2               Contract INFORMATION

Background

2.1         The proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road (HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao Bridge (HZMB) at the HKSAR Boundary with the Hong Kong Boundary Crossing Facilities (HKBCF) situated at the north eastern waters of the Hong Kong International Airport, opening a new and direct connection route between Hong Kong, Macao and the Western Pearl River Delta. 

2.2         The HKLR comprises a 9.4km long viaduct section from the HKSAR boundary to Scenic Hill on the Airport Island; a 1km tunnel section to the reclamation formed along the east coast of the Airport Island and a 1.6km long at-grade road section on the reclamation connecting to the HKBCF. The tunnel section of HKLR will pass under Scenic Hill, Airport Road and Airport Railway to minimize the environmental and visual impacts to Tung Chung residents.

2.3         An application (No ESB-110/2003) for an Environmental Impact Assessment (EIA) Study Brief under Section 5(1) of the Environmental Impact Assessment Ordinance (EIAO) was submitted by Highways Department (the Project Proponent) on 8 October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection has subsequently been renamed as HKLR.  EPD issued an EIA Study Brief (No: ESB-110/2003) in November 2003 to the Project Proponent to carry out an EIA study.

2.4         An EIA Study (Reg. No. AEIAR-144/2009) has been undertaken to provide information on nature and extent of environmental impacts arising from the construction and operation of HKLR. The Environmental Permit was issued on 4 November 2009 (Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the Director of Environmental Protection amends the Environmental Permit (No. EP-352/2009) based on the Application No. VEP-339/2011 and the environmental Permit (Permit No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the Highways Department as the Permit Holder. Subsequently, the Director of Environmental Protection amends the Environmental Permits (No. EP-352/2009/A, EP-352/2009/B, EP-352/2009/C) based on the Application No. VEP-409/2013, VEP-411/2013 and VEP-459/2014 respectively. The environmental Permit (Permit No. EP-352/2009/D) was then issued on 22 December 2014.

2.5         Figure 1a-d  shows the layout of the Contract and the scope of the Contract works comprises the following major items:

 

¡P           a dual 3-lane carriageway in the form of viaduct from the HKSAR boundary (connecting with the HZMB Main Bridge) to the Scenic Hill (connecting with the tunnel under separate Contract No. HY/2011/03), of approximately 9.4km in length with a hard shoulder for each bound of carriageway and a utilities trough on the outer edge of each bound of viaducts;

¡P           a grade-separated turnaround facility located near San Shek Wan, composed of sliproads in the form of viaduct with single-lane carriageway bifurcated from the HKLR mainline with an elevated junction above the mainline;

¡P           provision of ancillary facilities including, but not limited to, meteorological enhancement measures including the provisioning of anemometers and modification of the wind profiler station at hillside of Sha Lo Wan, provisioning of a compensatory marine radar, and provisioning of security systems; and

¡P           associated civil, structural, geotechnical, marine, environmental protection, landscaping, drainage and highways electrical and mechanical (E&M) works, street lightings, traffic aids and sign gantries, marine navigational aids, ship impact protection system, water mains and fire hydrants, lightning protection system, structural health monitoring and maintenance management system (SHM&MMS), supervisory control and data acquisition (SCADA) system, as well as operation and maintenance provisions of viaducts, provisioning of facilities for installation of traffic control and surveillance system (TCSS), provisioning of facilities for installation of telecommunication cables/equipments and reprovisioning works of affected existing facilities/utilities.

Contract Organisation

2.6         Different parties with different levels of involvement in the Contract organization include:

Ÿ   Supervising Officer¡¦s Representative (SOR) ¡V Ove Arup & Partners Hong Kong Limited (ARUP)

Ÿ   Contractor ¡VDragages -China Harbour-VSL JV   (DCVJV)

Ÿ   Environmental Team (ET) ¡V Cinotech Consultants Ltd. (Cinotech)

 

2.7         The proposed project organization and lines of communication with respect to the on-site environmental management structure are shown in Figure 2. The key personnel contact names and numbers are summarized in Table 2.1.

Table 2.1        Key Contacts of the Contract

Party

Position

Name

Phone No.

Fax No.

SOR (ARUP)

CRE

Mr. Michael Chan

3767 5803

3767 5922

Mr. Colin Meadows

3767 5801

ENPO/IEC

(Ramboll Environ)

Environmental Project Office Leader

Mr. Y. H Hui

3465 2888

3465 2899

Independent Environmental Checker

Mr. Antony Wong

3465 2888

3465 2899

Contractor (DCVJV)

Deputy Project Director

Mr. W.K Poon

3121 6638

3121 6688

Environmental Officer

Mr. CHU Chung Sing

3121 6672

24-hour Hotline

--

6898 6161

--

ET

(Cinotech)

Environmental Team Leader

Dr. Priscilla Choy

2151 2089

3107 1388

 

2.8         Ramboll Environ Hong Kong Limited (Ramboll Environ) is employed by the Highways Department as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) for the Project.

Construction Programme

 

2.9         A copy of Contractor¡¦s construction programme is provided in Appendix A.

Summary of Construction Works Undertaken During Reporting Period

2.10     The major site activities undertaken in the reporting period  included:

June 2015:

Land Viaduct (P85 to Abutment at SHT) & Marine Viaduct (P81 - P84)

(a)      P81L&R - pile cap were completed; 2 pours of column were completed in this reporting period.

(b)     P82L - ELS excavation was suspended due to settlement.

(c)      P82R - excavation works are in progress.

(d)     P83L - ELS excavation is in progress.

(e)      P83R - 4 pours of column were completed in this reporting period.

(f)      P84L&R - column head were completed.

(g)     Portal Works:

Pier Location

Progress

P84

Steel bracket and girders erection completed;

Pier head construction is in progress

P86

Installation of steel bracket and girder system is in progress

P87

Removal of formwork & falsework is in progress

P88

Removal of falsework & steel bracket system was completed.

P89

Erection of soffit formwork was completed, formwork & falsework erection is in progress

P90

Steel fixing is in progress, target for concreting on 30 June 2015

P91

Portal was cast on 9 June 2015. Nailing work and removal of formwork is in progress

P92

Erection of formwork and kickers were completed;

Steel fixing to start

P93

Removal of steel cross beams were completed

 

Marine Viaduct (P0 to P80)

Piling Testing, Coring and Grouting (locations other than P68 & P75):

(a) Inter-face coring tests were carried out at D18.

(b) Full depth coring test was carried at D20-L3.

(c) Sonic test was carried out at D18.

(d) Grouting work was carried out at D17.


 

Progress at P68

(a) Casing installation at R3 to R5 and L2 & L5.

         (b)  P68- L3, L4 and L6 were cast.

(c)  P68-L1 excavation was completed with installed rebar cage for concreting at the end of June 2015.

(d)  Two RCD were set up onto R5 and L5 casings at end of June 2015 for commencing of socket drilling.

 

Progress at P69

(a)     Setting up for cofferdam construction work was completed at early June and working platform construction was commenced.

(b)    Right hand side (RHS) working platform was completed and installation of sheetpiles on RHS cofferdam in progress.

(c)     Left hand side (LHS) working platform construction was completed at the end of June.

Progress at P75

(a)     RHS concrete plug was concreted.

(b)    RCD guide frame was installed on the RHS box.

(c)     RCD guide frame was installed on the RHS box.

(d)    RCD excavation is in progress at R2 and R4.

(e)     Excavation to formation at the LHS continued.

Disposal from Marine Works

(a)    The disposals in this reporting period are shown in below table.

Disposal Location

No of Trip

Type of Materials

TM38

0

Inert Materials

TMCLK

0

Inert Materials

HK Open Sea Mud Pits

0

Types II Marine Mud

Cross Boundary Disposal

0

Type I Marine Mud

Pilecap Construction:

(a)  Precast shells installed in this reporting period - two CP3 at P55; Four CP6 at P79 and P80; Four CP1 at P6 and P8; One CP12 at P26L.

(b)   Stage 1 concreting was completed at P11, P26R & P55.

(c)  Stage 1 works is in progress at P79.

(d) Stage 2 concreting was completed at P2L, P7, P11, P13, P26R & P58L.

(e)  Stage 2 works is in progress at P55.

(f) Kingpost installation and associated steel welding works for precast shell installation are in progress at P9.

(g) Advanced concrete trimming (inside casing) works were carried out at P5, P6, P8, P9, P56 & P57 and concrete trimming (inside cap shell) at P55.

(h) Submerged pile cap works with cofferdam:

Pier Location

Side

Progress

P73

L

Backfilling and removal of cofferdam completed on 19-Jun-15

R

Backfilling and removal of cofferdam completed on 19-Jun-15

P74

L

Grouting works around bored pile is in progress

R

Drilling of grouting holes is in progress

P75

L

Rock excavation is in progress

R

Rock excavation is in progress

 

In-situ Column Construction

(a)    1st lift works is in progress at P1, P3, P4, P7, P15, P23, P58 & P78.

(b)   1st lift concrete was poured at P1, P3, P4, P23, P54, P53-Ramp, P59-Ramp, and P78.

(c)    2nd lift works is in progress at P54, P53-Ramp, P59-Ramp and P78.

(d)   2nd lift concrete was poured at P70.

(e)    Pier head works is in progress at P70.

(f)    Pier head concreting: NIL.

 

Precast Column Erection

Description

Location completed in this reporting period

Number of Units erected/ Number of Columns completed in this reporting period

Cumulative No. of Piers completed

(up to 28th of each month)

Precast Column Segment

P25

2

20 (P21, P25, P27-P44)

Precast Column Pier Head

P28, P29

4

17 (P28-P44)

Vertical Tendons Stressed

P28, P29, P34

6

12.5 (P28, P29, P34, P35(1/2), P36-P44)

Grouting Vertical Tendons

P36, P37, P38, P39

8

9 (P36-P44)

Pier Head Concrete

P40, P41, P42

6

5 (P40-P44)

 

 


In-situ Double Blade Column Construction

Pier Location

Side

Progress

P17

L

1st lift in progress

R

1st lift in progress

P18

L

Poured concrete up to 5th lift and 6th lift in progress

R

Poured concrete up to 5th lift and 6th lift in progress

P72

L

Poured concrete to 2nd lift and pierhead in progress

R

Poured concrete to 2nd lift and pierhead in progress

P77

L

Works commenced

R

Works commenced

P77

L

1st lift in progress

R

Poured concrete to 1st lift and 2nd lift in progress

 

Marine Portal

(a)    Dismantling of scaffolding at Portal P52 completed. Removal of temporary supporting platform is in progress.

(b)   Temporary bearing wall of Portal P60 casted. Dismantling of soffit platform is in progress.

 

Deck Erection

(a)      Setting up of Equipment:

Type of Equipment

Status

 

Lifting Frames 1 (LF1)

Assembly of first set of LF1 almost completed.

Assembly of the second to fourth set of LF1 is on-going at WA4;

Steelwork for the 3rd and 4th set of Lifting Frames is under fabrication with some deliveries commenced.

 

Lifting Frames 3

(LF3)

Fabrication of LF3 in China is almost completed for 8 sets. Most of the major components have been completed and have been delivered to site.  Assembly of the first 2 sets of LF3 is completed. The 3rd and 4th sets are almost completed at WA4. Assembly of the 5th to 7th sets have been commenced at WA4 and they are targeted to be completed by mid-July.

 

Launching Gantry 1 (LG1)

Segment erection to P112L & P111L completed in his reporting period, LG1 launching to P108.

 

Launching Gantry 2

 

(LG2)

Erection of P46 to P48 completed (120 segments in total), launching back and forward to P45.

 

(b)     Segment erection:

Type

Location of Segments erected in this reporting period

Number of Segments erected in this reporting period

Cumulative No. of Segments erected

(up to 28th of each month)

LG1

P108R & P111L & P112L

22

242

LG2

P48

40

120

SOP

-

-

36

 

Precast Segment

(a)      Segment Casting:

-             Storage for long span & type D segments is still a key concern.

-             Production affected by inclement weather (5 days).

-            2 nos. of type D & 4 nos. of type CH mould were suspended due to storage problem.

Item

Number in this reporting period

Cumulative No. of Precast Segment Completed

(up to 28th of each month)

Segment Cast

172

2261

 

(b)     Off-site Storage:

Area

No. in Off-site Storage

A1

134

A2

207

A3

236

A4

-

Remarks: A fourth off-site storage facilities was identified for long span segments and preparation works was completed. Segments are to be delivered.

Precast Concrete Shell Casting

(a)    Summary of precast shell cast in the precast yard:

Type of Shell

Number of Precast Shell Cast in this reporting period

Cumulative No. of Precast Shell Completed

(up to 28th of each month)

CP1

4

94

CP2

Completed

12

CP3

0

12

CP4

Completed

8

CP5

Completed

6

CP6

Completed

4

CP11

Completed

1

CP12

Completed

1

F1

1

1

 

Precast Column & Precast Pier Head Casting

(a)      Progress of the precast column & precast pier head casting:

-     All casting works for the based column were completed and the moulds were dismantled. 4 moulds (2 piers and 2 pier heads) are now in service for precasting works.

-      Totally 25 precast elements (19 piers with 6m high, 3 monolithic pier heads and 3 pier heads with bearing support) were cast in this reporting period. 

-      All the 3m high piers were completed in this period (in total 39 elements).

-      Cumulatively 254 precast elements were cast.

Delivery  for Precast Concrete Elements (by barge)

(a)      Precast Deck Segments:

-             Number of additional barges engaged in this period: 0

-             Cumulative number of barges: 13 (3 barges tied up on L/S storage)

-             Number of deck segment deliveries in this period: 10 trips

-             Cumulative number of deck segment deliveries: 95 trips

Segment Types

Segment Delivered in this reporting period

Cumulative No. of Precast Segment Delivered

(up to 28th of each month)

A

42

172

B

0

0

C

0

0

D

0

0

E

10

262

(b)     Precast column units:

-             Number of additional barges engaged in this period: 0

-             Cumulative number of barges: 2

-             Number of column unit deliveries in this period: 3 trips

-             Cumulative number of column unit deliveries: 30 trips

Unit Types

Number of units delivered in this reporting period

Cumulative No. of Precast Column Delivered

(up to 28th of month)

3m

1

19

6m

17

73

PH1

0

20

PH2

4

14

 

(c)      Temporary storage of long span segments:

-       Barge #968 was not able to delivery long span segments at mid-June caused impacts on the scheduling of deliveries.

(d)     General:

-       Delays in the segment unloading has impacts on the delivery cycle time to the extent that there are number of barges overstayed for 14 days in Hong Kong.

-       First delivery of long span segment for P20¡¦s SOP (type CH) arrived in Hong Kong before end of June.

 

July 2015:

Land Viaduct (P85 to Abutment at SHT) & Marine Viaduct (P81 - P84)

(a)    P81L&R - 3 pours of column were completed in this reporting period.

(b)     P82L - ELS excavation works are in progress.

(c)      P82R - excavation works and waling installation completed, pile cap work is in progress.

(d)     P83L - ELS excavation is in progress.

(e)      P83R - 4 pours of column were completed in this reporting period.

(f)      Portal Works:

Pier Location

Progress

P84

Falsework erection is in progress

P86

Erection of falsework and soffit formwork is in progress

P87

Removal of steel bracket system was completed

P89

Steel fixing  is in progress

P90

Removal of formwork is in progress

P91

Removal of falsework is in progress

P92

Portal was concreted on 17 July 2015

P93

Erection of steel bracket system is in progress

 

Marine Viaduct (P0 to P80)

Piling Testing, Coring and Grouting (locations other than P68 & P75):

(a) Grouting work was carried out at P18 and P20.

 

Progress at P68

(a) P68 - L1, L2, L4, R4 and R5 were cast, total 8 nos. complete.

(b)  One RCD was set up on R6 casing at end of July 2015 for socket drilling.

 

Progress at P69

(a)    Sheetpiling work at ¡§R¡¨ and ¡§L¡¨ side are in progress.

 


Progress at P75

(a)    P75 R- side - 4 piles were cast.

(b)   Excavation to formation at the L-side continues.

Pile Cap Construction

(a)    Precast shells installation - two CP3 at P57.

(b)   Stage 1 concreting was completed at P2R, P57, P79 & P80.

(c)    Stage 1 works is in progress at P26L.

(d)   Stage 2 concreting was completed at P55.

(e)    Stage 2 works is in progress at P57 & P79.

(f)    Kingpost installation and associated steel welding works for precast shell installation are in progress at P5R.

(g)   Advanced concrete trimming (inside casing) works were carried out at P5R, P9, D18-L, D18-R & P56 and concrete trimming (inside cap shell) at P2R, P6, P26L & P57.

 (h)       Submerged pile cap works with cofferdam:

Pier Location

Side

Progress

P72

L

Backfilling and removal of cofferdam start on 21-Jul-15

R

Backfilling and removal of cofferdam start on 21-Jul-15

P74

L

Grouting works around bored pile is in progress

Trimming of concrete for extension of pile head is in progress

R

Drilling of grouting holes is in progress

Excavation around the footprint of pile cap is in progress

P75

L

Rock excavation is in progress

R

Rock excavation is in progress

 

In-situ Column (Single) Construction

(a)    1st lift works is in progress at P1, P7, P11 & P13.

(b)   1st lift concrete was poured at P7, P15 & P58.

(c)    2nd lift works is in progress at P58, P53-Ramp, P59-Ramp & P78.

(d)   2nd lift concrete was poured at P53-Ramp, P54 & P59-Ramp.

(e)    Pier head works is in progress at P54 & P70.

(f)    Pier head concreting: NIL

 

Precast Column Erection

Description

Location completed in this reporting period

Number of Units erected/ Number of Columns completed in this reporting period

Cumulative No. of Piers completed

(up to 28th of each month)

Commencement

(ie. starting from 1st precast unit)

P16, P24

22 (P16, P21, P24, P25, P27-P44)

Commencement

(i.e. starting from 1st precast unit)

Completion

(i.e. completed installation of pier head unit)

Nil

17 (P28-P44)

Completion

(i.e. completed installation of pier head unit)

Vertical Tendons Stressed

P30(50%), P32(50%), P33,

P35 (50%)

15 (P28, P29, P30(1/2), P32(1/2), P33-P44)

Vertical Tendons Stressed

Grouting Vertical Tendons

P28, P34

11 (P28, P34, P36-P44)

Grouting Vertical Tendons

Pier Head Concrete

P39

6 (P39-P44)

Pier Head Concrete

 

In-situ Double Blade Column Construction

Pier Location

Side

Progress

P17

L

Poured concrete up to 2nd lift and started to construct 3rd lift

R

Poured concrete up to 1st lift and 2nd lift in progress

P18

L

All cast in July 2015 during this reporting period, total 7 lifts

R

Poured concrete up to 6th lift and 7th lift in progress

P72

L

All cast in July 2015, total 3 lifts (including pierhead)

P76

L

Poured concrete up to 1st lift and 2nd lift in progress

R

Poured concrete up to 1st lift and 2nd lift in progress

P77

L

Poured concrete up to 1st lift and 2nd lift in progress

R

Poured concrete up to 2nd lift and started to construct 3rd lift

 

Marine Portal

(a)    Removal of temporary supporting platform at Portal P52 & P60 was completed.

 

Deck Erection

(a)      Setting up of Equipment:

Type of Equipment

Status

 

Lifting Frames 1 (LF1)

Assembly of first set of LF1 at WA4 almost completed.

Assembly of the second to fourth set of LF1 is on-going at WA4;

Steelwork for the 3rd and 4th set of Lifting Frames is under fabrication with some deliveries commenced.

 

Lifting Frames 3

(LF3)

Fabrication of LF3 in China is completed for the 8 sets. Most of the major components have been delivered to site.  Assembly of the first 4 sets of LF3 is completed and they have started operation at P64.  Assembly of the 5th set is completed. The 6th, 7th and 8th sets have been commenced at WA4 and they are targeted to be completed by mid-August.

 

Launching Gantry 1 (LG1)

Segment erection from P114 to P107 completed;

Erection of P106 is in progress.

 

Launching Gantry 2

 

(LG2)

Erection of P45 to P48 completed (160 segments in total).

 

(b)     Segment erection:

Type

Location of Segments erected in this reporting period

Number of Segments erected in this reporting period

Cumulative No. of Segments erected

(up to 28th of each month)

LG1*

P108, P107 & P106

60

302

LG2

P45

40

160

LF3

P64

6

6

SOP

P42, P43 & P62

              12

54

Long Span SOP

P20

6

6

          *  includes  crane erection for P109

 

Precast Segment

(a)      Segment Casting:

-            Storage for all types of segments is still a key concern.

-            Production affected by inclement weather (8 days).

-            2 nos. of type D & 4 nos. of type CH mould were suspended due to storage issue.

-            4 nos. type E, 10 nos. type A, 6 nos. type CH and 1 no. type B were suspended in Mid-July due to storage issue.

-            6 nos. of segments at storage line 3 were toppled on 13 July 2015. The incident is under investigation.

Item

Number in this reporting period

Cumulative No. of Precast Segment Completed

(up to 28th of each month)

Segment Cast

101

2362

 

(b)     Off-site Storage:

Area

No. in Off-site Storage

A1

134

A2

224

A3

174

A4

34 (l/S segment only)

 

Precast Concrete Shell Casting

(a)    Summary of precast shell cast in the precast yard:

Type of Shell

Number of Precast Shell Cast in this reporting period

Cumulative No. of Precast Shell Completed

(up to 28th of each month)

CP1

Completed

94

CP2

Completed

12

CP3

2

14

CP4

Completed

8

CP5

Completed

6

CP6

Completed

4

CP11

Completed

1

CP12

Completed

1

F1 & F1A

1

2

F2 & F2A

0

0

 

Precast Column & Precast Pier Head Casting

(a)      Progress of the precast column & precast pier head casting:

-     All casting works for the pier heads with bearing support were completed (total 30 units) and the mould was dismantled in this report period.

-      3 moulds (2 piers and 1 pier head) are now in service for precasting works.

-      Totally 23 precast units (16 piers with 6m high, 4 monolithic pier heads and 3 pier heads with bearing support) were cast in this reporting period.

-      Cumulatively 277 precast units were cast.

Delivery  for Precast Concrete Elements (by barge)

(a)      Precast Deck Segments:

-             Number of additional barges engaged in this period: 0

-             Cumulative number of barges: 14 (2 barges tied up on L/S storage)

-             Number of deck segment deliveries in this period: 23 trips

-             Cumulative number of deck segment deliveries: 116 trips

Segment Types

Segment Delivered in this reporting period

Cumulative No. of Precast Segment Delivered

(up to 28th of each month)

A

57

224

B

0

0

C

2

6

D

3

4

E

74

342

(b)     Precast column units:

-             Number of additional barges engaged in this period: 0

-             Cumulative number of barges: 2

-             Number of column unit deliveries in this period: 3 trips

-             Cumulative number of column unit deliveries: 33 trips

 

Unit Types

Number of units delivered in this reporting period

Cumulative No. of Precast Column Delivered

(up to 28th of month)

3m

4

23

6m

13

86

PH1

2

22

PH2

0

14

 

(c)      Temporary storage of long span segments:

-            3 barges have been unloaded at CCCC4 yard. 2 barges remain with long span stored with P20 +1, +2. These barges will not unload at CCCC4 and the segments will remain stored on the barges until required for delivery to Hong Kong which is estimated to be mid to late September 2015.

(d)     General:

-       Delays in the segment unloading continue to impact on the delivery cycle to the extent that there are number of barges overstayed for 14 days in Hong Kong.

-       Loading and unloading was impacted by inclement weather (typhoon and heavy rain events).

-       It has been necessary to deploy 2 additional barges to columns delivery in order to overcome storage issues and potential stoppages at MBEC precast yard.

 

August 2015:

Land Viaduct (P85 to Abutment at SHT) & Marine Viaduct (P81 - P84)

(a)    P81L&R - 5 pours of column were completed.

(b)     P82L - ELS excavation works is in progress.

(c)      P82R - Pile cap was completed, column work is in progress.

(d)     P83L - ELS excavation works is in progress.

(e)      P83R ¡V Column works was completed.

(f)      Portal Works:

Pier Location

Progress

P84

Formwork erection is in progress

P85

Falsework and formwork erection is in progress

P86

Portal was concreted on 26 August 2015

P89

Portal was cast on 31 July 2015. Removal of formwork and falsework is in progress

P90

Portal was concreted on 30 June 2015

Removal of falsework and steel beams are in progress

P91

Portal was cast on 9 June 2015

Removal of steel cross beams and brackets at L-side was completed

P92

Portal was concreted on 17 July 2015. Removal of falsework is in progress

 

Marine Viaduct (P0 to P80)

Progress at P68

(a) P68 ¡V R3 and R6 were cast, total 10 piles were complete.

(b)  One RCD was set up on R1 casing on 27 Aug 2015 for socket drilling.

 

Progress at P69

(a)    Sheetpiling works at R-side is in progress.

(b)   Sheetpiling works at L-side was completed. Shear pins in L-side is in progress. Fabrication of L-side 1st and 2nd layer waling and struts works are in progress.

 

Progress at P75

(a)    Excavation to formation at the L-side continues.

 

Pile Cap Construction

(a)    Precast shells installation ¡V 6 CP1 at P5, P9, P10 and 2 CP3 at P56.

(b)   Stage 1 concreting was completed at P6, P8, P9 &P26L.

(c)    Stage 1 works is in progress at P5 and P56.

(d)   Stage 2 concreting was completed at P2R, P57, P79L and P80.

(e)    Stage 2 works is in progress at P6, P9 and P26L.

(f)    Kingpost installation and associated steel welding works for precast shelll installation are in progress at D17L.

(g)   Advanced concrete trimming (inside casing) works were carried out at P10, D17R, D18L&R, D19L, D20L&R, concrete trimming (inside cap shell) were carried out at P6 and P56.

 (h)       Submerged pile cap works with cofferdam:

Pier Location

Side

Progress

P72

L

Backfilling and removal of cofferdam completed on 20-Aug-15

R

Backfilling and removal of cofferdam completed on 20-Aug-15

P74

L

Concreting works of pile cap completed on 21-Aug-15

R

Excavation around the footprint of pile cap completed and additional of protection concrete wall was casted

Blinding layer was casted on 21-Aug-15

Trimming of pile head concrete is in progress

P75

L

Rock excavation is in progress

R

Rock excavation is in progress

 

In-situ Column (Single) Construction

(a)    1st lift works is in progress at P2 & P11.

(b)   1st lift concrete was poured at P11, P13, P55, P54-Ramp & P58-Ramp.

(c)    2nd lift works is in progress at P55, P54-Ramp & P58-Ramp.

(d)   2nd lift concrete was poured at P78.

(e)    3rd life works is in progress at P78.

(f)    Pier head works is in progress at P54, P58 & P70.

(g)   Pier head concrete was poured at P58 & P70.

 

Precast Column Erection

Description

Location completed in this reporting period

Number of Units erected/ Number of Columns completed in this reporting period

Cumulative No. of Piers completed

(up to 28th of each month)

Commencement

(ie. starting from 1st precast unit)

P14, P15

24 (P14-P16, P21, P24, P25, P27-P44)

Commencement

(ie. starting from 1st precast unit)

Completion

(ie.completed installation of pier head unit)

P25, P27

19 (P25, P27-P44)

Completion

(ie.completed installation of pier head unit)

Vertical Tendons Stressed

P30 (50%)

15.5 (P28, P29, P30, P32(1/2), P33-P44)

Vertical Tendons Stressed

Grouting Vertical Tendons

P29, P30, P35

14 (P28-P30, P34-P44)

Grouting Vertical Tendons

Pier Head Concrete

P36-P38

9 (P36-P44)

Pier Head Concrete

 

In-situ Double Blade Column Construction

Pier Location

Side

Progress

P17

L

Poured concrete up to 4th lift and started to construct 5th lift

R

Poured concrete up to 4th lift and started to construct 5th lift

P76

L

Poured concrete up to 2nd lift and 3rd lift in progress

R

Poured concrete up to 3rd lift and started to construct pierhead

P77

L

Poured concrete up to 3rd lift and started to construct pierhead

R

Poured concrete up to 3rd lift and started to construct pierhead

P79

L

Commenced in this reporting period

R

Commenced in this reporting period

 

 

 

Deck Erection

(a)      Setting up of Equipment:

Type of Equipment

Status

 

Lifting Frames 1 (LF1)

Assembly of first two sets of LF1 at WA4 almost completed.

Assembly of the third and fourth set of LF1 is on-going at WA4

Completion of assembly is targeted by end of September

 

Lifting Frames 3

(LF3)

First set of LF3 has started operation at P64

Second set of machines is being assembled at WA4 and is targeted to be completed in early September

 

Launching Gantry 1 (LG1)

Segment erection from P114 to P106 completed

 

Launching Gantry 2

 

(LG2)

No segment erection since 27 July 2015 due to machine breakdown

 

(b)     Segment erection:

Type

Location of Segments erected in this reporting period

Number of Segments erected in this reporting period

Cumulative No. of Segments erected

(up to 28th of each month)

LG1*

P106

28

330

LG2

-

0

160

LF3

P64

25

32

Typical Span SOP

P41,P42, P49

12

56

Long Span SOP

P19

6

12

          *  includes  crane erection for P109

 

Precast Segment

(a)      Segment Casting:

-            Production affected by inclement weather (5.5 days).

-            L/S segments temporary stored at CCCC4¡¦s Machong yard.

-            Off yard storage extension is in progress.

-            All types of segment moulds (34nos) were resumed works on 27 Aug 15.

-            6 nos. of segments at storage line 3 were toppled on 13 July 2015. The 6 damaged segments were removed and re-casting of the new segments are in progress.

-            Line 1 modification of L/S storage ground beam for MCH1 segment in progress.

Item

Number in this reporting period

Cumulative No. of Precast Segment Completed

(up to 28th of each month)

Segment Cast

93

2455

 

(b)     Off-site Storage:

Area

No. in Off-site Storage

A1

134 (A)

A2

206 (A)

A3

237 (A, B, E)

A4

116(L/S) & 16(D)

 

Precast Concrete Shell Casting

(a)    Summary of precast shell cast in the precast yard:

Type of Shell

Number of Precast Shell Cast in this reporting period

Cumulative No. of Precast Shell Completed

(up to 28th of each month)

CP1

Completed

94

CP2

Completed

12

CP3

Completed

14

CP4

Completed

8

CP5

Completed

6

CP6

Completed

4

CP11

Completed

1

CP12

Completed

1

F1 & F1A

0

2

F2 & F2A

1

1

 

Precast Column & Precast Pier Head Casting

(a)      Progress of the precast column & precast pier head casting:

-     All casting works for the 6m piers, monolithic pier heads were completed.

-      Totally 16 precast units (10 piers with 6m high, 6 monolithic pier heads) were cast in this reporting period.

-      Cumulatively 293 precast units were cast.

-      Precast pier head 2-R-H would be re-cast around September.

Delivery  for Precast Concrete Elements (by barge)

(a)      Precast Deck Segments:

-             Number of additional barges engaged in this period: 0

-             Cumulative number of barges: 14 (2 barges tied up on L/S storage)

-             Number of deck segment deliveries in this period: 21 trips

-             Cumulative number of deck segment deliveries: 137 trips


 

Segment Types

Segment Delivered in this reporting period

Cumulative No. of Precast Segment Delivered

(up to 28th of each month)

A

45

269

B

0

0

C

12

18

D

5

9

E

36

378

(b)     Precast column units:

-             Number of additional barges engaged in this period: 0

-             Cumulative number of barges: 2

-             Number of column unit deliveries in this period: 2 trips

-             Cumulative number of column unit deliveries: 35 trips

 

Unit Types

Number of units delivered in this reporting period

Cumulative No. of Precast Column Delivered

(up to 28th of month)

3m

0

23

6m

8

94

PH1

4

26

PH2

0

14

 

(c)      Temporary storage of long span segments:

-            2 barges remain with long span stored with P20 +1, +2. These barges will not unload at CCCC4 and the segments will remain stored on the barges until required for delivery to Hong Kong which is estimated to be mid to late September 2015.

(d)     General:

-       Delivery to LG2 has been interrupted by mechanical failure of support jacks during this period.

Status of Environmental Licences, Notification and Permits

 

2.11     The valid environmental licenses and permits were attached in the Monthly EM&A Reports.