2               Contract INFORMATION

Background

2.1         The proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road (HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao Bridge (HZMB) at the HKSAR Boundary with the Hong Kong Boundary Crossing Facilities (HKBCF) situated at the north eastern waters of the Hong Kong International Airport, opening a new and direct connection route between Hong Kong, Macao and the Western Pearl River Delta. 

2.2         The HKLR comprises a 9.4km long viaduct section from the HKSAR boundary to Scenic Hill on the Airport Island; a 1km tunnel section to the reclamation formed along the east coast of the Airport Island and a 1.6km long at-grade road section on the reclamation connecting to the HKBCF. The tunnel section of HKLR will pass under Scenic Hill, Airport Road and Airport Railway to minimize the environmental and visual impacts to Tung Chung residents.

2.3         An application (No ESB-110/2003) for an Environmental Impact Assessment (EIA) Study Brief under Section 5(1) of the Environmental Impact Assessment Ordinance (EIAO) was submitted by Highways Department (the Project Proponent) on 8 October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection has subsequently been renamed as HKLR.  EPD issued an EIA Study Brief (No: ESB-110/2003) in November 2003 to the Project Proponent to carry out an EIA study.

2.4         An EIA Study (Reg. No. AEIAR-144/2009) has been undertaken to provide information on nature and extent of environmental impacts arising from the construction and operation of HKLR. The Environmental Permit was issued on 4 November 2009 (Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the Director of Environmental Protection amends the Environmental Permit (No. EP-352/2009) based on the Application No. VEP-339/2011 and the environmental Permit (Permit No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the Highways Department as the Permit Holder. Subsequently, the Director of Environmental Protection amends the Environmental Permits (No. EP-352/2009/A, EP-352/2009/B, EP-352/2009/C) based on the Application No. VEP-409/2013, VEP-411/2013 and VEP-459/2014 respectively. The environmental Permit (Permit No. EP-352/2009/D) was then issued on 22 December 2014.

2.5         Figure 1a-d  shows the layout of the Contract and the scope of the Contract works comprises the following major items:

 

¡P           a dual 3-lane carriageway in the form of viaduct from the HKSAR boundary (connecting with the HZMB Main Bridge) to the Scenic Hill (connecting with the tunnel under separate Contract No. HY/2011/03), of approximately 9.4km in length with a hard shoulder for each bound of carriageway and a utilities trough on the outer edge of each bound of viaducts;

¡P           a grade-separated turnaround facility located near San Shek Wan, composed of sliproads in the form of viaduct with single-lane carriageway bifurcated from the HKLR mainline with an elevated junction above the mainline;

¡P           provision of ancillary facilities including, but not limited to, meteorological enhancement measures including the provisioning of anemometers and modification of the wind profiler station at hillside of Sha Lo Wan, provisioning of a compensatory marine radar, and provisioning of security systems; and

¡P           associated civil, structural, geotechnical, marine, environmental protection, landscaping, drainage and highways electrical and mechanical (E&M) works, street lightings, traffic aids and sign gantries, marine navigational aids, ship impact protection system, water mains and fire hydrants, lightning protection system, structural health monitoring and maintenance management system (SHM&MMS), supervisory control and data acquisition (SCADA) system, as well as operation and maintenance provisions of viaducts, provisioning of facilities for installation of traffic control and surveillance system (TCSS), provisioning of facilities for installation of telecommunication cables/equipments and reprovisioning works of affected existing facilities/utilities.

Contract Organisation

2.6         Different parties with different levels of involvement in the Contract organization include:

Ÿ   Supervising Officer¡¦s Representative (SOR) ¡V Ove Arup & Partners Hong Kong Limited (ARUP)

Ÿ   Contractor ¡VDragages -China Harbour-VSL JV   (DCVJV)

Ÿ   Environmental Team (ET) ¡V Cinotech Consultants Ltd. (Cinotech)

 

2.7         The proposed project organization and lines of communication with respect to the on-site environmental management structure are shown in Figure 2. The key personnel contact names and numbers are summarized in Table 2.1.

Table 2.1        Key Contacts of the Contract

Party

Position

Name

Phone No.

Fax No.

SOR (ARUP)

CRE

Mr. Michael Chan

3767 5803

3767 5922

Mr. Colin Meadows

3767 5801

ENPO/IEC

(Ramboll Environ)

Environmental Project Office Leader

Mr. Y. H Hui

3465 2888

3465 2899

Independent Environmental Checker

Mr. Antony Wong

3465 2888

3465 2899

Contractor (DCVJV)

Deputy Project Director

Mr. W.K Poon

3121 6638

3121 6688

Environmental Officer

Mr. CHU Chung Sing

3121 6672

24-hour Hotline

--

6898 6161

--

ET

(Cinotech)

Environmental Team Leader

Dr. Priscilla Choy

2151 2089

3107 1388

 

2.8         Ramboll Environ Hong Kong Limited (Ramboll Environ) is employed by the Highways Department as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) for the Project.

Construction Programme

 

2.9         A copy of Contractor¡¦s construction programme is provided in Appendix A.

Summary of Construction Works Undertaken During Reporting Period

2.10     The major site activities undertaken in the reporting period  included:

March 2017:

Ancillary and Associated Facilities

(a)    P115 & P114 interface area - Reinstatement of slope area temporarily on-hold pending for drainage and reinstatement detailing coupling with the additional maintenance path;

(b)   Reinstatement of sloping seawall at P103, P104 and P101, P102 are in progress;

(c)    The precast parapet progress is summarized as follows:

Item

Number in this month

Cumulative No. of Precast Parapet Completed

(up to end of month)

Parapet Casting

788

4939

Parapet Installation

542

3174

In-situ concreting works

1296

7586

 

(d)   The central barrier progress is summarized as follows:

Type

Item

Monthly Workdone

Cumulative Workdone

(up to end of month)

Central barrier (precast method)

Precast

597

4885

Installation

150

1144

Central barrier (precast + in-situ method)

In-fill concreting #

57

1414

# ¡§In-fill concreting¡¨ will be carried out after installation of precast units or formworks for precast method and in-situ method respectively. After the in-fill concreting works, the central barrier shall be regarded as completed.

 

(e)    The side barrier progress is summarized as follows:

Type

Item

Monthly Workdone

Cumulative Workdone

(up to 28th of month)

Side barrier (precast method)

Precast

825

4786

Installation

606

2240

Side barrier (precast + in-situ method)

In-fill concreting #

524

3070

# ¡§In-fill concreting¡¨ will be carried out after installation of precast units or formworks for precast method and in-situ method respectively. After the in-fill concreting works, the side barrier shall be regarded as completed.

 

(f)    Construction of the longitudinal stitching from P92 to P87 & P37 to P29 is in progress;

(g)   Sealing of deck openings and preparation deck surface for waterproofing is in progress;

(h)   Waterproofing and asphalt laying at ML16 to ML19 is in progress;

(i)     Watermain installation from P99 to P97 and P44 to P37 & P29 to P21 is in progress;

(j)     Sign gantry GW13, GE15, GE13, GE14, GE12 and GW12 were erected.

E&M Works

(a)    E&M works from ML3 to ML1 is in progress;

(b)   E&M ducting installation from ML5 to ML4 is in progress and E&M ducting installation from ML3 commenced;

(c)    E&M works inside SHT building is in progress;

(d)   Street light cables and poles installation in ML19 & ML18 is in progress;

(e)    Cable hanger installation from ML19 to ML15 is in progress;

(f)    Cable hanger installation from ML6 to ML4 continues;

(g)   Cable hanger installation at ML2 and ML3 commenced;

(h)   E&M ducting installation at radar platform completed;

(i)     Construction of Load Centre 7 completed;

(j)     Construction of Load Centre 8 to 10 commenced.

 

Deck Erection

(a)      Segment erection in March 2017:

Type

Location of Segments erected in this reporting period

Number of Segments erected in this reporting period

Cumulative No. of Segments erected

(up to 28th of each month)

Launching Gantry 1 (LG1)

All completed

0

1020

Launching Gantry 2

(LG2)

All completed

0

1776

Lifting Frames 1

(LF1), Hanger Beam (HB) and Crane Barge

P67, P78 and P82 

73

1214

Lifting Frames 1

(LF1), Hanger Beam (HB) and Crane Barge

All completed

0

842

Typical Span SOP

All completed

0

242

Long Span SOP

All completed

0

96

Movement Joint (MJ) SOP Airport Channel

All completed

0

20

Short Span (SS) and Movement Joint (MJ) SOP type B

All completed

0

16

Typical Span

Segment type B

P55R, P56R&L, P59R&L

62

272

Segment Lifter / Crane Barge

P69

82

200

 

External Prestressing Tendon Installation

Viaduct

Activities

Quantities

Unit

 

ML19C

Threading

Stressing

Grouting

47.55

12

9.42

T

U

M3

 

ML19R

Threading

Stressing

Grouting

48.65

12

9.64

T

U

M3

 

ML19L

Threading

Stressing

Grouting

46.91

12

9.29

T

U

M3

 

ML18R

Threading

Stressing

Grouting

77.90

18

15.38

T

U

M3

 

ML18L

Threading

Stressing

Grouting

76.40

18

15.08

T

U

M3

 

ML17R

Threading

Stressing

Grouting

63.09

16

12.44

T

U

M3

 

ML17L

Threading

Stressing

Grouting

62.86

16

12.39

T

U

M3

 

ML16R

Threading

Stressing

Grouting

56.69

15

9.91

T

U

M3

 

ML16L

Threading

Stressing

Grouting

87.34

18

17.2

T

U

M3

ML15R

Threading

Stressing

Grouting

108.74

18

21.15

T

U

M3

ML15L

Threading

Stressing

Grouting

106.26

18

21.45

T

U

M3

ML14R

Threading

Stressing

Grouting

116.06

16

23.04

T

U

M3

ML14L

Threading

Stressing

Grouting

118.55

16

23.54

T

U

M3

ML13R

Threading

Stressing

Grouting

122.22

16

24.27

T

U

M3

ML13L

Threading

Stressing

Grouting

212.71

16

24.17

T

U

M3

ML12R

Threading

Stressing

Grouting

166.28

26

32.99

T

U

M3

ML12L

Threading

Stressing

Grouting

165.41

24

32.83

T

U

M3

ML11R

Threading

Stressing

Grouting

164.83

24

32.72

T

U

M3

ML11L

Threading

Stressing

Grouting

166.74

24

33.10

T

U

M3

ML10R

 

Threading

Stressing

Grouting

121.69

16

24.17

T

U

M3

ML10L

Threading

Stressing

Grouting

122.16

16

24.26

T

U

M3

ML09R

Threading

Stressing

Grouting

140.32

32

27.73

T

U

M3

ML09L

Threading

Stressing

Grouting

129.46

32

25.56

T

U

M3

ML08R

Threading

Stressing

Grouting

85.72

24

16.89

T

U

M3

ML08L

Threading

Stressing

Grouting

85.72

24

16.89

T

U

M3

 

ML07R

Threading

Stressing

Grouting

129.58

32

25.59

T

U

M3

 

ML07L

Threading

Stressing

Grouting

140.43

32

27.76

T

U

M3

 

ML06R

Threading

Stressing

Grouting

113.04

24

22.35

T

U

M3

 

ML06L

Threading

Stressing

Grouting

113.04

24

22.35

T

U

M3

 

ML05R

Threading

Stressing

Grouting

113.68

24

22.48

T

U

M3

 

ML05L

Threading

Stressing

Grouting

112.39

24

22.22

T

U

M3

 

ML04R

Threading

Stressing

Grouting

113.04

24

22.35

T

U

M3

 

ML04L

Threading

Stressing

Grouting

113.04

24

22.35

T

U

M3

 

ML03R

Threading

Stressing

Grouting

199.65

32

39.615

T

U

M3

 

ML03L

Threading

Stressing

Grouting

201.13

32

29.9

T

U

M3

 

ML02R

Threading

Stressing

Grouting

113.72

24

22.49

T

U

M3

 

ML02L

Threading

Stressing

Grouting

113.73

24

22.49

T

U

M3

ML1R

Threading

Stressing

Grouting

113.72

24

22.49

T

U

M3

ML1L

Threading

Stressing

Grouting

113.73

24

22.49

T

U

M3

 

Internal Prestressing Grouting Progress

Viaduct

Activities

Quantities

Unit

ML19C

Air test & Grouting

14.09

M3

ML19R

Air test & Grouting

14.90

M3

ML19L

Air test & Grouting

13.90

M3

ML18R

Air test & Grouting

25.24

M3

ML18L

Air test & Grouting

24.76

M3

ML17R

Air test & Grouting

23.47

M3

ML17L

Air test & Grouting

23.46

M3

ML16R

Air test & Grouting

36.54

M3

ML16L

Air test & Grouting

35.46

M3

ML15R

Air test & Grouting

39.34

M3

ML15L

Air test & Grouting

39.69

M3

ML14R

Air test & Grouting

104.9

M3

ML14L

Air test & Grouting

106.55

M3

ML13R

Air test & Grouting

108.28

M3

ML13L

Air test & Grouting

107.73

M3

ML12R

Air test & Grouting

121.77

M3

ML12L

Air test & Grouting

121.00

M3

ML11R

Air test & Grouting

111.47

M3

ML11L

Air test & Grouting

112.75

M3

ML10R

Air test & Grouting

89.33

M3

ML10L

Air test & Grouting

89.59

M3

ML09R

Air test & Grouting

63.27

M3

ML09L

Air test & Grouting

57.86

M3

ML08R

Air test & Grouting

36.58

M3

ML08L

Air test & Grouting

36.56

M3

ML07R

Air test & Grouting

59.61

M3

ML07L

Air test & Grouting

60.05

M3

ML06R

Air test & Grouting

58.31

M3

ML06L

Air test & Grouting

58.31

M3

ML05R

Air test & Grouting

58.62

M3

ML05L

Air test & Grouting

58.01

M3

ML04R

Air test & Grouting

57.64

M3

ML04L

Air test & Grouting

57.69

M3

ML03R

Air test & Grouting

126.65

M3

ML03L

Air test & Grouting

127.63

M3

ML02R

Air test & Grouting

62.74

M3

ML02L

Air test & Grouting

62.74

M3

ML01R

Air test & Grouting

53.80

M3

ML01L

Air test & Grouting

53.80

M3

 

Turnaround Facilities

(a)      Erection of BG01 & BG02 were completed;

(b)     Stitching works between 2 Box Girders BG01, BG02 and SOPs is in progress;

(c)      Construction of I-beams in casting yard is in progress;

(d)     Erection of I-beam supporting towers is in progress.

 

Delivery for Precast Concrete Elements (by barge)

(e)      Precast Deck Segments:

-     Number of barges engaged in this period: 11.

-      Number of deck segment deliveries in this period:32 trips.

-      Cumulative number of deck segment deliveries: 1114 trips.

-      The last segment was completed loading successfully on last trip on 28 March 2017.

Segment Types

Segment Delivered in this reporting period

Cumulative No. of Precast Segment Delivered

(up to end of month)

A

18

2480

B

56

304

C

98

1700

D

0

216

E

0

1014

 

April 2017:

Ancillary and Associated Facilities

(a)    P115 & P114 interface area - Reinstatement of slope area temporarily on-hold pending for drainage and reinstatement detailing coupling with the additional maintenance path;

(b)   Reinstatement of sloping seawall at P96 to P100 are in progress;

(c)    The precast facial parapet progress is summarized as follows:

Item

Number in this month

Cumulative No. of Precast Parapet Completed

(up to end of month)

Precast Parapet Facial Panel  Casting

660

5599

Precast Parapet Facial Panel Installation

248

3422

In-situ concreting works

593

8179

 

(d)   The central barrier progress is summarized as follows:

Type

Item

Monthly Workdone

Cumulative Workdone

(up to end of month)

Central barrier (precast method)

Precast

461

5346

Installation

236

1380

Central barrier (precast + in-situ method)

In-fill concreting #

413

1827

# ¡§In-fill concreting¡¨ will be carried out after installation of precast units or formworks for precast method and in-situ method respectively. After the in-fill concreting works, the central barrier shall be regarded as completed.

 

(e)    The side barrier progress is summarized as follows:

Type

Item

Monthly Workdone

Cumulative Workdone

(up to 28th of month)

Side barrier (precast method)

Precast

457

5243

Installation

469

2709

Side barrier (precast + in-situ method)

In-fill concreting #

1356

4426

# ¡§In-fill concreting¡¨ will be carried out after installation of precast units or formworks for precast method and in-situ method respectively. After the in-fill concreting works, the side barrier shall be regarded as completed.

 

(f)    Construction of the longitudinal stitching from P92 to P87 & P37 to P27 is in progress;

(g)   Sealing of deck openings and preparation deck surface for waterproofing is in progress;

(h)   Watermain installation from P88 to P94 and P44 to P26 & P19 to P21 is in progress;

(i)     Sign gantry GW12, GW13, GE15, GE13, GE14, GE12 and GW12, GE5, were erected.

 

E&M Works

(a)    E&M works from ML3 to ML1 is in progress;

(b)   E&M ducting installation in ML3 is in progress and E&M ducting installation from ML1 to ML2 commenced;

(c)    E&M works inside SHT building is in progress;

(d)   Street light cables and poles installation in ML19 & ML18 is in progress;

(e)    Cable hanger installation from ML19 to ML15 was completed;

(f)    Cable hanger installation from ML6 to ML4 continues;

(g)   Cable hanger installation at ML2 and ML3 continues;

(h)   Construction of Load Centre 8, 9 and 10 commenced.

 

Deck Erection

(a)      All segment erections were completed except 16 segments at turnaround facilities. A summary is shown below:

Type

Location of Segments erected in this reporting period

Number of Segments erected in this reporting period

Cumulative No. of Segments erected

(up to end of the month)

Launching Gantry 1 (LG1)

All completed

0

1020

Launching Gantry 2

(LG2)

All completed

0

1776

Lifting Frames 1

(LF1), Hanger Beam (HB) and Crane Barge

P67, P78 and P82 

73

1214

Lifting Frames 1

(LF1), Hanger Beam (HB) and Crane Barge

All completed

0

842

Typical Span SOP

All completed

0

242

Long Span SOP

All completed

0

96

Movement Joint (MJ) SOP Airport Channel

All completed

0

20

Short Span (SS) and Movement Joint (MJ) SOP type B

All completed

0

16

Typical Span

Segment type B

P56R&L

0

272

Segment Lifter / Crane Barge

P69

82

200

 

External Prestressing Tendon Installation

Viaduct

Activities

Quantities

Unit

 

ML19C

Threading

Stressing

Grouting

47.55

12

9.42

T

U

M3

 

ML19R

Threading

Stressing

Grouting

48.65

12

9.64

T

U

M3

 

ML19L

Threading

Stressing

Grouting

46.91

12

9.29

T

U

M3

 

ML18R

Threading

Stressing

Grouting

77.90

18

15.38

T

U

M3

 

ML18L

Threading

Stressing

Grouting

76.40

18

15.08

T

U

M3

 

ML17R

Threading

Stressing

Grouting

63.09

16

12.44

T

U

M3

 

ML17L

Threading

Stressing

Grouting

62.86

16

12.39

T

U

M3

 

ML16R

Threading

Stressing

Grouting

56.69

15

9.91

T

U

M3

 

ML16L

Threading

Stressing

Grouting

87.34

18

17.2

T

U

M3

ML15R

Threading

Stressing

Grouting

108.74

18

21.15

T

U

M3

ML15L

Threading

Stressing

Grouting

106.26

18

21.45

T

U

M3

ML14R

Threading

Stressing

Grouting

116.06

16

23.04

T

U

M3

ML14L

Threading

Stressing

Grouting

118.55

16

23.54

T

U

M3

ML13R

Threading

Stressing

Grouting

122.22

16

24.27

T

U

M3

ML13L

Threading

Stressing

Grouting

212.71

16

24.17

T

U

M3

ML12R

Threading

Stressing

Grouting

166.28

26

32.99

T

U

M3

ML12L

Threading

Stressing

Grouting

165.41

24

32.83

T

U

M3

ML11R

Threading

Stressing

Grouting

164.83

24

32.72

T

U

M3

ML11L

Threading

Stressing

Grouting

166.74

24

33.10

T

U

M3

ML10R

 

Threading

Stressing

Grouting

121.69

16

24.17

T

U

M3

ML10L

Threading

Stressing

Grouting

122.16

16

24.26

T

U

M3

ML09R

Threading

Stressing

Grouting

140.32

32

27.73

T

U

M3

ML09L

Threading

Stressing

Grouting

129.46

32

25.56

T

U

M3

ML08R

Threading

Stressing

Grouting

85.72

24

16.89

T

U

M3

ML08L

Threading

Stressing

Grouting

85.72

24

16.89

T

U

M3

 

ML07R

Threading

Stressing

Grouting

129.58

32

25.59

T

U

M3

 

ML07L

Threading

Stressing

Grouting

140.43

32

27.76

T

U

M3

 

ML06R

Threading

Stressing

Grouting

113.04

24

22.35

T

U

M3

 

ML06L

Threading

Stressing

Grouting

113.04

24

22.35

T

U

M3

 

ML05R

Threading

Stressing

Grouting

113.68

24

22.48

T

U

M3

 

ML05L

Threading

Stressing

Grouting

112.39

24

22.22

T

U

M3

 

ML04R

Threading

Stressing

Grouting

113.04

24

22.35

T

U

M3

 

ML04L

Threading

Stressing

Grouting

113.04

24

22.35

T

U

M3

 

ML03R

Threading

Stressing

Grouting

199.65

32

39.615

T

U

M3

 

ML03L

Threading

Stressing

Grouting

201.13

32

29.9

T

U

M3

 

ML02R

Threading

Stressing

Grouting

113.72

24

22.49

T

U

M3

 

ML02L

Threading

Stressing

Grouting

113.73

24

22.49

T

U

M3

ML1R

Threading

Stressing

Grouting

113.72

24

22.49

T

U

M3

ML1L

Threading

Stressing

Grouting

113.73

24

22.49

T

U

M3

 

Internal Prestressing Grouting Progress

Viaduct

Activities

Quantities

Unit

ML19C

Air test & Grouting

14.09

M3

ML19R

Air test & Grouting

14.90

M3

ML19L

Air test & Grouting

13.90

M3

ML18R

Air test & Grouting

25.24

M3

ML18L

Air test & Grouting

24.76

M3

ML17R

Air test & Grouting

23.47

M3

ML17L

Air test & Grouting

23.46

M3

ML16R

Air test & Grouting

36.54

M3

ML16L

Air test & Grouting

35.46

M3

ML15R

Air test & Grouting

39.34

M3

ML15L

Air test & Grouting

39.69

M3

ML14R

Air test & Grouting

104.9

M3

ML14L

Air test & Grouting

106.55

M3

ML13R

Air test & Grouting

108.28

M3

ML13L

Air test & Grouting

107.73

M3

ML12R

Air test & Grouting

121.77

M3

ML12L

Air test & Grouting

121.00

M3

ML11R

Air test & Grouting

111.47

M3

ML11L

Air test & Grouting

112.75

M3

ML10R

Air test & Grouting

89.33

M3

ML10L

Air test & Grouting

89.59

M3

ML09R

Air test & Grouting

63.27

M3

ML09L

Air test & Grouting

57.86

M3

ML08R

Air test & Grouting

36.58

M3

ML08L

Air test & Grouting

36.56

M3

ML07R

Air test & Grouting

59.61

M3

ML07L

Air test & Grouting

60.05

M3

ML06R

Air test & Grouting

58.31

M3

ML06L

Air test & Grouting

58.31

M3

ML05R

Air test & Grouting

58.62

M3

ML05L

Air test & Grouting

58.01

M3

ML04R

Air test & Grouting

57.64

M3

ML04L

Air test & Grouting

57.69

M3

ML03R

Air test & Grouting

126.65

M3

ML03L

Air test & Grouting

127.63

M3

ML02R

Air test & Grouting

62.74

M3

ML02L

Air test & Grouting

62.74

M3

ML01R

Air test & Grouting

53.80

M3

ML01L

Air test & Grouting

53.80

M3

 

Turnaround Facilities

(a)      Mid-stitches between Box Girders and stitches between Box Girders and SOPs are completed except longitudinal stitch between box girders;

(b)     Four I-beams were delivered on site.

 

Road Pavement

Road Pavement

Total (m2)

Monthly Workdone (m2)

Cumulative Workdone

(m2)

A

284440

0

34133

B

284440

0

25600

C

274688

0

0

 

May 2017:

Ancillary and Associated Facilities

(a)    P115 & P114 interface area - Reinstatement of slope area temporarily on-hold pending for drainage and reinstatement detailing coupling with the additional maintenance path;

(b)   Reinstatement of sloping seawall at P96 to P101 are in progress;

(c)    The precast facial parapet progress is summarized as follows:

Item

Number in this month

Cumulative No. of Precast Parapet Completed

(up to 28th of month)

Precast Parapet Facial Panel  Casting

692

6340

Precast Parapet Facial Panel Installation

130

3577

In-situ concreting works

311

8549

 

(d)   The central barrier progress is summarized as follows:

Type

Item

Monthly Workdone

Cumulative Workdone

(up to 28th of month)

Central barrier (precast method)

Precast

248

5714

Installation

224

1628

Central barrier (precast + in-situ method)

In-fill concreting #

168

2031

# ¡§In-fill concreting¡¨ will be carried out after installation of precast units or formworks for precast method and in-situ method respectively. After the in-fill concreting works, the central barrier shall be regarded as completed.

 

(e)    The side barrier progress is summarized as follows:

Type

Item

Monthly Workdone

Cumulative Workdone

(up to 28th of month)

Side barrier (precast method)

Precast

285

5691

Installation

188

2999

Side barrier (precast + in-situ method)

In-fill concreting #

561

5038

# ¡§In-fill concreting¡¨ will be carried out after installation of precast units or formworks for precast method and in-situ method respectively. After the in-fill concreting works, the side barrier shall be regarded as completed.

 

(f)    Construction of the longitudinal stitching from P92 to P87 & P37 to P25 is in progress;

(g)   Sealing of deck openings and preparation deck surface for waterproofing is in progress;

(h)   Watermain installation from P44 to P4 is in progress;

(i)       Sign gantry GW13, GW12, GW11, GE15, GE14, GE13, GE12, GE1 to GE5 and GW1 to GE4, were erected.

(j)     Chek Lap Kok South Road realignment* is in progress.

 

Note:

*Minor Modification Works:-

¡PShifting the bus stop location;

¡PShifting the old alignment near P109 southward; and

¡PRe-instating the underground drainage with the new alignment due to the minor modification works above.

 

E&M Works

(a)    E&M works from ML2 to ML1 is in progress;

(b)   E&M ducting installation in ML1 to ML3 is in progress;

(c)    E&M ducting installation from ML6 to ML1 commenced;

(d)   E&M duct installation at deck void in ML7 and ML8 commenced;

(e)    E&M works inside SHT building is in progress;

(f)    Cable hanger installation from ML6 to ML4 completed;

(g)   Cable hanger installation between ML1 and ML3 continues;

(h)   Construction of Load Centre 8, 9 and 10 completed;

(i)     Pillar box installation was completed for load centre 7 and load centre 8;

(j)     Street light cables and poles installation in ML19 & ML18 is in progress;

(k)   Completion of installation for TCSS¡¦s CCTV high mast at CH.12+600 and 13+190;

(l)     Completion of installation for C&ED¡¦s CCTV high mast at CH12+280.

 

Deck Erection

(a)    6 segments were erected at P56 of the ramp at turnaround facilities. Last 10 segments are remaining to be erected.

(b)   LF1-B launching from P82 to P80 were completed;

(c)    Segment lifter dismantling has started at WA4.

 

External Prestressing Tendon Installation

Viaduct

Activities

Quantities

Unit

 

ML19C

Threading

Stressing

Grouting

47.55

12

9.42

T

U

M3

 

ML19R

Threading

Stressing

Grouting

48.65

12

9.64

T

U

M3

 

ML19L

Threading

Stressing

Grouting

46.91

12

9.29

T

U

M3

 

ML18R

Threading

Stressing

Grouting

77.90

18

15.38

T

U

M3

 

ML18L

Threading

Stressing

Grouting

76.40

18

15.08

T

U

M3

 

ML17R

Threading

Stressing

Grouting

63.09

16

12.44

T

U

M3

 

ML17L

Threading

Stressing

Grouting

62.86

16

12.39

T

U

M3

 

ML16R

Threading

Stressing

Grouting

56.69

15

9.91

T

U

M3

 

ML16L

Threading

Stressing

Grouting

87.34

18

17.2

T

U

M3

ML15R

Threading

Stressing

Grouting

108.74

18

21.15

T

U

M3

ML15L

Threading

Stressing

Grouting

106.26

18

21.45

T

U

M3

ML14R

Threading

Stressing

Grouting

116.06

16

23.04

T

U

M3

ML14L

Threading

Stressing

Grouting

118.55

16

23.54

T

U

M3

ML13R

Threading

Stressing

Grouting

122.22

16

24.27

T

U

M3

ML13L

Threading

Stressing

Grouting

212.71

16

24.17

T

U

M3

ML12R

Threading

Stressing

Grouting

166.28

26

32.99

T

U

M3

ML12L

Threading

Stressing

Grouting

165.41

24

32.83

T

U

M3

ML11R

Threading

Stressing

Grouting

164.83

24

32.72

T

U

M3

ML11L

Threading

Stressing

Grouting

166.74

24

33.10

T

U

M3

ML10R

 

Threading

Stressing

Grouting

121.69

16

24.17

T

U

M3

ML10L

Threading

Stressing

Grouting

122.16

16

24.26

T

U

M3

ML09R

Threading

Stressing

Grouting

140.32

32

27.73

T

U

M3

ML09L

Threading

Stressing

Grouting

129.46

32

25.56

T

U

M3

ML08R

Threading

Stressing

Grouting

85.72

24

16.89

T

U

M3

ML08L

Threading

Stressing

Grouting

85.72

24

16.89

T

U

M3

 

ML07R

Threading

Stressing

Grouting

129.58

32

25.59

T

U

M3

 

ML07L

Threading

Stressing

Grouting

140.43

32

27.76

T

U

M3

 

ML06R

Threading

Stressing

Grouting

113.04

24

22.35

T

U

M3

 

ML06L

Threading

Stressing

Grouting

113.04

24

22.35

T

U

M3

 

ML05R

Threading

Stressing

Grouting

113.68

24

22.48

T

U

M3

 

ML05L

Threading

Stressing

Grouting

112.39

24

22.22

T

U

M3

 

ML04R

Threading

Stressing

Grouting

113.04

24

22.35

T

U

M3

 

ML04L

Threading

Stressing

Grouting

113.04

24

22.35

T

U

M3

 

ML03R

Threading

Stressing

Grouting

199.65

32

39.615

T

U

M3

 

ML03L

Threading

Stressing

Grouting

201.13

32

29.9

T

U

M3

 

ML02R

Threading

Stressing

Grouting

113.72

24

22.49

T

U

M3

 

ML02L

Threading

Stressing

Grouting

113.73

24

22.49

T

U

M3

ML1R

Threading

Stressing

Grouting

113.72

24

22.49

T

U

M3

ML1L

Threading

Stressing

Grouting

113.73

24

22.49

T

U

M3

 

Internal Prestressing Grouting Progress

Viaduct

Activities

Quantities

Unit

ML19C

Air test & Grouting

14.09

M3

ML19R

Air test & Grouting

14.90

M3

ML19L

Air test & Grouting

13.90

M3

ML18R

Air test & Grouting

25.24

M3

ML18L

Air test & Grouting

24.76

M3

ML17R

Air test & Grouting

23.47

M3

ML17L

Air test & Grouting

23.46

M3

ML16R

Air test & Grouting

36.54

M3

ML16L

Air test & Grouting

35.46

M3

ML15R

Air test & Grouting

39.34

M3

ML15L

Air test & Grouting

39.69

M3

ML14R

Air test & Grouting

104.9

M3

ML14L

Air test & Grouting

106.55

M3

ML13R

Air test & Grouting

108.28

M3

ML13L

Air test & Grouting

107.73

M3

ML12R

Air test & Grouting

121.77

M3

ML12L

Air test & Grouting

121.00

M3

ML11R

Air test & Grouting

111.47

M3

ML11L

Air test & Grouting

112.75

M3

ML10R

Air test & Grouting

89.33

M3

ML10L

Air test & Grouting

89.59

M3

ML09R

Air test & Grouting

63.27

M3

ML09L

Air test & Grouting

57.86

M3

ML08R

Air test & Grouting

36.58

M3

ML08L

Air test & Grouting

36.56

M3

ML07R

Air test & Grouting

59.61

M3

ML07L

Air test & Grouting

60.05

M3

ML06R

Air test & Grouting

58.31

M3

ML06L

Air test & Grouting

58.31

M3

ML05R

Air test & Grouting

58.62

M3

ML05L

Air test & Grouting

58.01

M3

ML04R

Air test & Grouting

57.64

M3

ML04L

Air test & Grouting

57.69

M3

ML03R

Air test & Grouting

126.65

M3

ML03L

Air test & Grouting

127.63

M3

ML02R

Air test & Grouting

62.74

M3

ML02L

Air test & Grouting

62.74

M3

ML01R

Air test & Grouting

53.80

M3

ML01L

Air test & Grouting

53.80

M3

 

Turnaround Facilities

(a)      Mid-stitches between Box Girders and stitches between Box Girders and SOPs were completed. Longitudinal stitch between box girders is in progress;

(b)     Strands installation and stressing for extended platforms are in progress.

 

Road Pavement

Road Pavement

Total (m2)

Monthly Workdone (m2)

Cumulative Workdone

(m2)

A

284440

0

34133

B

284440

0

25600

C

274688

0

0

 

Status of Environmental Licences, Notification and Permits

 

2.11     The valid environmental licenses and permits were attached in the Monthly EM&A Reports.