Event / Action Plan for Air
Quality
|
EVENT |
ACTION |
||||||
|
ET |
IEC |
SO |
CONTRACTOR |
||||
|
ACTION
LEVEL |
|||||||
|
1.
Exceedance for one
sample |
1. Identify source, investigate the causes
of exceedance and propose remedial measures; 2. Inform IEC and SO; 3. Repeat measurement to confirm finding; 4. Increase monitoring frequency to daily. |
1. Check
monitoring data submitted by ET; 2. Check
Contractor¡¦s working method. |
1. Notify
Contractor. |
1. Rectify any unacceptable practice; 2. Amend working methods if appropriate. |
|||
|
2.Exceedance
for two or more consecutive samples |
1. Identify source; 2. Inform IEC and SO; 3. Advise the SO on the effectiveness of
the proposed remedial measures; 4. Repeat measurements to confirm
findings; 5. Increase monitoring frequency to daily; 6. Discuss with IEC and Contractor on
remedial actions required; 7. If exceedance continues, arrange
meeting with IEC and SO; 8. If exceedance stops, cease additional
monitoring. |
1. Check monitoring data submitted
by ET; 2. Check Contractor¡¦s working
method; 3. Discuss with ET and Contractor on
possible remedial measures; 4. Advise the ET on the
effectiveness of the proposed remedial measures; 5. Supervise Implementation of
remedial measures. |
1. Confirm receipt of notification of
failure in writing; 2. Notify Contractor; 3. Ensure remedial measures properly implemented. |
1. Submit proposals for remedial to SO within 3 working days of
notification; 2. Implement the agreed proposals; 3. Amend proposal if appropriate. |
|||
|
LIMIT LEVEL |
|||||||
|
1.Exceedance
for one sample |
1. Identify
source, investigate the causes of exceedance and propose remedial measures; 2. Inform SO, Contractor and EPD; 3. Repeat measurement to confirm finding; 4. Increase monitoring frequency to daily; 5. Assess effectiveness of Contractor¡¦s remedial actions
and keep IEC, EPD and SO informed of the results. |
1. Check
monitoring data submitted by ET; 2. Check Contractor¡¦s working method; 3. Discuss with ET and Contractor on possible remedial
measures; 4. Advise the SO on the effectiveness of the proposed
remedial measures; 5. Supervise
implementation of remedial measures. |
1. Confirm
receipt of notification of failure in writing; 2. Notify Contractor; 3. Ensure remedial measures properly implemented. |
1. Take immediate action to avoid further exceedance; 2. Submit proposals for remedial actions to IEC within 3 working
days of notification; 3. Implement the agreed proposals; 4. Amend
proposal if appropriate. |
|||
|
2.Exceedance
for two or more consecutive samples |
1. Notify
IEC, SO, Contractor and EPD; 2. Identify source; 3. Repeat measurement to confirm findings; 4. Increase monitoring frequency to daily; 5. Carry out analysis of Contractor¡¦s working procedures to
determine possible mitigation to be implemented; 6. Arrange meeting with IEC and SO to discuss the remedial
actions to be taken; 7. Assess effectiveness of Contractor¡¦s remedial actions and
keep IEC, EPD and SO informed of the results; 8. If exceedance stops, cease additional monitoring. |
1. Discuss
amongst SO, ET, and Contractor on the potential remedial actions; 2. Review Contractor¡¦s remedial actions whenever
necessary to assure their effectiveness and advise the SO accordingly; 3. Supervise the implementation of remedial measures. |
1. Confirm
receipt of notification of failure in writing; 2. Notify Contractor; 3. In consultation with the IEC, agree with the Contractor on the
remedial measures to be implemented; 4. Ensure remedial measures properly implemented; 5. If exceedance continues, consider what portion of the work is
responsible and instruct the Contractor to stop that portion of work until
the exceedance is abated. |
1. Take immediate action to avoid further exceedance; 2. Submit proposals for remedial
actions to IEC within 3 working days of notification; 3. Implement the agreed proposals; 4. Resubmit proposals if problem
still not under control; 5. Stop the relevant portion of
works as determined by the SO until the exceedance is abated. |
|||
Abbreviations: ET ¡V Environmental Team, IEC ¡V Independent
Environmental Checker, SO ¡V Supervising Office
Event / Action Plan for
Construction Noise
|
EVENT |
ACTION |
|||
|
|
ET |
IEC |
SO |
CONTRACTOR |
|
Action Level |
1. Identify source, investigate the
causes of exceedance and propose remedial measures; 2. Notify IEC and Contractor; 3. Report the results of investigation to
the IEC, SO and Contractor; 4. Discuss with the Contractor and
formulate remedial measures; 5. Increase monitoring frequency to check
mitigation effectiveness. |
1. Review the analysed results
submitted by the ET; 2. Review the proposed remedial
measures by the Contractor and advise the SO accordingly; 3.
Supervise the implementation of remedial measures. |
1. Confirm receipt of notification of
failure in writing; 2. Notify Contractor; 3. Require Contractor to propose remedial
measures for the analysed noise problem; 4. Ensure remedial measures are properly
implemented |
1. Submit noise mitigation proposals
to IEC; 2. Implement noise mitigation
proposals. |
|
Limit Level |
1. Identify source; 2. Inform IEC, SO, EPD and Contractor; 3. Repeat measurements to confirm
findings; 4. Increase monitoring frequency; 5. Carry out analysis of Contractor¡¦s working
procedures to determine possible mitigation to be implemented; 6. Inform IEC, SO and EPD the causes and actions
taken for the exceedances; 7. Assess effectiveness of Contractor¡¦s remedial
actions and keep IEC, EPD and SO informed of the results; 8. If exceedance stops, cease additional
monitoring. |
1. Discuss amongst SO, ET, and Contractor on the
potential remedial actions; 2. Review
Contractors remedial actions whenever necessary to assure their effectiveness
and advise the SO accordingly; 3. Supervise
the implementation of remedial measures. |
1. Confirm receipt of notification of failure in
writing; 2. Notify Contractor; 3. Require Contractor to propose remedial
measures for the analysed noise problem; 4. Ensure remedial measures properly
implemented; 5. If exceedance continues, consider what
portion of the work is responsible and instruct the Contractor to stop that
portion of work until the exceedance is abated. |
1. Take immediate action to avoid further
exceedance; 2. Submit proposals for remedial actions to
IEC within 3 working days of
notification; 3. Implement the agreed proposals; 4. Resubmit proposals if problem still not under
control; 5. Stop the relevant portion of works as
determined by the SO until the exceedance is abated. |
Event and Action Plan for Water Quality
|
Event |
ET Leader |
IEC |
SO |
Contractor |
|
Action level being exceeded by
one sampling day |
Repeat in situ
measurement on next day of exceedance to confirm findings; Identify source(s) of impact; Inform IEC, contractor and SO; Check monitoring data, all plant, equipment and Contractor's
working methods. |
Check monitoring data submitted by ET and Contractor¡¦s working
methods. |
Confirm receipt of notification of non-compliance in writing; Notify Contractor. |
Inform the SO and confirm notification of the non-compliance in
writing; Rectify unacceptable practice; Amend working methods if appropriate. |
|
Action level being exceeded by two or more consecutive sampling days |
Repeat measurement on next day of exceedance to confirm
findings; Identify source(s) of impact; Inform IEC, contractor, SO and EPD; Check monitoring data, all plant, equipment and Contractor's
working methods; Discuss
mitigation measures with IEC, ER and Contractor; Ensure mitigation measures are implemented; Increase the monitoring frequency to daily until no exceedance
of Action level; |
Check monitoring data submitted by ET and Contractor¡¦s working
method; Discuss with ET and Contractor on possible remedial actions; Review the proposed mitigation measures submitted by Contractor
and advise the SO accordingly; Supervise the implementation of mitigation measures. |
Discuss with IEC on the proposed mitigation measures; Ensure mitigation measures are properly implemented; Assess the effectiveness of the implemented mitigation measures. |
Inform the Supervising Officer and confirm notification of the
non-compliance in writing; Rectify unacceptable practice; Check all plant and equipment and consider changes of working
methods; Submit proposal of additional mitigation measures to SO within 3
working days of notification and discuss with ET, IEC and SO; Implement the agreed mitigation measures. |
|
Limit
level being exceeded by one sampling day |
Repeat measurement on next day of exceedance to confirm
findings; Identify source(s) of impact; Inform IEC, contractor, SO and EPD; Check monitoring data, all plant, equipment and Contractor's
working methods; Discuss mitigation measures with IEC, SO and Contractor; |
Check monitoring data submitted by ET and Contractor¡¦s working
method; Discuss with ET and Contractor on possible remedial actions; Review the proposed mitigation measures submitted by Contractor
and advise the SO accordingly. |
Confirm receipt of notification of failure in writing; Discuss with IEC, ET and Contractor on the proposed mitigation
measures; Request Contractor to review the working methods. |
Inform the SO and confirm notification of the non-compliance in
writing; Rectify unacceptable practice; Check all plant and equipment and consider changes of working
methods; Submit proposal of mitigation measures to SO within 3 working
days of notification and discuss with ET, IEC and SO. |
|
Limit level being exceeded by two or more consecutive sampling
days |
Repeat measurement on next day of exceedance to confirm
findings; Identify source(s) of impact; Inform IEC, contractor, SO and EPD; Check monitoring data, all plant, equipment and Contractor's
working methods; Discuss mitigation measures with IEC, SO and Contractor; Ensure mitigation measures are
implemented; Increase the
monitoring frequency to daily until no exceedance of Limit level for two
consecutive days; |
Check monitoring data submitted by ET and Contractor¡¦s working
method; Discuss with ET and Contractor on possible remedial actions; Review the Contractor¡¦s mitigation measures whenever necessary
to assure their effectiveness and advise the SO accordingly; Supervise the implementation of mitigation measures. |
Discuss with IEC, ET and Contractor on
the proposed mitigation measures; Request Contractor to critically review the working methods; Make agreement on the mitigation measures to be
implemented; Ensure mitigation measures are properly implemented; Consider and instruct, if necessary, the Contractor to slow down
or to stop all or part of the construction activities until no exceedance of
Limit level. |
Take immediate action to avoid further exceedance; Submit proposal of mitigation measures to SO within 3 working
days of notification and discuss with ET, IEC and SO; Implement the agreed mitigation measures; Resubmit proposals of mitigation measures if problem still not
under control; As directed by the Supervising Officer, to slow down or to stop
all or part of the construction activities until no exceedance of Limit
level. |
Event Action Plan for Dolphin
Monitoring
|
Event
|
ET
Leader |
IEC
|
ER
/ SOR |
Contractor
|
|
Action
Level |
1. Repeat statistical data analysis to confirm findings. 2. Review all available and relevant data, including raw data
and statistical analysis results of other parameters covered in the EM&A,
to ascertain if differences are as a result of natural variation or
previously observed seasonal differences. 3. Identify source(s) of impact. 4. Inform the IEC, ER/SOR and Contractor, 5. Check monitoring data. 6. Review to ensure all the dolphin protective measure are
fully and properly implemented and advise on additional measures if
necessary. |
1.
Check monitoring data
submitted by ET and Contractor. 2.
Discuss monitoring
results and findings with the ET and the Contractor. |
1. Discuss monitoring data with the IEC and any other
measures proposed by the ET. 2.
If ER/SOR is satisfied
with the proposal of any other measures, ER/SOR to signify the agreement in
writing on the measures to be implemented. |
1.
Inform the ER/SOR and confirm notification of the
non-compliance in writing. 2.
Discuss with the ET and
the IEC to propose measures to the IEC and the ER/SOR. 3.
Implement the agreed
measures. |
|
Event |
ET
Leader |
IEC |
ER
/ SOR |
Contractor |
|
Limit
Level |
1.
Repeat statistical data
analysis to confirm findings. 2.
Review all available and
relevant data, including raw data and statistical analysis results of other
parameters covered in the EM&A, to ascertain if differences are as a
result of natural variation or previously observed seasonal differences. 3.
Identify source(s) of
impact. 4.
Inform the IEC, ER/SOR
and Contractor of findings, 5.
Check monitoring data. 6.
Repeat reviewing to
ensure all the dolphin protective measure are fully and properly implemented
and advise on additional measures if necessary. 7.
If the ET proves that the
source of impact is caused by any of the construction activity by the works
contract, the ET to arrange a meeting to discuss with IEC, ER/SOR and
Contractor for necessity of additional dolphin monitoring, and/or any other
potential mitigation measures (eg, consider to modify the perimeter silt
curtain or consider to control/temporarily stop relevant construction
activities¡Ketc), and submit to the IEC a proposal of additional dolphin
monitoring and/or mitigation measures where necessary. |
1. Check monitoring data submitted by ET and
Contractor; 2. Discuss monitoring results and findings with
the ET and the Contractor; 3. Attend the meeting to discuss with ET,
ER/SOR and Contractor the necessity of additional dolphin monitoring and
other potential mitigation measures. 4. Review proposals for additional
monitoring and any other mitigation measures submitted by ET and Contractor,
and advise ER/SOR of the results and findings accordingly. 5. Supervise / Audit the implementation of
additional monitoring and/or any other mitigation measures, and advise ER/SOR
of the results and findings accordingly. |
1. Attend the meeting to discuss with ET, IEC and Contractor
the necessity of additional dolphin monitoring and any other potential
mitigation measures. 2. If ER/SOR is satisfied with proposals for additional
dolphin monitoring and/or any other mitigation measures submitted by the ET
and Contractor and verified by the IEC, ER/SOR to signify the agreement in
writing on such proposals and any other mitigation measures. 3. Supervise the implementation of
additional monitoring and/or any other mitigation
measures. |
1. Inform the ER/SOR and confirm notification of the non-compliance in writing;
2. Attend the meeting to discuss with ET,
IEC and ER/SOR the necessity of additional dolphin monitoring and any other
potential mitigation measures. 3. Jointly submit with ET to IEC a proposal
of additional dolphin monitoring and/or any other mitigation measures when
necessary. 4. Implement the agreed additional dolphin
monitoring and/or any other mitigation measures. |