2               Contract INFORMATION

Background

2.1         The proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road (HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao Bridge (HZMB) at the HKSAR Boundary with the Hong Kong Boundary Crossing Facilities (HKBCF) situated at the north eastern waters of the Hong Kong International Airport, opening a new and direct connection route between Hong Kong, Macao and the Western Pearl River Delta. 

2.2         The HKLR comprises a 9.4km long viaduct section from the HKSAR boundary to Scenic Hill on the Airport Island; a 1km tunnel section to the reclamation formed along the east coast of the Airport Island and a 1.6km long at-grade road section on the reclamation connecting to the HKBCF. The tunnel section of HKLR will pass under Scenic Hill, Airport Road and Airport Railway to minimize the environmental and visual impacts to Tung Chung residents.

2.3         An application (No ESB-110/2003) for an Environmental Impact Assessment (EIA) Study Brief under Section 5(1) of the Environmental Impact Assessment Ordinance (EIAO) was submitted by Highways Department (the Project Proponent) on 8 October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection has subsequently been renamed as HKLR.  EPD issued an EIA Study Brief (No: ESB-110/2003) in November 2003 to the Project Proponent to carry out an EIA study.

2.4         An EIA Study (Reg. No. AEIAR-144/2009) has been undertaken to provide information on nature and extent of environmental impacts arising from the construction and operation of HKLR. The Environmental Permit was issued on 4 November 2009 (Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the Director of Environmental Protection amends the Environmental Permit (No. EP-352/2009) based on the Application No. VEP-339/2011 and the environmental Permit (Permit No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the Highways Department as the Permit Holder. Subsequently, the Director of Environmental Protection amends the Environmental Permits (No. EP-352/2009/A and EP-352/2009/B) based on the Application No. VEP-409/2013 and VEP-411/2013 respectively. The environmental Permit (Permit No. EP-352/2009/C) was then issued on 5 September 2013.

2.5         Figure 1a-d  shows the layout of the Contract and the scope of the Contract works comprises the following major items:

 

·           a dual 3-lane carriageway in the form of viaduct from the HKSAR boundary (connecting with the HZMB Main Bridge) to the Scenic Hill (connecting with the tunnel under separate Contract No. HY/2011/03), of approximately 9.4km in length with a hard shoulder for each bound of carriageway and a utilities trough on the outer edge of each bound of viaducts;

·           a grade-separated turnaround facility located near San Shek Wan, composed of sliproads in the form of viaduct with single-lane carriageway bifurcated from the HKLR mainline with an elevated junction above the mainline;

·           provision of ancillary facilities including, but not limited to, meteorological enhancement measures including the provisioning of anemometers and modification of the wind profiler station at hillside of Sha Lo Wan, provisioning of a compensatory marine radar, and provisioning of security systems; and

·           associated civil, structural, geotechnical, marine, environmental protection, landscaping, drainage and highways electrical and mechanical (E&M) works, street lightings, traffic aids and sign gantries, marine navigational aids, ship impact protection system, water mains and fire hydrants, lightning protection system, structural health monitoring and maintenance management system (SHM&MMS), supervisory control and data acquisition (SCADA) system, as well as operation and maintenance provisions of viaducts, provisioning of facilities for installation of traffic control and surveillance system (TCSS), provisioning of facilities for installation of telecommunication cables/equipments and reprovisioning works of affected existing facilities/utilities.

Contract Organisation

2.6         Different parties with different levels of involvement in the Contract organization include:

Ÿ   Supervising Officer’s Representative (SOR) – Ove Arup & Partners Hong Kong Limited (ARUP)

Ÿ   Contractor –Dragages -China Harbour-VSL JV   (DCVJV)

Ÿ   Environmental Team (ET) – Cinotech Consultants Ltd. (Cinotech)

 

2.7         The proposed project organization and lines of communication with respect to the on-site environmental management structure are shown in Figure 2. The key personnel contact names and numbers are summarized in Table 2.1.

Table 2.1        Key Contacts of the Contract

Party

Position

Name

Phone No.

Fax No.

SOR (ARUP)

CRE

Mr. Michael Chan

3767 5803

3767 5922

Mr. Colin Meadows

3767 5801

ENPO/IEC

(Environ)

Environmental Project Office Leader

Mr. Y. H Hui

3465 2888

3465 2899

Independent Environmental Checker

Mr. Antony Wong

3465 2888

3465 2899

Contractor (DCVJV)

Deputy Project Director

Mr. W.K Poon

3121 6638

3121 6688

Environmental Officer

Mr. CHU Chung Sing

3121 6672

24-hour Hotline

--

6898 6161

--

ET

(Cinotech)

Environmental Team Leader

Dr. H.F Chan

2151 2088

3107 1388

 

2.8         ENVIRON Hong Kong Ltd. (Environ) is employed by the Highways Department as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) for the Project.

Construction Programme

 

2.9         A copy of Contractor’s construction programme is provided in Appendix A.

Summary of Construction Works Undertaken During Reporting Period

2.10     The major site activities undertaken in the reporting period  included:

September 2014:

Land Viaduct (P85 to Abutment at SHT) & Marine Viaduct (P81 - P84)

(a)      Pile construction is in progress at P81 to P83 and 4 piles were concreted in this reporting period.

(b)     Total 110 pours for column were completed with 13 pours in this reporting period; 33 columns was completed to top level (18 gridlines - P95 to P97 and P99 to P114).

(c)      P81 pile works commenced.

(d)     Pre-bored for sheet pile for cofferdam construction at P84 about 45% completed.

(e)      Seawall block coring and breaking at P82L was completed & P83L is in progress.

(f)      Portal P103 was concreted on 26 August 2014, dismantling of steel girders and brackets are in progress.

(g)     Portal P111 & P113 falsework dismantling was completed.

(h)     Portal P104 was concreted on 23 September 2014.

(i)       Portal P114 formwork erection is in progress.

(j)       Portal P108 side formwork erection is in progress.

(k)     Portal P107 and P106 cross road steel portal beams erection were completed and corresponding falsework erection is in progress.

(l)       Portal P102 steel bracket system erection was completed and corresponding falsework erection is in progress.

(m)   Portal P101 steel girders and cross beams erection is in progress.

 

Marine Viaduct (P0 to P80)

RCD Method:

(a)  Construction of the temporary platform for piling works at P68 was suspended since 10 June 2014 and the Contractor modified the platform followed the SO instruction.

(b)  Piling works at P69 was suspended on 12 July (9 out of 12 piles already completed).

(c)  Works started at P75: Mooring bits and silt curtain installation are in progress.

(d)  Piling jackets were installed at P20, P23 and P80.

(e)  Piling jackets were dismantled at P17, P62, P63 and P80.

(f)  Pile excavations and casing installation were in progress at P15, P17, P20, P24, P25, P31, P32, P67 and P80 with 26 nos. piles concreted in the reporting period.

(g)  Inter-face coring tests were carried out at P28, P29, P32, P58, P63 and P67.

(h)        Full depth coring test was carried at P27 and P63.

(i)    Sonic tests were carried out at P27, P28, P29, P32, P58, P63 and P67.

(j)    Grouting works were carried out at P29, P59, P62, P63 and P67.

 

Kelly Method:

(k) Installation of temporary piles were carried out at P1.

(l)         Installation of platforms were carried out at P1.

(m)        Installation of permanent casing were carried out at P1 and P3.

(n)  Piling platform removal and temporary pile extraction were carried out at P11, P17b, P17c and P33.

(o) Pile excavation by Kelly method are in progress at P2, P3, P12 and P21 with 11 piles concreted in the reporting period.

(p)  Inter-face core tests were carried out at P30.

(q) Full depth coring was carried out at P16-R2 and P30-R1.

(r) Sonic tests were carried out at P30.

(s)   Toe grouting works were carried out at P4 and P16.

(t)   Disposal: 3 trips of inert materials to HKBCF, 3 trips of Type I materials, 2 trips of Type II materials were disposed.

Pilecap Construction:

(a)  10 precast cap shells were installed at P33, P34, P35, P61 and P64.

(b)   Stage 1 concreting was completed at P20R, P36, P50, P60, P66 and P65.

(c)  Stage 1 works is in progress at P19, P50, P60, P65 and P66.

(d) Stage 2 concreting was completed at P20, P36, P37, P38 and P50.

(e)  Stage 2 works is in progress at P20, P36, P37, P38, P50 and P66.

(f) Kingpost installation and associated steel welding works for precast shell installation are in progress at P18, P33, P34, P35, P61 and P64.

(g) Concrete trimming and advanced trimming (inside casing) works were carried out at P18, P33, P53, P62, P63 and P67.

(h)  Submerged pilecap works with cofferdam:

-       P70L: Installation 1st and 2nd layer of waling & strut completed.

-       P70R: Installation of 1st layer of waling & strut completed. Installation of 2nd layer of waling & strut is in progress.

-       P71L: Cofferdam work was completed. Formwork & top layers of reinforcement for pile cap is on-going.

-        P71R: Due to high rockhead, concrete waling beam is required. Concrete pouring for 2nd layer of concrete waling beam was completed. Preparation works for the last layer pouring is in progress.

-       P72L: Installation of waling strut at 2nd layer is substantially completed.

-         P72R: 2 layers of waling & strut were completed. Excavation will be commenced.

-         P73L: Concrete plug was poured. Installation of 3rd layer of waling & strut is in progress.

-        P73R: Excavation is substantially completed, sheet pile cleaning by divers is in progress.

-        P74L: Installation of 1st layer of waling & strut was completed.

-        P74R: Re-driving sheet pile is in progress.

-        P76: Installation of temporary working platform is in progress.

-        P77: Installation of temporary working platform was completed.

-        P78L: Installation of sheet pile was completed. Preparation works for installation of waling & strut is in progress.

-        P78R: Installation of sheet pile was completed. Preparation work for installation of waling & strut is in progress.

 

In-situ Column Construction

(a)    1st lift works in progress at P38, P39, P41, P42L, P48L, P49, P51 and P52.

(b)   1st lift concrete was poured at P39, P41, P42L, P48L, P49, P51 and P52.

(c)    2nd lift works in progress at P39, P41, P42L, P48, P51 and P52.

(d)   2nd lift concreting was poured: P45 and P49.

(e)    Pier head works in progress at: P45 and P49.

(f)    Pier head concreting: Nil in this reporting period.

 

Precast Column Erection

(g)   Preparatory works have been completed for precast column erection at P43 and P44. The first batch of precast column delivery is in progress.

 


Deck Erection

(a) Works for segment erection:

-        Off-site fabrication of the first 3 sets of Lifting Frames is substantially completed in Dongguan with delivery of all 6 sets of Lifting Frames 2 (LF2).

-        Segment Unloading Frame (SUF) load test was completed.

-        Assembly of Launching Gantry 2 (LG2) continues at River Trade Terminal (RTT). Winches have been tested.

-        Launching Gantry 1 (LG1) assembly continues at Portion C with all components on site and erection commenced.

-        Assembly and erection of LF2 continues with 2 frames having been erected at P109. One of the frames has been load tested. Other 2 frames are assembled at adjacent to P109 and 2 frames are assembled at WA4.

-        The first 2 segments on P109L have been erected by LF2.

-        12 winches have been delivered to Hong Kong.

-        Segments on Pier (SOP) erection at P47 has commenced.

Precast Segment

(a) Progress for mould assembly:

Type of Segment

Number of Segment

Status

A

10

Completed (including 2 nos. SPO)

B

1

Completed

D

2

Completed

E

4

Completed

CH1

2

Completed

CH2

2

Completed

CH3

2

Completed

CH4

2

Completed

CH5

2

Completed

CP (long span SOP)

3

2 CPA complete, CPB in progress

DT

1

Completed

E/EV

2

Under fabrication

(b)  90 segments were cast in this reporting period.

(c) Cumulative total 1057 segments cast.

(d)  The first 12 segments were loaded onto barges and delivered to Hong Kong.

(e)  Piling works have commenced for the precast yard extension for both additional moulds and segment storage.

(f) Transportation of segments to a nearby secondary storage yard has commenced in Zhongshan.

Precast Concrete Shell Casting

(a)    Summary of precast shell cast in the precast yard:

Type of Shell

Number of Precast Shell Cast in this reporting period

Cumulative No. of Precast Shell Completed (up to 28th of each month)

CP1

4

45

CP2

3

12

CP4

1

6

 

Ground Investigations

-       1 drill rig was mobilized to Pier 1 piling platform for additional holes.

-       Predrilling works were carried out at P1 in this reporting period.

-       1 nos. of additional pre-drills was completed in this reporting period. Total 725 piles have completed predrills (including GI used as predrill).

-       Total 115 gridline (100%) out of 115 were completed for pre-drilling. Additional predrills are required for the friction piles at P1 and P7 for SPT tests and these shall be carried out on the piling platforms.

-       Total 113 gridlines for first issue of Founding Level Proposals were submitted. 1 no. was submitted in this reporting period.

 

October 2014:

 

Land Viaduct (P85 to Abutment at SHT) & Marine Viaduct (P81 - P84)

(a)    Pile construction is in progress at P81 to P82 and 4 piles were concreted in this reporting period.

(b)     Total 122 pours for column were completed with 12 pours in this reporting period; 44 columns was completed to top level (21 gridlines - P93 and P95 to P114).

(c)      Pre-bored for sheet pile for cofferdam construction at P84 was completed. Excavation and waling installation is in progress.

(d)     Pre-bored for sheet pile for cofferdam construction at P83R commenced.

(e)      Sewage diversion at P83 commenced.

(f)      Portal P103 was concreted on 26 August 2014. Dismantling of steel girders and brackets was completed.

(g)     Portal P111 & P113 falsework dismantling was completed. Dismantling of falsework is in progress.

(h)     Portal P114 was concreted on 28 October 2014.

(i)       Portal P108 was concreted on 25 October 2014.

(j)       Portal P107 and P106 erection of formwork is in progress.

(k)     Portal P102 erection of side formwork is in progress.

(l)       Portal P101 erection of side formwork is in progress.

(m)   Portal P97 erection of cross beams is in progress.

(n)     Portal P100 erection of falsework and girders is in progress.

(o)     Portal P99 foundation work for falsework supports is in progress.

 

Marine Viaduct (P0 to P80)

RCD Method:

(a)  Construction of the temporary platform for piling works at P68 was suspended since 10 June 2014. The Contractor removed the rockfill platform followed the SO instruction.

(b)  Piling works at P69 was suspended on 12 July 2014 (9 out of 12 piles already completed).

(c) Remobilization for P75’s works started on 25 September 2014. Excavation by grabbing and chiseling is in progress.

(d)  Piling jackets were installed at P5, P9, P10, P18 and P23.

(e)  Piling jackets were dismantled at P13, P15, P20, P25, P32, P63, P67 and P80.

(f)  Pile excavations and casing installation were in progress at P5, P9, P15, P18, P20, P23, P31 and P80 with 20 nos. piles concreted in the reporting period.

(g)  Inter-face coring tests were carried out at P31, P32, P55, P56, P79 and P80.

(h)        No Full depth coring test was carried during the reporting period.

(i)    Sonic tests were carried out at P28, P31, P32, P55, P56 and P80.

(j)    Grouting works were carried out at P14, P27, P28, P29, P32, P54, P58 and P67.

 

Kelly Method:

(k) Installation of temporary piles were carried out at P2 and P7.

(l)         Installation of platforms were carried out at P7.

(m)        Installation of permanent casing were carried out at P7.

(n)  Piling platform removal and temporary pile extraction were carried out at P2 and P30.

(o) Pile excavation by Kelly method are in progress at P1, P2, P3, P7 & P12 and 8 piles concreted in the reporting period.

(p)  All end bearing piles by Kelly Method has been completed.

(q) Inter-face core tests were carried out at P21.

(r) Full depth coring was carried out at P30-R1.

(s)   No sonic tests were carried out in this reporting period.

(t)   Toe grouting works were carried out at P4 and P16.

Disposal

(a)    2 trips of inert materials & 1 trip of inert materials to TM38 & HKLR03 Project respectively, 3 trips of Type I materials & 1 trip of Type II materials were disposed to HK open sea mud pits. 3 trips of marine mud to Cross Border were disposed.

Pilecap Construction:

(a)  6 precast cap shells were installed at P18, P62 & P63.

(b)   Stage 1 concreting was completed at P19, P33, P34, P35, P61 & P64.

(c)  Stage 1 works is in progress at P19, P33, P34, P35, P61, P62 & P64.

(d) Stage 2 concreting was completed at P19, P60, P65 & P66.

(e)  Stage 2 works is in progress at P19, P34, P35, P60, P61, P64, P65 & P66.

(f) Kingpost installation and associated steel welding works for precast shell installation are in progress at P18, P29, P62, P63 & P67.

(g) Concrete trimming and advanced trimming (inside casing) works were carried out at P17, P27, P28, P29, P59, P63 & P67.

(h)  Submerged pilecap works with cofferdam:

-       P70L: Excavation is in progress.

-       P70R: Excavation is in progress.

-       P71L: Concreting works of pile cap was completed on 6-Oct-14.

-               P71R: Additional concrete plug and 3rd layer of waling & strut were completed. Dewatering, cleaning and drainage works before casting of blinding layer is in progress.

-       P72L: Installation of waling strut at 2nd layer is substantially completed. Additional grouting works was carried out.

-       P72R: Excavation is substantially completed. Sheet pile cleaning by divers is in progress.

-       P73L: Installation of 3rd layer of waling & strut was completed. Dewatering, cleaning and drainage works before casting of blinding layer is in progress.

-       P73R: Concrete Plug was casted on 10-Oct-14. Installation of 3rd layer of waling & strut was completed. Dewatering is in progress.

-       P74L: Installation of 2nd layer of waling & strut in progress.

-       P74R: Installation of shear pin was completed.

-       P76L: Installation of temporary working platform was completed.

-       P76R: Installation of sheet pile is in progress.

-       P77L: Installation of sheet pile is in progress.

-       P77R: Installation of sheet pile is in progress.

-       P78L: Installation of 1st & 2nd waling & strut were completed.

-       P78R: Installation of 1st & 2nd waling & strut were completed.

 

In-situ Column Construction

(a)    1st lift works is in progress at P36, P37, P38 and P66.

(b)   1st lift concrete was poured at P37 & P38.

(c)    2nd lift works is in progress at P48-R, P51 and P52.

(d)   2nd lift concreting was poured: P48-R, P51 and P52.

(e)    Pier head works is in progress at: P45, P48-R and P52.

(f)    Pier head concreting : Nil in this reporting period.

 

Precast Column Erection

(g)   The initial Precast Column sections have been installed and concreted on P43 and P44. The 2nd batch of precast column delivery is in progress.

 

In-situ Double Blade Column Construction

(h)   1st lift works is in progress at P20 and P71.

 

Deck Erection

(a) Setting up of Equipment:

-        Off-site fabrication of the first 3 sets of Lifting Frames is substantially completed in Dongguan with delivery of all 6 sets of Lifting Frames 2 (LF2), Steelwork for the 4th set of Lifting Frames is under fabrication with some deliveries having commenced.

-        Segment Unloading Frame (SUF) is fully operational;

-        Assembly of Launching Gantry 2 (LG2) continues at River Trade Terminal (RTT). Winches have been tested.

-        Launching Gantry 1 (LG1) assembly continues at Portion C with all components on site, Lower Cross Beam (LCB)’s erected and the first 50m section of truss erected.

-        An accident occurred with the collapse of the 4th set of LF2 at Pier P109R on the morning of 19th October 2014. All works on LF2 at P109 have been suspended pending for Labour Department Investigation.

-        A total of 10 segments have been erected on P109, 4 segments on P110 and 4 SOP segments on P47. Segments on Pier (SOP) segments for P46 are on site awaiting erection after completion of temporary works.

Precast Segment

(a) Progress for mould assembly:

Type of Segment

Number of Segment

Status

A

10

Completed (including 2 nos. SPO)

B

1

Completed

D

2

Completed

E

4

Completed

CH1

2

Completed

CH2

2

Completed

CH3

2

Completed

CH4

2

Completed

CH5

2

Completed

CP (long span SOP)

3

2 CPA complete, CPB in progress

DT

1

Completed

E/EV

2

Under fabrication

(b)  119 segments were cast in this reporting period.

(c) Cumulative total 1176 segments cast.

(d)  48 segments have been delivered to site.

(e)  Piling works have commenced for the precast yard extension for both additional moulds and segment storage.

(f) Transportation of segments to off-yard storage at nearby area in Zhongshan has commenced.

Precast Concrete Shell Casting

(a)    Summary of precast shell cast in the precast yard:

Type of Shell

Number of Precast Shell Cast in this reporting period

Cumulative No. of Precast Shell Completed (up to 28th of each month)

CP1

5

50

CP2

Completed

12

CP4

2

8

CP5

0

2

CP1

5

50

 


Ground Investigations

-       4 drill rigs were mobilized for additional predrilling works at P2 (compensation pile), P7 (additional SPT’s) and D18 (pile moved).

-       5 nos. of additional pre-drills were completed in this reporting period. All 725 piles have completed predrills (including GI used as predrill).

-       Total 115 gridline (100%) out of 115 were completed for pre-drilling. Additional predrills are required for the friction piles at P1 and P7 for SPT tests and these shall be carried out on the piling platforms.

-       Total 115 gridlines for first issue of Founding Level Proposals were submitted. 2 no. was submitted in this reporting period.

 

November 2014:

Land Viaduct (P85 to Abutment at SHT) & Marine Viaduct (P81 - P84)

(a)    Pile construction is in progress at P82 to P83 and 4 piles were concreted in this reporting period.

(b)     Total 139 pours for column were completed with 17 pours in this reporting period; 51 columns were completed to top level (25 gridlines - P90 to P114).

(c)      P84L water plugging and rebar fixing are in progress, P84R excavation is in progress.

(d)     Pre-bored for sheet pile for cofferdam construction at P83R was completed.

(e)      Pre-bored for sheet pile for cofferdam construction at P81R commenced.

(f)      Sewage diversion at P83 is in progress.

(g)     P83L piling work commenced.

(h)     Portal P107 and P106 were concreted on 17 and 21 November 2014 respectively. Dismantling of side formwork is in progress.

(i)       Portal P104 dismantling of steel bracket system was completed.

(j)       Portal P108 dismantling of falsework and steel bracket system is in progress.

(k)     Portal P114 dismantling of formwork was completed, temporary supporting jacks and nailing to be installed before falsework removal.

(l)       Portal P102 steel fixing is in progress and will be concreted on 29 November 2014.

(m)   Portal P101 steel fixing is in progress.

(n)     Portal P97 formwork erection was completed and steel fixing will be commenced.

(o)     Portal P98 erection of steel bracket system is in progress.

(p)     Portal P100 erection of formwork is in progress.

(q)     Portal P99 erection of falsework and steel beam supports are in progress.

(r)       Portal P96 portal foundation work is in progress.

 

Marine Viaduct (P0 to P80)

RCD Method:

(a)  Construction of the temporary platform for piling works at P68 was suspended since 10 June 2014.

(b) Piling works at P69 was suspended on 12 July 2014 (9 out of 12 piles already completed).

(c) Remobilization for P75’s works started on 25 September 2014. Excavation by backhoe on flat top barge is on going.

(d)  Piling jackets were installed at P8.

(e)  Piling jackets were dismantled at P23 and D20.

(f)  Pile excavations and casing installation are in progress at P5, P9, P10 and P23 with 13 nos. piles concreted in the reporting period.

(g)  Inter-face coring tests were carried out at P23, P24, P25, P26 and P79.

(h)        Full depth coring test was carried at P79.

(i)    Sonic tests were carried out at P22, P24, P25, P26 and P79.

(j)    Grouting works were carried out at P53 and P79.

 

Kelly Method:

(k) Re-installation of platform was carried out at P2.

(l)         Installation of permanent casing was carried out at P2R1a.

(m)        Piling platform removal and temporary pile extraction were carried out at P16, P31 & P32.

(n)  Pile excavation by Kelly method is in progress at P1, & P7 and 9 piles concreted in the reporting period.

(o) All end-bearing piles by Kelly Method have been completed.

(p)  Inter-face core tests were carried out at P12 & P21.

(q) Full depth coring was carried out at P12-R3 & P30-R1.

(r) Sonic tests were carried out at P2, P3, P12, P19-L & P21.

(s)   Toe grouting works were carried out at P2 & P3.


Disposal from Marine Works

(a)    The disposals in this reporting period are shown in below table.

Disposal Location

No of Trip

Type of Materials

TM38

3

Inert Materials

TMCLK

2

Inert Materials

HK Open Sea Mud Pits

1

Type II Materials

Cross Boundary Disposal

5

Marine Mud

Pilecap Construction:

(a)  10 precast cap shells were installed at P27, P28, P29, P63 & P67.

(b)   Stage 1 concreting was completed at P18, P29, P62, P63 & P67.

(c)  Stage 1 works is in progress at P18, P29, P62, P63, P67 & P68.

(d) Stage 2 concreting was completed at P18L, P33, P34, P35, P61, P62 & P64.

(e)  Stage 2 works is in progress at P18L&R, P29, P33, P34, P35, P61, P62, P63 & P64.

(f) Kingpost installation and associated steel welding works for precast shell installation are in progress at P17, P27, P28, P30, P32 & P59.

(g) Concrete trimming and advanced trimming (inside casing) works were carried out at P14, P16, P17, P27, P28, P29, P30, P32, P53, P58, P59, P63, & P67.

(h)  Submerged pilecap works with cofferdam:

 

Pier Location

Side

Progress

P70

L

Excavation completed;

Concrete plug was casted on 18-Nov-14

R

Excavation, concrete plug and blinding layering completed;

Trimming of pile head concrete in progress

P71

L

Concreting works of pile cap completed on 6-Oct-14

R

Trimming of pile head concrete completed;

Cleaning works before formwork and steel fixing works in progress

P72

L

Excavation works in progress

R

Concrete plug completed;

Dewatering for Installation of 3rd layer of waling in progress

P73

L

Installation of formwork and steel fixing for pile cap is in progress;

R

Trimming of pile head concrete is in progress;

P74

L

Excavation works in progress

R

Excavation works in progress

P76

L

Installation of sheet pile completed;

Removal of temporary working platform in progress;

R

Installation of sheet pile completed;

Installation of shear pin to be started

P77

L

Installation of 1st waling & strut in progress

R

Installation of sheet pile completed.

Removal of temporary working platform in progress;

P78

L

Excavation works is in progress

R

Excavation works is in progress

 

In-situ Column Construction

(a)    1st lift works is in progress at P34, P35, P36, P60, P65 & P66.

(b)   1st lift concrete was poured at P35, P36, P60 & P65.

(c)    2nd lift works is in progress :  N/A.

(d)   2nd lift concreting was poured: N/A.

(e)    Pier head works is in progress at: P45, P48-R, P49, P52, P60, P65 & P66.

(f)    Pier head concreting in progress at P45, P48-R & P52.

 

Precast Column Erection

(g)   P39 – Base unit (1 of 3) installed.

(h)   P40 – Base unit (1 of 3) installed.

(i)     P41 – All units installed.

(j)     P43 – All units installed.

(k)   P44 – All units installed and prestressed tendon installation completed.

 

In-situ Double Blade Column Construction

(l)     1st lift works is in progress at P19.

(m) 2nd lift works is in progress at P20.

(n)   1st lift works is in progress at P71.

 

Deck Erection

(a)      Setting up of Equipment:

Type of Equipment

Status

Segment Unloading Frame (SUF)

Fully operational

Lifting Frames 1 (LF1)

Assembly of the first set of LF1 is on-going at WA4 but is hampered by lack of available area;

 

Steelwork for the 4th set of Lifting Frames is under fabrication with some deliveries commenced;

Lifting Frames 2 (LF2)

LF2 at P109-P110R has been removed

 

Launching Gantry 1 (LG1)

LG1 assembly continues at Portion C with all components on site;

 

Lower Cross Beam (LCB)’s and elements 3 – 14 of the main trusses erected

Launching Gantry 2 (LG2)

Loading out of barges with LG2 components at River Trade Terminal (RTT) has commenced with assembly imminent at P47/P46

 

-        A total of 22 segments have been erected to date with the P46 Segments on Pier (SOP) segments erected during the month.

Precast Segment

(a)      Progress for mould assembly:

Type of Segment

Number of Mould

Status

A

10

Completed (including 2 nos. SPO)

B

1

Completed

D

2

Completed

E

4

Completed

CH1

2

Completed

CH2

2

Completed

CH3

2

Completed

CH4

2

Completed

CH5

2

Completed

CP (long span SOP)

4

2 CPA complete,  1 * CPB complete

DT

1

Completed

E/EV

2

Under fabrication

(b)  210 segments were cast in this reporting period.

(c) Cumulative total 1386 segments cast.

(d)  76 segments have been delivered to site (28 in this reporting period).

(e) Piling works were completed for the precast yard extension for both additional moulds and segment storage; Storage plinths are well underway.

(f) Transportation of segments to an off-yard storage yard at nearby area in Zhongshan continues.

Precast Concrete Shell Casting

(a)    Summary of precast shell cast in the precast yard:

Type of Shell

Number of Precast Shell Cast in this reporting period

Cumulative No. of Precast Shell Completed (up to 28th of each month)

CP1

6

56

CP2

Completed

12

CP3

2

2

CP4

Completed

8

CP5

2

4

 

Ground Investigations

-       All ground investigation / predrilling holes were completed. No drill rig is on site for this purpose. The Contractor is working to complete the reporting.

-       All Founding Level Proposals have been issued. The Contractor is working to close out comments and review as piling works proceeding on site.

 

Status of Environmental Licences, Notification and Permits

 

2.11     The valid environmental licenses and permits were attached in the Monthly EM&A Reports.