1.
This is the 22nd Quarterly Environmental Monitoring and Audit
(EM&A) Report prepared by Cinotech Consultants
Limited for the project ¡§Contract No. HY/2011/09 ¡V
Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road ¡V Section between HKSAR
Boundary and Scenic Hill¡¨
(hereinafter called the ¡§Contract¡¨). This report documents the
findings of EM&A Works performed in the period between June to August 2018.
Environmental
Monitoring and Audit Progress
2.
A summary of the monitoring activities in this reporting period is
listed in Table I below:
Table I Summary
Table for Monitoring Activities in the Reporting Period
Parameter(s) |
Monitoring Date(s) |
1-hr TSP Monitoring |
6th, 12th,
15th, 21st and 27th June 2018 3rd, 9th,
13th, 19th, 25th and 31st July
2018 6th, 10th,
16th, 22nd and 28th August 2018 |
24-hr TSP Monitoring |
|
Noise Monitoring |
1st, 7th,
13th, 22nd and 28th June 2018 4th, 10th,
20th and 26th July 2018 1st, 7th,
17th, 23rd and 29th August 2018 |
Water Quality Monitoring |
1st, 4th,
6th, 9th, 11th, 13th, 15th,
18th, 20th, 22nd, 25th, 27th
and 29th June 2018 2nd, 4th,
6th, 9th, 11th, 13th, 17th,
19th, 21st, 23rd, 25th, 27th
and 30th July 2018 1st, 3rd,
6th, 8th, 10th, 13th, 15th,
17th, 20th, 22nd, 24th, 28th
and 30th August 2018 |
4th and 20th
June 2018 10th and 19th
July 2018 2nd and 9th
August 2018 |
|
Environmental Site
Inspection |
5th, 12th,
19th and 26th June 2018 3rd, 10th,
17th, 24th and 31st July 2018 7th, 14th,
21st and 28th August 2018 |
Archaeological Site
Inspection |
19th June 2018 |
Breaches of Action and Limit Levels
3.
Summary of the environmental exceedances of the reporting period is
tabulated in Table II.
Table II Summary Table
for Events Recorded in the Reporting Period
Environmental Monitoring |
Parameter |
No. of Exceedance |
No. of Exceedance related to the Construction Activities of this
Contract |
||
Action Level |
Limit Level |
Action Level |
Limit Level |
||
Air Quality |
1-hr TSP |
0 |
0 |
0 |
0 |
24-hr TSP |
0 |
0 |
0 |
0 |
|
Noise |
Leq(30min) |
0 |
0 |
0 |
0 |
Water Quality |
Dissolved Oxygen
(DO) (Surface & Middle) |
0 |
0 |
0 |
0 |
Dissolved Oxygen
(DO) (Bottom) |
0 |
0 |
0 |
0 |
|
Turbidity |
0 |
0 |
0 |
0 |
|
Suspended Solids
(SS) |
19 |
0 |
0 |
0 |
|
Dolphin
Monitoring |
Line-transect
Vessel Surveys |
0 |
0 |
0 |
0 |
4.
Environmental monitoring works were performed in the reporting period
and all monitoring results were checked and reviewed. The details of each exceedance were
attached in the Monthly EM&A Reports.
Complaint Log
5.
No environmental complaint was received in the reporting period.
Notification of Summons and Successful Prosecutions
6.
No notification of summons and successful prosecution was received in
the reporting period.
7.
This report has been developed in compliance with the reporting
requirements for the quarterly EM&A Summary Report
as required by the EM&A Manual for Hong Kong Link Road (EM&A Manual).
Future Key Issues
8.
Major site activities for the coming reporting month will include:
Marine Portion
¡P
Installation of cat ladders at pile cap walls
Land
Portion
¡P
Reinstatement of South Perimeter Road