Table of Contents                                                      

                        Executive Summary                                                     

1                      Introduction                                                                 

1.1                   Background                                                                   

1.2                   Scope of Report                                                          

1.3                   Organization Structure                                         

1.4                   Summary of Construction Works                       

2                      EM&A Results                                                                

2.1                   Air Quality                                                                      

2.2                   Noise Monitoring                                                         

2.3                   Water Quality Monitoring                                      

2.4                   Dolphin Monitoring                                                    

2.5                   EM&A Site Inspection                                                  

2.6                   Waste Management Status                                     

2.7                   Environmental Licenses and Permits                

2.8                   Implementation Status of Environmental Mitigation Measures                                                  

2.9                   Summary of Exceedances of the Environmental Quality Performance Limit    

2.10                 Summary of Complaints, Notification of Summons and Successful Prosecutions         

3                      Future Key Issues                                                        

3.1                   Construction Programme for the Coming Month                                                                                

3.2                   Key Issues for the Coming Month                        

3.3                   Monitoring Schedule for the Coming Month 

4                      Conclusions and Recommendations                  

4.1                   Conclusions                                                                  

    


List of Appendices

Appendix A     Project Organization for Environmental Works

Appendix B     Three Month Rolling Construction Programmes

Appendix C     Implementation Schedule of Environmental Mitigation Measures (EMIS)

Appendix D     Monthly Summary of Waste Flow Table

Appendix E     Cumulative Statistics on Exceedances, Complaints, Notifications of Summons and Successful Prosecutions

 

Executive Summary

Under Contract No. HY/2012/07, Gammon Construction Limited (GCL) is commissioned by the Highways Department (HyD) to undertake the design and construction of the Southern Connection Viaduct Section of the Tuen MunChek Lap Kok Link Project (TM-CLK Link Project) while AECOM Asia Company Limited was appointed by HyD as the Supervising Officer.  For implementation of the environmental monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong, Limited (ERM) has been appointed as the Environmental Team (ET).  Ramboll Hong Kong Ltd. was employed by the HyD as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) in accordance with Environmental Permit No. EP-354/2009/A.  Further applications for variation of environmental permit (VEP), EP-354/2009/B, EP-354/2009/C and EP-354/2009/D, were granted on 28 January 2014, 10 December 2014 and 13 March 2015, respectively.

The southern landfall of TM-CLK Link lies alongside the Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary Crossing Facilities (HKBCF) where a reclamation area is constructed by Contract No. HY/2010/02 under Environmental Permit No. EP-353/2009/K and EP-354/2009/D.  Upon the agreement and confirmation between the Supervising Officer Representatives and Contractors of HY/2010/02 and HY/2012/07 in September 2015, part of the reclamation area for southern landfall under EP-353/2009/K and EP-354/2009/D was handed-over to Contract No. HY/2012/07.  Another part of the southern landfall area under EP-354/2009/D was handed-over to Contract No. HY/2012/07 after completion of reclamation works by Contract No. HY/2010/02 in June 2016.

The construction phase of the Contract commenced on 31 October 2013.  The impact monitoring of the EM&A programme, including air quality, noise, water quality and marine ecological monitoring as well as environmental site inspections, commenced on 31 October 2013.

This is the seventy-seventh Monthly EM&A report presenting the EM&A works carried out during the period from 1 to 16 March 2020 for the Southern Connection Viaduct Section in accordance with the Updated EM&A Manual of the TM-CLK Link Project.  As informed by the Contractor, there are no major works to be undertaken in the monitoring period of March 2020.

A summary of monitoring and audit activities conducted in the reporting period is listed below:

Joint Environmental Site Inspection                   2 sessions

Breaches of Action and Limit Levels for Air Quality

No air quality monitoring was scheduled for the reporting month as construction works was substantially completed on 31 July 2019.  Notification of temporary suspension of air quality monitoring has been approved by EPD on 28 August 2019.

Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020.  The construction phase EM&A programme of the Contract has been terminated since 16 March 2020.  No construction air quality monitoring programme was undertaken in the reporting period.

Breaches of Action and Limit Levels for Noise

No noise monitoring was scheduled for the reporting month as construction works was substantially completed on 31 July 2019.  Notification of temporary suspension of noise monitoring has been approved by EPD on 28 August 2019. 

Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020.  The construction phase EM&A programme of the Contract has been terminated since 16 March 2020.  No construction noise monitoring programme was undertaken in the reporting period.

Impact Dolphin Monitoring

Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020.  The construction phase EM&A programme of the Contract has been terminated since 16 March 2020.  No dolphin impact monitoring programme was undertaken in the reporting period.

No marine works were undertaken during the reporting period, therefore, daily 250 m marine mammal exclusion zone monitoring was not undertaken during the reporting period. 

Environmental Complaints, Non-compliance & Summons

No environmental complaints, notification of summons or successful prosecution recorded in the reporting period.

Reporting Change

Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020.  The construction phase EM&A programme of the Contract has been terminated since 16 March 2020.

Upcoming Works for the Next Reporting Period

There are no major works to be undertaken in April 2020.

Future Key Issues

There are no major works to be undertaken in April 2020.

 

1               Introduction

1.1                            Background

According to the findings of the Northwest New Territories (NWNT) Traffic and Infrastructure Review conducted by the Transport Department, Tuen Mun Road, Ting Kau Bridge, Lantau Link and North Lantau Highway would be operating beyond capacity after 2016.  This forecast has been based on the estimated increase in cross boundary traffic, developments in the Northwest New Territories (NWNT), and possible developments in North Lantau, including the Airport developments, the Lantau Logistics Park (LLP) and the Hong Kong – Zhuhai – Macao Bridge (HZMB).  In order to cope with the anticipated traffic demand, two new road sections between NWNT and North Lantau – Tuen MunChek Lap Kok Link (TM-CLKL) and Tuen Mun Western Bypass (TMWB) are proposed.

An Environmental Impact Assessment (EIA) of TM-CLKL (the Project) was prepared in accordance with the EIA Study Brief (No. ESB-175/2007) and the Technical Memorandum of the Environmental Impact Assessment Process (EIAO-TM).  The EIA Report was submitted under the Environmental Impact Assessment Ordinance (EIAO) in August 2009.  Subsequent to the approval of the EIA Report (EIAO Register Number AEIAR-146/2009), an Environmental Permit (EP-354/2009) for TM-CLKL was granted by the Director of Environmental Protection (DEP) on 4 November 2009, and EP variation (EP-354/2009/A) was issued on 8 December 2010.

Under Contract No. HY/2012/07, Gammon Construction Limited (GCL) is commissioned by the Highways Department (HyD) to undertake the design and construction of the Southern Connection Viaduct Section of TM-CLKL (“the Contract”) while AECOM Asia Company Limited was appointed by HyD as the Supervising Officer.  For implementation of the environmental monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong, Limited (ERM) has been appointed as the Environmental Team (ET).  Ramboll Hong Kong Ltd. was employed by HyD as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) in accordance with Environmental Permit No. EP-354/2009/A.  Further applications for variation of environmental permit (VEP), EP-354/2009/B, EP-354/2009/C and EP-354/2009/D, were granted on 28 January 2014, 10 December 2014 and 13 March 2015, respectively.

The southern landfall of TM-CLK Link lies alongside the Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary Crossing Facilities (HKBCF) where a reclamation area is constructed by Contract No. HY/2010/02 under Environmental Permit No. EP-353/2009/K and EP-354/2009/D.  Upon the agreement and confirmation between the Supervising Officer Representatives and Contractors of HY/2010/02 and HY/2012/07 in September 2015, part of the reclamation area for southern landfall under EP-353/2009/K and EP-354/2009/D was handed-over to Contract No. HY/2012/07.  Another part of the southern landfall area under EP-354/2009/D was handed-over to Contract No. HY/2012/07 after completion of reclamation works by Contract No. HY/2010/02 in June 2016.

The construction phase of the Contract commenced on 31 October 2013.  The impact monitoring phase of the EM&A programme, including air quality, noise, water quality and marine ecological monitoring as well environmental site inspections, commenced on 31 October 2013.

Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020.  The construction phase EM&A programme of the Contract has been terminated since 16 March 2020.

The general layout plan of the Contract components is presented in Figures 1.1 & 1.2a to l.

1.2                            Scope of Report

This is the seventy-seventh Monthly EM&A Report under the Contract No. HY/2012/07 Tuen MunChek Lap Kok Link – Southern Connection Viaduct Section.  This report presents a summary of the environmental monitoring and audit works during the period from 1 to 16 March 2020.

1.3                            Organization Structure

The organization structure of the Contract is shown in Appendix A.  The key personnel contact names and contact details are summarized in Table 1.1 below.


Table 1.1        Contact Information of Key Personnel

Party

Position

Name

Telephone

Fax

HyD (Highways Department)

Project Coordinator

Stanley Chan

2762 3406

3188 6614

 

Senior Engineer

Steven Shum

 

2762 4133

3188 6614

SOR

(AECOM Asia Company Limited)

 

Chief Resident Engineer

Daniel Ip

3553 3800

2492 2057

 

Resident Engineer

 

Chan Wah Fu

2293 6434

3691 2899

ENPO / IEC

(Ramboll Hong Kong Ltd.)

ENPO Leader

 

Y.H. Hui

3465 2850

3465 2899

IEC

Dr. F.C. Tsang

3465 2851

3465 2899

 

Contractor

(Gammon Construction Limited)

 

 

 

 

Environmental Officer

 

Roy Leung

3520 0387

3520 0486

 

24-hour Complaint Hotline

 

 

9738 4332

 

ET (ERM-HK)

ET Leader

Dr. Jasmine Ng

2271 3311

2723 5660

1.4                            Summary of Construction Works

The construction phase of the Contract commenced on 31 October 2013.  The three-month rolling construction programme is shown in Appendix B.  The jetty removal works and reinstatement was hand over to Contract No.: HY/2012/08 TMCLKL Northern Connection Sub-Sea Tunnel Section.   

As informed by the Contractor, no major works were carried out in the reporting month.

The Environmental Sensitive Receivers in the vicinity of the Project are shown in Figure 1.3.

The environmental mitigation measures implementation schedule is presented in Appendix C.

 

2               EM&A Results

The EM&A programme required environmental monitoring for air quality, noise, water quality and marine ecology as well as environmental site inspections for air quality, noise, water quality, waste management, marine ecology and landscape and visual impacts.  The EM&A requirements and related findings for each component are summarized in the following sections.

2.1                            Air Quality

 

No air quality monitoring was scheduled for the reporting month as construction works was substantially completed on 31 July 2019.  Notification of temporary suspension of air quality monitoring has been approved by EPD on 28 August 2019.

Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020.  The construction phase EM&A programme of the Contract has been terminated since 16 March 2020.  No construction air quality monitoring programme was undertaken in the reporting period.

2.2                            Noise Monitoring

No noise monitoring was scheduled for the reporting month as construction works was substantially completed on 31 July 2019.  Notification of temporary suspension of noise monitoring has been approved by EPD on 28 August 2019.

Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020.  The construction phase EM&A programme of the Contract has been terminated since 16 March 2020.  No construction noise monitoring programme was undertaken in the reporting period.

2.3                            Water Quality Monitoring

Post-construction water quality monitoring was completed on 23 December 2019.  

2.4                            Dolphin Monitoring

Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020.  The construction phase EM&A programme of the Contract has been terminated since 16 March 2020.  No dolphin impact monitoring programme was undertaken in the reporting period.

2.4.1                        Marine Mammal Exclusion Zone Monitoring

No marine works were undertaken during the reporting period, therefore, daily 250 m marine mammal exclusion zone monitoring was not undertaken during the reporting period. 

Passive Acoustic Monitoring (PAM) had been decommissioned as no marine piling works was carried out outside the daylight hours since September 2015. 

2.5                            EM&A Site Inspection

Site inspections were carried out on a weekly basis to monitor the implementation of proper environmental pollution control and mitigation measures under the Contract.  In the reporting month, two (2) site inspections were carried out on 2 and 13 March 2020. 

Key observations during the site inspections are summarized in Table 2.1.

 Table 2.1        Specific Observations Identified during the Weekly Site Inspections in this Reporting Month

Inspection Date

Environmental Observations

Recommendations/ Remarks

2 March 2020

Viaduct C

Ÿ   Nil.

Viaduct C

Ÿ   Nil.

13 March 2020

Viaduct D

Ÿ   Nil.

Viaduct D

Ÿ   Nil.

No particular observations were identified during environmental site inspections in the reporting month.

Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020.  The construction phase EM&A programme of the Contract has been terminated since 16 March 2020.  No weekly site audit was undertaken since 16 March 2020.

2.6                            Waste Management Status

The Contractor has submitted application form for registration as chemical waste producer under the Contract.  Sufficient numbers of receptacles were available for general refuse collection and sorting.

Wastes generated during this reporting period include mainly construction wastes (inert and non-inert) and recyclable materials.  Reference has been made to the waste flow table prepared by the Contractor (Appendix D).  The quantities of different types of wastes are summarized in Table 2.2.


Table 2.2      Quantities of Different Waste Generated in the Reporting Period

Month/

Year

Inert C&D Materials (a) (m3)

Imported Fill (m3)

Inert Construction Waste Re-used

(m3)

Non-inert Construction Waste (b) (kg)

Recyclable Materials (c)  (kg)

Chemical Wastes (kg)

Marine Sediment (m3)

Category L

Category M

(Mp & Mf)

Category H

March 2020

38

0

0

0

0

0

0

0

0

Notes:

(a)   Inert construction wastes include hard rock and large broken concrete, and materials disposed as public fill.

(b)   Non-inert construction wastes include general refuse disposed at landfill.

(c)   Recyclable materials include metals, paper, cardboard, plastics, timber, felled trees and others.

The Contractor was advised to properly maintain on site C&D materials and waste collection, sorting and recording system, dispose of C&D materials and wastes at designated ground and maximize reuse/ recycle of C&D materials and wastes.  The Contractor was also reminded to properly maintain the site tidiness and dispose of the wastes accumulated on site regularly and properly.

For chemical waste containers, the Contractor was reminded to treat properly and store temporarily in designated chemical waste storage area on site in accordance with the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes.

2.7                            Environmental Licenses and Permits

The status of environmental licensing and permit is summarized in Table 2.3 below.


Table 2.3        Summary of Environmental Licensing and Permit Status

License/ Permit

License or Permit No.

Date of Issue

Date of Expiry

License/ Permit Holder

Remarks

Environmental Permit

EP-354/2009/D

13 Mar 2015

N/A

HyD

Tuen Mun- Chek Lap Kok Link

Environmental Permit

EP-353/2009/K

11 Apr 2016

N/A

HyD

Hong Kong Boundary Crossing Facilities

Construction Dust Notification

361571

5 Jul 2013

N/A

GCL

 

Construction Dust Notification

362093

17 Jul 2013

N/A

GCL

For Area 23

Chemical Waste Registration

5213-961-G2380-13

10 Oct 2013

N/A

GCL

Chemical waste produced in Contract No. HY/2012/07

(Area 1 adjacent to Cheng Tung Road, Siu Ho Wan)

Chemical Waste Registration

5213-961-G2380-14

10 Oct 2013

N/A

GCL

Chemical waste produced in Contract No. HY/2012/07

(Area 2 adjacent to Cheung Tung Road, Pak Mong Village)

Chemical Waste Registration

5213-974-G2588-03

4 Nov 2013

N/A

GCL

Chemical waste produced in Contract No. HY/2012/07

(WA5 adjacent to Cheung Tung Road, Yam O)

Chemical Waste Registration

5213-951-G2380-17

12 Jun 2014

N/A

GCL

Viaducts A, B, C, D & E

Construction Waste Disposal Account

7017735

10 Jul 2013

N/A

GCL

-

Construction Waste Disposal Account

7019470

3 Mar 2014

N/A

GCL

Vessel CHIT Account

Construction Noise Permit for night works and works in general holidays

GW-RS1108-19

12 December 2019

11 June 2020

GCL

Broad Permit for Whole Site Areas

Construction Noise Permit for night works and works in general holidays

GW-RW0592-19

18 December 2019

13 June 2020

GCL

General works at WA5

Construction Noise Permit for night works and works in general holidays

 

 

 

                                            

GW-RS0153-20

19 March 2020

31 March 2020

GCL

Defect Repairing at under-bridge of Viaduct B and C


2.8                            Implementation Status of Environmental Mitigation Measures

In response to the site audit findings, the Contractors carried out corrective actions.

A summary of the Implementation Schedule of Environmental Mitigation Measures (EMIS) is presented in Appendix C.  The necessary mitigation measures were implemented properly for this Contract.

The landscape and visual (L&V) mitigation measures were also monitored on weekly basis in the reporting period.  The monitoring status is summarized in Appendix C.

2.9                            Summary of Exceedances of the Environmental Quality Performance Limit

Post-construction water quality monitoring was completed on 23 December 2019. 

No air quality, noise and dolphin impact monitoring was conducted in the reporting period.

Cumulative statistics on exceedances is provided in Appendix E.

2.10                         Summary of Complaints, Notification of Summons and Successful Prosecutions

The Environmental Complaint Handling Procedure is provided in Figure 2.1.

There was no environmental complaint, notification of summons or successful prosecution recorded in the reporting period.

Statistics on complaints, notifications of summons, successful prosecutions are summarized in Appendix E.

                                       

3               Future Key Issues

3.1                            Construction Programme for the Coming Month

As informed by the Contractor, there are no major works to be undertaken in April 2020.

3.2                            Key Issues for the Coming Month

As informed by the Contractor, there are no major works to be undertaken in April 2020.

3.3                            Monitoring Schedule for the Coming Month

Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020.  The construction phase EM&A programme of the Contract has been terminated since 16 March 2020.

 

4               Conclusions and Recommendations

4.1                            Conclusions

This Seventy-seventh Monthly EM&A Report presents the findings of the EM&A activities undertaken during the period from 1 to 16 March 2020 in accordance with the Updated EM&A Manual and the requirements of the Environmental Permits (EP-354/2009/D and EP-353/2009/K).

No Air quality (1-hour TSP and 24-hour TSP), noise and dolphin monitoring were carried out in the reporting month.  Post-construction water quality monitoring (DO, turbidity and SS) was completed on 23 December 2019. 

Environmental site inspections were carried out two (2) times in March 2020.  Recommendations on remedial actions were given to the Contractor for the deficiencies identified during the site audits.

There was no environmental complaint, notification of summons or successful prosecution recorded in the reporting period.

Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020.  The construction phase EM&A programme of the Contract has been terminated since 16 March 2020.