Table 4.10   Major Construction Program for Contract No. HY/ 2011/09

Description

Period

Commencement of the Contract

May 2012

Construction Commencement

February 2013

Piling

April 2013 – September 2015

Pile Cap and Piers

December 2013 – May 2016

Deck Segment Erection

March 2015 – June 2017