1.1
Cinotech Consultants Limited (Cinotech)
was appointed by Dragages -China Harbour-VSL JV (hereinafter called “the Contractor”) as the Environmental Team (ET)
to undertake the Environmental Monitoring and Audit (EM&A) programme during construction phase of the Contract No.
HY/2011/09 – Hong Kong-Zhuhai-Macao Bridge Hong Kong Link Road – Section
between HKSAR Boundary and Scenic Hill” (hereinafter
called the “Contract”) in
accordance with EP Conditions 2.1.
1.2
This is the 23rd Quarterly EM&A report which summarises the impact monitoring results and audit findings
for the EM&A programme in the period between September and November 2018.
1.3
The structure of the report is as follows:
Section 1: Introduction
- purpose and structure of the report.
Section 2: Contract
Information - summarises background and scope of
the Contract, site description, project organization and contact details,
construction programme, the construction works
undertaken and the status of Environmental Permits/Licenses during the
reporting month.
Section 3: Environmental
Monitoring and Audit Requirements - summarises
the monitoring parameters, monitoring frequency, monitoring locations, Action
and Limit Levels, Event / Action Plans, site audit summary and environmental
mitigation measures.
Section 4: Environmental
Monitoring Results - summarises the environmental
monitoring results in terms of air quality, noise, water quality, dolphin and
waste management.
Section 5: Environmental
Non-conformance - summarises any monitoring
exceedance, environmental complaints, environmental summons and successful
prosecutions within the reporting period.
Section 6: Conclusions and
Recommendation