EXECUTIVE SUMMARY

Introduction

1.              This is the 15th Quarterly Environmental Monitoring and Audit (EM&A) Report prepared by Cinotech Consultants Limited for the project ¡§Contract No. HY/2011/09 ¡V Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road ¡V Section between HKSAR Boundary and Scenic Hill¡¨ (hereinafter called the ¡§Contract¡¨). This report documents the findings of EM&A Works performed in the period between September to November 2016.

Environmental Monitoring and Audit Progress

2.              A summary of the monitoring activities in this reporting period is listed in Table I below:

Table I            Summary Table for Monitoring Activities in the Reporting Period

Parameter(s)

Monitoring Date(s)

1-hr TSP Monitoring

2nd, 8th, 14th, 20th, 26th and 30th September 2016

6th, 12th, 18th, 24th and 28th October 2016

3rd, 9th, 15th, 21st and 25th November 2016

24-hr TSP Monitoring

Noise Monitoring

9th, 15th, 21st and 27th September 2016

7th, 13th, 19th and 25th October 2016

4th, 10th, 16th and 22nd November 2016

Water Quality Monitoring

2nd, 5th, 7th, 10th, 12th, 14th, 17th, 19th, 21st, 24th, 26th, 28th and 30th September 2016

3rd, 5th, 7th, 11th, 13th, 15th, 17th, 19th, 22nd, 24th, 26th, 28th and 31st October 2016

2nd, 4th, 8th, 10th, 12th, 14th, 16th, 18th, 22nd, 24th, 26th, 28th and 30th November 2016

Dolphin Monitoring (Line-transect Vessel Surveys)

9th and 20th September 2016

14th and 20th October 2016

4th and 11th November 2016

Environmental Site Inspection

6th, 13th, 20th and 27th September 2016

4th, 11th, 18th and 25th October 2016

1st, 8th, 15th, 22nd and 29th November 2016

Archaeological Site Inspection

20th September 2016

Breaches of Action and Limit Levels

3.              Summary of the environmental exceedances of the reporting period is tabulated in Table II.

Table II          Summary Table for Events Recorded in the Reporting Period

 

Environmental Monitoring

Parameter

No. of Exceedance

No. of Exceedance related to the Construction Activities of this Contract

Action Level

Limit Level

Action Level

Limit Level

Air Quality

1-hr TSP

0

0

0

0

24-hr TSP

0

0

0

0

Noise

Leq(30min)

0

0

0

0

Water Quality

Dissolved Oxygen (DO) (Surface & Middle)

0

0

0

0

Dissolved Oxygen (DO) (Bottom)

0

0

0

0

Turbidity

0

0

0

0

Suspended Solids (SS)

39

6

0

0

Dolphin Monitoring

Line-transect Vessel Surveys

0

0

0

0

 

4.              Environmental monitoring works were performed in the reporting period and all monitoring results were checked and reviewed.  The details of each exceedance were attached in the Monthly EM&A Reports.

Complaint Log

 

5.              No environmental complaint was received in the reporting period.

Notification of Summons and Successful Prosecutions

 

6.              No notification of summons and successful prosecution was received in the reporting period.

Reporting Changes

 

7.              This report has been developed in compliance with the reporting requirements for the quarterly EM&A Summary Report as required by the EM&A Manual for Hong Kong Link Road (EM&A Manual).

Future Key Issues

8.              Major site activities for the coming reporting month will include:

WA4

l Cross Beam Precast Shell construction

 

Ancillary and Associated Facilities

l E&M installation

l E&M ducting installation

l Construction of Load Centre (CL1)

l Installation of carrier drains

l Installation of precast parapet skins

l Erection of Radar Platform

l Construction of median and side barriers

l Construction of longitudinal stitching

l Erection of gantry posts for Sign gantry

l Reinstatement of slope area and drainage works

l Reinstatement of sloping seawall

 

Marine Viaduct (P0 to P80)

 

Deck Erection

l Segment erection

l Erection of SOP segments

l Erection of cantilever

l Construction of cross beam precase shell

l In-situ RC works

l Erection of precase SOP unit to Turnaround

l Alignment and levels adjustment

l Construction of temporary platform

 

External Prestressing Tendon Installation

 

Internal Prestressing Grouting