2               Contract INFORMATION

Background

2.1         The proposed Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road (HKLR) is 12km long connecting the Hong Kong-Zhuhai-Macao Bridge (HZMB) at the HKSAR Boundary with the Hong Kong Boundary Crossing Facilities (HKBCF) situated at the north eastern waters of the Hong Kong International Airport, opening a new and direct connection route between Hong Kong, Macao and the Western Pearl River Delta. 

2.2         The HKLR comprises a 9.4km long viaduct section from the HKSAR boundary to Scenic Hill on the Airport Island; a 1km tunnel section to the reclamation formed along the east coast of the Airport Island and a 1.6km long at-grade road section on the reclamation connecting to the HKBCF. The tunnel section of HKLR will pass under Scenic Hill, Airport Road and Airport Railway to minimize the environmental and visual impacts to Tung Chung residents.

2.3         An application (No ESB-110/2003) for an Environmental Impact Assessment (EIA) Study Brief under Section 5(1) of the Environmental Impact Assessment Ordinance (EIAO) was submitted by Highways Department (the Project Proponent) on 8 October 2003 with a Project Profile (No. No. PP-201/2003) for the Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection. The Hong Kong - Zhuhai - Macao Bridge Hong Kong Section and North Lantau Highway Connection has subsequently been renamed as HKLR.  EPD issued an EIA Study Brief (No: ESB-110/2003) in November 2003 to the Project Proponent to carry out an EIA study.

2.4         An EIA Study (Reg. No. AEIAR-144/2009) has been undertaken to provide information on nature and extent of environmental impacts arising from the construction and operation of HKLR. The Environmental Permit was issued on 4 November 2009 (Permit No. EP-352/2009). Pursuant to Section 13 of the EIAO, the Director of Environmental Protection amends the Environmental Permit (No. EP-352/2009) based on the Application No. VEP-339/2011 and the environmental Permit (Permit No. EP-352/2009/A) was issued on 9 November 2011 for HKLR to the Highways Department as the Permit Holder. Subsequently, the Director of Environmental Protection amends the Environmental Permits (No. EP-352/2009/A, EP-352/2009/B, EP-352/2009/C) based on the Application No. VEP-409/2013, VEP-411/2013 and VEP-459/2014 respectively. The environmental Permit (Permit No. EP-352/2009/D) was then issued on 22 December 2014.

2.5         Figure 1a-d  shows the layout of the Contract and the scope of the Contract works comprises the following major items:

 

¡P           a dual 3-lane carriageway in the form of viaduct from the HKSAR boundary (connecting with the HZMB Main Bridge) to the Scenic Hill (connecting with the tunnel under separate Contract No. HY/2011/03), of approximately 9.4km in length with a hard shoulder for each bound of carriageway and a utilities trough on the outer edge of each bound of viaducts;

¡P           a grade-separated turnaround facility located near San Shek Wan, composed of sliproads in the form of viaduct with single-lane carriageway bifurcated from the HKLR mainline with an elevated junction above the mainline;

¡P           provision of ancillary facilities including, but not limited to, meteorological enhancement measures including the provisioning of anemometers and modification of the wind profiler station at hillside of Sha Lo Wan, provisioning of a compensatory marine radar, and provisioning of security systems; and

¡P           associated civil, structural, geotechnical, marine, environmental protection, landscaping, drainage and highways electrical and mechanical (E&M) works, street lightings, traffic aids and sign gantries, marine navigational aids, ship impact protection system, water mains and fire hydrants, lightning protection system, structural health monitoring and maintenance management system (SHM&MMS), supervisory control and data acquisition (SCADA) system, as well as operation and maintenance provisions of viaducts, provisioning of facilities for installation of traffic control and surveillance system (TCSS), provisioning of facilities for installation of telecommunication cables/equipments and reprovisioning works of affected existing facilities/utilities.

Contract Organisation

2.6         Different parties with different levels of involvement in the Contract organization include:

Ÿ   Supervising Officer¡¦s Representative (SOR) ¡V Ove Arup & Partners Hong Kong Limited (ARUP)

Ÿ   Contractor ¡VDragages -China Harbour-VSL JV   (DCVJV)

Ÿ   Environmental Team (ET) ¡V Cinotech Consultants Ltd. (Cinotech)

 

2.7         The proposed project organization and lines of communication with respect to the on-site environmental management structure are shown in Figure 2. The key personnel contact names and numbers are summarized in Table 2.1.

Table 2.1        Key Contacts of the Contract

Party

Position

Name

Phone No.

Fax No.

SOR (ARUP)

CRE

Mr. Michael Chan

3767 5803

3767 5922

Mr. Dennis Leung

3767 5801

ENPO/IEC

(Ramboll Hong Kong Limited)

Environmental Project Office Leader

Mr. Y. H Hui

3465 2888

3465 2899

Independent Environmental Checker

Mr. Antony Wong

3465 2888

3465 2899

Contractor (DCVJV)

Deputy Project Director

Mr. W.K Poon

3121 6638

3121 6688

Environmental Officer

Mr. CHU Chung Sing

3121 6672

24-hour Hotline

--

6898 6161

--

ET

(Cinotech)

Environmental Team Leader

Dr. Priscilla Choy

2151 2089

3107 1388

 

2.8         Ramboll Hong Kong Limited is employed by the Highways Department as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) for the Project.

Construction Programme

 

2.9         A copy of Contractor¡¦s construction programme is provided in Appendix A.

Summary of Construction Works Undertaken During Reporting Period

2.10     The major site activities undertaken in the reporting period  included:

December 2017:

Ancillary and Associated Facilities

(a)    P115 & P114 interface area - Breaking off the concrete footings for reinstatement of slope underneath the deck is in progress;

(b)   Reinstatement of sloping seawall at P94 to P90 and P85 to P87 are in progress;

(c)    All precast parapet facial panels were completed and progress of this reporting period is summarized as follows:

Item

Number in this month

Cumulative No. of Precast Parapet Completed

(up to 28th of month)

Precast Parapet Facial Panel  Casting

73

6906

Precast Parapet Facial Panel Installation

187

6715

In-situ concreting works

561

20145

 

(d)   The central barrier progress is summarized as follows:

Type

Item

Monthly Workdone

Cumulative Workdone

(up to 28th of month)

Central barrier (precast method)

Precast

223

6080

Installation

366

6070

Central barrier (precast + in-situ method)

In-fill concreting #

883

9105

# ¡§In-fill concreting¡¨ will be carried out after installation of precast units or formworks for precast method and in-situ method respectively. After the in-fill concreting works, the central barrier shall be regarded as completed.

 

(e)    The side barrier progress is summarized as follows:

Type

Item

Monthly Workdone

Cumulative Workdone

(up to 28th of month)

Side barrier (precast method)

Precast

364

6660

Installation

582

6578

Side barrier (precast + in-situ method)

In-fill concreting #

2062

19732

# ¡§In-fill concreting¡¨ will be carried out after installation of precast units or formworks for precast method and in-situ method respectively. After the in-fill concreting works, the side barrier shall be regarded as completed.

 

(f)    Construction of the longitudinal stitching to all bridges were completed except stitching between ML8 and Ramps;

(g)   Sealing of deck openings and preparation of deck surface for waterproofing at ML8 & ML9 and ML10R to ML18L  are in progress;

(h)   Fire hydrants at P0, P4, P8, P12, P16, P18-P19, P21, P25-P26, P30, P34, P38-P39, P42-P43, P51-P52, P60-P61, P65, P68, P71, P73, P75-P76, P77-P78, P80, P82-P83, P86, P91, P97, P102-P103, P108-P109 and P112 were installed. Fire main at ML7 and ML8 are in progress;

(i)     Installation of utility trough covers are in progress;

(j)     Erection of the sign gantries were completed;

(k)   Installation of the additional pier number and information signs  at ML3 was completed at ML3;

(l)     Installation of the additional pier number and information signs at ML4 to ML9 commenced;

(m) Installation of the headroom sign and vessel length restriction sign at ML3 commenced;

(n)   Installation of the height restriction sign commenced at ML12;

(o)   Construction of concrete carriageway for Chek Lap Kok South Road realignment* were completed;

(p)   Site clearance/formation work to the reinstatement of South Perimeter Road between P84 to P81 in progress.

 

Note:

*Minor Modification Works:-

¡PShifting the bus stop location;

¡PShifting the old alignment near P109 southward; and

¡PRe-instating the underground drainage with the new alignment due to the minor modification works above.

 

E&M Works

(a)    E&M ducting installation from ML7;

(b)   E&M ducting installation from ML7 to ML10 and ML12 continues;

(c)    E&M works inside SHT building is in progress;

(d)   Cable hanger installation at M9 and ML10 completed;

(e)    Cable hanger installation at ML8 commenced;

(f)    Cable hanger installation at ML11, ML12 and ML13 completed;

(g)   Street light cables and poles installation at ML1 continues;

(h)   LV and HV cable laying works at ML1 to ML6 and ML16 to ML19 completed;

(i)     LV and HV cable laying works at ML13 to ML15 continues;

(j)     Cable tray installation of SMS system at ML12 and ML13 commenced;

(k)   GPS pole installation from ML1 to ML14 continues;

(l)     Cable laying works for HKPF at ML1 to ML6 continues;

(m) Installation of electrical sliding barrier between P0 and P1 commenced.

 

Removal of Temporary Works at P68 - P70

(a)    P69 & 70 Jetty Dismantling Works  - Removal the temporary jetty in progress (around 25% completed);

(b)   P68 Platform Removal Works - Removal of temporary platform has been commenced.

 

Movement Joint

 

(a)    Overall 40 nos. installed with both nosing casted;

(b)   The last movement joint at P115R, is pending for the access road diversion open on the T001 tunnel by the Contract HY/2011/03.

 

Turnaround Facilities

(a)      Roof finishing and ground level finish of mobile telecom equipment room were cast;

(b)     Waterproof membrane for mobile telecom equipment room were applied;

(c)      Dismantling of sling platform completed;

(d)     Dismantling of box girder support tower completed;

(e)      Dismantling of extended platform completed;

(f)      Type K1 kerb for traffic island installed;

(g)     Installation of type III parapet completed.

 

10m at P0

(a)      Extended wing at P0 completed;

(b)     Construction of central barrier completed;

(c)      Construction of side barriers are in progress.

 

Road Pavement

Road Pavement

Total (m2)

Monthly Workdone (m2)

Cumulative Workdone

(m2)

Base Course

284440

44683

264520

Wearing Course

284440

57981

261264

Friction Course

274688

114035

129530

 

January 2018:

Ancillary and Associated Facilities

(a)    P115 & P114 interface area - Breaking off the concrete footings for reinstatement of slope underneath the deck is in progress;

(b)   Reinstatement of sloping seawall P84 to P87, P88 to P90, P91 to P93 and P104 to P107 are in progress;

(c)    All central barriers were completed and the progress of this reporting period is summarized as follows:

Item

Number in this month

Cumulative No. of Precast Parapet Completed

(up to 28th of month)

Precast Parapet Facial Panel  Casting

8

6098

Precast Parapet Facial Panel Installation

10

6098

In-situ concreting works

14

9150

# ¡§In-fill concreting¡¨ will be carried out after installation of precast units or formworks for precast method and in-situ method respectively. After the in-fill concreting works, the side barrier shall be regarded as completed.

* Precasting of typical and special units all completed.

 

 

 

 

 

(d)   The side barrier progress is summarized as follows:

Type

Item

Monthly Workdone

Cumulative Workdone

(up to 28th of month)

Side barrier (precast method)

Precast

62

6722

Installation

70

6722

Side barrier (precast + in-situ method)

In-fill concreting #

210

20166

# ¡§In-fill concreting¡¨ will be carried out after installation of precast units or formworks for precast method and in-situ method respectively. After the in-fill concreting works, the side barrier shall be regarded as completed.

* Precasting of typical and special units all completed.

 

(e)    Construction of the longitudinal stitching to all bridges were completed;

(f)    Sealing of deck openings and preparation of deck surface for waterproofing are completed, except section of waterproofing at ML19R near the movement joint;

(g)   All Fire hydrants pipes installation were completed except the fire main at ML8 between P56 & 60 and is in progress;

(h)   Installation of utility trough covers are in progress;

(i)     Installation of the additional pier number and information signs at ML11 to ML12 are in progress;

(j)     Installation of the headroom sign and vessel length restriction sign at ML3 are in progress;

(k)   Installation of the height restriction sign at ML12 completed;

(l)     Construction of drainage at P110 commenced;

(m) Fill slope for Chek Lap Kok South Road realignment* completed;

(n)   Site clearance/formation works to the reinstatement of South Perimeter Road between P84 to P81 are in progress.

 

Note:

*Minor Modification Works:-

¡PShifting the bus stop location;

¡PShifting the old alignment near P109 southward; and

¡PRe-instating the underground drainage with the new alignment due to the minor modification works above.

 

E&M Works

(a)    E&M ducting installation from ML7 to ML10 and ML12 completed;

(b)   E&M ducting installation at turnaround completed;

(c)    E&M works inside SHT building is in progress;

(d)   Cable hanger installation at ML8 completed;

(e)    Street light cables and poles installation completed;

(f)    LV and HV cable laying works at ML13 to ML15 completed;

(g)   Cable tray installation of SMS system at ML12 and ML13 completed;

(h)   GPS pole installation from ML1 to ML14 completed;

(i)     Cable laying works for HKPF at ML1 to ML6 continues;

(j)     Installation of manual barrier gate at ML 5, ML 8 & ML 12 completed

(k)   Installation of electrical sliding barrier at ML1 completed.

 

 

 

Removal of Temporary Works at P68 - P70

(a)    P69 & 70 Jetty Dismantling Works  - Removal the temporary jetty in progress (around 50% completed);

(b)   P68 Platform Removal Works - Removal of temporary steel platform has been completed, breaking the concrete slab on the seawall block platform is in progress;

 

Movement Joint

(a)    The last movement joint at P115R, is pending for Contract HY/2011/03 to divert the access from T002 to T001.

 

Turnaround Facilities

(a)      Mobile telecom equipment room was completed;

(b)     Dismantling of SOP supporting towers is in progress.

 

10m at P0

(a)      Construction of  side barriers was completed;

(b)     Laying of asphalt at P0 interface was completed.

 

Road Pavement

Road Pavement

Total (m2)

Monthly Workdone (m2)

Cumulative Workdone

(m2)

Base Course

284440

19720

284240

Wearing Course

284440

16136

277400

Friction Course

274688

108113

237643

 

February 2018:

Ancillary and Associated Facilities

(a)    P115 & P114 interface area - Breaking off the concrete footings for reinstatement of slope underneath the deck is in progress;

(b)   Reinstatement of sloping seawall at P86 to P87, P88 to P90, P92 to P93 and P104 to P107 are in progress;

(c)    Waterproofing works at ML19R near the movement joint was completed;

(d)   All fire mains, hydrants installation were completed;

(e)    Stage 1 to Stage 4 watermain pressure tests were completed;

(f)    Installation of utility trough covers were completed except the locations at high mast, movement joints, valve chambers and cables access locations;

(g)   Installation of the additional pier number and information signs at ML11 to ML12 are in progress;

(h)   Installation of the headroom sign and vessel length restriction sign at ML3 were completed;

(i)     Construction of drainage at P110 completed;

(j)     Construction of drainage at P113 commenced;

(k)   Site clearance/formation works to the reinstatement of South Perimeter Road between P84 to P81 are in progress;

 

 

E&M Works

(a)    E&M works inside SHT building is in progress;

(b)   LV and HV cable laying works at ML13 to ML15 completed;

(c)    LV and HV cable laying works at ML12 to ML8 completed;

(d)   GPS installation from ML1 to ML14 completed;

(e)    Cable laying works for HKPF completed;

 

Removal of Temporary Works at P68 - P70

(a)    P69 & 70 Jetty Dismantling Works  - Removal the temporary jetty in progress (around 75% completed);

(b)   P68 Platform Removal Works - Breaking the concrete slab on the seawall block platform was completed. Removal of the marine concrete blocks is in progress.

 

Movement Joint

(a)    As T001 tunnel is not opened for our bridge deck traffic by the Contract HY/2011/03, we closed our only bridge deck access at P115R for the last movement joint construction. Overtime day and night shifts were implemented for the last MJ works and it was completed on 4 Feb 18.

 

Turnaround Facilities

(a)      Dismantling of SOP supporting towers completed.

 

10m Works at P0 Interface

(a)      Road marking at P0 area in progress.

 

Road Pavement

(a)      Road pavement works were completed with following progress in this reporting period:

Road Pavement

Total (m2)

Monthly Workdone (m2)

Bridge Units

Cumulative Workdone

(m2)

Completion Percentage

 

Base Course

284,440

200

P115-R

284,440

100%

Wearing Course

284,440

7,040

Ramp(RHS)

Turnaround

P115-R

284,440

100%

Friction Course

274,688

37,045

ML7-R&L(SL,HS)

ML8-R&L(SL,HS)

ML9-R&L(SL,HS)

ML19-R

274,688

100%

 

Status of Environmental Licences, Notification and Permits

 

2.11     The valid environmental licenses and permits were attached in the Monthly EM&A Reports.