2               Contract INFORMATION

Background

2.1         The proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road (HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao Bridge (HZMB) at the HKSAR Boundary with the Hong Kong Boundary Crossing Facilities (HKBCF) situated at the north eastern waters of the Hong Kong International Airport, opening a new and direct connection route between Hong Kong, Macao and the Western Pearl River Delta. 

2.2         The HKLR comprises a 9.4km long viaduct section from the HKSAR boundary to Scenic Hill on the Airport Island; a 1km tunnel section to the reclamation formed along the east coast of the Airport Island and a 1.6km long at-grade road section on the reclamation connecting to the HKBCF. The tunnel section of HKLR will pass under Scenic Hill, Airport Road and Airport Railway to minimize the environmental and visual impacts to Tung Chung residents.

2.3         An application (No ESB-110/2003) for an Environmental Impact Assessment (EIA) Study Brief under Section 5(1) of the Environmental Impact Assessment Ordinance (EIAO) was submitted by Highways Department (the Project Proponent) on 8 October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection has subsequently been renamed as HKLR.  EPD issued an EIA Study Brief (No: ESB-110/2003) in November 2003 to the Project Proponent to carry out an EIA study.

2.4         An EIA Study (Reg. No. AEIAR-144/2009) has been undertaken to provide information on nature and extent of environmental impacts arising from the construction and operation of HKLR. The Environmental Permit was issued on 4 November 2009 (Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the Director of Environmental Protection amends the Environmental Permit (No. EP-352/2009) based on the Application No. VEP-339/2011 and the environmental Permit (Permit No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the Highways Department as the Permit Holder. Subsequently, the Director of Environmental Protection amends the Environmental Permits (No. EP-352/2009/A, EP-352/2009/B, EP-352/2009/C) based on the Application No. VEP-409/2013, VEP-411/2013 and VEP-459/2014 respectively. The environmental Permit (Permit No. EP-352/2009/D) was then issued on 22 December 2014.

2.5         Figure 1a-d  shows the layout of the Contract and the scope of the Contract works comprises the following major items:

 

¡P           a dual 3-lane carriageway in the form of viaduct from the HKSAR boundary (connecting with the HZMB Main Bridge) to the Scenic Hill (connecting with the tunnel under separate Contract No. HY/2011/03), of approximately 9.4km in length with a hard shoulder for each bound of carriageway and a utilities trough on the outer edge of each bound of viaducts;

¡P           a grade-separated turnaround facility located near San Shek Wan, composed of sliproads in the form of viaduct with single-lane carriageway bifurcated from the HKLR mainline with an elevated junction above the mainline;

¡P           provision of ancillary facilities including, but not limited to, meteorological enhancement measures including the provisioning of anemometers and modification of the wind profiler station at hillside of Sha Lo Wan, provisioning of a compensatory marine radar, and provisioning of security systems; and

¡P           associated civil, structural, geotechnical, marine, environmental protection, landscaping, drainage and highways electrical and mechanical (E&M) works, street lightings, traffic aids and sign gantries, marine navigational aids, ship impact protection system, water mains and fire hydrants, lightning protection system, structural health monitoring and maintenance management system (SHM&MMS), supervisory control and data acquisition (SCADA) system, as well as operation and maintenance provisions of viaducts, provisioning of facilities for installation of traffic control and surveillance system (TCSS), provisioning of facilities for installation of telecommunication cables/equipments and reprovisioning works of affected existing facilities/utilities.

Contract Organisation

2.6         Different parties with different levels of involvement in the Contract organization include:

Ÿ   Supervising Officer¡¦s Representative (SOR) ¡V Ove Arup & Partners Hong Kong Limited (ARUP)

Ÿ   Contractor ¡VDragages -China Harbour-VSL JV   (DCVJV)

Ÿ   Environmental Team (ET) ¡V Cinotech Consultants Ltd. (Cinotech)

 

2.7         The proposed project organization and lines of communication with respect to the on-site environmental management structure are shown in Figure 2. The key personnel contact names and numbers are summarized in Table 2.1.

Table 2.1        Key Contacts of the Contract

Party

Position

Name

Phone No.

Fax No.

SOR (ARUP)

CRE

Mr. Michael Chan

3767 5803

3767 5922

Mr. Colin Meadows

3767 5801

ENPO/IEC

(Ramboll Environ)

Environmental Project Office Leader

Mr. Y. H Hui

3465 2888

3465 2899

Independent Environmental Checker

Mr. Antony Wong

3465 2888

3465 2899

Contractor (DCVJV)

Deputy Project Director

Mr. W.K Poon

3121 6638

3121 6688

Environmental Officer

Mr. CHU Chung Sing

3121 6672

24-hour Hotline

--

6898 6161

--

ET

(Cinotech)

Environmental Team Leader

Dr. Priscilla Choy

2151 2089

3107 1388

 

2.8         Ramboll Environ Hong Kong Limited (Ramboll Environ) is employed by the Highways Department as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) for the Project.

Construction Programme

 

2.9         A copy of Contractor¡¦s construction programme is provided in Appendix A.

Summary of Construction Works Undertaken During Reporting Period

2.10     The major site activities undertaken in the reporting period  included:

September 2016:

Ancillary and Associated Facilities

(a)    P115 & P114 interface area - Reinstatement of slope area temporarily on-hold pending for drainage and reinstatement detailing;  

(b)   Installation of precast parapet skins between P44 to P38 is in progress. The Progress is as follows:

Item

Number in this month

Cumulative No. of Precast Parapet Completed

(up to end of month)

Parapet Casting

345

1522

Parapet Installation

68

688

 

(c)    Construction of side barriers from P103 to P113 is in progress, currently total 177m in-situ side barriers were cast and 51 m precast side barriers were installed;

(d)   Construction of median barriers from P112 to P99 is in progress, currently total 165m of in-situ median barriers were cast and 96m precast median barriers were installed;

(e)    Construction of longitudinal stitching between P99 to P102 (concrete planking) is in progress;

(f)    E&M installation at ML6 continues;

(g)   E&M ducting installation at ML15 to ML17;

(h)   Construction of Load Centre 1 (LC1) commence;

(i)     Installation of carrier drains from P113 to P106 is in progress;

(j)     Erection of Radar Platform at P20 is in progress.

Deck Erection

(a)      Segment erection in September 2016:

Type

Location of Segments erected in this reporting period

Number of Segments erected in this reporting period

Cumulative No. of Segments erected

(up to 28th of each month)

Launching Gantry 1 (LG1)*

All completed

0

1020

Launching Gantry 2

(LG2)

P13 and P12

120

1316

Lifting Frames 1

(LF1) and Hanger Beam (HB)

P71, P73, P76, P77 and P79

52

622

Lifting Frames 3

(LF3) and Hanger Beam (HB)

P52, P60 & P76

33

686

Typical Span SOP

P08, P07, P06 and P05

16

224

Long Span SOP

P68 & P82

10

82

Movement Joint (MJ) SOP Airport Channel

N/A

0

8

Short Span (SS) SOP type B

P57 & P58

4

12

 

External Prestressing Tendon Installation

Viaduct

Activities

Quantities

Unit

Done %

 

ML19C

Threading

Stressing

Grouting

47.55

12

9.42

T

U

M3

100%

100%

100%

 

ML19R

Threading

Stressing

Grouting

48.65

12

9.64

T

U

M3

100%

100%

100%

 

ML19L

Threading

Stressing

Grouting

46.91

12

9.29

T

U

M3

100%

100%

100%

 

ML18R

Threading

Stressing

Grouting

77.90

18

15.38

T

U

M3

100%

100%

100%

 

ML18L

Threading

Stressing

Grouting

76.40

18

15.08

T

U

M3

100%

100%

100%

 

ML17R

Threading

Stressing

Grouting

63.09

16

12.44

T

U

M3

100%

100%

100%

 

ML17L

Threading

Stressing

Grouting

62.86

16

12.39

T

U

M3

100%

100%

100%

 

ML16R

Threading

Stressing

Grouting

56.69

15

9.91

T

U

M3

100%

100%

78%

 

ML16L

Threading

Stressing

Grouting

87.34

18

17.2

T

U

M3

100%

100%

70%

 

ML07R

Threading

Stressing

Grouting

129.58

32

25.59

T

U

M3

26%

17%

0%

 

ML07L

Threading

Stressing

Grouting

140.43

32

27.76

T

U

M3

24%

16%

0%

 

ML06R

Threading

Stressing

Grouting

113.04

24

22.35

T

U

M3

100%

100%

100%

 

ML06L

Threading

Stressing

Grouting

113.04

24

22.35

T

U

M3

100%

100%

100%

 

ML05R

Threading

Stressing

Grouting

113.68

24

22.48

T

U

M3

100%

100%

70%

 

ML05L

Threading

Stressing

Grouting

112.39

24

22.22

T

U

M3

100%

100%

70%

 

ML04R

Threading

Stressing

Grouting

113.04

24

22.35

T

U

M3

30%

30%

0%

 

ML04L

Threading

Stressing

Grouting

113.04

24

22.35

T

U

M3

30%

30%

0%

ML03R

Threading

Stressing

Grouting

199.65

32

39.615

T

U

M3

72%

31%

0%

ML03L

Threading

Stressing

Grouting

201.13

32

29.9

T

U

M3

00%

00%

0%

ML02R

Threading

Stressing

Grouting

113.72

24

22.49

T

U

M3

5%

8%

0%

ML02L

Threading

Stressing

Grouting

113.73

24

22.49

T

U

M3

5%

8%

0%

 

Internal Prestressing Grouting Progress

Viaduct

Activities

Quantities

Unit

Done %

ML19C

Air test & Grouting

14.09

M3

100%

ML19R

Air test & Grouting

14.90

M3

100%

ML19L

Air test & Grouting

13.90

M3

100%

ML18R

Air test & Grouting

25.24

M3

100%

ML18L

Air test & Grouting

24.76

M3

96%

ML17R

Air test & Grouting

23.47

M3

100%

ML17L

Air test & Grouting

23.46

M3

100%

ML16R

Air test & Grouting

36.54

M3

99%

ML16L

Air test & Grouting

35.46

M3

99%

ML15R

Air test & Grouting

39.34

M3

45%

ML15L

Air test & Grouting

39.69

M3

44%

ML09R

Air test & Grouting

63.27

M3

24%

ML09L

Air test & Grouting

57.86

M3

32%

ML08R

Air test & Grouting

36.58

M3

31%

ML08L

Air test & Grouting

36.56

M3

31%

ML07R

Air test & Grouting

59.61

M3

46%

ML07L

Air test & Grouting

60.05

M3

55%

ML06R

Air test & Grouting

58.31

M3

100%

ML06L

Air test & Grouting

58.31

M3

100%

ML05R

Air test & Grouting

58.62

M3

55%

ML05L

Air test & Grouting

58.01

M3

91%

ML04R

Air test & Grouting

57.64

M3

32%

ML04L

Air test & Grouting

57.69

M3

41%

ML03R

Air test & Grouting

126.65

M3

0%

ML03L

Air test & Grouting

127.63

M3

0%

ML02R

Air test & Grouting

62.74

M3

11%

ML02L

Air test & Grouting

62.74

M3

10%

 

Precast Segment

(a)      Segment Casting:

-            Production affected by inclement weather:  2.5 days.

-            All new moulds are under full operation.

-            16 nos. of new Type B* segments were completed in early September 2016 for accommodating I-beam connection of turnaround facility.

-            Mould no. 11 has been modifying from Type C production to Type A after casting P74. There are 10 nos moulds in operation for Type A segment production at the end of Sep 2016.

-            All SOPs, type CH1 to 10 and type C casting were completed in mid-September 2016.

 

Item

Number in this reporting period

Cumulative No. of Precast Segment Completed

(up to 28th of each month)

Segment Cast

306

5228

Remarks: Cumulative no. excludes the 7 nos. recast following damages to segments due to toppled incident at the casting yard.

 

(b)     Off-site Storage:

Area

No. in Off-site Storage

A3

36

 

Delivery for Precast Concrete Elements (by barge)

(a)      Precast Deck Segments:

-     Number of barges engaged in this period: 18.

-      Number of deck segment deliveries in this period: 42 trips.

-      Cumulative number of deck segment deliveries: 818 trips.

Segment Types

Segment Delivered in this reporting period

Cumulative No. of Precast Segment Delivered

(up to 28th of each month)

A

117

2001

B

12

42

C

80

794

D

4

196

E

0

1014

 

October 2016:

Ancillary and Associated Facilities

(k)   P115 & P114 interface area - Reinstatement of slope area temporarily on-hold pending for drainage and reinstatement detailing coupling with the additional maintenance path;

(l)     Reinstatement of sloping seawall at P102 and P103;

(m) Installation of precast parapet skins between P44 to P38 is in progress. The Progress is as follows:

Item

Number in this month

Cumulative No. of Precast Parapet Completed

(up to end of month)

Completion Percentage

(%)

Parapet Casting

462

1984

29.5%

Parapet Installation

242

930

13.8%

 

(n)   Construction of side barriers from P102 to P113 is in progress, currently total 229m in-situ side barriers were cast and 183m precast side barriers were installed;

(o)   Construction of median barriers from P112 to P97 is in progress, currently total 218m of in-situ median barriers were cast and 274m precast median barriers were installed;

(p)   Construction of longitudinal stitching between P96 to P102 (concrete planking) is in progress;

(q)   E&M installation at ML4 continues;

(r)     E&M ducting installation at ML6 continues;

(s)    Construction of Load Centre 1 (LC1) was completed ;

(t)     Installation of carrier drains from P113 to P98 is in progress ;

(u)   Erection of Radar Platform at P20 is in progress.

Deck Erection

(b)     Segment erection in October 2016:

Type

Location of Segments erected in this reporting period

Number of Segments erected in this reporting period

Cumulative No. of Segments erected

(up to 28th of each month)

Launching Gantry 1 (LG1)

All completed

0

1020

Launching Gantry 2

(LG2)

P11, P10 and P09

124

1440

Lifting Frames 1

(LF1) and Hanger Beam (HB)

P70, P71, P77 and P79

104

694

Lifting Frames 3

(LF3) and Hanger Beam (HB)

P52, P53, P60 & P76

 

44

762

Typical Span SOP

P3 and P4

8

232

Long Span SOP

P75 & P82

8

90

Movement Joint (MJ) SOP Airport Channel

P74

4

12

Short Span (SS) SOP type B

P59

4

16

 

External Prestressing Tendon Installation

Viaduct

Activities

Quantities

Unit

Done %

 

ML19C

Threading

Stressing

Grouting

47.55

12

9.42

T

U

M3

100%

100%

100%

 

ML19R

Threading

Stressing

Grouting

48.65

12

9.64

T

U

M3

100%

100%

100%

 

ML19L

Threading

Stressing

Grouting

46.91

12

9.29

T

U

M3

100%

100%

100%

 

ML18R

Threading

Stressing

Grouting

77.90

18

15.38

T

U

M3

100%

100%

100%

 

ML18L

Threading

Stressing

Grouting

76.40

18

15.08

T

U

M3

100%

100%

100%

 

ML17R

Threading

Stressing

Grouting

63.09

16

12.44

T

U

M3

100%

100%

100%

 

ML17L

Threading

Stressing

Grouting

62.86

16

12.39

T

U

M3

100%

100%

100%

 

ML16R

Threading

Stressing

Grouting

56.69

15

9.91

T

U

M3

100%

100%

78%

 

ML16L

Threading

Stressing

Grouting

87.34

18

17.2

T

U

M3

100%

100%

10%

 

ML08R

Threading

Stressing

Grouting

85.72

24

16.89

T

U

M3

100%

0%

0%

 

ML08L

Threading

Stressing

Grouting

85.72

24

16.89

T

U

M3

100%

0%

0%

 

ML07R

Threading

Stressing

Grouting

129.58

32

25.59

T

U

M3

25%

17%

0%

 

ML07L

Threading

Stressing

Grouting

140.43

32

27.76

T

U

M3

23%

16%

0%

 

ML06R

Threading

Stressing

Grouting

113.04

24

22.35

T

U

M3

100%

100%

100%

 

ML06L

Threading

Stressing

Grouting

113.04

24

22.35

T

U

M3

100%

100%

100%

 

ML05R

Threading

Stressing

Grouting

113.68

24

22.48

T

U

M3

100%

100%

100%

 

ML05L

Threading

Stressing

Grouting

112.39

24

22.22

T

U

M3

100%

100%

100%

ML04R

Threading

Stressing

Grouting

113.04

24

22.35

T

U

M3

100%

100%

0%

ML04L

Threading

Stressing

Grouting

113.04

24

22.35

T

U

M3

100%

100%

0%

ML03R

Threading

Stressing

Grouting

199.65

32

39.615

T

U

M3

100%

25%

0%

ML03L

Threading

Stressing

Grouting

201.13

32

29.9

T

U

M3

33%

100%

0%

ML02R

Threading

Stressing

Grouting

113.72

24

22.49

T

U

M3

5%

8%

0%

ML02L

Threading

Stressing

Grouting

113.73

24

22.49

T

U

M3

5%

8%

0%

 

Internal Prestressing Grouting Progress

Viaduct

Activities

Quantities

Unit

Done %

ML19C

Air test & Grouting

14.09

M3

100%

ML19R

Air test & Grouting

14.90

M3

100%

ML19L

Air test & Grouting

13.90

M3

100%

ML18R

Air test & Grouting

25.24

M3

100%

ML18L

Air test & Grouting

24.76

M3

96%

ML17R

Air test & Grouting

23.47

M3

100%

ML17L

Air test & Grouting

23.46

M3

100%

ML16R

Air test & Grouting

36.54

M3

99%

ML16L

Air test & Grouting

35.46

M3

99%

ML15R

Air test & Grouting

39.34

M3

45%

ML15L

Air test & Grouting

39.69

M3

44%

ML09R

Air test & Grouting

63.27

M3

25%

ML09L

Air test & Grouting

57.86

M3

32%

ML08R

Air test & Grouting

36.58

M3

47%

ML08L

Air test & Grouting

36.56

M3

31%

ML07R

Air test & Grouting

59.61

M3

46%

ML07L

Air test & Grouting

60.05

M3

55%

ML06R

Air test & Grouting

58.31

M3

100%

ML06L

Air test & Grouting

58.31

M3

100%

ML05R

Air test & Grouting

58.62

M3

68%

ML05L

Air test & Grouting

58.01

M3

91%

ML04R

Air test & Grouting

57.64

M3

74%

ML04L

Air test & Grouting

57.69

M3

61%

ML03R

Air test & Grouting

126.65

M3

0%

ML03L

Air test & Grouting

127.63

M3

0%

ML02R

Air test & Grouting

62.74

M3

11%

ML02L

Air test & Grouting

62.74

M3

10%

Turnaround Facilities

(a)        2 SOP based at Turnaround Facility were erected. Alignment and levels adjustment is in progress.

Precast Segment

(c)      Segment Casting:

Item

Number in this reporting period

Cumulative No. of Precast Segment Completed

(up to 28th of each month)

Completion Percentage

(%)

Segment Cast

261

5489

96.1%

Remarks: Cumulative no. excludes the 7 nos. recast following damages to segments due to toppled incident at the casting yard.

(d)     Production affected by inclement weather: 11 days

(e)      All Type B* segments were completed in mid-October 2016.

(f)      All SOPs, type CHV1 to 3, CH1 and type C casting were completed.

(g)     2 nos. wet-joint (2 nos. in total for CHV type) in between CHV07 &06 were completed.

(h)     Wet joint (7 nos. in total for CH type) in between CH15 & 16 was commenced.

(i)       All segments in off-yard storage A3 were transported back to CCCC2¡¦s precast yard in Zhongshan.

 

Delivery for Precast Concrete Elements (by barge)

(b)     Precast Deck Segments:

-     Number of barges engaged in this period: 18.

-      Number of deck segment deliveries in this period: 62 trips.

-      Cumulative number of deck segment deliveries: 880 trips.

 

Segment Types

Segment Delivered in this reporting period

Cumulative No. of Precast Segment Delivered

(up to 28th of each month)

A

159

2160

B

8

50

C

146

940

D

6

202

E

0

1014

 

November 2016:

Ancillary and Associated Facilities

(v)   P115 & P114 interface area - Reinstatement of slope area temporarily on-hold pending for drainage and reinstatement detailing coupling with the additional maintenance path;

(w) Reinstatement of sloping seawall at P81, P103 and P104 in progress;

(x)   The precast parapet progress is summarized as follows:

Item

Number in this month

Cumulative No. of Precast Parapet Completed

(up to end of month)

Completion Percentage

(%)

Parapet Casting

530

n/a

2514

Parapet Installation

227

P29 - P44

P114-P115

1157

 

(y)   Construction of side barriers from P100 to P113 is in progress, currently total 307m in-situ side barriers were cast and 837m precast side barriers were installed;

(z)    Construction of median barriers from P33 & P43 and P112 to P96 is in progress, currently total 322m of in-situ median barriers were cast and 416m precast median barriers were installed;

(aa)Construction of stitching from P44 to P41 is in progress;

(bb)                Construction of longitudinal stitching between P93 to P102 (concrete planking) is in progress;

(cc)E&M installation at ML9 continues;

(dd)               E&M ducting installation at ML6 continues;

(ee)E&M installation in Transformer Room and HV Room in SHT building continues;

(ff) Installation of carrier drains from P115 to P93 is in progress;

(gg)                Erection of Radar Platform at P20 is in progress;

(hh)                Sealing of deck openings is in progress.

 

Deck Erection

(c)      Segment erection in November 2016:

Type

Location of Segments erected in this reporting period

Number of Segments erected in this reporting period

Cumulative No. of Segments erected

(up to 28th of each month)

Percentage

(total no.)

LG1

All completed

0

1020

100% (1020)

LG2

P08, P07, P06 and P05

156

1596

91% (1749)

LF1 & HB

P68, P70, P74, P77, P79 and P80

133

827

62% (1340)

LF3 & HB

P60 and P76

35

798

89% (900)

Typical Span SOP

P2 and P1

8

240

 

99% (242)

Long Span SOP

-

0

90

94% (96)

MJ SOP Airport Channel

P78

4

16

80% (20)

SS & MJ SOP type B

All completed

0

16

100% (16)

Typical Span

Segment type B

P54L

6

6

4% (148)

Segment Lifter

-

0

0

0% (183)

 

External Prestressing Tendon Installation

Viaduct

Activities

Quantities

Unit

Done %

 

ML19C

Threading

Stressing

Grouting

47.55

12

9.42

T

U

M3

100%

100%

100%

 

ML19R

Threading

Stressing

Grouting

48.65

12

9.64

T

U

M3

100%

100%

100%

 

ML19L

Threading

Stressing

Grouting

46.91

12

9.29

T

U

M3

100%

100%

100%

 

ML18R

Threading

Stressing

Grouting

77.90

18

15.38

T

U

M3

100%

100%

100%

 

ML18L

Threading

Stressing

Grouting

76.40

18

15.08

T

U

M3

100%

100%

100%

 

ML17R

Threading

Stressing

Grouting

63.09

16

12.44

T

U

M3

100%

100%

100%

 

ML17L

Threading

Stressing

Grouting

62.86

16

12.39

T

U

M3

100%

100%

100%

 

ML16R

Threading

Stressing

Grouting

56.69

15

9.91

T

U

M3

100%

100%

100%

 

ML16L

Threading

Stressing

Grouting

87.34

18

17.2

T

U

M3

100%

100%

100%

ML15R

Threading

Stressing

Grouting

108.74

18

21.15

T

U

M3

87.77%

0%

0%

ML15L

Threading

Stressing

Grouting

106.26

18

21.45

T

U

M3

87.78%

0%

0%

ML08R

Threading

Stressing

Grouting

85.72

24

16.89

T

U

M3

100%

0%

0%

ML08L

Threading

Stressing

Grouting

85.72

24

16.89

T

U

M3

100%

0%

0%

 

ML07R

Threading

Stressing

Grouting

129.58

32

25.59

T

U

M3

25%

17%

0%

 

ML07L

Threading

Stressing

Grouting

140.43

32

27.76

T

U

M3

23%

16%

0%

 

ML06R

Threading

Stressing

Grouting

113.04

24

22.35

T

U

M3

100%

100%

100%

 

ML06L

Threading

Stressing

Grouting

113.04

24

22.35

T

U

M3

100%

100%

100%

 

ML05R

Threading

Stressing

Grouting

113.68

24

22.48

T

U

M3

100%

100%

100%

 

ML05L

Threading

Stressing

Grouting

112.39

24

22.22

T

U

M3

100%

100%

100%

 

ML04R

Threading

Stressing

Grouting

113.04

24

22.35

T

U

M3

100%

100%

100%

 

ML04L

Threading

Stressing

Grouting

113.04

24

22.35

T

U

M3

100%

100%

24%

 

ML03R

Threading

Stressing

Grouting

199.65

32

39.615

T

U

M3

100%

81%

0%

 

ML03L

Threading

Stressing

Grouting

201.13

32

29.9

T

U

M3

33%

75%

0%

 

ML02R

Threading

Stressing

Grouting

113.72

24

22.49

T

U

M3

69%

8%

0%

 

ML02L

Threading

Stressing

Grouting

113.73

24

22.49

T

U

M3

64%

8%

0%

 

Internal Prestressing Grouting Progress

Viaduct

Activities

Quantities

Unit

Done %

ML19C

Air test & Grouting

14.09

M3

100%

ML19R

Air test & Grouting

14.90

M3

100%

ML19L

Air test & Grouting

13.90

M3

100%

ML18R

Air test & Grouting

25.24

M3

100%

ML18L

Air test & Grouting

24.76

M3

96%

ML17R

Air test & Grouting

23.47

M3

100%

ML17L

Air test & Grouting

23.46

M3

100%

ML16R

Air test & Grouting

36.54

M3

99%

ML16L

Air test & Grouting

35.46

M3

99%

ML15R

Air test & Grouting

39.34

M3

45%

ML15L

Air test & Grouting

39.69

M3

44%

ML09R

Air test & Grouting

63.27

M3

25%

ML09L

Air test & Grouting

57.86

M3

32%

ML08R

Air test & Grouting

36.58

M3

31%

ML08L

Air test & Grouting

36.56

M3

31%

ML07R

Air test & Grouting

59.61

M3

46%

ML07L

Air test & Grouting

60.05

M3

55%

ML06R

Air test & Grouting

58.31

M3

100%

ML06L

Air test & Grouting

58.31

M3

100%

ML05R

Air test & Grouting

58.62

M3

91%

ML05L

Air test & Grouting

58.01

M3

91%

ML04R

Air test & Grouting

57.64

M3

83%

ML04L

Air test & Grouting

57.69

M3

83%

ML03R

Air test & Grouting

126.65

M3

0%

ML03L

Air test & Grouting

127.63

M3

0%

ML02R

Air test & Grouting

62.74

M3

0%

ML02L

Air test & Grouting

62.74

M3

0%

 

Turnaround Facilities

(b)       Formwork erection and steel fixing for 2 nos. SOP in-situ part at Turnaround is in progress;

(c)        Megashor towers assembly for box girder supports is in progress;

(d)       BG01 and CB01 & 02 were cast at Pan Yu casting yard;

(e)        Erection of formwork for BG02 and construction of CB03 is in progress.

 

Precast Segment

(j)       Segment Casting:

Item

Number in this month

Cumulative No. of Precast Segment Completed

(up to end of month)

Completion Percentage

(%)

Segment Cast

203

5692

99.6% (5714)

Remarks: Cumulative no. excludes the 7 nos. recast following damages to segments due to toppled incident at the casting yard.

(k)     Production affected by inclement weather: 2.5 days

(l)       All Type B* segments were completed in mid-November 2016.

(m)   All SOPs, type CHV1 to 4, CH1 to CH2, CH4 and type C casting were completed.

(n)     2 nos. wet-joint (2 nos. in total for CHV type) in between CHV07 &06 were completed.

(o)     6 nos. wet joint (7 nos. in total for CH type) in between CH15 & 16 were completed.

(p)     All segments in off-yard storage A3 were transported back to CCCC2¡¦s precast yard in Zhongshan.

(q)     The last segment is tentatively to be cast on 12 December 2016.

 

Delivery for Precast Concrete Elements (by barge)

(c)      Precast Deck Segments:

-     Number of barges engaged in this period: 18.

-      Number of deck segment deliveries in this period: 72 trips.

-      Cumulative number of deck segment deliveries: 952 trips.

 

Segment Types

Segment Delivered in this reporting period

Cumulative No. of Precast Segment Delivered

(up to 28th of each month)

Percentage (total no.)

A

182

2342

94.4% (2480)

B

14

64

21.1% (304)

C

152

1092

64.2% (1700)

D

8

210

97.2% (216)

E

0

1014

100% (1014)

 

Status of Environmental Licences, Notification and Permits

 

2.11     The valid environmental licenses and permits were attached in the Monthly EM&A Reports.