Table I            Summary Table for Monitoring Activities in the Reporting Period

 

Parameter(s)

Monitoring Date(s)

1-hr TSP Monitoring

3rd, 8th, 12th, 18th, 24th and 30th September 2014

6th, 10th, 16th, 22nd and 28th October 2014

3rd, 7th, 13th, 19th and 25th November 2014

24-hr TSP Monitoring

Noise Monitoring

4th , 10th , 19th  and 25th September 2014

3rd , 7th , 13th, 23rd and 29th October 2014

4th , 10th , 20th and 26th November 2014

Water Quality Monitoring

1st, 3rd, 5th, 8th, 10th, 12th, 15th, 18th, 20th , 22nd, 24th, 26th and 29th September 2014

1st, 3rd, 6th, 8th, 10th, 13th, 15th, 17th, 20th , 22nd, 24th, 27th, 29th and 31st October 2014

3rd, 5th, 7th, 10th, 12th, 15th, 17th, 19th , 21st, 24th, 26th and 28th November 2014

Dolphin Monitoring (Line-transect Vessel Surveys)

10th  and 23th September 2014

8th  and 22nd October 2014

5th  and 17th November 2014

Additional Land-based Dolphin Behaviour and Movement Monitoring

1st  and 5th September 2014

20th  and 27th October 2014

10th  and 24th November 2014

Environmental Site Inspection

2nd, 10th, 17th, 26th and 30th September 2014

7th, 14th, 21st and 31st October 2014

4th, 11th, 18th and 28th November 2014

Archaeological Site Inspection

30th September 2014