Table
4.10 Major Construction
Program for Contract No. HY/ 2011/09
|
Description |
Period |
|
Commencement
of the Contract |
May
2012 |
|
Construction Commencement |
February
2013 |
|
Piling |
April
2013 – September 2015 |
|
Pile
Cap and Piers |
December
2013 – May 2016 |
|
March
2015 – June 2017 |