EXECUTIVE SUMMARY

Introduction

1.              This is the 5th Quarterly Environmental Monitoring and Audit (EM&A) Report prepared by Cinotech Consultants Limited for the project “Contract No. HY/2011/09 – Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road – Section between HKSAR Boundary and Scenic Hill” (hereinafter called the “Contract”). This report documents the findings of EM&A Works performed in the period between March and May 2014.

Environmental Monitoring and Audit Progress

2.              A summary of the monitoring activities in this reporting period is listed in Table I below:

Table I            Summary Table for Monitoring Activities in the Reporting Period

 

Parameter(s)

Monitoring Date(s)

1-hr TSP Monitoring

5th, 11th, 17th, 21st and 27th March 2014

2nd, 8th, 14th, 17th, 23rd and 29th April 2014

5th, 9th, 15th, 21st, 27th and 30th May 2014

24-hr TSP Monitoring

Noise Monitoring

6th, 12th , 18st  and 24th March 2014

3rd, 9th , 15th , 22nd and 30th April 2014

7th , 16th , 22nd and 28th May 2014

Water Quality Monitoring

1st, 3th, 5th, 7th, 10th, 12th, 14th, 17th, 19th, 21st, 24th , 27th, 29th and 31st March 2014

2nd, 4th, 7th, 10th, 12th, 14th, 16th, 18th, 22nd, 24th , 26th, 28th and 30th April 2014

2nd, 5th, 7th, 10th, 12th, 14th, 16th, 19th, 21st, 23rd , 26th, 28th and 30th May 2014

Dolphin Monitoring (Line-transect Vessel Surveys)

12th  and 26th March 2014

15th  and 23rd April 2014

7th  and 20th May 2014

Additional Land-based Dolphin Behaviour and Movement Monitoring

14th and 19th March 2014

16th and 25th April 2014

19th and 27th May 2014

Environmental Site Inspection

5th, 11th , 18th and 28th March 2014

1st, 8th , 15th, 25th and 29th April 2014

7th , 13th, 20th and 30th May 2014

Archaeological Site Inspection

21st March 2014

Breaches of Action and Limit Levels

3.              Summary of the environmental exceedances of the reporting period is tabulated in Table II.

Table II          Summary Table for Events Recorded in the Reporting Period

 

Environmental Monitoring

Parameter

No. of Exceedance

No. of Exceedance related to the Construction Activities of this Contract

Action Level

Limit Level

Action Level

Limit Level

Air Quality

1-hr TSP

0

0

0

0

24-hr TSP

0

0

0

0

Noise

Leq(30min)

0

0

0

0

Water Quality

Dissolved Oxygen (DO) (Surface & Middle)

0

0

0

0

Dissolved Oxygen (DO) (Bottom)

0

0

0

0

Turbidity

6

1

0

0

Suspended Solids (SS)

24

6

0

0

Dolphin Monitoring

Line-transect Vessel Surveys

0

0

0

0

 

4.              Environmental monitoring works were performed in the reporting period and all monitoring results were checked and reviewed.  The details of each exceedance were attached in the Monthly EM&A Reports.

Complaint Log

 

5.              Summary of the environmental complaints of the reporting period is tabulated in Table III.

Table III         Summary Table for Complaints Recorded in the Reporting Period

Complaint Log Ref.

Location

Received Date

Nature of Complaint

Com-2014-03-001

Near Sha Lo Wan

5 March 2014

Chemical / Waste Management

Com-2014-03-002

In the vicinity of the waters outside Sha Lo Wan

11 March 2014

Noise

Com-2014-04-001

Construction marine works by the company Bauer Hong Kong in Tung Chung

14 April 2014

Ecology

Com-2014-05-001

At the shore of Sha Lo Wan

13 May 2014

Ecology

Com-2014-05-002

At the shore of Sha Lo Wan

27 May 2014

Ecology

Com-2014-05-003

Pier 39 to 50

29 May 2014

Water Quality and Waste Management

Notification of Summons and Successful Prosecutions

 

6.              No notification of summons and successful prosecution was received in the reporting period.

Reporting Changes

 

7.              This report has been developed in compliance with the reporting requirements for the quarterly EM&A Summary Report as required by the EM&A Manual for Hong Kong Link Road (EM&A Manual).

Future Key Issues

8.              Major site activities for the coming reporting month will include:

WA4

Ÿ   Fabrication of rebar cages

Ÿ   Fabrication of temporary piling platforms

WA7

Ÿ   Fabrication of rebar cages

Ÿ   Loading and Unloading of rebar materials

 

Marine Viaduct (P0 to P80)

Ÿ   Construction of the temporary jetty

Ÿ   Installation of temporary casings, piling jackets, temporary piles, platform and permanent casings

Ÿ   Dismantling of piling jacket

Ÿ   Piling platform removal works

Ÿ   Pile excavation by Reverse Circulation Drill (RCD) method method

Ÿ   Pile excavation by Kelly method

Ÿ   Inter-face coring test, full depth coring test, sonic test, friction test

Ÿ   and load test   

Ÿ   Predrilling works

Ÿ   Operation of floating concrete batching plants

Ÿ   Trimming of pile head

Ÿ   Grouting works

Ÿ   Concreting for pile cap

Ÿ   Driving of sheet piling

Ÿ   Trial water cracking and trial shaft grouting

Ÿ   Installation of recast shells and waterproofing works

Ÿ   Advanced concrete breaking works inside the permanent steel casing

Ÿ   Steel fixing to the column and formwork installation

Ÿ   Kingpost installation for precast cap and associated steel welding works

 

Land Viaduct (P81 to P114)

Ÿ   Land piling and concreting works

Ÿ   Rebar threading for coupler

Ÿ   Backfilling

Ÿ   Tree transplant and maintenance works

Ÿ   Installation of portal beam

Ÿ   Excavation works and Earth Lateral Support (ELS)

Ÿ   Pouring of pile cap and pile head breaking

Ÿ   Formation works

Ÿ   Pours of column

Ÿ   Erection of side formwork for the portal and kickers

Ÿ   Road diversion works

Ÿ   Pre-drilling works, pile cap, column and portal construction

Ÿ   Side formwork and wing slab soffit formwork

Ÿ   Waling of ELS and backfill

Ÿ   Steel fixing for bottom mat and side bars

Ÿ   Carriageway diversion

Ÿ   Tendon ducts

Ÿ   Falsework erection

Ÿ   Temporary carriageway for diversion at P82 & P83