2.1
The proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road
(HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao Bridge (HZMB) at the
HKSAR Boundary with the Hong Kong Boundary Crossing Facilities (HKBCF) situated
at the north eastern waters of the Hong Kong International Airport, opening a
new and direct connection route between Hong Kong, Macao and the Western Pearl
River Delta.
2.2
The HKLR comprises a 9.4km long viaduct section from the HKSAR boundary
to Scenic Hill on the Airport Island; a 1km tunnel section to the reclamation
formed along the east coast of the Airport Island and a 1.6km long at-grade
road section on the reclamation connecting to the HKBCF. The tunnel section of
HKLR will pass under Scenic Hill, Airport Road and Airport Railway to minimize
the environmental and visual impacts to Tung Chung residents.
2.3
An application (No ESB-110/2003) for an Environmental Impact Assessment
(EIA) Study Brief under Section 5(1) of the Environmental Impact Assessment
Ordinance (EIAO) was submitted by Highways Department (the Project Proponent)
on 8 October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong
Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway
Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North
Lantau Highway Connection has subsequently been renamed as HKLR. EPD issued an EIA Study Brief (No:
ESB-110/2003) in November 2003 to the Project Proponent to carry out an EIA
study.
2.4
An EIA Study (Reg. No. AEIAR-144/2009) has been undertaken to provide
information on nature and extent of environmental impacts arising from the
construction and operation of HKLR. The Environmental Permit was issued on 4
November 2009 (Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the
Director of Environmental Protection amends the Environmental Permit (No.
EP-352/2009) based on the Application No. VEP-339/2011 and the environmental
Permit (Permit No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the
Highways Department as the Permit Holder. Subsequently, the Director of
Environmental Protection amends the Environmental Permits (No. EP-352/2009/A,
EP-352/2009/B, EP-352/2009/C) based on the Application No. VEP-409/2013, VEP-411/2013
and VEP-459/2014 respectively. The environmental Permit (Permit No.
EP-352/2009/D) was then issued on 22 December 2014.
2.5
Figure 1a-d shows the layout of the Contract
and the scope of the Contract works comprises the following major items:
¡P
a dual 3-lane carriageway in the form of
viaduct from the HKSAR boundary (connecting with the HZMB Main Bridge) to the
Scenic Hill (connecting with the tunnel under separate Contract No.
HY/2011/03), of approximately 9.4km in length with a hard shoulder for each
bound of carriageway and a utilities trough on the outer edge of each bound of
viaducts;
¡P
a grade-separated turnaround facility located near San Shek Wan, composed of sliproads
in the form of viaduct with single-lane carriageway bifurcated from the HKLR
mainline with an elevated junction above the mainline;
¡P
provision of ancillary facilities including, but not limited to,
meteorological enhancement measures including the provisioning of anemometers
and modification of the wind profiler station at hillside of Sha Lo Wan,
provisioning of a compensatory marine radar, and provisioning of security
systems; and
¡P
associated civil, structural, geotechnical, marine, environmental
protection, landscaping, drainage and highways electrical and mechanical
(E&M) works, street lightings, traffic aids and sign gantries, marine
navigational aids, ship impact protection system, water mains and fire
hydrants, lightning protection system, structural health monitoring and
maintenance management system (SHM&MMS), supervisory control and data
acquisition (SCADA) system, as well as operation and maintenance provisions of
viaducts, provisioning of facilities for installation of traffic control and
surveillance system (TCSS), provisioning of facilities for installation of
telecommunication cables/equipments and reprovisioning works of affected existing
facilities/utilities.
2.6
Different parties with different levels of involvement in the Contract
organization include:
Supervising Officer¡¦s Representative (SOR) ¡V
Ove Arup & Partners Hong Kong Limited (ARUP)
Contractor ¡VDragages
-China Harbour-VSL JV (DCVJV)
Environmental Team (ET) ¡V Cinotech
Consultants Ltd. (Cinotech)
2.7
The proposed project organization and lines of communication with
respect to the on-site environmental management structure are shown in Figure 2. The key personnel contact
names and numbers are summarized in Table
2.1.
Table 2.1 Key
Contacts of the Contract
|
Party |
Position |
Name |
Phone
No. |
Fax
No. |
|
SOR (ARUP) |
CRE |
Mr. Michael Chan |
3767 5803 |
3767 5922 |
|
Mr. Colin Meadows |
3767 5801 |
|||
|
ENPO/IEC (Ramboll Environ) |
Environmental Project Office Leader |
Mr. Y. H Hui |
3465 2888 |
3465 2899 |
|
Independent Environmental Checker |
Mr. Antony Wong |
3465 2888 |
3465 2899 |
|
|
Contractor
(DCVJV) |
Deputy Project Director |
Mr. W.K Poon |
3121 6638 |
3121 6688 |
|
Environmental Officer |
Mr. CHU Chung Sing |
3121 6672 |
||
|
24-hour Hotline |
-- |
6898 6161 |
-- |
|
|
ET (Cinotech) |
Environmental Team Leader |
Dr. Priscilla Choy |
2151 2089 |
3107 1388 |
2.8
Ramboll Environ Hong Kong Limited (Ramboll
Environ) is employed
by the Highways Department as the Independent Environmental Checker (IEC) and
Environmental Project Office (ENPO) for the Project.
2.9
A copy of Contractor¡¦s
construction programme is provided in Appendix A.
Summary of Construction Works Undertaken During Reporting Period
2.10
The major site
activities undertaken in the reporting period included:
December
2015:
Land Viaduct
(P85 to Abutment at SHT) & Marine Viaduct (P81 - P84)
(a) P83R backfilling and removal of
wailings and struts are in progress.
(b) P83L pier head was completed.
(c) P82R reinstatement works
(backfilling and removal of wailings and struts) commenced.
(d) P82L 4 pours of column was
completed.
(e) P81R removal of cofferdam was
completed.
(f) P81L removal of cofferdam is in
progress.
(g) Portal Works:
|
Pier Location |
Progress |
|
P84 |
Removal of steel brackets are in progress |
|
P85 |
Removal of steel bracket system was completed |
(h) Formwork erection and steel
fixing for in-situ deck to Scenic Hill Abutment are in progress.
Marine Viaduct (P0 to P80)
Progress at
P68, P69 & P75
|
Pier Location |
Progress |
|
|
Right
Hand Side (RHS) |
Left Hand Side (LHS) |
|
|
P68 |
Cofferdam completed; Trimming of concrete pile head completed; Installation of formwork to be started. |
Remove rockfill platform
for rock breaking for cofferdam
installation |
|
P69 |
Cofferdam completed; Blinding layer completed. Trimming of concrete pile head
to be started. |
Cofferdam completed; Trimming of concrete pile head in progress |
|
P75 |
Enhancement work to cofferdam to improve water tightness
in progress |
Enhancement work to cofferdam to improve water tightness
in progress |
Pile Cap
Construction
(a) Precast
shells installation - all shells erected.
(b) Stage 1
concreting - D19R-F1 & D20R-F1.
(c) Stage 2
works - D19R-F1 & D20R-F1.
(d) Stage 2
concreting - D19R-F1.
(e) Kingpost
installation and associated steel welding works for precast shell installation:
all completed.
(f) Advanced
concrete trimming (inside casing) works:
all completed.
(g) Concrete
trimming (inside cap shell): all completed.
(h) Submerged
pile cap works with cofferdam (excluded P69 & P75):
|
Pier Location |
Side |
Progress |
Completed Pile Cap with Cofferdam Backfilled and
Removed |
|
P74 |
L |
Concreting works of pile cap completed on 21-Aug-15, pier
construction in progress |
P70 - P73, P76 - P77 |
|
R |
Concreting works of pile cap completed on 29-Sep-15, pier
construction in progress |
||
|
P78 |
L |
Concreting works of pile cap completed on 24-Jan-15, pier
construction in progress |
|
|
R |
Concreting works of pile cap completed on 30-Jan-15, pier
construction in progress |
In-situ Column (Single) Construction
(a) 1st lift works is in progress at P5 & P67.
(b) 1st lift concrete was poured at P5 & P67.
(c) 2nd lift works is in progress: P56 Ramp.
(d) 2nd lift concrete pouring: NIL.
(e) 3rd lift works is in progress at P55 Ramp, P57 Ramp and P74.
(f) 3rd lift concrete pouring: P55 Ramp, P57 Ramp and P74L.
(g) Pier head works is in progress:
P56, P57 and P78.
(h) Pier head concrete pouring: NIL.
Precast Column Erection
|
Description |
Pier Location (in this reporting period) |
Cumulative No. of Gridline (up to
28th of each month) |
|
Commencement
(i.e.
starting from 1st
precast unit) |
P12 |
29 (P12
- P16, P21 - P44) |
|
Completion
(i.e.
completed installation of pier head unit) |
P22,
P26 |
27 (P13
- P16, P21, P22, P24 -P44) |
|
Vertical
Tendons Stressed |
P13,
P14 |
22 (P13,
P14, P24, P25, P27 -P44) |
|
Grouting
Vertical Tendons |
P13,
P14, P24 |
22 (P13,
P14, P24, P25, P27 -P44) |
|
Pier
Head Concrete |
P27 -
P28 |
18 (P27
- P44) |
In-situ Double Blade Column Construction
|
Pier Location |
Side |
Progress |
Completed Columns |
|
P80 |
L |
All casting completed in December 2015, total 3 lifts |
P17 - P20 P71 - P73 P76 - P79 |
|
R |
All casting completed in December 2015, total 3 lifts |
Deck Erection
(a)
Setting up of Equipment:
|
Type of Equipment |
Status |
|
Lifting
Frames 1 (LF1) |
1st set loaded on
flat barge awaiting for mobilization at P20 |
(b)
Segment erection:
|
Type |
Location of Segments erected in this reporting
period |
Number of Segments erected in this reporting period |
Cumulative No. of Segments erected (up to 28th of each month) |
|
Launching
Gantry 1 (LG1)* |
P97,
P98, P99 and P100 |
60 |
554 |
|
Launching
Gantry 2 (LG2) |
P39,
P40 and P49 |
92 |
412 |
|
Hanger
Beam (HB) |
P20 |
8 |
8 |
|
Lifting
Frames 3 (LF3) |
P62,P63,P65,P66 |
43 |
166 |
|
Typical
Span SOP |
P36
and P54 |
8 |
96 |
|
Long
Span SOP |
P18 |
4 |
28 |
* includes crane erection for P109
Precast Segment
(a)
Segment Casting:
-
Production affected by inclement weather: 1 days.
-
Long span (L/S) segments temporary stored at
CCCC4¡¦s Machong yard (A4).
-
Off yard storage extension (A2 & A3) for
typical segments completed.
-
Line 1 modification of L/S storage ground beam for
MCH1 segment was completed. The corresponding modification of L/S storage
ground beam is in progress.
-
Additional Line 0 for storage for L/S segments
under construction.
-
L/S segments of P71 loaded on barges for temporary
storage (total 40 L/S segment were stored on 9 barges).
|
Item |
Number in this reporting period |
Cumulative No. of Precast Segment Completed (up to 28th of each month) |
|
Segment
Cast |
145 |
3164 |
(b)
Off-site Storage:
|
Area |
No. in Off-site Storage |
|
A1 |
0 |
|
A2 |
384 |
|
A3 |
222 |
|
A4 |
116(L/S) & 38(D) |
Delivery for Precast Concrete Elements (by barge)
(a)
Precast
Deck Segments:
- Number
of additional barges engaged in this period: 0.
- Number of deck segment deliveries in this period: 58 trips.
- Cumulative number of deck segment deliveries: 293 trips.
|
Segment Types |
Segment Delivered in this reporting period |
Cumulative No. of Precast Segment Delivered (up to 28th of each month) |
|
A |
195 |
723 |
|
B |
0 |
0 |
|
C |
10 |
38 |
|
D |
19 |
49 |
|
E |
74 |
586 |
(a)
Precast column units:
-
Number of additional barges
engaged in this period: 0
-
Cumulative number of barges: 1
-
Number of column unit
deliveries in this period: 2 trips
-
Cumulative number of column
unit deliveries: 46 trips
|
Unit Types |
Number of units delivered in this reporting period |
Cumulative No. of Precast Column Delivered (up to 28th of month) |
|
3m |
0 |
27 |
|
6m |
10 |
142 |
|
PH1 |
2 |
34 |
|
PH2 |
0 |
20 |
(b)
Temporary storage of long span segments:
-
First two long span barges sent
to Hong Kong P20-S1 & P20-S2.
-
7 barges remain at Zhongshan port loaded with long span segments.
-
Two barges have been loaded
with Long Span P71-S6 & P71-S7 for storage on pilecap
in site.
January 2016:
Land Viaduct
(P85 to Abutment at SHT) & Marine Viaduct (P81 - P84)
(a) P81R & P81L - Removal of
cofferdam was completed, and removal of filled platform is in progress.
(b) P82 - Reinstatement works
(backfilling and removal of wailings and struts) is in progress at R-side,
backfilling is in progress at L-side.
(c) P83R - Removal of sheet pile
cofferdam was completed and open cut excavation at P83R is in progress for
associate vertical seawall reinstatement at L-side.
(d) P83L - Removal of sheet piles is
in progress.
(e) P82L & P83L columns were
completed.
(f) Portal Works at P84 - Removal of
steel brackets was completed.
(g) In-situ end segments at P115
Abutment was completed.
Marine Viaduct (P0 to P80)
Pile Cap
Construction
(a) All
emerged pile cap completed except P68L.
(b) All submerged pile cap works with
cofferdam complete except P69R and P75.
(c) Progress at P68, P69 & P75:
|
Pier Location |
Progress |
|
|
Right Hand Side (RHS) |
Left Hand Side (LHS) |
|
|
P68 |
Concreting works of pile cap completed on 12-Jan-16 |
Remove rockfill
platform for rock breaking for
cofferdam installation and sheetpiles installation |
|
P69 |
Steel re-bar fixing for pile
cap in progress |
Concreting works of pile cap completed on 18-Jan-16. |
|
P75 |
Works to enhance water
tightness completed. Blinding layer in progress |
Enhancement work to cofferdam
to improve water tightness in progress |
In-situ Column (Single) Construction
(a) 2nd lift works is in progress: P67.
(b) 2nd lift concrete pouring: P56 Ramp.
(c) 3rd lift concrete pouring: P56 Ramp and P74R.
(d) Pier head works is in progress: P74.
(e) Pier head concrete pouring: P56 and P78.
Precast Column Erection
|
Description |
Pier Location (in this reporting period) |
Cumulative No. of Gridline (up to
28th of each month) |
|
Commencement (i.e. starting from 1st
precast unit) |
P10, P11 |
31
(P10-P16, P21-P44) |
|
Completion
(i.e.
completed installation of pier head unit) |
P22 |
27 (P13
- P16, P21, P22, P24 -P44) |
|
Vertical
Tendons Stressed |
P22,
P26 |
24
(P13, P14, P22, P24-P44) |
|
Grouting
Vertical Tendons |
P14,
P22, P26 |
24
(P13, P14, P22, P24-P44) |
|
Pier
Head Concrete |
P24,
P25 |
20
(P24, P25, P27-P44) |
Remarks: Strong
wind disruption as notified under Claim No.064 affected the erection works
In-situ Double Blade Column Construction
|
Pier Location |
Side |
Progress |
Completed Columns |
|
P69 |
L |
Formwork assembly |
P17 -
P20, P71 - P73, P76, P77, P79, P80, P82 and P83 (i.e.
all completed except P68, P69 & P75) |
|
R |
Formwork assembly |
Deck Erection
(a) Setting
up of Equipment: 2nd set of LF1 is ready for installation at P19.
(b)
Segment erection:
|
Type |
Location of Segments erected in this reporting
period |
Number of Segments erected in this reporting period |
Cumulative No. of Segments erected (up to 28th of each month) |
|
Launching
Gantry 1 (LG1)* |
P94,
P95, P96 and P97 |
93 |
672 |
|
Launching
Gantry 2 (LG2) |
P35, P36 and P37 |
108 |
548 |
|
Hanger
Beam (HB) |
P19 |
8 |
16 |
|
Lifting
Frames 1 (LF1) |
P20 |
4 |
4 |
|
Lifting
Frames 3 (LF3) |
P49,P50,P54 and P66 |
48 |
240 |
|
Typical
Span SOP |
P31 and P53 |
8 |
112 |
|
Long
Span SOP |
P17 |
6 |
36 |
* includes crane
erection for P109
Remarks: Strong wind disruption as
notified under Claim No.064 affected the erection works.
Precast Segment
(a)
Segment Casting:
-
Production affected by inclement weather: 14.5 days.
-
Long span (L/S) segments temporary stored at
CCCC4¡¦s Machong yard (A4).
-
Off yard storage extension (A2 & A3) for
typical segments was completed.
-
Line 1 modification of L/S storage ground beam for
MCH1 segment was completed. The corresponding modification of L/S storage
ground beam is in progress.
-
Additional Line 0 for storage for L/S segments is
under construction.
-
L/S segments of P71 loaded on barges for temporary
storage (total 40 L/S segments were stored on 9 barges).
|
Item |
Number in this reporting period |
Cumulative No. of Precast Segment Completed (up to 28th of each month) |
|
Segment
Cast |
115 |
3318 |
Remarks: Cumulative no.
includes 6 nos. of damaged segment due to toppled incident at the casting yard.
(b)
Off-site Storage:
|
Area |
No. in Off-site Storage |
|
A1 |
0 |
|
A2 |
222 |
|
A3 |
193 |
|
A4 |
112(L/S) & 38(D) |
Delivery for Precast Concrete Elements (by barge)
(a)
Precast
Deck Segments:
- Number
of additional barges engaged in this period: 0.
- Number of deck segment deliveries in this period: 51 trips.
- Cumulative number of deck segment deliveries: 349 trips.
|
Segment Types |
Segment Delivered in this reporting period |
Cumulative No. of Precast Segment Delivered (up to 28th of each month) |
|
A |
136 |
875 |
|
B |
2 |
2 |
|
C |
36 |
74 |
|
D |
10 |
61 |
|
E |
84 |
682 |
(b) Precast column units:
-
Number of additional barges
engaged in this period: 0
-
Cumulative number of barges: 1
-
Number of column unit delivery
trips in this period: 2 trips
-
Cumulative number of column
unit delivery trips: 48 trips
|
Unit Types |
Number of units delivered in this reporting period |
Cumulative No. of Precast Column Delivered (up to 28th of month) |
|
3m |
2 |
29 |
|
6m |
8 |
150 |
|
PH1 |
0 |
34 |
|
PH2 |
2 |
22 |
(c)
Temporary storage of long span segments:
-
4 barges remains at Zhongshan port loaded with long span segments.
-
Segments deliveries have been
affected during the last week of January 2016 due to inclement weather and
material break down at the precasting yard.
February 2016:
Land Viaduct
(P85 to Abutment at SHT) & Marine Viaduct (P81 - P84)
(a) P81R & P81L - Removal of
filled platform to intermediate stage was completed for SOP erection.
(b) P82 - Reinstatement works
(removal of sheet piles in P82R & P82L) is in progress.
(c) P83R - Removal of filled platform
at P83R is in progress.
(d) P83L ¡V Reinstatement of vertical
seawall is in progress.
(e) In-situ end segments at P115
Abutment was completed.
Marine Viaduct (P0 to P80)
Pile Cap
Construction
(a) All pile
cap construction was completed except P68L and P75.
(b) Progress at this reporting period
at P68, P69 & P75.
|
Pier Location |
Progress |
|
|
Right Hand Side (RHS) |
Left Hand Side (LHS) |
|
|
P68 |
Concreting works of pile cap
completed on 12-Jan-16 |
Concreting work of cofferdam
plug completed on 24-Feb-16 |
|
P69 |
Concreting works of pile cap
completed on 30-Jan-16. |
Concreting works of pile cap
completed on 18-Jan-16. |
|
P75 |
Re-bar steel fixing for pile
cap in progress |
Enhancement work to cofferdam
to improve water tightness in progress |
In-situ Column (Single) Construction
(a) 2nd lift concrete pouring: P67.
(b) 4th lift concrete pouring: P56 Ramp.
(c) Pier head works is in progress: P67.
(d) Pier head concrete pouring: P74.
Precast Column Erection
|
Description |
Pier Location (in this reporting period) |
Cumulative No. of Gridline (up to
28th of each month) |
|
Commencement
(i.e.
starting from 1st precast unit) |
P8, P9 |
33 (P8-P16,
P21-P44) |
|
Completion
(i.e.
completed installation of pier head unit) |
P11,
P23 |
29 (P11,
P13-P16, P21-P44) |
|
Vertical
Tendons Stressed |
P16,
P23 |
26
(P13, P14, P16, P22-P44) |
|
Grouting
Vertical Tendons |
P16 |
25
(P13, P14, P16, P22, P24-P44) |
|
Pier
Head Concrete |
P14, P26 |
22 (P14,
P24 -P44) |
Remarks: Strong
wind disruption as notified under Claim No.064 affected the erection works
In-situ Double Blade Column Construction
(a) All
in-situ double blade column was completed except P68, P69 and P75.
(b) Progress
at this reporting period at P69:
|
Pier Location |
Side |
Progress |
|
P69 |
L |
1st lift in
progress |
|
R |
1st lift in
progress |
Deck Erection
(a) Setting
up of Equipment: 2nd set of LF1 is installed at P19.
(b) Segment
erection in February 2016:
|
Type |
Location of Segments erected in this reporting
period |
Number of Segments erected in this reporting period |
Cumulative No. of Segments erected (up to 28th of each month) |
|
Launching
Gantry 1 (LG1)* |
P93,
P94 and P95 |
58 |
730 |
|
Launching
Gantry 2 (LG2) |
P33,
P34 and P35 |
92 |
640 |
|
Lifting
Frames 1 (LF1)
and Hanger Beam (HB) |
P19,
P20, P71 and P72 |
31 |
51 |
|
Lifting
Frames 3 (LF3) |
P49,P50
and P54 |
40 |
280 |
|
Typical
Span SOP |
P28,
P29, P30 and P55 |
16 |
128 |
|
Long
Span SOP |
P73,
P76 |
12 |
48 |
* includes crane
erection for P109
Remarks: Strong wind disruption and
cold weather as notified under Claim No.064 and 067 affected the erection
works.
Precast Segment
(a)
Segment Casting:
-
Production affected by inclement weather: 4.5 days.
-
Long span (L/S) segments temporary stored at
CCCC4¡¦s Machong yard (A4) were moved to Dong Tai
storage yard.
-
Transportation of 36 nos. of type D segments from
CCCC4 back to CCCC2 in progress for returning the storage area of CCCC4.
-
Additional Line 0 for storage for L/S segments is
under construction. 5 bays of storage, transverse rail and testing and
commissioning of 250T gantry were completed.
-
L/S segments of P71 are on barges for temporary
storage (total 8 L/S segments were stored on 2 barges).
|
Item |
Number in this reporting period |
Cumulative No. of Precast Segment Completed (up to 28th of each month) |
|
Segment
Cast |
87 |
3405 |
Remarks: Cumulative no.
excludes 7 nos. of damaged segment due to toppled incident at the casting yard.
(b)
Off-site Storage:
|
Area |
No. in Off-site Storage |
|
A1 |
0 |
|
A2 |
212 |
|
A3 |
191 |
|
A4 |
112(L/S) & 20(D) |
Delivery for Precast Concrete Elements (by barge)
(a)
Precast
Deck Segments:
- Number
of additional barges engaged in this period: 4.
- Number of deck segment deliveries in this period: 59 trips.
- Cumulative number of deck segment deliveries: 408 trips.
|
Segment Types |
Segment Delivered in this reporting period |
Cumulative No. of Precast Segment Delivered (up to 28th of each month) |
|
A |
144 |
1019 |
|
B |
0 |
2 |
|
C |
56 |
130 |
|
D |
14 |
75 |
|
E |
70 |
752 |
(b) Precast column units:
-
Number of additional barges
engaged in this period: 0
-
Cumulative number of barges: 1
-
Number of column unit delivery
trips in this period: 4 trips
-
Cumulative number of column
unit delivery trips: 52 trips
|
Unit Types |
Number of units delivered in this reporting period |
Cumulative No. of Precast Column Delivered (up to 28th of month) |
|
3m |
4 |
33 |
|
6m |
16 |
166 |
|
PH1 |
4 |
38 |
|
PH2 |
2 |
24 |
(c) Temporary storage of long span
segments:
-
2 barges remain at Zhongshan
port loaded with long span segments.
2.11
The valid environmental licenses and permits were attached in
the Monthly EM&A Reports.