Table I Summary
Table for Monitoring Activities in the Reporting Period
Parameter(s) |
Monitoring Date(s) |
1-hr TSP Monitoring |
1st, 7th,
13th, 17th, 23rd and 29th March
2017 3rd, 7th,
13th, 19th, 25th and 28th April
2017 4th, 10th,
16th, 22nd and 26th May 2017 |
24-hr TSP Monitoring |
|
Noise Monitoring |
2nd, 8th, 14th, 24th and
30th March 2017 5nd, 11th, 20th and 26th April
2017 5th, 11th, 17th, 23rd and
29th May 2017 |
Water Quality Monitoring |
1st, 3rd,
6th, 8th, 10th, 13th, 15th,
17th, 20th 3rd, 6th,
8th, 10th, 12th, 14th, 18th,
20th, 22nd, 24th, 26th and 28th April 2017 2nd, 4th,
6th, 8th, 10th, 12th, 15th,
17th, 19th, 22nd, 24th, 26th
and 29th and 31th May 2017 |
1st and 13th
March 2017 5th and 13th
April 2017 8th and 19th
May 2017 |
|
Environmental Site Inspection |
7th, 14th,
21st and 28th March 2017 6th, 11th,
18th and 25th April 2017 2nd, 9th,
16th, 23rd and 31st May 2017 |
Archaeological Site Inspection |
14th March 2017 |