2.1
The proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road
(HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao Bridge (HZMB) at the
HKSAR Boundary with the Hong Kong Boundary Crossing Facilities (HKBCF) situated
at the north eastern waters of the Hong Kong International Airport, opening a
new and direct connection route between Hong Kong, Macao and the Western Pearl
River Delta.
2.2
The HKLR comprises a 9.4km long viaduct section from the HKSAR boundary
to Scenic Hill on the Airport Island; a 1km tunnel section to the reclamation
formed along the east coast of the Airport Island and a 1.6km long at-grade
road section on the reclamation connecting to the HKBCF. The tunnel section of
HKLR will pass under Scenic Hill, Airport Road and Airport Railway to minimize
the environmental and visual impacts to Tung Chung residents.
2.3
An application (No ESB-110/2003) for an Environmental Impact Assessment
(EIA) Study Brief under Section 5(1) of the Environmental Impact Assessment
Ordinance (EIAO) was submitted by Highways Department (the Project Proponent)
on 8 October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong
Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway
Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North
Lantau Highway Connection has subsequently been renamed as HKLR. EPD issued an EIA Study Brief (No:
ESB-110/2003) in November 2003 to the Project Proponent to carry out an EIA
study.
2.4
An EIA Study (Reg. No. AEIAR-144/2009) has been undertaken to provide
information on nature and extent of environmental impacts arising from the
construction and operation of HKLR. The Environmental Permit was issued on 4
November 2009 (Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the
Director of Environmental Protection amends the Environmental Permit (No.
EP-352/2009) based on the Application No. VEP-339/2011 and the environmental
Permit (Permit No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the
Highways Department as the Permit Holder. Subsequently, the Director of
Environmental Protection amends the Environmental Permits (No. EP-352/2009/A,
EP-352/2009/B, EP-352/2009/C) based on the Application No. VEP-409/2013, VEP-411/2013
and VEP-459/2014 respectively. The environmental Permit (Permit No.
EP-352/2009/D) was then issued on 22 December 2014.
2.5
Figure 1a-d shows the layout of the Contract
and the scope of the Contract works comprises the following major items:
¡P
a dual 3-lane carriageway in the form of
viaduct from the HKSAR boundary (connecting with the HZMB Main Bridge) to the
Scenic Hill (connecting with the tunnel under separate Contract No.
HY/2011/03), of approximately 9.4km in length with a hard shoulder for each
bound of carriageway and a utilities trough on the outer edge of each bound of
viaducts;
¡P
a grade-separated turnaround facility located near San Shek Wan, composed of sliproads
in the form of viaduct with single-lane carriageway bifurcated from the HKLR
mainline with an elevated junction above the mainline;
¡P
provision of ancillary facilities including, but not limited to,
meteorological enhancement measures including the provisioning of anemometers
and modification of the wind profiler station at hillside of Sha Lo Wan,
provisioning of a compensatory marine radar, and provisioning of security
systems; and
¡P
associated civil, structural, geotechnical, marine, environmental
protection, landscaping, drainage and highways electrical and mechanical
(E&M) works, street lightings, traffic aids and sign gantries, marine
navigational aids, ship impact protection system, water mains and fire
hydrants, lightning protection system, structural health monitoring and
maintenance management system (SHM&MMS), supervisory control and data
acquisition (SCADA) system, as well as operation and maintenance provisions of
viaducts, provisioning of facilities for installation of traffic control and
surveillance system (TCSS), provisioning of facilities for installation of
telecommunication cables/equipments and reprovisioning works of affected existing
facilities/utilities.
2.6
Different parties with different levels of involvement in the Contract
organization include:
Supervising Officer¡¦s Representative (SOR) ¡V
Ove Arup & Partners Hong Kong Limited (ARUP)
Contractor ¡VDragages
-China Harbour-VSL JV (DCVJV)
Environmental Team (ET) ¡V Cinotech
Consultants Ltd. (Cinotech)
2.7
The proposed project organization and lines of communication with
respect to the on-site environmental management structure are shown in Figure 2. The key personnel contact
names and numbers are summarized in Table
2.1.
Table 2.1 Key
Contacts of the Contract
|
Party |
Position |
Name |
Phone
No. |
Fax
No. |
|
SOR (ARUP) |
CRE |
Mr. Michael Chan |
3767 5803 |
3767 5922 |
|
Mr. Colin Meadows |
3767 5801 |
|||
|
ENPO/IEC (Ramboll Environ) |
Environmental Project Office Leader |
Mr. Y. H Hui |
3465 2888 |
3465 2899 |
|
Independent Environmental Checker |
Mr. Antony Wong |
3465 2888 |
3465 2899 |
|
|
Contractor
(DCVJV) |
Deputy Project Director |
Mr. W.K Poon |
3121 6638 |
3121 6688 |
|
Environmental Officer |
Mr. CHU Chung Sing |
3121 6672 |
||
|
24-hour Hotline |
-- |
6898 6161 |
-- |
|
|
ET (Cinotech) |
Environmental Team Leader |
Dr. Priscilla Choy |
2151 2089 |
3107 1388 |
2.8
Ramboll Environ Hong Kong Limited (Ramboll
Environ) is employed
by the Highways Department as the Independent Environmental Checker (IEC) and
Environmental Project Office (ENPO) for the Project.
2.9
A copy of Contractor¡¦s
construction programme is provided in Appendix A.
Summary of Construction Works Undertaken During Reporting Period
2.10
The major site
activities undertaken in the reporting period included:
September
2017:
Ancillary and
Associated Facilities
(a)
P115 & P114 interface area - Breaking off the
concrete footings for reinstatement of slope underneath the deck is in
progress;
(b)
Reinstatement of sloping seawall at P94 to P92 and P84
to P87 are in progress;
(c)
The precast parapet facial panel progress is summarized
as follows:
|
Item |
Number in this month |
Cumulative No. of
Precast Parapet Completed (up to 28th
of month) |
|
Precast
Parapet Facial Panel Casting |
14 |
6794 |
|
Precast
Parapet Facial Panel Installation |
559 |
5183 |
|
In-situ
concreting works |
1336 |
12387 |
(d)
The central barrier progress is summarized as follows:
|
Type |
Item |
Monthly Workdone |
Cumulative Workdone (up to 28th of
month) |
|
Central
barrier (precast method) |
Precast |
11 |
5782 |
|
Installation |
636 |
3699 |
|
|
Central
barrier (precast + in-situ method) |
In-fill
concreting # |
578 |
4977 |
# ¡§In-fill concreting¡¨ will
be carried out after installation of precast units or formworks for precast
method and in-situ method respectively. After the in-fill concreting works, the
central barrier shall be regarded as completed.
(e)
The side barrier progress is summarized as follows:
|
Type |
Item |
Monthly Workdone |
Cumulative Workdone (up to 28th of
month) |
|
Side
barrier (precast method) |
Precast |
29 |
6004 |
|
Installation |
521 |
4838 |
|
|
Side
barrier (precast + in-situ method) |
In-fill
concreting # |
1311 |
13384 |
# ¡§In-fill concreting¡¨ will
be carried out after installation of precast units or formworks for precast
method and in-situ method respectively. After the in-fill concreting works, the
side barrier shall be regarded as completed.
(f)
Construction of the longitudinal stitching at ML7, ML9,
ML10, ML11, ML12, ML13 and ML14 are in progress. Longitudinal from ML1 to ML6
were completed except P0 to P1;
(g)
Sealing of deck openings and preparation deck surface
for waterproofing at ML3 to ML1 and ML7 is in progress;;
(h)
Fire mains at P8, P68, P71 and P73 were installed;
(i)
Sign gantry GE10 & GW10 were erected;
(j)
Installation of stormwater
drainage for Chek Lap Kok
South Road realignment;
(k)
Site clearance/formation work to the reinstatement of
South Perimeter Road between P84 to P81 in progress.
E&M Works
(a)
E&M ducting installation at ML1 continues;
(b)
E&M ducting installation at ML7 continues;
(c)
E&M ducting installation at ML10 commence;
(d)
E&M ducting installation from ML11 and ML14
continue;
(e)
E&M works inside SHT building is in progress;
(f)
Cable hanger installation at ML11 continue;
(g)
Construction of Load Centre 6 completed;
(h)
Construction of Load Centre 3 continue;
(i)
Street light cables and poles installation at ML2 and ML4
commenced;
(j)
Street light cables and poles installation at ML1 continue;
(k)
LV and HV cable laying works at ML1 to ML6 and ML15 to
ML19 continue;
(l)
Optic fibre laying works for
the SMS scope from SHT tunnel to HMA building commenced;
(m)
Cable tray
installation of SMS system at ML3 and ML4 commenced;
(n)
Optic fibre cable laying works
at ML14 to ML19 commenced.
Deck Erection
(a)
P0¡¦s Dismantling Works at LHS
i.
LHS¡¦s temporary T1 truss was removed by SLU jacks on LHS;
ii.
Temporary supporting structure on RHS was retrieved from
the seabed and stored at WA7;
iii.
RHS¡¦s temporary T2 truss was removed by SLU jacks.
(b)
Stitching works
i.
Span tendon stressing works on ML09 were completed
ii.
All load transfers of bridge bearing to piers (ML09) were
completed.
(c)
Movement Joints
i.
Installation of movement joints at P45L, P92R, P99R,
P104R and P111R complete;
ii.
Installation of movement joints at P29R, P84R and
P92L in progress;
iii.
Surface preparation (breaking temporary concrete)
prior to movement joints installation in progress.
External Prestressing Tendon Installation
|
Viaduct |
Activities |
Quantities |
Unit |
|
ML19C |
Threading Stressing Grouting |
47.55 12 9.42 |
T U M3 |
|
ML19R |
Threading Stressing Grouting |
48.65 12 9.64 |
T U M3 |
|
ML19L |
Threading Stressing Grouting |
46.91 12 9.29 |
T U M3 |
|
ML18R |
Threading Stressing Grouting |
77.90 18 15.38 |
T U M3 |
|
ML18L |
Threading Stressing Grouting |
76.40 18 15.08 |
T U M3 |
|
ML17R |
Threading Stressing Grouting |
63.09 16 12.44 |
T U M3 |
|
ML17L |
Threading Stressing Grouting |
62.86 16 12.39 |
T U M3 |
|
ML16R |
Threading Stressing Grouting |
56.69 15 9.91 |
T U M3 |
|
ML16L |
Threading Stressing Grouting |
87.34 18 17.2 |
T U M3 |
|
ML15R |
Threading Stressing Grouting |
108.74 18 21.15 |
T U M3 |
|
ML15L |
Threading Stressing Grouting |
106.26 18 21.45 |
T U M3 |
|
ML14R |
Threading Stressing Grouting |
116.06 16 23.04 |
T U M3 |
|
ML14L |
Threading Stressing Grouting |
118.55 16 23.54 |
T U M3 |
|
ML13R |
Threading Stressing Grouting |
122.22 16 24.27 |
T U M3 |
|
ML13L |
Threading Stressing Grouting |
212.71 16 24.17 |
T U M3 |
|
ML12R |
Threading Stressing Grouting |
166.28 26 32.99 |
T U M3 |
|
ML12L |
Threading Stressing Grouting |
165.41 24 32.83 |
T U M3 |
|
ML11R |
Threading Stressing Grouting |
164.83 24 32.72 |
T U M3 |
|
ML11L |
Threading Stressing Grouting |
166.74 24 33.10 |
T U M3 |
|
ML10R |
Threading Stressing Grouting |
121.69 16 24.17 |
T U M3 |
|
ML10L |
Threading Stressing Grouting |
122.16 16 24.26 |
T U M3 |
|
ML09R |
Threading Stressing Grouting |
140.32 32 27.73 |
T U M3 |
|
ML09L |
Threading Stressing Grouting |
129.46 32 25.56 |
T U M3 |
|
ML08R |
Threading Stressing Grouting |
85.72 24 16.89 |
T U M3 |
|
ML08L |
Threading Stressing Grouting |
85.72 24 16.89 |
T U M3 |
|
ML07R |
Threading Stressing Grouting |
129.58 32 25.59 |
T U M3 |
|
ML07L |
Threading Stressing Grouting |
140.43 32 27.76 |
T U M3 |
|
ML06R |
Threading Stressing Grouting |
113.04 24 22.35 |
T U M3 |
|
ML06L |
Threading Stressing Grouting |
113.04 24 22.35 |
T U M3 |
|
ML05R |
Threading Stressing Grouting |
113.68 24 22.48 |
T U M3 |
|
ML05L |
Threading Stressing Grouting |
112.39 24 22.22 |
T U M3 |
|
ML04R |
Threading Stressing Grouting |
113.04 24 22.35 |
T U M3 |
|
ML04L |
Threading Stressing Grouting |
113.04 24 22.35 |
T U M3 |
|
ML03R |
Threading Stressing Grouting |
199.65 32 39.615 |
T U M3 |
|
ML03L |
Threading Stressing Grouting |
201.13 32 29.9 |
T U M3 |
|
ML02R |
Threading Stressing Grouting |
113.72 24 22.49 |
T U M3 |
|
ML02L |
Threading Stressing Grouting |
113.73 24 22.49 |
T U M3 |
|
ML1R |
Threading Stressing Grouting |
113.72 24 22.49 |
T U M3 |
|
ML1L |
Threading Stressing Grouting |
113.73 24 22.49 |
T U M3 |
Internal Prestressing Grouting Progress
|
Viaduct |
Activities |
Quantities |
Unit |
|
ML19C |
Air
test & Grouting |
14.09 |
M3 |
|
ML19R |
Air
test & Grouting |
14.90 |
M3 |
|
ML19L |
Air test
& Grouting |
13.90 |
M3 |
|
ML18R |
Air
test & Grouting |
25.24 |
M3 |
|
ML18L |
Air
test & Grouting |
24.76 |
M3 |
|
ML17R |
Air
test & Grouting |
23.47 |
M3 |
|
ML17L |
Air
test & Grouting |
23.46 |
M3 |
|
ML16R |
Air
test & Grouting |
36.54 |
M3 |
|
ML16L |
Air
test & Grouting |
35.46 |
M3 |
|
ML15R |
Air
test & Grouting |
39.34 |
M3 |
|
ML15L |
Air
test & Grouting |
39.69 |
M3 |
|
ML14R |
Air
test & Grouting |
104.9 |
M3 |
|
ML14L |
Air
test & Grouting |
106.55 |
M3 |
|
ML13R |
Air
test & Grouting |
108.28 |
M3 |
|
ML13L |
Air
test & Grouting |
107.73 |
M3 |
|
ML12R |
Air
test & Grouting |
121.77 |
M3 |
|
ML12L |
Air
test & Grouting |
121.00 |
M3 |
|
ML11R |
Air
test & Grouting |
111.47 |
M3 |
|
ML11L |
Air
test & Grouting |
112.75 |
M3 |
|
ML10R |
Air
test & Grouting |
89.33 |
M3 |
|
ML10L |
Air
test & Grouting |
89.59 |
M3 |
|
ML09R |
Air
test & Grouting |
63.27 |
M3 |
|
ML09L |
Air
test & Grouting |
57.86 |
M3 |
|
ML08R |
Air
test & Grouting |
36.58 |
M3 |
|
ML08L |
Air
test & Grouting |
36.56 |
M3 |
|
ML07R |
Air
test & Grouting |
59.61 |
M3 |
|
ML07L |
Air
test & Grouting |
60.05 |
M3 |
|
ML06R |
Air
test & Grouting |
58.31 |
M3 |
|
ML06L |
Air
test & Grouting |
58.31 |
M3 |
|
ML05R |
Air
test & Grouting |
58.62 |
M3 |
|
ML05L |
Air
test & Grouting |
58.01 |
M3 |
|
ML04R |
Air
test & Grouting |
57.64 |
M3 |
|
ML04L |
Air
test & Grouting |
57.69 |
M3 |
|
ML03R |
Air
test & Grouting |
126.65 |
M3 |
|
ML03L |
Air
test & Grouting |
127.63 |
M3 |
|
ML02R |
Air
test & Grouting |
62.74 |
M3 |
|
ML02L |
Air
test & Grouting |
62.74 |
M3 |
|
ML01R |
Air
test & Grouting |
53.80 |
M3 |
|
ML01L |
Air
test & Grouting |
53.80 |
M3 |
Turnaround Facilities
(a) Top
slab for longitudinal stitch (RHS) between box girders was cast;
(b) Petrol
interceptor rebar fixing was completed;
(c) Bottom
slab between BG, IB and CB falsework and formwork was erected;
(d) Wing
slab falsework erection is in progress;
(e) Rebar
fixing for Insitu beam (56-55-R) is in progress;
(f) Sling
platform erection was in progress and UB900 at P56-55-L and P56-57-L was
erected;
(g) MJ
opening at P53 was cast;
(h) P53
& P59 cross tie beam between ramp segment and main bridge were cast;
(i) Ramp
B segment at MJ Pier P59, grouting bearing plinth were completed;
(j) Ramp
B segment at MJ Pier P53 and P59, load transfer on bearing were completed;
(k) Ramp
B segment concrete stitching was in progress and last 4 number were completed
at P55-P56 and P56-P57 both LHS and RHS, span tendons stressing is in progress.
Road Pavement
|
Road Pavement |
Total (m2) |
Monthly Workdone (m2) |
Cumulative Workdone (m2) |
|
Base
Course |
284440 |
47093 |
124570 |
|
Wearing
Course |
284440 |
44237 |
113181 |
|
Friction
Course |
274688 |
0 |
0 |
October
2017:
Ancillary and
Associated Facilities
(a)
P115 & P114 interface area - Breaking off the
concrete footings for reinstatement of slope underneath the deck is in
progress;
(b)
Reinstatement of sloping seawall at P94 to P90 and P84 to
P87 are in progress;
(c)
The precast parapet facial panel progress is summarized
as follows:
|
Item |
Number in this month |
Cumulative No. of
Precast Parapet Completed (up to 28th
of month) |
|
Precast
Parapet Facial Panel Casting |
19 |
6813 |
|
Precast
Parapet Facial Panel Installation |
473 |
5656 |
|
In-situ
concreting works |
1130 |
13517 |
(d)
The central barrier progress is summarized as follows:
|
Type |
Item |
Monthly Workdone |
Cumulative Workdone (up to 28th of
month) |
|
Central
barrier (precast method) |
Precast |
52 |
5834 |
|
Installation |
1099 |
4798 |
|
|
Central
barrier (precast + in-situ method) |
In-fill
concreting # |
1713 |
6690 |
# ¡§In-fill concreting¡¨ will
be carried out after installation of precast units or formworks for precast
method and in-situ method respectively. After the in-fill concreting works, the
central barrier shall be regarded as completed.
(e)
The side barrier progress is summarized as follows:
|
Type |
Item |
Monthly Workdone |
Cumulative Workdone (up to 28th of
month) |
|
Side
barrier (precast method) |
Precast |
109 |
6113 |
|
Installation |
732 |
5570 |
|
|
Side
barrier (precast + in-situ method) |
In-fill
concreting # |
2273 |
15657 |
# ¡§In-fill concreting¡¨ will
be carried out after installation of precast units or formworks for precast
method and in-situ method respectively. After the in-fill concreting works, the
side barrier shall be regarded as completed.
(f)
Construction of the longitudinal stitching at ML7, ML9,
ML12 and ML13 are in progress. Longitudinal from ML1 to ML6 were completed;
(g)
Sealing of deck openings and preparation deck surface
for waterproofing at ML7, ML10, ML11 and ML14 are in progress;;
(h)
Fire hydrants at P0, P8, P68, P71 and P73 were
installed, fire main at ML1 and ML14 are in progress;
(i)
Installation of stormwater
drainage for Chek Lap Kok
South Road realignment;
(j)
Construction of concrete carriageway for Chek Lap Kok South Road
realignment;
(k)
Site clearance/formation work to the reinstatement of
South Perimeter Road between P84 to P81 in progress.
E&M Works
(a)
E&M ducting installation at ML1 and ML11 completed;
(b)
E&M ducting installation at ML7 and ML10 continue;
(c)
E&M ducting installation at ML8 and ML9 commence;
(d)
E&M ducting installation from ML12 and ML14
continue;
(e)
E&M works inside SHT building is in progress;
(f)
Cable hanger installation at ML11 continue;
(g)
Cable hanger installation at ML12 and ML13 commence;
(h)
Construction of Load Centre 5 completed;
(i)
Construction of Load Centre 3 continue;
(j)
Street light cables and poles installation at ML2 to ML6
completed;
(k)
Street light cables and poles installation at ML1 continue;
(l)
LV and HV cable laying works at ML1 to ML6 and ML15 to
ML19 continue;
(m)
Optic fibre laying works for the SMS scope from SHT tunnel to HMA
building complete;
(n)
Cable tray
installation of SMS system at ML3 and ML4 continue;
(o)
Optic fibre cable laying works
at ML14 to ML19 complete;
(p)
GPS pole installation commence from ML1 to ML14.
Deck Erection
(a)
P67 Dismantling Works
i.
Dismantling of RMD towers were completed and transported
to WA4;
ii.
All temporary piles were removed.
(b)
Movement Joints
i.
Installation of movement joints at P29R, P37L, P74R,
P78R, P84R, P92L, P99L, P104L and P111L were completed;
ii.
Installation of movement joints at P8R, P21L,
P29L, P45R, P67R, P70R, P74R, P78R, P84L and P115C in progress;
iii.
Surface preparation (breaking temporary concrete)
prior to movement joints installation in progress.
External Prestressing Tendon Installation
|
Viaduct |
Activities |
Quantities |
Unit |
|
ML19C |
Threading Stressing Grouting |
47.55 12 9.42 |
T U M3 |
|
ML19R |
Threading Stressing Grouting |
48.65 12 9.64 |
T U M3 |
|
ML19L |
Threading Stressing Grouting |
46.91 12 9.29 |
T U M3 |
|
ML18R |
Threading Stressing Grouting |
77.90 18 15.38 |
T U M3 |
|
ML18L |
Threading Stressing Grouting |
76.40 18 15.08 |
T U M3 |
|
ML17R |
Threading Stressing Grouting |
63.09 16 12.44 |
T U M3 |
|
ML17L |
Threading Stressing Grouting |
62.86 16 12.39 |
T U M3 |
|
ML16R |
Threading Stressing Grouting |
56.69 15 9.91 |
T U M3 |
|
ML16L |
Threading Stressing Grouting |
87.34 18 17.2 |
T U M3 |
|
ML15R |
Threading Stressing Grouting |
108.74 18 21.15 |
T U M3 |
|
ML15L |
Threading Stressing Grouting |
106.26 18 21.45 |
T U M3 |
|
ML14R |
Threading Stressing Grouting |
116.06 16 23.04 |
T U M3 |
|
ML14L |
Threading Stressing Grouting |
118.55 16 23.54 |
T U M3 |
|
ML13R |
Threading Stressing Grouting |
122.22 16 24.27 |
T U M3 |
|
ML13L |
Threading Stressing Grouting |
212.71 16 24.17 |
T U M3 |
|
ML12R |
Threading Stressing Grouting |
166.28 26 32.99 |
T U M3 |
|
ML12L |
Threading Stressing Grouting |
165.41 24 32.83 |
T U M3 |
|
ML11R |
Threading Stressing Grouting |
164.83 24 32.72 |
T U M3 |
|
ML11L |
Threading Stressing Grouting |
166.74 24 33.10 |
T U M3 |
|
ML10R |
Threading Stressing Grouting |
121.69 16 24.17 |
T U M3 |
|
ML10L |
Threading Stressing Grouting |
122.16 16 24.26 |
T U M3 |
|
ML09R |
Threading Stressing Grouting |
140.32 32 27.73 |
T U M3 |
|
ML09L |
Threading Stressing Grouting |
129.46 32 25.56 |
T U M3 |
|
ML08R |
Threading Stressing Grouting |
85.72 24 16.89 |
T U M3 |
|
ML08L |
Threading Stressing Grouting |
85.72 24 16.89 |
T U M3 |
|
ML07R |
Threading Stressing Grouting |
129.58 32 25.59 |
T U M3 |
|
ML07L |
Threading Stressing Grouting |
140.43 32 27.76 |
T U M3 |
|
ML06R |
Threading Stressing Grouting |
113.04 24 22.35 |
T U M3 |
|
ML06L |
Threading Stressing Grouting |
113.04 24 22.35 |
T U M3 |
|
ML05R |
Threading Stressing Grouting |
113.68 24 22.48 |
T U M3 |
|
ML05L |
Threading Stressing Grouting |
112.39 24 22.22 |
T U M3 |
|
ML04R |
Threading Stressing Grouting |
113.04 24 22.35 |
T U M3 |
|
ML04L |
Threading Stressing Grouting |
113.04 24 22.35 |
T U M3 |
|
ML03R |
Threading Stressing Grouting |
199.65 32 39.615 |
T U M3 |
|
ML03L |
Threading Stressing Grouting |
201.13 32 29.9 |
T U M3 |
|
ML02R |
Threading Stressing Grouting |
113.72 24 22.49 |
T U M3 |
|
ML02L |
Threading Stressing Grouting |
113.73 24 22.49 |
T U M3 |
|
ML1R |
Threading Stressing Grouting |
113.72 24 22.49 |
T U M3 |
|
ML1L |
Threading Stressing Grouting |
113.73 24 22.49 |
T U M3 |
Internal Prestressing Grouting Progress
|
Viaduct |
Activities |
Quantities |
Unit |
|
ML19C |
Air
test & Grouting |
14.09 |
M3 |
|
ML19R |
Air
test & Grouting |
14.90 |
M3 |
|
ML19L |
Air
test & Grouting |
13.90 |
M3 |
|
ML18R |
Air
test & Grouting |
25.24 |
M3 |
|
ML18L |
Air
test & Grouting |
24.76 |
M3 |
|
ML17R |
Air
test & Grouting |
23.47 |
M3 |
|
ML17L |
Air
test & Grouting |
23.46 |
M3 |
|
ML16R |
Air
test & Grouting |
36.54 |
M3 |
|
ML16L |
Air
test & Grouting |
35.46 |
M3 |
|
ML15R |
Air
test & Grouting |
39.34 |
M3 |
|
ML15L |
Air
test & Grouting |
39.69 |
M3 |
|
ML14R |
Air
test & Grouting |
104.9 |
M3 |
|
ML14L |
Air
test & Grouting |
106.55 |
M3 |
|
ML13R |
Air
test & Grouting |
108.28 |
M3 |
|
ML13L |
Air
test & Grouting |
107.73 |
M3 |
|
ML12R |
Air
test & Grouting |
121.77 |
M3 |
|
ML12L |
Air
test & Grouting |
121.00 |
M3 |
|
ML11R |
Air test
& Grouting |
111.47 |
M3 |
|
ML11L |
Air
test & Grouting |
112.75 |
M3 |
|
ML10R |
Air
test & Grouting |
89.33 |
M3 |
|
ML10L |
Air
test & Grouting |
89.59 |
M3 |
|
ML09R |
Air
test & Grouting |
63.27 |
M3 |
|
ML09L |
Air
test & Grouting |
57.86 |
M3 |
|
ML08R |
Air
test & Grouting |
36.58 |
M3 |
|
ML08L |
Air
test & Grouting |
36.56 |
M3 |
|
ML07R |
Air
test & Grouting |
59.61 |
M3 |
|
ML07L |
Air
test & Grouting |
60.05 |
M3 |
|
ML06R |
Air
test & Grouting |
58.31 |
M3 |
|
ML06L |
Air
test & Grouting |
58.31 |
M3 |
|
ML05R |
Air
test & Grouting |
58.62 |
M3 |
|
ML05L |
Air
test & Grouting |
58.01 |
M3 |
|
ML04R |
Air
test & Grouting |
57.64 |
M3 |
|
ML04L |
Air
test & Grouting |
57.69 |
M3 |
|
ML03R |
Air
test & Grouting |
126.65 |
M3 |
|
ML03L |
Air
test & Grouting |
127.63 |
M3 |
|
ML02R |
Air
test & Grouting |
62.74 |
M3 |
|
ML02L |
Air
test & Grouting |
62.74 |
M3 |
|
ML01R |
Air
test & Grouting |
53.80 |
M3 |
|
ML01L |
Air
test & Grouting |
53.80 |
M3 |
Turnaround Facilities
(a) Top
slab for longitudinal stitch (LHS) between box girders was cast;
(b) Bottom
slab between BG, IB and CB (4 of 4) were cast;
(c) Wing
slab falsework erection completed;
(d) Wing
slab formwork completed in down chainage. Rebar fixing
for wing slab in progress;
(e) All
steel members of sling platform erected;
(f) Falsework
and formwork for top slab between IB and ramp segment in progress. Rebar fixing
for top slab will follow;
(g) Rebar
fixing for Insitu beam (4 of 4) completed;
(h) Type
3 parapet (main deck and ramp) installation in progress;
(i) Insitu barrier for type 3 parapet
rebar fixing in progress;
(j) P55-P56
and P56-P57 both LHS and RHS, span tendons stressing were completed.
Road Pavement
|
Road Pavement |
Total (m2) |
Monthly Workdone (m2) |
Cumulative Workdone (m2) |
|
Base
Course |
284440 |
45155 |
169725 |
|
Wearing
Course |
284440 |
46058 |
159239 |
|
Friction
Course |
274688 |
0 |
0 |
November 2017:
Ancillary and
Associated Facilities
(a)
P115 & P114 interface area - Breaking off the
concrete footings for reinstatement of slope underneath the deck is in
progress;
(b)
Reinstatement of sloping seawall at P94 to P90 and P84
to P87 are in progress;
(c)
The precast parapet facial panel progress is summarized
as follows:
|
Item |
Number in this month |
Cumulative No. of
Precast Parapet Completed (up to 28th
of month) |
|
Precast
Parapet Facial Panel Casting |
25 |
6833 |
|
Precast
Parapet Facial Panel Installation |
901 |
6528 |
|
In-situ
concreting works |
2295 |
19080 |
(d)
The central barrier progress is summarized as follows:
|
Type |
Item |
Monthly Workdone |
Cumulative Workdone (up to 28th of
month) |
|
Central
barrier (precast method) |
Precast |
18 |
5857 |
|
Installation |
853 |
5704 |
|
|
Central
barrier (precast + in-situ method) |
In-fill
concreting # |
1469 |
8222 |
# ¡§In-fill concreting¡¨ will
be carried out after installation of precast units or formworks for precast
method and in-situ method respectively. After the in-fill concreting works, the
central barrier shall be regarded as completed.
(e)
The side barrier progress is summarized as follows:
|
Type |
Item |
Monthly Workdone |
Cumulative Workdone (up to 28th of
month) |
|
Side
barrier (precast method) |
Precast |
168 |
6296 |
|
Installation |
382 |
5996 |
|
|
Side
barrier (precast + in-situ method) |
In-fill
concreting # |
1931 |
17670 |
# ¡§In-fill concreting¡¨ will
be carried out after installation of precast units or formworks for precast
method and in-situ method respectively. After the in-fill concreting works, the
side barrier shall be regarded as completed.
(f)
Construction of the longitudinal stitching to all
bridges completed except ML8 area;
(g)
Sealing of deck openings and preparation of deck surface
for waterproofing at ML9 and ML13 are in progress;
(h)
Fire hydrants at P0, P4, P8, P12, P16, P18-P19, 30, P34,
P38-P39, P42-P43, P51-P52, P65, P68, P71, P73, P75-P76, P77-P78, P80, P82-P83,
P86, P91, P97, P102-P103, P108-P109 and P112 were installed. Fire main at ML12
and ML13 are in progress;
(i)
Installation of utility trough covers are in progress;
(j)
Erection of the remaining sign gantries at ML8, ML9 and
ML10;
(k)
Installation of stormwater
drainage for Chek Lap Kok
South Road realignment* were completed;
(l)
Installation of the additional pier number and
information signs commenced at ML3;
(m)
Construction of concrete carriageway for Chek Lap Kok South Road
realignment* are in progress;
(n)
Site clearance/formation work to the reinstatement of
South Perimeter Road between P84 to P81 in progress.
Note:
*Minor Modification Works:-
¡PShifting the bus stop location;
¡PShifting the old alignment near P109 southward; and
¡PRe-instating the underground drainage with the new
alignment due to the minor modification works above.
E&M Works
(a)
E&M ducting installation from ML7 to ML10, ML12 and
ML14 continue;
(b)
E&M works inside SHT building is in progress;
(c)
Cable hanger installation at ML9 and ML10 commenced;
(d)
Cable hanger installation at ML11, ML12 and ML13
continue;
(e)
Construction of Load Centre 5 completed;
(f)
Street light cables and poles installation at ML1
continue;
(g)
LV and HV cable laying works at ML1 to ML6 and ML15 to
ML19 continue
(h)
LV and HV cable laying works at ML7 commence;
(i)
Cable tray installation of SMS system at ML3 and ML4
completed;
(j)
GPS pole installation from ML1 to ML14 continue;
(k)
Cable laying works for HKPF at ML1 to ML6 commence.
Deck Erection
(a)
P69 & 70 Jetty Dismantling Works
i.
Setting up a 150ton crawler crane on the jetty.
(b)
Movement Joints
i.
Overall 38 nos. installed with 34 nos. both nosing
casted;
ii.
Installation of movement joints in progress in the month
at P0L&R, P8L&R, P16L&R, P21L&R, P29L, P37R, P53L&R,
P59L&R, P67L&R, P70L&R, P74L, P81L&R, P84L and P115L&C;
iii.
At end November total 36 nos. movement joints complete
(both noising casted) out of total 41 nos. Completed gridline P8, P16, P21,
P29, P37, P45, P67, P70, P74, P78, P81, P84, P92, P99, P104 and P111.
(c)
Remaining internal prestressing
tendons at ML8 & ML9 were grouted in early November.
Turnaround Facilities
(a) Wing
slabs (2 of 2) for Turnaround Facility were cast;
(b) 4
movement joints on the turnaround ramps at P53 and P59 had been completed;
(c) Dismantle
of wing slab falsework completed;
(d) Sling
platform dismantle in progress (2 of 4 dismantled);
(e) Mobile
telecom equipment room was cast;
(f) Type
3 parapet (main deck and ramp) installation in progress;
(g) Insitu barrier for type 1 and type
3 parapet are in progress
10m at P0
(a) Erection
of falsework for extending the wing to the utility trough in progress;
(b) Fabrication
& erection of the formwork to the central barrier carried out and the
central barrier was casted before end November;
Road Pavement
|
Road Pavement |
Total (m2) |
Monthly Workdone (m2) |
Cumulative Workdone (m2) |
|
Base
Course |
284440 |
50112 |
219837 |
|
Wearing
Course |
284440 |
44044 |
203283 |
|
Friction
Course |
274688 |
15495 |
15495 |
2.11 The valid environmental licenses
and permits were attached in the Monthly EM&A Reports.