2.1
The proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road
(HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao Bridge (HZMB) at the
HKSAR Boundary with the Hong Kong Boundary Crossing Facilities (HKBCF) situated
at the north eastern waters of the Hong Kong International Airport, opening a
new and direct connection route between Hong Kong, Macao and the Western Pearl
River Delta.
2.2
The HKLR comprises a 9.4km long viaduct section from the HKSAR boundary
to Scenic Hill on the Airport Island; a 1km tunnel section to the reclamation
formed along the east coast of the Airport Island and a 1.6km long at-grade
road section on the reclamation connecting to the HKBCF. The tunnel section of
HKLR will pass under Scenic Hill, Airport Road and Airport Railway to minimize
the environmental and visual impacts to Tung Chung residents.
2.3
An application (No ESB-110/2003) for an Environmental Impact Assessment
(EIA) Study Brief under Section 5(1) of the Environmental Impact Assessment
Ordinance (EIAO) was submitted by Highways Department (the Project Proponent)
on 8 October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong
Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway
Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North
Lantau Highway Connection has subsequently been renamed as HKLR. EPD issued an EIA Study Brief (No:
ESB-110/2003) in November 2003 to the Project Proponent to carry out an EIA
study.
2.4
An EIA Study (Reg. No. AEIAR-144/2009) has been undertaken to provide
information on nature and extent of environmental impacts arising from the
construction and operation of HKLR. The Environmental Permit was issued on 4
November 2009 (Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the
Director of Environmental Protection amends the Environmental Permit (No.
EP-352/2009) based on the Application No. VEP-339/2011 and the environmental
Permit (Permit No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the
Highways Department as the Permit Holder. Subsequently, the Director of
Environmental Protection amends the Environmental Permits (No. EP-352/2009/A,
EP-352/2009/B, EP-352/2009/C) based on the Application No. VEP-409/2013, VEP-411/2013
and VEP-459/2014 respectively. The environmental Permit (Permit No.
EP-352/2009/D) was then issued on 22 December 2014.
2.5
Figure 1a-d shows the layout of the Contract
and the scope of the Contract works comprises the following major items:
¡P
a dual 3-lane carriageway in the form of
viaduct from the HKSAR boundary (connecting with the HZMB Main Bridge) to the
Scenic Hill (connecting with the tunnel under separate Contract No.
HY/2011/03), of approximately 9.4km in length with a hard shoulder for each
bound of carriageway and a utilities trough on the outer edge of each bound of
viaducts;
¡P
a grade-separated turnaround facility located near San Shek Wan, composed of sliproads
in the form of viaduct with single-lane carriageway bifurcated from the HKLR
mainline with an elevated junction above the mainline;
¡P
provision of ancillary facilities including, but not limited to, meteorological
enhancement measures including the provisioning of anemometers and modification
of the wind profiler station at hillside of Sha Lo Wan, provisioning of a
compensatory marine radar, and provisioning of security systems; and
¡P
associated civil, structural, geotechnical, marine, environmental
protection, landscaping, drainage and highways electrical and mechanical
(E&M) works, street lightings, traffic aids and sign gantries, marine
navigational aids, ship impact protection system, water mains and fire
hydrants, lightning protection system, structural health monitoring and
maintenance management system (SHM&MMS), supervisory control and data
acquisition (SCADA) system, as well as operation and maintenance provisions of
viaducts, provisioning of facilities for installation of traffic control and
surveillance system (TCSS), provisioning of facilities for installation of
telecommunication cables/equipments and reprovisioning works of affected existing
facilities/utilities.
2.6
Different parties with different levels of involvement in the Contract
organization include:
Supervising Officer¡¦s Representative (SOR) ¡V
Ove Arup & Partners Hong Kong Limited (ARUP)
Contractor ¡VDragages
-China Harbour-VSL JV (DCVJV)
Environmental Team (ET) ¡V Cinotech
Consultants Ltd. (Cinotech)
2.7
The proposed project organization and lines of communication with
respect to the on-site environmental management structure are shown in Figure 2. The key personnel contact
names and numbers are summarized in Table
2.1.
Table 2.1 Key
Contacts of the Contract
Party |
Position |
Name |
Phone
No. |
Fax
No. |
SOR (ARUP) |
CRE |
Mr. Michael Chan |
3767 5803 |
3767 5922 |
Mr. Colin Meadows |
3767 5801 |
|||
ENPO/IEC (Ramboll Environ) |
Environmental Project Office Leader |
Mr. Y. H Hui |
3465 2888 |
3465 2899 |
Independent Environmental Checker |
Mr. Antony Wong |
3465 2888 |
3465 2899 |
|
Contractor
(DCVJV) |
Deputy Project Director |
Mr. W.K Poon |
3121 6638 |
3121 6688 |
Environmental Officer |
Mr. CHU Chung Sing |
3121 6672 |
||
24-hour Hotline |
-- |
6898 6161 |
-- |
|
ET (Cinotech) |
Environmental Team Leader |
Dr. Priscilla Choy |
2151 2089 |
3107 1388 |
2.8
Ramboll Environ Hong Kong Limited (Ramboll
Environ) is employed
by the Highways Department as the Independent Environmental Checker (IEC) and
Environmental Project Office (ENPO) for the Project.
2.9
A copy of Contractor¡¦s
construction programme is provided in Appendix A.
Summary of Construction Works Undertaken During Reporting Period
2.10
The major site
activities undertaken in the reporting period included:
September
2016:
Ancillary and
Associated Facilities
(a) P115 & P114 interface area -
Reinstatement of slope area temporarily on-hold pending for drainage and
reinstatement detailing;
(b) Installation of precast parapet
skins between P44 to P38 is in progress. The Progress is as follows:
Item |
Number in this month |
Cumulative No. of
Precast Parapet Completed (up to end of month) |
Parapet
Casting |
345 |
1522 |
Parapet
Installation |
68 |
688 |
(c) Construction of side barriers
from P103 to P113 is in progress, currently total 177m in-situ side barriers
were cast and 51 m precast side barriers were installed;
(d) Construction of median barriers
from P112 to P99 is in progress, currently total 165m of in-situ median
barriers were cast and 96m precast median barriers were installed;
(e) Construction of longitudinal
stitching between P99 to P102 (concrete planking) is in progress;
(f) E&M installation at ML6
continues;
(g) E&M ducting installation at
ML15 to ML17;
(h) Construction of Load Centre 1
(LC1) commence;
(i) Installation of carrier drains
from P113 to P106 is in progress;
(j) Erection of Radar Platform at P20
is in progress.
Deck Erection
(a)
Segment erection in September 2016:
Type |
Location of Segments erected in this reporting
period |
Number of Segments erected in this reporting period |
Cumulative No. of Segments erected (up to 28th of each month) |
Launching
Gantry 1 (LG1)* |
All
completed |
0 |
1020 |
Launching
Gantry 2 (LG2) |
P13
and P12 |
120 |
1316 |
Lifting
Frames 1 (LF1)
and Hanger Beam (HB) |
P71,
P73, P76, P77 and P79 |
52 |
622 |
Lifting
Frames 3 (LF3)
and Hanger Beam (HB) |
P52,
P60 & P76 |
33 |
686 |
Typical
Span SOP |
P08,
P07, P06 and P05 |
16 |
224 |
Long
Span SOP |
P68
& P82 |
10 |
82 |
Movement
Joint (MJ) SOP Airport Channel |
N/A |
0 |
8 |
Short
Span (SS) SOP type B |
P57
& P58 |
4 |
12 |
External Prestressing Tendon Installation
Viaduct |
Activities |
Quantities |
Unit |
Done % |
ML19C |
Threading Stressing Grouting |
47.55 12 9.42 |
T U M3 |
100% 100% 100% |
ML19R |
Threading Stressing Grouting |
48.65 12 9.64 |
T U M3 |
100% 100% 100% |
ML19L |
Threading Stressing Grouting |
46.91 12 9.29 |
T U M3 |
100% 100% 100% |
ML18R |
Threading Stressing Grouting |
77.90 18 15.38 |
T U M3 |
100% 100% 100% |
ML18L |
Threading Stressing Grouting |
76.40 18 15.08 |
T U M3 |
100% 100% 100% |
ML17R |
Threading Stressing Grouting |
63.09 16 12.44 |
T U M3 |
100% 100% 100% |
ML17L |
Threading Stressing Grouting |
62.86 16 12.39 |
T U M3 |
100% 100% 100% |
ML16R |
Threading Stressing Grouting |
56.69 15 9.91 |
T U M3 |
100% 100% 78% |
ML16L |
Threading Stressing Grouting |
87.34 18 17.2 |
T U M3 |
100% 100% 70% |
ML07R |
Threading Stressing Grouting |
129.58 32 25.59 |
T U M3 |
26% 17% 0% |
ML07L |
Threading Stressing Grouting |
140.43 32 27.76 |
T U M3 |
24% 16% 0% |
ML06R |
Threading Stressing Grouting |
113.04 24 22.35 |
T U M3 |
100% 100% 100% |
ML06L |
Threading Stressing Grouting |
113.04 24 22.35 |
T U M3 |
100% 100% 100% |
ML05R |
Threading Stressing Grouting |
113.68 24 22.48 |
T U M3 |
100% 100% 70% |
ML05L |
Threading Stressing Grouting |
112.39 24 22.22 |
T U M3 |
100% 100% 70% |
ML04R |
Threading Stressing Grouting |
113.04 24 22.35 |
T U M3 |
30% 30% 0% |
ML04L |
Threading Stressing Grouting |
113.04 24 22.35 |
T U M3 |
30% 30% 0% |
ML03R |
Threading Stressing Grouting |
199.65 32 39.615 |
T U M3 |
72% 31% 0% |
ML03L |
Threading Stressing Grouting |
201.13 32 29.9 |
T U M3 |
00% 00% 0% |
ML02R |
Threading Stressing Grouting |
113.72 24 22.49 |
T U M3 |
5% 8% 0% |
ML02L |
Threading Stressing Grouting |
113.73 24 22.49 |
T U M3 |
5% 8% 0% |
Internal Prestressing Grouting Progress
Viaduct |
Activities |
Quantities |
Unit |
Done % |
ML19C |
Air
test & Grouting |
14.09 |
M3 |
100% |
ML19R |
Air
test & Grouting |
14.90 |
M3 |
100% |
ML19L |
Air
test & Grouting |
13.90 |
M3 |
100% |
ML18R |
Air
test & Grouting |
25.24 |
M3 |
100% |
ML18L |
Air
test & Grouting |
24.76 |
M3 |
96% |
ML17R |
Air
test & Grouting |
23.47 |
M3 |
100% |
ML17L |
Air
test & Grouting |
23.46 |
M3 |
100% |
ML16R |
Air
test & Grouting |
36.54 |
M3 |
99% |
ML16L |
Air
test & Grouting |
35.46 |
M3 |
99% |
ML15R |
Air
test & Grouting |
39.34 |
M3 |
45% |
ML15L |
Air
test & Grouting |
39.69 |
M3 |
44% |
ML09R |
Air
test & Grouting |
63.27 |
M3 |
24% |
ML09L |
Air
test & Grouting |
57.86 |
M3 |
32% |
ML08R |
Air
test & Grouting |
36.58 |
M3 |
31% |
ML08L |
Air
test & Grouting |
36.56 |
M3 |
31% |
ML07R |
Air
test & Grouting |
59.61 |
M3 |
46% |
ML07L |
Air
test & Grouting |
60.05 |
M3 |
55% |
ML06R |
Air
test & Grouting |
58.31 |
M3 |
100% |
ML06L |
Air
test & Grouting |
58.31 |
M3 |
100% |
ML05R |
Air
test & Grouting |
58.62 |
M3 |
55% |
ML05L |
Air
test & Grouting |
58.01 |
M3 |
91% |
ML04R |
Air
test & Grouting |
57.64 |
M3 |
32% |
ML04L |
Air
test & Grouting |
57.69 |
M3 |
41% |
ML03R |
Air
test & Grouting |
126.65 |
M3 |
0% |
ML03L |
Air
test & Grouting |
127.63 |
M3 |
0% |
ML02R |
Air
test & Grouting |
62.74 |
M3 |
11% |
ML02L |
Air
test & Grouting |
62.74 |
M3 |
10% |
Precast Segment
(a)
Segment Casting:
-
Production affected by inclement weather: 2.5 days.
-
All new moulds are under full operation.
-
16 nos. of new Type B* segments were completed in
early September 2016 for accommodating I-beam connection of turnaround
facility.
-
Mould no. 11 has been modifying from Type C
production to Type A after casting P74. There are 10 nos
moulds in operation for Type A segment production at
the end of Sep 2016.
-
All SOPs, type CH1 to 10 and type C casting were
completed in mid-September 2016.
Item |
Number in this reporting period |
Cumulative No. of Precast Segment Completed (up to 28th of each month) |
Segment
Cast |
306 |
5228 |
Remarks: Cumulative no.
excludes the 7 nos. recast following damages to segments due to toppled
incident at the casting yard.
(b)
Off-site Storage:
Area |
No. in Off-site Storage |
A3 |
36 |
Delivery for Precast Concrete Elements (by barge)
(a)
Precast
Deck Segments:
- Number
of barges engaged in this period: 18.
- Number of deck segment deliveries in this period: 42 trips.
- Cumulative number of deck segment deliveries: 818 trips.
Segment Types |
Segment Delivered in this reporting period |
Cumulative No. of Precast Segment Delivered (up to 28th of each month) |
A |
117 |
2001 |
B |
12 |
42 |
C |
80 |
794 |
D |
4 |
196 |
E |
0 |
1014 |
October
2016:
Ancillary and
Associated Facilities
(k) P115 & P114 interface area -
Reinstatement of slope area temporarily on-hold pending for drainage and
reinstatement detailing coupling with the additional maintenance path;
(l) Reinstatement of sloping seawall
at P102 and P103;
(m) Installation of precast parapet
skins between P44 to P38 is in progress. The Progress is as follows:
Item |
Number in this month |
Cumulative No. of
Precast Parapet Completed (up to end of month) |
Completion
Percentage (%) |
Parapet
Casting |
462 |
1984 |
29.5% |
Parapet
Installation |
242 |
930 |
13.8% |
(n) Construction of side barriers
from P102 to P113 is in progress, currently total 229m in-situ side barriers
were cast and 183m precast side barriers were installed;
(o) Construction of median barriers
from P112 to P97 is in progress, currently total 218m of in-situ median
barriers were cast and 274m precast median barriers were installed;
(p) Construction of longitudinal
stitching between P96 to P102 (concrete planking) is in progress;
(q) E&M installation at ML4
continues;
(r) E&M ducting installation at
ML6 continues;
(s) Construction of Load Centre 1
(LC1) was completed ;
(t) Installation of carrier drains
from P113 to P98 is in progress ;
(u) Erection of Radar Platform at P20
is in progress.
Deck Erection
(b)
Segment erection in October 2016:
Type |
Location of Segments erected in this reporting
period |
Number of Segments erected in this reporting period |
Cumulative No. of Segments erected (up to 28th of each month) |
Launching
Gantry 1 (LG1) |
All
completed |
0 |
1020 |
Launching
Gantry 2 (LG2) |
P11,
P10 and P09 |
124 |
1440 |
Lifting
Frames 1 (LF1)
and Hanger Beam (HB) |
P70,
P71, P77 and P79 |
104 |
694 |
Lifting
Frames 3 (LF3)
and Hanger Beam (HB) |
P52, P53, P60 & P76 |
44 |
762 |
Typical
Span SOP |
P3 and
P4 |
8 |
232 |
Long
Span SOP |
P75
& P82 |
8 |
90 |
Movement
Joint (MJ) SOP Airport Channel |
P74 |
4 |
12 |
Short
Span (SS) SOP type B |
P59 |
4 |
16 |
External Prestressing Tendon Installation
Viaduct |
Activities |
Quantities |
Unit |
Done % |
ML19C |
Threading Stressing Grouting |
47.55 12 9.42 |
T U M3 |
100% 100% 100% |
ML19R |
Threading Stressing Grouting |
48.65 12 9.64 |
T U M3 |
100% 100% 100% |
ML19L |
Threading Stressing Grouting |
46.91 12 9.29 |
T U M3 |
100% 100% 100% |
ML18R |
Threading Stressing Grouting |
77.90 18 15.38 |
T U M3 |
100% 100% 100% |
ML18L |
Threading Stressing Grouting |
76.40 18 15.08 |
T U M3 |
100% 100% 100% |
ML17R |
Threading Stressing Grouting |
63.09 16 12.44 |
T U M3 |
100% 100% 100% |
ML17L |
Threading Stressing Grouting |
62.86 16 12.39 |
T U M3 |
100% 100% 100% |
ML16R |
Threading Stressing Grouting |
56.69 15 9.91 |
T U M3 |
100% 100% 78% |
ML16L |
Threading Stressing Grouting |
87.34 18 17.2 |
T U M3 |
100% 100% 10% |
ML08R |
Threading Stressing Grouting |
85.72 24 16.89 |
T U M3 |
100% 0% 0% |
ML08L |
Threading Stressing Grouting |
85.72 24 16.89 |
T U M3 |
100% 0% 0% |
ML07R |
Threading Stressing Grouting |
129.58 32 25.59 |
T U M3 |
25% 17% 0% |
ML07L |
Threading Stressing Grouting |
140.43 32 27.76 |
T U M3 |
23% 16% 0% |
ML06R |
Threading Stressing Grouting |
113.04 24 22.35 |
T U M3 |
100% 100% 100% |
ML06L |
Threading Stressing Grouting |
113.04 24 22.35 |
T U M3 |
100% 100% 100% |
ML05R |
Threading Stressing Grouting |
113.68 24 22.48 |
T U M3 |
100% 100% 100% |
ML05L |
Threading Stressing Grouting |
112.39 24 22.22 |
T U M3 |
100% 100% 100% |
ML04R |
Threading Stressing Grouting |
113.04 24 22.35 |
T U M3 |
100% 100% 0% |
ML04L |
Threading Stressing Grouting |
113.04 24 22.35 |
T U M3 |
100% 100% 0% |
ML03R |
Threading Stressing Grouting |
199.65 32 39.615 |
T U M3 |
100% 25% 0% |
ML03L |
Threading Stressing Grouting |
201.13 32 29.9 |
T U M3 |
33% 100% 0% |
ML02R |
Threading Stressing Grouting |
113.72 24 22.49 |
T U M3 |
5% 8% 0% |
ML02L |
Threading Stressing Grouting |
113.73 24 22.49 |
T U M3 |
5% 8% 0% |
Internal Prestressing Grouting Progress
Viaduct |
Activities |
Quantities |
Unit |
Done % |
ML19C |
Air
test & Grouting |
14.09 |
M3 |
100% |
ML19R |
Air
test & Grouting |
14.90 |
M3 |
100% |
ML19L |
Air
test & Grouting |
13.90 |
M3 |
100% |
ML18R |
Air
test & Grouting |
25.24 |
M3 |
100% |
ML18L |
Air
test & Grouting |
24.76 |
M3 |
96% |
ML17R |
Air
test & Grouting |
23.47 |
M3 |
100% |
ML17L |
Air
test & Grouting |
23.46 |
M3 |
100% |
ML16R |
Air
test & Grouting |
36.54 |
M3 |
99% |
ML16L |
Air
test & Grouting |
35.46 |
M3 |
99% |
ML15R |
Air
test & Grouting |
39.34 |
M3 |
45% |
ML15L |
Air
test & Grouting |
39.69 |
M3 |
44% |
ML09R |
Air
test & Grouting |
63.27 |
M3 |
25% |
ML09L |
Air
test & Grouting |
57.86 |
M3 |
32% |
ML08R |
Air
test & Grouting |
36.58 |
M3 |
47% |
ML08L |
Air
test & Grouting |
36.56 |
M3 |
31% |
ML07R |
Air
test & Grouting |
59.61 |
M3 |
46% |
ML07L |
Air
test & Grouting |
60.05 |
M3 |
55% |
ML06R |
Air
test & Grouting |
58.31 |
M3 |
100% |
ML06L |
Air
test & Grouting |
58.31 |
M3 |
100% |
ML05R |
Air
test & Grouting |
58.62 |
M3 |
68% |
ML05L |
Air
test & Grouting |
58.01 |
M3 |
91% |
ML04R |
Air
test & Grouting |
57.64 |
M3 |
74% |
ML04L |
Air
test & Grouting |
57.69 |
M3 |
61% |
ML03R |
Air
test & Grouting |
126.65 |
M3 |
0% |
ML03L |
Air
test & Grouting |
127.63 |
M3 |
0% |
ML02R |
Air
test & Grouting |
62.74 |
M3 |
11% |
ML02L |
Air
test & Grouting |
62.74 |
M3 |
10% |
Turnaround Facilities
(a)
2
SOP based at Turnaround Facility were erected. Alignment and levels adjustment
is in progress.
Precast Segment
(c)
Segment Casting:
Item |
Number in this reporting period |
Cumulative No. of Precast Segment Completed (up to 28th of each month) |
Completion Percentage (%) |
Segment
Cast |
261 |
5489 |
96.1% |
Remarks: Cumulative no.
excludes the 7 nos. recast following damages to segments due to toppled
incident at the casting yard.
(d)
Production affected by inclement weather: 11 days
(e)
All Type B* segments were completed in mid-October
2016.
(f)
All SOPs, type CHV1 to 3, CH1 and type C casting
were completed.
(g)
2 nos. wet-joint (2 nos. in total for CHV type) in
between CHV07 &06 were completed.
(h)
Wet joint (7 nos. in total for CH type) in between
CH15 & 16 was commenced.
(i)
All segments in off-yard storage A3 were
transported back to CCCC2¡¦s precast yard in Zhongshan.
Delivery for Precast Concrete Elements (by barge)
(b)
Precast
Deck Segments:
- Number
of barges engaged in this period: 18.
- Number of deck segment deliveries in this period: 62 trips.
- Cumulative number of deck segment deliveries: 880 trips.
Segment Types |
Segment Delivered in this reporting period |
Cumulative No. of Precast Segment Delivered (up to 28th of each month) |
A |
159 |
2160 |
B |
8 |
50 |
C |
146 |
940 |
D |
6 |
202 |
E |
0 |
1014 |
November 2016:
Ancillary and
Associated Facilities
(x) The precast parapet progress
is summarized as follows:
Item |
Number in this month |
Cumulative No. of
Precast Parapet Completed (up to end of month) |
Completion
Percentage (%) |
Parapet
Casting |
530 |
n/a |
2514 |
Parapet
Installation |
227 |
P29 -
P44 P114-P115 |
1157 |
(y) Construction of side barriers
from P100 to P113 is in progress, currently total 307m in-situ side barriers
were cast and 837m precast side barriers were installed;
(z) Construction of median
barriers from P33 & P43 and P112 to P96 is in progress, currently total
322m of in-situ median barriers were cast and 416m precast median barriers were
installed;
(aa)Construction of stitching
from P44 to P41 is in progress;
(bb)
Construction of longitudinal stitching between P93 to
P102 (concrete planking) is in progress;
(cc)E&M installation at ML9
continues;
(dd)
E&M ducting installation at ML6 continues;
(ee)E&M installation in
Transformer Room and HV Room in SHT building continues;
(ff) Installation of carrier
drains from P115 to P93 is in progress;
(gg)
Erection of Radar Platform at P20 is in progress;
(hh)
Sealing of deck openings is in progress.
Deck Erection
(c)
Segment erection in November 2016:
Type |
Location of Segments erected in this reporting
period |
Number of Segments erected in this reporting period |
Cumulative No. of Segments erected (up to 28th of each month) |
Percentage (total no.) |
LG1 |
All
completed |
0 |
1020 |
100%
(1020) |
LG2 |
P08, P07, P06 and P05 |
156 |
1596 |
91% (1749) |
LF1
& HB |
P68, P70, P74, P77, P79 and P80 |
133 |
827 |
62% (1340) |
LF3
& HB |
P60 and P76 |
35 |
798 |
89% (900) |
Typical
Span SOP |
P2 and P1 |
8 |
240 |
99% (242) |
Long
Span SOP |
- |
0 |
90 |
94% (96) |
MJ SOP
Airport Channel |
P78 |
4 |
16 |
80% (20) |
SS
& MJ SOP type B |
All completed |
0 |
16 |
100% (16) |
Typical
Span Segment
type B |
P54L |
6 |
6 |
4% (148) |
Segment
Lifter |
- |
0 |
0 |
0% (183) |
External Prestressing Tendon Installation
Viaduct |
Activities |
Quantities |
Unit |
Done % |
ML19C |
Threading Stressing Grouting |
47.55 12 9.42 |
T U M3 |
100% 100% 100% |
ML19R |
Threading Stressing Grouting |
48.65 12 9.64 |
T U M3 |
100% 100% 100% |
ML19L |
Threading Stressing Grouting |
46.91 12 9.29 |
T U M3 |
100% 100% 100% |
ML18R |
Threading Stressing Grouting |
77.90 18 15.38 |
T U M3 |
100% 100% 100% |
ML18L |
Threading Stressing Grouting |
76.40 18 15.08 |
T U M3 |
100% 100% 100% |
ML17R |
Threading Stressing Grouting |
63.09 16 12.44 |
T U M3 |
100% 100% 100% |
ML17L |
Threading Stressing Grouting |
62.86 16 12.39 |
T U M3 |
100% 100% 100% |
ML16R |
Threading Stressing Grouting |
56.69 15 9.91 |
T U M3 |
100% 100% 100% |
ML16L |
Threading Stressing Grouting |
87.34 18 17.2 |
T U M3 |
100% 100% 100% |
ML15R |
Threading Stressing Grouting |
108.74 18 21.15 |
T U M3 |
87.77% 0% 0% |
ML15L |
Threading Stressing Grouting |
106.26 18 21.45 |
T U M3 |
87.78% 0% 0% |
ML08R |
Threading Stressing Grouting |
85.72 24 16.89 |
T U M3 |
100% 0% 0% |
ML08L |
Threading Stressing Grouting |
85.72 24 16.89 |
T U M3 |
100% 0% 0% |
ML07R |
Threading Stressing Grouting |
129.58 32 25.59 |
T U M3 |
25% 17% 0% |
ML07L |
Threading Stressing Grouting |
140.43 32 27.76 |
T U M3 |
23% 16% 0% |
ML06R |
Threading Stressing Grouting |
113.04 24 22.35 |
T U M3 |
100% 100% 100% |
ML06L |
Threading Stressing Grouting |
113.04 24 22.35 |
T U M3 |
100% 100% 100% |
ML05R |
Threading Stressing Grouting |
113.68 24 22.48 |
T U M3 |
100% 100% 100% |
ML05L |
Threading Stressing Grouting |
112.39 24 22.22 |
T U M3 |
100% 100% 100% |
ML04R |
Threading Stressing Grouting |
113.04 24 22.35 |
T U M3 |
100% 100% 100% |
ML04L |
Threading Stressing Grouting |
113.04 24 22.35 |
T U M3 |
100% 100% 24% |
ML03R |
Threading Stressing Grouting |
199.65 32 39.615 |
T U M3 |
100% 81% 0% |
ML03L |
Threading Stressing Grouting |
201.13 32 29.9 |
T U M3 |
33% 75% 0% |
ML02R |
Threading Stressing Grouting |
113.72 24 22.49 |
T U M3 |
69% 8% 0% |
ML02L |
Threading Stressing Grouting |
113.73 24 22.49 |
T U M3 |
64% 8% 0% |
Internal Prestressing Grouting Progress
Viaduct |
Activities |
Quantities |
Unit |
Done % |
ML19C |
Air
test & Grouting |
14.09 |
M3 |
100% |
ML19R |
Air
test & Grouting |
14.90 |
M3 |
100% |
ML19L |
Air
test & Grouting |
13.90 |
M3 |
100% |
ML18R |
Air
test & Grouting |
25.24 |
M3 |
100% |
ML18L |
Air
test & Grouting |
24.76 |
M3 |
96% |
ML17R |
Air
test & Grouting |
23.47 |
M3 |
100% |
ML17L |
Air
test & Grouting |
23.46 |
M3 |
100% |
ML16R |
Air
test & Grouting |
36.54 |
M3 |
99% |
ML16L |
Air
test & Grouting |
35.46 |
M3 |
99% |
ML15R |
Air
test & Grouting |
39.34 |
M3 |
45% |
ML15L |
Air
test & Grouting |
39.69 |
M3 |
44% |
ML09R |
Air
test & Grouting |
63.27 |
M3 |
25% |
ML09L |
Air
test & Grouting |
57.86 |
M3 |
32% |
ML08R |
Air
test & Grouting |
36.58 |
M3 |
31% |
ML08L |
Air
test & Grouting |
36.56 |
M3 |
31% |
ML07R |
Air
test & Grouting |
59.61 |
M3 |
46% |
ML07L |
Air
test & Grouting |
60.05 |
M3 |
55% |
ML06R |
Air
test & Grouting |
58.31 |
M3 |
100% |
ML06L |
Air
test & Grouting |
58.31 |
M3 |
100% |
ML05R |
Air
test & Grouting |
58.62 |
M3 |
91% |
ML05L |
Air
test & Grouting |
58.01 |
M3 |
91% |
ML04R |
Air
test & Grouting |
57.64 |
M3 |
83% |
ML04L |
Air
test & Grouting |
57.69 |
M3 |
83% |
ML03R |
Air
test & Grouting |
126.65 |
M3 |
0% |
ML03L |
Air
test & Grouting |
127.63 |
M3 |
0% |
ML02R |
Air
test & Grouting |
62.74 |
M3 |
0% |
ML02L |
Air
test & Grouting |
62.74 |
M3 |
0% |
Turnaround Facilities
(b)
Formwork
erection and steel fixing for 2 nos. SOP in-situ part at Turnaround is in
progress;
(c)
Megashor towers
assembly for box girder supports is in progress;
(d) BG01 and
CB01 & 02 were cast at Pan Yu casting yard;
(e)
Erection of formwork for BG02 and construction of
CB03 is in progress.
Precast Segment
(j)
Segment Casting:
Item |
Number in this month |
Cumulative No. of Precast Segment Completed (up to end of month) |
Completion Percentage (%) |
Segment
Cast |
203 |
5692 |
99.6%
(5714) |
Remarks: Cumulative no.
excludes the 7 nos. recast following damages to segments due to toppled
incident at the casting yard.
(k)
Production affected by inclement weather: 2.5 days
(l)
All Type B* segments were completed in mid-November
2016.
(m)
All SOPs, type CHV1 to 4, CH1 to CH2, CH4 and type
C casting were completed.
(n)
2 nos. wet-joint (2 nos. in total for CHV type) in
between CHV07 &06 were completed.
(o)
6 nos. wet joint (7 nos. in total for CH type) in
between CH15 & 16 were completed.
(p)
All segments in off-yard storage A3 were
transported back to CCCC2¡¦s precast yard in Zhongshan.
(q)
The last segment is tentatively to be cast on 12
December 2016.
Delivery for Precast Concrete Elements (by barge)
(c)
Precast
Deck Segments:
- Number
of barges engaged in this period: 18.
- Number of deck segment deliveries in this period: 72 trips.
- Cumulative number of deck segment deliveries: 952 trips.
Segment Types |
Segment Delivered in this reporting period |
Cumulative No. of Precast Segment Delivered (up to 28th of each month) |
Percentage (total no.) |
A |
182 |
2342 |
94.4%
(2480) |
B |
14 |
64 |
21.1%
(304) |
C |
152 |
1092 |
64.2%
(1700) |
D |
8 |
210 |
97.2% (216) |
E |
0 |
1014 |
100%
(1014) |
2.11 The valid environmental licenses
and permits were attached in the Monthly EM&A Reports.