EXECUTIVE SUMMARY

Introduction

1.              This is the 9th Quarterly Environmental Monitoring and Audit (EM&A) Report prepared by Cinotech Consultants Limited for the project “Contract No. HY/2011/09 – Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road – Section between HKSAR Boundary and Scenic Hill” (hereinafter called the “Contract”). This report documents the findings of EM&A Works performed in the period between March and May 2015.

Environmental Monitoring and Audit Progress

2.              A summary of the monitoring activities in this reporting period is listed in Table I below:

Table I            Summary Table for Monitoring Activities in the Reporting Period

 

Parameter(s)

Monitoring Date(s)

1-hr TSP Monitoring

5th, 11th, 17th, 23rd and 27th March 2015

2nd, 8th, 14th, 20th, 24th and 30th April 2015

6th, 12th, 18th, 22nd and 28th May 2015

24-hr TSP Monitoring

Noise Monitoring

6th, 12th, 18th and 24th March 2015

9th, 15th, 21st and 27th April 2015

7th, 13th, 19th and 29th May 2015

Water Quality Monitoring

2nd, 4th, 6th, 9th, 11th, 13th, 17th, 19th, 21st, 23rd, 25th, 27th and 31st March 2015

2nd, 4th, 6th, 8th, 10th, 13th, 15th, 17th, 20th, 22nd, 24th, 27th and 29th April 2015

2nd, 4th, 6th, 8th, 11th, 13th, 15th, 18th, 20th, 22nd, 25th, 27th and 29th May 2015

Dolphin Monitoring (Line-transect Vessel Surveys)

19th  and 27th March 2015

2nd and 13th April 2015

7th and 15th May 2015

Additional Land-based Dolphin Behaviour and Movement Monitoring

9th  and 13th March 2015

14th  and 20th April 2015

11th  and 19th May 2015

Environmental Site Inspection

3rd, 10th, 17th, 23rd and 31st March 2015

9th, 14th, 21st and 29th April 2015

5th, 12th, 18st and 26th May 2015

Archaeological Site Inspection

17th March 2015

Breaches of Action and Limit Levels

3.              Summary of the environmental exceedances of the reporting period is tabulated in Table II.

Table II          Summary Table for Events Recorded in the Reporting Period

 

Environmental Monitoring

Parameter

No. of Exceedance

No. of Exceedance related to the Construction Activities of this Contract

Action Level

Limit Level

Action Level

Limit Level

Air Quality

1-hr TSP

0

0

0

0

24-hr TSP

0

0

0

0

Noise

Leq(30min)

0

0

0

0

Water Quality

Dissolved Oxygen (DO) (Surface & Middle)

0

0

0

0

Dissolved Oxygen (DO) (Bottom)

0

0

0

0

Turbidity

0

0

0

0

Suspended Solids (SS)

8

6

0

0

Dolphin Monitoring

Line-transect Vessel Surveys

0

0

0

0

 

4.              Environmental monitoring works were performed in the reporting period and all monitoring results were checked and reviewed.  The details of each exceedance were attached in the Monthly EM&A Reports.

Complaint Log

 

5.              No environmental complaint was received in the reporting period.

Notification of Summons and Successful Prosecutions

 

6.              No notification of summons and successful prosecution was received in the reporting period.

Reporting Changes

 

7.              This report has been developed in compliance with the reporting requirements for the quarterly EM&A Summary Report as required by the EM&A Manual for Hong Kong Link Road (EM&A Manual).

Future Key Issues

8.              Major site activities for the coming reporting month will include:

WA4

Ÿ   Fabrication of lifting frames

Ÿ   Deliveries of frame structures

 

WA7

Ÿ   Fabrication of cofferdam frame structures

Ÿ   Maintenance of Reverse Circulation Drill (RCD) equipment

 

Marine Viaduct (P0 to P80)

Reverse Circulation Drill (RCD) Method:

Ÿ   Temporary platform formation

Ÿ   Installation of Jacket

Ÿ   Dismantling of piling jackets

Ÿ   Pile excavation and casing installation

Ÿ   Inter-face tests, full depth coring test and sonic test

Ÿ   Grouting works

 

Pile Cap Construction:

Ÿ   Installation of precast cap shells

Ÿ   Concreting

Ÿ   Kingpost installation and associated steel welding works

Ÿ   Concreting trimming

Ÿ   Rock excavation

Ÿ   Steel Fixing works of pile cap

 

Works with Cofferdam:

Ÿ   Installation of waling strut

Ÿ   Installation of sheet pile

Ÿ   Installation of temporary working platform

Ÿ   Installation of shear pin

Ÿ   Installation of bored pile casing

Ÿ   Excavation works and casting of concrete plug

Ÿ   Dewatering works and sealing works

Ÿ   Additional welding

 

Column Construction:

Ÿ   Lifting works

Ÿ   Lift concreting

Ÿ   Pier head works

Ÿ   Pier head concreting

 

 

Precast Column Erection

Ÿ   Installation of base units and precast units

Ÿ   Stressing of vertical nailing tendons

 

Deck Erection

Ÿ   Setting up of equipment

Ÿ   Segment erection

 

Precast Segment

Ÿ   Segment casting

 

Land Viaduct (P81 to Abutment at Scenic Hill Tunnel (SHT))

Ÿ   Pile construction

Ÿ   Pouring of column

Ÿ   Excavation works and waling & struts installation work

Ÿ   Sewage diversion

Ÿ   Pre-bored sheet pile

Ÿ   Pile cap excavation work and waling & struts installation

Ÿ   Erection of steel girders and cross beams

Ÿ   Erection of vertical formwork and kickers

Ÿ   Steel fixing for portal

Ÿ   Removal of falsework

Ÿ   Formworks

Ÿ   Construction of temporary foundations

Ÿ   Segment deliveries

Ÿ   Segment erection