Table I Summary
Table for Monitoring Activities in the Reporting Period
Parameter(s) |
Monitoring Date(s) |
*1-hr TSP Monitoring |
5th, 11th,
15th, 21st and 27th September 2017 2nd, 7th,
13th, 19th, 25th and 31st October
2017 6th, 7th,
10th, 16th, 22nd and 28th November
2017 |
*24-hr TSP Monitoring |
|
Noise Monitoring |
6th, 12th,
22nd and 28th September 2017 4th, 10th,
20th, 25th and 31st October 2017 1st, 7th,
17th, 23rd and 29th November 2017 |
Water Quality Monitoring |
1st, 5th, 7th, 9th,
11th, 13th, 15th, 18th, 20th,
22nd, 25th, 27th and 29th September
2017 2nd, 4th, 6th, 9th,
11th, 14th, 16th, 18th, 20th,
23rd, 25th, 27th and 30th October
2017 1st, 3rd, 6th, 8th,
10th, 13th, 15th, 17th, 20th,
22nd, 24th, 28th and 30th
November 2017 |
7th and 13th September 2017 10th and 24th October 2017 9th and 22nd November 2017 |
|
Environmental Site
Inspection |
5th, 12th, 19th and
26th September 2017 3rd, 10th, 17th ,
24th and 31st October 2017 7th, 14th, 21st
and 28th November 2017 |
Archaeological Site
Inspection |
12th September 2017 |
*1hr TSP (2nd and 3rd hour for AMS1) & 24 hr TSP at AMS1 and AMS4 on 6 November 2017 were cancelled
and postponed to be conducted on 7 November 2017 due to the failure of power
supply from the premises. The power supply was resumed on 7 November 2017.