2.1
The proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road
(HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao Bridge (HZMB) at the
HKSAR Boundary with the Hong Kong Boundary Crossing Facilities (HKBCF) situated
at the north eastern waters of the Hong Kong International Airport, opening a
new and direct connection route between Hong Kong, Macao and the Western Pearl
River Delta.
2.2
The HKLR comprises a 9.4km long viaduct section from the HKSAR boundary
to Scenic Hill on the Airport Island; a 1km tunnel section to the reclamation
formed along the east coast of the Airport Island and a 1.6km long at-grade
road section on the reclamation connecting to the HKBCF. The tunnel section of
HKLR will pass under Scenic Hill, Airport Road and Airport Railway to minimize
the environmental and visual impacts to Tung Chung residents.
2.3
An application (No ESB-110/2003) for an Environmental Impact Assessment
(EIA) Study Brief under Section 5(1) of the Environmental Impact Assessment
Ordinance (EIAO) was submitted by Highways Department (the Project Proponent)
on 8 October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong
Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway
Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North
Lantau Highway Connection has subsequently been renamed as HKLR. EPD issued an EIA Study Brief (No:
ESB-110/2003) in November 2003 to the Project Proponent to carry out an EIA
study.
2.4
An EIA Study (Reg. No. AEIAR-144/2009) has been undertaken to provide
information on nature and extent of environmental impacts arising from the
construction and operation of HKLR. The Environmental Permit was issued on 4
November 2009 (Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the
Director of Environmental Protection amends the Environmental Permit (No.
EP-352/2009) based on the Application No. VEP-339/2011 and the environmental
Permit (Permit No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the
Highways Department as the Permit Holder. Subsequently, the Director of
Environmental Protection amends the Environmental Permits (No. EP-352/2009/A
and EP-352/2009/B) based on the Application No. VEP-409/2013 and VEP-411/2013
respectively. The environmental Permit (Permit No. EP-352/2009/C) was then issued
on 5 September 2013.
2.5
Figure 1a-d shows the layout of the Contract
and the scope of the Contract works comprises the following major items:
·
a dual 3-lane carriageway in the form of
viaduct from the HKSAR boundary (connecting with the HZMB Main Bridge) to the
Scenic Hill (connecting with the tunnel under separate Contract No.
HY/2011/03), of approximately 9.4km in length with a hard shoulder for each
bound of carriageway and a utilities trough on the outer edge of each bound of
viaducts;
·
a grade-separated turnaround facility located near San Shek Wan, composed of sliproads
in the form of viaduct with single-lane carriageway bifurcated from the HKLR
mainline with an elevated junction above the mainline;
·
provision of ancillary facilities including, but not limited to,
meteorological enhancement measures including the provisioning of anemometers
and modification of the wind profiler station at hillside of Sha Lo Wan, provisioning of a compensatory marine radar,
and provisioning of security systems; and
·
associated civil, structural, geotechnical, marine, environmental
protection, landscaping, drainage and highways electrical and mechanical
(E&M) works, street lightings, traffic aids and sign gantries, marine
navigational aids, ship impact protection system, water mains and fire
hydrants, lightning protection system, structural health monitoring and
maintenance management system (SHM&MMS), supervisory control and data
acquisition (SCADA) system, as well as operation and maintenance provisions of
viaducts, provisioning of facilities for installation of traffic control and
surveillance system (TCSS), provisioning of facilities for installation of
telecommunication cables/equipments and reprovisioning works of affected existing
facilities/utilities.
2.6
Different parties with different levels of involvement in the Contract
organization include:
Supervising Officer’s Representative (SOR)
– Ove Arup & Partners Hong Kong Limited (ARUP)
Contractor –Dragages
-China Harbour-VSL JV (DCVJV)
Environmental Team (ET) – Cinotech Consultants Ltd. (Cinotech)
2.7
The proposed project organization and lines of communication with respect
to the on-site environmental management structure are shown in Figure 2. The key personnel contact
names and numbers are summarized in Table
2.1.
Table 2.1 Key
Contacts of the Contract
Party |
Position |
Name |
Phone
No. |
Fax
No. |
SOR (ARUP) |
CRE |
Mr. Michael Chan |
3767 5803 |
3767 5922 |
Mr. Colin Meadows |
3767 5801 |
|||
ENPO/IEC (Environ) |
Environmental Project Office Leader |
Mr. Y. H Hui |
3465 2888 |
3465 2899 |
Independent Environmental Checker |
Mr. Antony Wong |
3465 2888 |
3465 2899 |
|
Contractor
(DCVJV) |
Deputy Project Director |
Mr. W.K Poon |
3121 6638 |
3121 6688 |
Environmental Officer |
Mr. CHU Chung Sing |
3121 6672 |
||
24-hour Hotline |
-- |
6898 6161 |
-- |
|
ET (Cinotech) |
Environmental Team Leader |
Dr. H.F Chan |
2151 2088 |
3107 1388 |
2.8
ENVIRON Hong Kong Ltd. (Environ) is employed by the Highways Department
as the Independent Environmental Checker (IEC) and Environmental Project Office
(ENPO) for the Project.
2.9
A copy of Contractor’s
construction programme is provided in Appendix A.
Summary of Construction Works Undertaken During Reporting Period
2.10
The major site
activities undertaken in the reporting period included:
September
2014:
Land
Viaduct (P85 to Abutment at SHT) & Marine Viaduct (P81 - P84)
(a) Pile construction is in progress at P81 to P83 and 4 piles were concreted
in this reporting period.
(b) Total 110 pours for column were completed with 13 pours in this
reporting period; 33 columns was completed to top level (18
gridlines - P95 to P97
and P99 to P114).
(c) P81 pile works commenced.
(d) Pre-bored for
sheet pile for cofferdam construction at P84 about 45% completed.
(e) Seawall block coring and breaking
at P82L was completed & P83L is in progress.
(f) Portal P103 was concreted on 26
August 2014, dismantling of steel girders and brackets are in progress.
(g) Portal P111 & P113 falsework dismantling was completed.
(h) Portal P104 was concreted on 23
September 2014.
(i) Portal P114 formwork erection is
in progress.
(j) Portal P108 side formwork
erection is in progress.
(k) Portal P107 and P106 cross road
steel portal beams erection were completed and corresponding falsework erection is in progress.
(l) Portal P102 steel bracket system
erection was completed and corresponding falsework
erection is in progress.
(m) Portal P101 steel girders and
cross beams erection is in progress.
Marine Viaduct (P0 to P80)
RCD Method:
(a) Construction of the temporary platform for
piling works at P68 was suspended since 10 June 2014 and the Contractor
modified the platform followed the SO instruction.
(b) Piling works at P69 was suspended on 12 July
(9 out of 12 piles already completed).
(c) Works started at P75: Mooring bits and silt curtain
installation are in progress.
(d) Piling jackets were installed at P20, P23
and P80.
(e) Piling jackets were dismantled at P17, P62,
P63 and P80.
(f) Pile excavations and casing installation
were in progress at P15, P17, P20, P24, P25, P31, P32, P67 and P80 with 26 nos.
piles concreted in the reporting period.
(g) Inter-face coring tests were carried out at
P28, P29, P32, P58, P63 and P67.
(h) Full depth coring test was carried at P27 and
P63.
(i) Sonic tests were carried out at
P27, P28, P29, P32, P58, P63 and P67.
(j) Grouting works were carried out
at P29, P59, P62, P63 and P67.
Kelly
Method:
(k) Installation of
temporary piles were carried out at P1.
(l) Installation
of platforms were carried out at P1.
(m) Installation of permanent casing were carried out at P1 and P3.
(n) Piling
platform removal and temporary pile extraction were carried out at P11, P17b,
P17c and P33.
(o) Pile excavation by Kelly method are in
progress at P2, P3, P12 and P21 with 11 piles concreted in
the reporting period.
(p) Inter-face
core tests were carried out at P30.
(q) Full
depth coring was carried out at P16-R2 and P30-R1.
(r) Sonic
tests were carried out at P30.
(s) Toe grouting works were carried out at P4 and P16.
(t) Disposal: 3 trips of inert materials to HKBCF, 3 trips of Type I
materials, 2 trips of Type II materials were disposed.
Pilecap Construction:
(a) 10 precast cap shells were installed at P33,
P34, P35, P61 and P64.
(b) Stage 1 concreting was completed
at P20R, P36, P50, P60, P66 and P65.
(c) Stage 1 works is in progress at P19, P50,
P60, P65 and P66.
(d) Stage 2 concreting was completed at P20,
P36, P37, P38 and P50.
(e) Stage 2 works is in progress at P20, P36,
P37, P38, P50 and P66.
(f) Kingpost
installation and associated steel welding works for precast shell installation
are in progress at P18, P33, P34, P35, P61 and P64.
(g) Concrete trimming and advanced trimming
(inside casing) works were carried out at P18, P33, P53, P62, P63 and P67.
- P70L:
Installation 1st and 2nd layer of waling & strut
completed.
- P70R: Installation of 1st layer of
waling & strut completed. Installation of 2nd layer of waling
& strut is in progress.
- P71L: Cofferdam work was completed. Formwork
& top layers of reinforcement for pile cap is on-going.
- P71R: Due
to high rockhead, concrete waling beam is required.
Concrete pouring for 2nd layer of concrete waling beam was
completed. Preparation works for the last layer pouring is in progress.
- P72L: Installation of waling strut at 2nd
layer is substantially completed.
-
P72R: 2 layers of waling & strut were completed. Excavation will be
commenced.
- P73L:
Concrete plug was poured. Installation of 3rd layer of waling &
strut is in progress.
- P73R: Excavation
is substantially completed, sheet pile cleaning by divers is in progress.
- P74L:
Installation of 1st layer of waling & strut was completed.
- P74R: Re-driving
sheet pile is in progress.
- P76:
Installation of temporary working platform is in progress.
- P77:
Installation of temporary working platform was completed.
- P78L:
Installation of sheet pile was completed. Preparation works for installation of
waling & strut is in progress.
- P78R:
Installation of sheet pile was completed. Preparation work for installation of
waling & strut is in progress.
In-situ Column Construction
(a) 1st lift works in progress at P38, P39, P41, P42L, P48L, P49,
P51 and P52.
(b) 1st lift concrete was poured at P39, P41, P42L, P48L, P49,
P51 and P52.
(c) 2nd lift works in progress at P39, P41, P42L, P48, P51 and
P52.
(d) 2nd lift concreting was poured: P45 and P49.
(e) Pier head works in progress at: P45 and P49.
(f) Pier head concreting: Nil in this reporting period.
Precast Column Erection
(g) Preparatory works have been completed for precast column erection at P43
and P44. The first batch of precast column delivery is in progress.
Deck Erection
(a) Works for segment erection:
- Off-site
fabrication of the first 3 sets of Lifting Frames is substantially completed in Dongguan with delivery of
all 6 sets of Lifting Frames 2 (LF2).
- Segment Unloading Frame (SUF) load
test was completed.
- Assembly
of Launching Gantry 2 (LG2) continues at River
Trade Terminal (RTT). Winches have been
tested.
- Launching
Gantry 1 (LG1) assembly continues at
Portion C with all components on site and erection commenced.
- Assembly and erection of LF2
continues with 2 frames having been erected at P109. One of the frames has been
load tested. Other 2 frames are assembled at adjacent to P109 and 2 frames are
assembled at WA4.
- The first 2 segments on P109L have
been erected by LF2.
- 12 winches have been delivered to
Hong Kong.
- Segments on Pier (SOP) erection at P47 has commenced.
Precast
Segment
(a) Progress for mould assembly:
Type of Segment |
Number of Segment |
Status |
A |
10 |
Completed
(including 2 nos. SPO) |
B |
1 |
Completed |
D |
2 |
Completed |
E |
4 |
Completed |
CH1 |
2 |
Completed |
CH2 |
2 |
Completed |
CH3 |
2 |
Completed |
CH4 |
2 |
Completed |
CH5 |
2 |
Completed |
CP
(long span SOP) |
3 |
2 CPA
complete, CPB in progress |
DT |
1 |
Completed |
E/EV |
2 |
Under
fabrication |
(b) 90 segments were
cast in this reporting period.
(c) Cumulative total 1057
segments cast.
(d) The first 12
segments were loaded onto barges and delivered to Hong Kong.
(e) Piling works have
commenced for the precast yard extension for both additional moulds and segment
storage.
(f) Transportation of segments to a nearby
secondary storage yard has commenced in Zhongshan.
Precast Concrete Shell Casting
(a) Summary
of precast shell cast in the precast yard:
Type of Shell |
Number of Precast Shell Cast in this reporting
period |
Cumulative No. of Precast Shell Completed (up to
28th of each month) |
CP1 |
4 |
45 |
CP2 |
3 |
12 |
CP4 |
1 |
6 |
Ground Investigations
- 1 drill rig was mobilized to Pier
1 piling platform for additional holes.
- Predrilling works were carried out at P1 in this reporting period.
- 1 nos. of additional pre-drills was completed in this reporting period. Total 725 piles have completed predrills (including GI used as predrill).
- Total 115 gridline (100%) out of 115 were completed for pre-drilling.
Additional predrills are required for the friction piles at P1 and P7 for SPT
tests and these shall be carried out on the piling platforms.
-
Total 113 gridlines for first
issue of Founding Level Proposals were submitted. 1 no. was submitted in this
reporting period.
October 2014:
Land
Viaduct (P85 to Abutment at SHT) & Marine Viaduct (P81 - P84)
(a) Pile construction is in progress at P81 to P82 and 4
piles were concreted in this reporting period.
(b) Total 122 pours for column were completed with 12 pours in this
reporting period; 44 columns was completed to top level (21 gridlines - P93 and P95 to P114).
(c) Pre-bored for
sheet pile for cofferdam construction at P84 was completed. Excavation and
waling installation is in progress.
(d) Pre-bored for sheet pile for
cofferdam construction at P83R commenced.
(e) Sewage diversion at P83 commenced.
(f) Portal P103 was concreted on 26
August 2014. Dismantling of steel girders and brackets was completed.
(g) Portal P111 & P113 falsework dismantling was completed. Dismantling of falsework is in progress.
(h) Portal P114 was concreted on 28
October 2014.
(i) Portal P108 was concreted on 25
October 2014.
(j) Portal P107 and P106 erection of
formwork is in progress.
(k) Portal P102 erection of side
formwork is in progress.
(l) Portal P101 erection of side
formwork is in progress.
(m) Portal P97 erection of cross
beams is in progress.
(n) Portal P100 erection of falsework and girders is in progress.
(o) Portal P99 foundation work for falsework supports is in progress.
Marine Viaduct (P0 to P80)
RCD Method:
(a) Construction of the temporary platform for
piling works at P68 was suspended since 10 June 2014. The Contractor removed the
rockfill platform followed the SO instruction.
(b) Piling works at P69 was suspended on 12 July
2014 (9 out of 12 piles already completed).
(c) Remobilization
for P75’s works started on 25 September 2014. Excavation by grabbing and
chiseling is in progress.
(d) Piling jackets were installed at P5, P9,
P10, P18 and P23.
(e) Piling jackets were dismantled at P13, P15,
P20, P25, P32, P63, P67 and P80.
(f) Pile excavations and casing installation
were in progress at P5, P9, P15, P18, P20, P23, P31 and P80 with 20 nos. piles
concreted in the reporting period.
(g) Inter-face coring tests were carried out at
P31, P32, P55, P56, P79 and P80.
(h) No Full depth coring test was carried during
the reporting period.
(i) Sonic tests were carried out at
P28, P31, P32, P55, P56 and P80.
(j) Grouting works were carried out
at P14, P27, P28, P29, P32, P54, P58 and P67.
Kelly
Method:
(k) Installation of
temporary piles were carried out at P2 and P7.
(l) Installation
of platforms were carried out at P7.
(m) Installation of permanent casing were carried out at P7.
(n) Piling
platform removal and temporary pile extraction were carried out at P2 and P30.
(o) Pile excavation by Kelly method are in
progress at P1, P2, P3, P7 & P12 and 8 piles concreted in the reporting
period.
(p) All
end bearing piles by Kelly Method has been completed.
(q) Inter-face
core tests were carried out at P21.
(r) Full
depth coring was carried out at P30-R1.
(s) No sonic tests were carried out in this reporting period.
(t) Toe grouting works were carried out at P4 and P16.
Disposal
(a)
2 trips of inert
materials & 1 trip of inert materials to TM38 & HKLR03 Project
respectively, 3 trips of Type I materials & 1 trip of Type II materials
were disposed to HK open sea mud pits. 3 trips of marine mud to Cross Border
were disposed.
Pilecap Construction:
(a) 6 precast cap shells were installed at P18,
P62 & P63.
(b) Stage 1 concreting was completed
at P19, P33, P34, P35, P61 & P64.
(c) Stage 1 works is in progress at P19, P33,
P34, P35, P61, P62 & P64.
(d) Stage 2 concreting was completed at P19,
P60, P65 & P66.
(e) Stage 2 works is in progress at P19, P34,
P35, P60, P61, P64, P65 & P66.
(f) Kingpost
installation and associated steel welding works for precast shell installation
are in progress at P18, P29, P62, P63 & P67.
(g) Concrete trimming and advanced trimming
(inside casing) works were carried out at P17, P27, P28, P29, P59, P63 & P67.
- P70L:
Excavation is in progress.
- P70R: Excavation is in progress.
- P71L: Concreting works of pile cap was
completed on 6-Oct-14.
- P71R: Additional
concrete plug and 3rd layer of waling & strut were completed.
Dewatering, cleaning and drainage works before casting of blinding layer is in
progress.
- P72L: Installation of waling strut at 2nd
layer is substantially completed. Additional grouting works was carried out.
- P72R: Excavation is substantially completed.
Sheet pile cleaning by divers is in progress.
- P73L: Installation of 3rd layer of waling
& strut was completed. Dewatering, cleaning and drainage works before casting
of blinding layer is in progress.
- P73R: Concrete Plug was casted on 10-Oct-14.
Installation of 3rd layer of waling & strut was completed. Dewatering is in
progress.
- P74L: Installation of 2nd layer of waling
& strut in progress.
- P74R: Installation of shear pin was
completed.
- P76L: Installation of temporary working
platform was completed.
- P76R: Installation of sheet pile is in
progress.
- P77L: Installation of sheet pile is in
progress.
- P77R: Installation of sheet pile is in progress.
- P78L: Installation of 1st & 2nd waling
& strut were completed.
- P78R: Installation of 1st & 2nd waling
& strut were completed.
In-situ Column Construction
(a) 1st lift works is in progress at P36, P37, P38 and P66.
(b) 1st lift concrete was poured at P37 & P38.
(c) 2nd lift works is in progress at P48-R, P51 and P52.
(d) 2nd lift concreting was poured: P48-R, P51 and P52.
(e) Pier head works is in progress at: P45, P48-R and P52.
(f) Pier head concreting : Nil in this reporting
period.
Precast Column Erection
(g) The initial Precast Column sections have been installed and concreted on
P43 and P44. The 2nd batch of precast column delivery is in progress.
In-situ Double Blade Column Construction
(h) 1st lift works is in progress at P20 and P71.
Deck Erection
(a) Setting up of Equipment:
- Off-site
fabrication of the first 3 sets of Lifting Frames is substantially completed in Dongguan with delivery of
all 6 sets of Lifting Frames 2 (LF2), Steelwork for the 4th set of
Lifting Frames is under fabrication with some deliveries having commenced.
- Segment Unloading Frame (SUF) is
fully operational;
- Assembly of Launching
Gantry 2 (LG2)
continues at River Trade Terminal (RTT). Winches have been tested.
- Launching
Gantry 1 (LG1) assembly
continues at Portion C with all components on site, Lower Cross Beam (LCB)’s erected and the first 50m section of truss erected.
- An accident occurred with the
collapse of the 4th set of LF2 at Pier P109R on the morning of 19th
October 2014. All works on LF2 at P109 have been suspended pending for Labour
Department Investigation.
- A total
of 10 segments have been erected on P109, 4 segments on P110 and 4 SOP segments
on P47. Segments on
Pier (SOP) segments for P46 are on site awaiting erection after completion of
temporary works.
Precast
Segment
(a) Progress for mould assembly:
Type of Segment |
Number of Segment |
Status |
A |
10 |
Completed (including 2 nos. SPO) |
B |
1 |
Completed |
D |
2 |
Completed |
E |
4 |
Completed |
CH1 |
2 |
Completed |
CH2 |
2 |
Completed |
CH3 |
2 |
Completed |
CH4 |
2 |
Completed |
CH5 |
2 |
Completed |
CP (long span SOP) |
3 |
2 CPA complete, CPB in progress |
DT |
1 |
Completed |
E/EV |
2 |
Under fabrication |
(b) 119 segments were
cast in this reporting period.
(c) Cumulative total 1176
segments cast.
(d) 48 segments have
been delivered to site.
(e) Piling works have commenced
for the precast yard extension for both additional moulds and segment storage.
(f) Transportation of segments to off-yard storage at nearby area in Zhongshan has commenced.
Precast Concrete Shell Casting
(a) Summary
of precast shell cast in the precast yard:
Type of Shell |
Number of Precast Shell Cast in this reporting
period |
Cumulative No. of Precast Shell Completed (up to
28th of each month) |
CP1 |
5 |
50 |
CP2 |
Completed |
12 |
CP4 |
2 |
8 |
CP5 |
0 |
2 |
CP1 |
5 |
50 |
Ground Investigations
- 4 drill rigs were mobilized for
additional predrilling works at P2 (compensation pile), P7 (additional SPT’s)
and D18 (pile moved).
- 5 nos. of additional pre-drills were completed in this reporting period. All 725 piles have completed predrills (including GI used as predrill).
- Total 115 gridline (100%) out of 115 were completed for pre-drilling.
Additional predrills are required for the friction piles at P1 and P7 for SPT
tests and these shall be carried out on the piling platforms.
- Total 115
gridlines for first issue of Founding Level Proposals were submitted. 2 no. was submitted in this
reporting period.
November
2014:
Land
Viaduct (P85 to Abutment at SHT) & Marine Viaduct (P81 - P84)
(a) Pile construction is in progress at P82 to P83 and 4 piles were
concreted in this reporting period.
(b) Total 139 pours for column were completed with 17 pours in this
reporting period; 51 columns were completed to top level (25 gridlines - P90 to P114).
(c) P84L water plugging and rebar
fixing are in progress, P84R excavation is in progress.
(d) Pre-bored for
sheet pile for cofferdam construction at P83R was completed.
(e) Pre-bored for sheet pile for
cofferdam construction at P81R commenced.
(f) Sewage diversion at P83 is in
progress.
(g) P83L piling work commenced.
(h) Portal P107 and P106 were
concreted on 17 and 21 November 2014 respectively. Dismantling of side formwork
is in progress.
(i) Portal P104 dismantling of steel
bracket system was completed.
(j) Portal P108 dismantling of falsework and steel bracket system is in progress.
(k) Portal P114 dismantling of
formwork was completed, temporary supporting jacks and nailing to be installed
before falsework removal.
(l) Portal P102 steel fixing is in
progress and will be concreted on 29 November 2014.
(m) Portal P101 steel fixing is in
progress.
(n) Portal P97 formwork erection was
completed and steel fixing will be commenced.
(o) Portal P98 erection of steel
bracket system is in progress.
(p) Portal P100 erection of formwork
is in progress.
(q) Portal P99 erection of falsework and steel beam supports are in progress.
(r) Portal P96 portal foundation work
is in progress.
Marine Viaduct (P0 to P80)
RCD Method:
(a) Construction of the temporary platform for
piling works at P68 was suspended since 10 June 2014.
(b) Piling works
at P69 was suspended on 12 July 2014 (9 out of 12 piles already completed).
(c) Remobilization
for P75’s works started on 25 September 2014. Excavation by backhoe on flat top
barge is on going.
(d) Piling jackets were installed at P8.
(e) Piling jackets were dismantled at P23 and
D20.
(f) Pile excavations and casing installation are
in progress at P5, P9, P10 and P23 with 13 nos. piles concreted in the
reporting period.
(g) Inter-face coring tests were carried out at
P23, P24, P25, P26 and P79.
(h) Full depth coring test was carried at P79.
(i) Sonic tests were carried out at
P22, P24, P25, P26 and P79.
(j) Grouting works were carried out
at P53 and P79.
Kelly
Method:
(k) Re-installation of
platform was carried out at P2.
(l) Installation
of permanent casing was carried out at P2R1a.
(m) Piling platform removal and temporary pile extraction were carried
out at P16, P31 & P32.
(n) Pile
excavation by Kelly method is in progress at P1, & P7 and 9 piles concreted
in the reporting period.
(o) All end-bearing piles by Kelly Method have
been completed.
(p) Inter-face
core tests were carried out at P12 & P21.
(q) Full
depth coring was carried out at P12-R3 & P30-R1.
(r) Sonic
tests were carried out at P2, P3, P12, P19-L & P21.
(s) Toe grouting works were carried out at P2 & P3.
Disposal from Marine Works
(a)
The disposals in this reporting
period are shown in below table.
Disposal Location |
No of Trip |
Type of Materials |
TM38 |
3 |
Inert
Materials |
TMCLK |
2 |
Inert
Materials |
HK
Open Sea Mud Pits |
1 |
Type
II Materials |
Cross
Boundary Disposal |
5 |
Marine
Mud |
Pilecap Construction:
(a) 10 precast cap shells were installed at P27,
P28, P29, P63 & P67.
(b) Stage 1 concreting was completed
at P18, P29, P62, P63 & P67.
(c) Stage 1 works is in progress at P18, P29,
P62, P63, P67 & P68.
(d) Stage 2 concreting was completed at P18L,
P33, P34, P35, P61, P62 & P64.
(e) Stage 2 works is in progress at P18L&R,
P29, P33, P34, P35, P61, P62, P63 & P64.
(f) Kingpost
installation and associated steel welding works for precast shell installation
are in progress at P17, P27, P28, P30, P32 & P59.
(g) Concrete trimming and advanced trimming
(inside casing) works were carried out at P14, P16, P17, P27, P28, P29, P30,
P32, P53, P58, P59, P63, & P67.
Pier Location |
Side |
Progress |
P70 |
L |
Excavation completed; Concrete plug was casted on 18-Nov-14 |
R |
Excavation, concrete plug and blinding layering
completed; Trimming of pile head concrete in progress |
|
P71 |
L |
Concreting works of pile cap completed on 6-Oct-14 |
R |
Trimming of pile head concrete completed; Cleaning works before formwork and steel fixing
works in progress |
|
P72 |
L |
Excavation works in progress |
R |
Concrete plug completed; Dewatering for Installation of 3rd layer of waling
in progress |
|
P73 |
L |
Installation of formwork and steel fixing for pile
cap is in progress; |
R |
Trimming of pile head concrete is in progress; |
|
P74 |
L |
Excavation works in progress |
R |
Excavation works in progress |
|
P76 |
L |
Installation of sheet pile completed; Removal of temporary working platform in progress; |
R |
Installation of sheet pile completed; Installation of shear pin to be started |
|
P77 |
L |
Installation of 1st waling & strut in progress |
R |
Installation of sheet pile completed. Removal of temporary working platform in progress; |
|
P78 |
L |
Excavation works is in progress |
R |
Excavation works is in progress |
In-situ Column Construction
(a) 1st lift works is in progress at P34, P35, P36, P60, P65 & P66.
(b) 1st lift concrete was poured at P35, P36, P60
& P65.
(c) 2nd lift works is in progress : N/A.
(d) 2nd lift concreting was poured: N/A.
(e) Pier head works is in progress at: P45, P48-R, P49, P52, P60, P65 & P66.
(f) Pier head concreting in progress at P45, P48-R & P52.
Precast Column Erection
(g) P39 – Base unit (1 of 3) installed.
(h) P40 – Base unit (1 of 3) installed.
(i) P41 – All units installed.
(j) P43 – All units installed.
(k) P44 – All units installed and prestressed
tendon installation completed.
In-situ Double Blade Column Construction
(l) 1st lift works is in progress at P19.
(m) 2nd lift works is in progress at P20.
(n) 1st lift works is in progress at P71.
Deck Erection
(a)
Setting up of Equipment:
Type of Equipment |
Status |
Segment
Unloading Frame (SUF) |
Fully
operational |
Lifting
Frames 1 (LF1) |
Assembly
of the first set of LF1 is on-going at WA4 but is hampered by lack of
available area; Steelwork
for the 4th set of Lifting Frames is under fabrication with some
deliveries commenced; |
Lifting
Frames 2 (LF2) |
LF2 at
P109-P110R has been removed |
Launching
Gantry 1 (LG1) |
LG1
assembly continues at Portion C with all components on site; Lower
Cross Beam (LCB)’s and elements 3 – 14 of the main trusses erected |
Launching
Gantry 2 (LG2) |
Loading
out of barges with LG2 components at River Trade Terminal (RTT) has commenced
with assembly imminent at P47/P46 |
- A total
of 22 segments have been erected to date with the P46 Segments on Pier (SOP) segments
erected during the month.
Precast
Segment
(a) Progress
for mould assembly:
Type of Segment |
Number of Mould |
Status |
A |
10 |
Completed
(including 2 nos. SPO) |
B |
1 |
Completed |
D |
2 |
Completed |
E |
4 |
Completed |
CH1 |
2 |
Completed |
CH2 |
2 |
Completed |
CH3 |
2 |
Completed |
CH4 |
2 |
Completed |
CH5 |
2 |
Completed |
CP
(long span SOP) |
4 |
2 CPA
complete, 1 * CPB complete |
DT |
1 |
Completed |
E/EV |
2 |
Under
fabrication |
(b) 210 segments were
cast in this reporting period.
(c) Cumulative total 1386
segments cast.
(d) 76 segments have
been delivered to site (28 in this reporting period).
(e) Piling works were completed for the precast yard extension for both
additional moulds and segment storage; Storage plinths are well underway.
(f) Transportation of segments to an off-yard storage yard at nearby area in
Zhongshan continues.
Precast Concrete Shell Casting
(a) Summary
of precast shell cast in the precast yard:
Type of Shell |
Number of Precast Shell Cast in this reporting
period |
Cumulative No. of Precast Shell Completed (up to
28th of each month) |
CP1 |
6 |
56 |
CP2 |
Completed |
12 |
CP3 |
2 |
2 |
CP4 |
Completed |
8 |
CP5 |
2 |
4 |
Ground Investigations
- All ground investigation /
predrilling holes were completed. No drill rig is on site for this purpose. The
Contractor is working to complete the reporting.
- All Founding Level Proposals have
been issued. The Contractor is working to close out comments and review as
piling works proceeding on site.
2.11
The valid environmental licenses and permits were attached in
the Monthly EM&A Reports.