Table 4.9             Summary of Land-based of Dolphin Behaviour and Movement Monitoring Requirements

EIA

EM&A Manual

Approved Monitoring Proposal

Requirement for Land-based of dolphin behaviour and movement monitoring

Ÿ  Land-based theodolite tracking to study dolphin behaviour near bored piling work site, and examine their north-south movement across the bridge alignment before, during and after bridge construction.

Ÿ  Land-based theodolite tracking to study dolphin behaviour near bored piling work site, and examine their north-south movement across the bridge alignment before, during and after bridge construction.

Ÿ  The behaviour near the bored piling sites and north-south movement across the bridge alignment of CWD should be monitored in the waters to the west of Airport.

Ÿ  Dolphin behaviour in response to bored piling works and movement near the bored piling sites should be monitored at the first three pier sites for 30 days from the start of bored piling activities in the waters to the west of Airport. However, the number of monitoring days is not well specified for the baseline period.

Ÿ  Therefore, reference to the requirements in the Tuen Mun ¡V Chek Lap Kok Link (TMCLKL) EM&A Manual was made, in which 30 days of theodolite tracking before(i) and 30 days of theodolite tracking from the start of bored piling activities(ii) will be conducted under the present study in order to maintain overall consistency of EM&A Programs for the Hong Kong-Zhuhai-Macao Bridge (HZMB) development.

Frequency

Baseline

Ÿ  Not specified

Ÿ  Baseline for dolphin north-south movement across the bridge alignment shall be established prior to the commencement of works and agreed with AFCD.

Ÿ  30 consecutive days (with 5-6 hours on each survey day).    

Ÿ  It should be noted that every attempt will be made to conduct the monitoring in favorable weather conditions (Beaufort Sea State 3 or below; good visibility of 2km or above).

Impact

Ÿ  Not specified

Ÿ  Dolphin behavior in response to bored piling and movement near the bored piling sites will be monitored at the three pier sites for 30 days from the start of bored piling activities in the waters to the west of Airport.

Ÿ  30 consecutive days (with 5-6 hours on each survey day).            

Ÿ  It should be noted that every attempt will be made to conduct the monitoring in favorable weather conditions (Beaufort Sea State 3 or below; good visibility of 2km or above).

Ÿ  In the proposal, the dolphin specialist has also proposed an additional 64 days of monitoring (twice per month, with 5-6 hours on each survey day) throughout the construction period to examine the impact of bridge construction on north-south movement of CWD across the bridge alignment.

Post-construction

Ÿ  Not specified

Ÿ  Not specified

Not specified

 



(i) Baseline Monitoring Frequency for Theodolite Tracking

(ii) Impact Monitoring Frequency for Theodolite Tracking