provisioning of facilities for installation of traffic control and surveillance system (TCSS), provisioning of facilities for installation of telecommunication cables/equipments and reprovisioning works of affected existing facilities/utilities.

Contract Organisation

2.6         Different parties with different levels of involvement in the Contract organization include:

Ÿ   Supervising Officer’s Representative (SOR) – Ove Arup & Partners Hong Kong Limited (ARUP)

Ÿ   Contractor –Dragages -China Harbour-VSL JV   (DCVJV)

Ÿ   Environmental Team (ET) – Cinotech Consultants Ltd. (Cinotech)

 

2.7         The proposed project organization and lines of communication with respect to the on-site environmental management structure are shown in Figure 2. The key personnel contact names and numbers are summarized in Table 2.1.

Table 2.1        Key Contacts of the Contract

Party

Position

Name

Phone No.

Fax No.

SOR (ARUP)

CRE

Mr. Michael Chan

3767 5803

3767 5922

Mr. Colin Meadows

3767 5801

ENPO/IEC

(Environ)

Environmental Project Office Leader

Mr. Y. H Hui

3465 2888

3465 2899

Independent Environmental Checker

Mr. Antony Wong

3465 2888

3465 2899

Contractor (DCVJV)

Deputy Project Director

Mr. W.K Poon

3121 6638

3121 6688

Environmental Officer

Mr. CHU Chung Sing

3121 6672

24-hour Hotline

--

6898 6161

--

ET

(Cinotech)

Environmental Team Leader

Dr. H.F Chan

2151 2088

3107 1388

 

2.8         ENVIRON Hong Kong Ltd. (Environ) is employed by the Highways Department as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) for the Project.

Construction Programme

 

2.9         A copy of Contractor’s construction programme is provided in Appendix A.

Summary of Construction Works Undertaken During Reporting Period

2.10     The major site activities undertaken in the reporting period  included:

December 2013:

Land Viaduct (P84 to Eastern Abutment at SHT) and Preparation Works

(a)    Land piling works are in progress with total 15 and21 nos. of pile concreted in Portion C and Portion A respectively. 6 piles were concreted in this reporting period. All land piling machines are carrying out piling works in Portion A due to  pending  of  existing  drainage,  watermain  and  Communication Cable (COM cable)  of  Airport Authority (AA) division  in Portion C;

(b)  18 pours of column were completed with 6 pours in this reporting period;

(c)  Rebar threading for coupler continues in Portion C;

(d) Hong Kong Airport Authority’s permit for formations of piling platform at P82 & P83 is still pending;

(e)  Tree transplanting was completed and maintenance works commenced.

(f)  Drainage diversion work remains in progress with laying of approximately 60m of  1200mm  diameter  pipe  and  50m  of  1350mm  diameter  pipe.  Excavation works and ELS are in progress;

(g)  Installation of portal beam at P109 is in progress;

(h) Earth Lateral Support (ELS) for pile cap construction at P111 and P112 were completed.  Pouring  of pile  cap  at  P111L  was  completed  and  P111R  are  in  progress.  Pile head breaking at P112 L & R are also in progress;

(i)  Formation work for Portal P110 was commenced.

Marine Viaduct (P0 to P84)

RCD Method:

(j)  Construction of temporary jetty works at P68 is in progress;

(k)  Installation of temporary casings at P55 & P59 is in progress;

(l)  Piling jackets were installed at P14, P22, P56, P57, P72 & P77;

(m)  Permanent casings were installed at P14L, P22L, P56R, P57R, P72R & P77R;

(n)  Pile excavation by RCD method in progress at P14, P22, P55, P56, P57 & P66 with 25 piles concreted in this reporting period;

(o)  Piling jackets were dismantled at P22R, P55L &P66;

(p)  Works with cofferdam:  Driving of sheet piling at P74 was commenced; Temporary platform at P71 was installed.

(q)  Inter-face coring tests were carried out at P46, P47 & P71;

(r)  Full depth coring tests were carried out at P71R-3;

(s)  Sonic tests were carried out at P71 & P73;

(t)  Grouting works were carried out at P47 & P71;

(u)  Barges moved back to Airport Channel on 23 Nov 13.

Kelly Method:

(v)  Installation of temporary piles, platforms and permanent casings at P17, P18, P36 were carried out;

(w)  Piling platform at P20 and P44 were removed;

(x)  Pile excavation by Kelly method in progress at P19, P42, P37, P38, P39 with 17 piles concreted in this reporting period;

(y)  P0 L & R precast shells were installed. Trimming of pile head is in progress;

(z)   Inter-face  Coring  Test  and  sonic  test  were  carried  out  to  completed  piles  at P20, P40, P48 and P7

Casting Yard / Floating Batching Plant

Progress of the precast concrete segment casting yard:

-  Construction of the two load-out jetties completed; test and commissioning under process.

-  All gantries (18 nos.) erected; 7 nos. tested and commissioned; 11 nos. under testing and commissioning.

-  Mould fabrications are on-going with 1 no. “Type “B”, 8 nos. “Type A” (including 2 no. Segments on pier (SOP)’s), 2 nos.  Type D moulds and 1 no.  “Type  CH2”  (long spans)  assembled;  other  “Type  CH”  and  “Type  CP”  mould  fabrication continues at casting yard.

-  Rebar jigs fabrication and installation continues with 18 of 30 nos. completed

-  Rebar and PT material delivery continues

-  A  total  of  64  segments  concreted  in  this reporting  period  and  up  to  end  of the reporting period total 150 segments casted. The floating concrete batching plant 1602 is in operation with 7 piles concreted;

Casting Yard for Precast Concrete Shell for Pilecap

3 nos. (cumulative 7 nos.) of CP1 precast shells were cast in precast yard and 2 nos. of CP1 precast shells were installed at Pier P0 in this reporting period.

 

January 2014:

 

Land Viaduct (P84 to Eastern Abutment at SHT) and Preparation Works

(a)  All  land  piling  machines  are  carrying  out  piling  works  in  Portion  A  due  to pending  the  completion  of  diversion  of  existing  drainage  &  watermain  and the commencement of COM cable of AA division in Portion C;

(b)  P114 area site formation for piling works was completed. Pile P114R was excavated to rock head and drilling of rock socket is in progress;

(c)  AA  COM  cable  slewing  was  completed  and  backfilled.  Piling equipment for Pile P113C was mobilized on site and pile excavation started;

(d) 27 pours of column were completed with 9 pours in this reporting period;

(e)  Rebar threading for coupler continues in Portion C;

(f)  AAHK’s  permit  for  the  construction  of  the  carriageway  diversion  and formations of piling platform at P82 & P83 is still pending for approval;

(g)  Tree transplanting was completed and its maintenance works are on-going.

(h) Drainage diversion works remains in progress.  Most pipes were laid except some pipes at manhole connection. MH2, MH3 & MH4 were completed. Backfilling was partially completed;

(i)  Waling  of  ELS for pile  cap  construction  at P111 L  & R  and  P112  L  &  R were removed upon completion of pile cap and backfilled up to the top level of the pile cap.

(j)  The  erection  of the  supporting false work  (brackets  and  main  carrier  beams) for  the   portal  beam  construction  at  P109  was  completed.  Erection of side formwork for the portal and kickers are in progress;

(k)  Formation work for Portal P110 was in progress.

Marine Viaduct (P0 to P84)

RCD Method:

(a)  Construction of temporary jetty for piling works atP68 is in progress;

(b)  Piling jackets were installed at P14R, P56L, P57L, P76R;

(c)  Permanent casings were installed at P14R, P55R, P56L, P59L, P59R & P77R;

(d)  Pile excavations are in progress at P14, P22, P55, P56, P57, P59, P72 & P77;

(e)  Piling jackets were dismantled at P14L, P55R, P57R & P73L;

(f)  Inter-face coring tests were carried out at P46, P50, P51, P65, P66 & P73;

(g)  No Full depth coring tests was carried out in this reporting period;

(h)  Sonic tests were carried out at P46, P50, P65 & P73;

(i)  Grouting works were carried out at P46 & P73;

Kelly Method:

(j)  Installation of temporary piles were carried out atP16 (friction test pile), P17, P18, P32, P33, P34, P35 & P36;

(k)  Installation of platforms were carried out at P16, P17, P18, P35 & P36;

(l)   Installation of permanent casing were carried out at P16, P18, P35 & P36;

(m) Piling  platform  removal  and  temporary  pile  extraction  were  carried  out  at P20, P38, P40 & P44;

(n)  Pile excavation by Kelly method are in progress at P16, P18, P19, P37 & P39;

(o)  Trial water cracking and trial shaft grouting at P18-L5 was completed;

(p)  Inter-face core test were carried out at P20, P37, P42, P45 & P49;

(q)  Sonic tests were carried out at P20, P44 & P49.

Pilecap Construction:

(r)  P0-L&R precast shells waterproofing works and stage one reinforced concrete works was completed. Stage two reinforced concrete works is in progress. Casting is scheduled to complete before end of January 2014;

(s) Installation of precast shells at P47 and P48 were completed. Waterproofing and stage 1 reinforced concrete works is in progress;

(t)  Preparation  work  for  the  installation  of  the  precast  shells  for  pilecap construction at P46 is in progress;

(u)  Advanced concrete breaking works inside the permanent steel casing at P20 and P44 has commenced;

(v)  Works with cofferdam: Driving of sheet piling at P74 was carried out; driving of sheet piling at P71 was commenced.

Precast Segment

(w) Progress of the precast concrete segment casting yard:

-  Test and commissioning of the two load-out jetties are in progress;

- All gantries in total of 18 nos. were erected. 7 nos. gantries were tested and commissioned and the remaining 11 nos. gantries areunder processing;

-  Mould fabrications for 1 no. Type B, 10 nos. Type A(including 2 no. SOP’s), 2 nos. Type D, 1 no. Type DT, 4 nos. Type E, and 1 no. Type CH2 (long spans) were assembled. Other Type CH and Type CP mould fabrication continues at the casting yard;

-  Rebar  jigs  fabrication  and  installation  continues  with  18  of  30  nos. completed;

-  Rebar and PT material delivery continues;

-  A total of 13 segments were cast in this reporting period and up to end of the reporting period total 169 segments cast.

Precast Concrete Shell Casting and Installation

3 nos. (cumulative 10 nos.) of CP1 precast shells and 1 no. (cumulative 1 no.) of CP4 precast shell were cast in precast yard.

 

February 2014:

Land Viaduct (P81 to Eastern Abutment at SHT) and Preparation Works

(a)  All land piling machines are carrying out piling works in Portion A and P114L due to pending the completion of diversion of existing drainage & watermain and  Communication Cable (COM cable) of Airport Authority (AA) in Portion C;

(b)  Piling work for P84 started;

(c)  Pile P114R rock excavation was completed with founding level inspected. Rebar cage installation and concreting will be carried out after completion of Pile P114L due to space constraint;

(d)  Pre-drilling at P106L started;

(e)  31 pours of column were completed with 4 pours in this reporting period;

(f)  Rebar threading for coupler continues in Portion C;

(g) Hong Kong Airport Authority’s permit for the construction of the carriageway diversion at P82 & P83 was received and site set up works started;

(h)  Hong Kong Airport Authority’s permit for formations of piling platform at P82 & P83 is still pending for approval;

(i)  Tree transplanting was completed and its maintenance works are on-going;

(j)  Drainage diversion works mostly completed;

(k)  Water pipes laying for water main diversion were mostly completed. Connection  to existing  water  main  pipe  and  testing  is  pending  for  AAHK’s permit;

(l)   Waling  of  ELS  for  pile  cap  construction  at  P111-L&R  were  removed  upon completion of pile cap and backfilled up to the top level of the pile cap;

(m)  Wailing of ELS and backfill at P112 started;

(n)  All side formwork and wing slab soffit for Portal P109 were completed. Steel fixing is in progress;

(o)  At portal P110, side formwork and wing slab soffit formwork were completed. Steel fixing for bottom mat and side bars are in progress.


Marine Viaduct (P0 to P84)

RCD Method:

(a)  Construction of temporary jetty for piling works atP68 remains in progress;

(b)  Piling jackets were installed at P61, P28L, P64 & P72L;

(c)  Piling jackets were dismantled at P22, P56 & P72R;

(d)  Permanent  casings  were  installed  or  spliced  at  P14R,  P57L,  P59,  P61,  P70, P76R & P72R;

(e)  Pile excavations are in progress at P14, P22, P57, P59, P61, P70, P72, P76 & P77 with 25 piles concreted in the reporting period;

(f)  Inter-face coring tests were carried out at P50, P66 & P73;

(g)  Full depth coring tests was carried out at P50;

(h)  Sonic tests were carried out at P51, P65 & P66;

(i)  Grouting works were carried out at P50 & P65;

Kelly Method:

(j)  Installation of temporary piles were carried out atP30, P31 & P32;

(k)  Installation of platforms were carried out at P17, P31, P33 & P34;

(l)  Installation of permanent casing were carried out at P33 & P34;

(m) Piling  platform  removal  and  temporary  pile  extraction  were  carried  out  at

P19, P37, P39, P40 & P42;

(n)  Pile excavation by Kelly method are in progress at P16, P18, P19, P37 & P39;

(o)  Pile excavation by Kelly method are in progress at  P18, P19, P35 & P36 with 13 piles concreted in the reporting period;

(p)  Friction test pile at P16: load test were carried out from 24 – 28 Feb 14;

(q)  Inter-face core test were carried out at P20, P37,  P39, P40, P42, P45, P49 & P78;

(r)   Full depth coring tests for P37-L3 and P42-R1 are in progress;

(s)   Sonic tests were carried out at P20, P44 & P49.

Pilecap Construction:

(t)  P0 - stage 2 concreting for pile cap was completed;

(u) P46 - Installation of precast shells and waterproofing works were completed. Pile trimming works are in progress;

(v) P47 – Installation of precast shells and 1st stage concreting were completed. Reinforcement fixing for 2nd stage concreting is in progress;

(w)  P48 – Installation of precast shells were completed;

(x)  Preparation  works  for  the  installation  of  the  precast  shells  for  pilecap construction at P44 are in progress;

(y)   Advanced  concrete  breaking  works  (pile  head  trimming)  at  P20,  P43  &  P49 are in progress whereas the works in P65 has been commenced;

(z)   Works with cofferdam: Driving of sheet piling at P71 in progress; erection of temporary working platform for sheet piling at P73R in progress.

 

Column Construction

(a)     P0-L&R steel fixing to the columns are in progress. Concreting is scheduled on March 2014 and 5 March 2014 for P0-R and P0-L respectively.

 

Deck Erection

(b)   Preparatory works for erection equipment are underway:

-          Lifting Frame LF2-1 fabrication commenced in Dongguan;

-          Modification for P109 Loading Installation commenced at Portion C.

 

Precast Segment

(a) Progress of the precast concrete segment casting yard:

-  Test and commissioning of the two load-out jetties are in progress;

- All gantries, in total of 18 nos., were erected. 7nos. gantries were tested and commissioned and the remaining 11 nos. gantries are under processing;  

-  Mould assembly for 1 no. Type B, 10nos. Type A (including 2 no. SOP’s), 2nos. Type D, 4nos. Type E (with 3 checked by survey), 1 no. Type CH2 (long spans) were assembled. Other Type CH and Type CP mould fabrication continues at the casting yard;

-  Rebar jigs fabrication and installation continues with 24 of 30 nos. (18 in Line No. 2 and 6 in Line No. 6) completed;  

-  Rebar and prestress tendon (PT) material delivery continues;

-  A  total  of  22  segments  were  cast  in  this  reporting  period  and  up  to  end  of  the reporting period total 191 segments cast.

Precast Concrete Shell Casting

(b) 2 nos. (cumulative 12  nos.)  of  CP1  precast  shells  and  no  (cumulative  1  no.) CP4 precast shell were cast in the reporting period.

Status of Environmental Licences, Notification and Permits

 

2.11     The valid environmental licenses and permits were attached in the Monthly EM&A Reports.