Executive Summary
1.1 Background
1.2 Scope of Report
1.3 Organization Structure
1.4 Summary of Construction Works
2.1 Air Quality
2.2 Noise Monitoring
2.3 Water Quality Monitoring
2.4 Dolphin Monitoring
2.5 EM&A Site Inspection
2.6 Waste Management Status
2.7 Environmental Licenses and Permits
2.8 Implementation Status of Environmental Mitigation Measures
2.9 Summary of Exceedances of the Environmental Quality Performance Limit
2.10 Summary of Complaints, Notification of Summons and Successful Prosecutions
3.1 Construction Programme for the Coming Month
3.2 Key Issues for the Coming Month
3.3 Monitoring Schedule for the Coming Month
4 Conclusions and Recommendations
4.1 Conclusions
List of Appendices
Appendix A Project Organization for Environmental Works
Appendix B Three Month Rolling Construction Programmes
Appendix C Implementation Schedule of Environmental Mitigation Measures (EMIS)
Appendix D Monthly Summary of Waste Flow Table
Under Contract No. HY/2012/07, Gammon Construction Limited (GCL) is commissioned by the Highways Department (HyD) to undertake the design and construction of the Southern Connection Viaduct Section of the Tuen Mun – Chek Lap Kok Link Project (TM-CLK Link Project) while AECOM Asia Company Limited was appointed by HyD as the Supervising Officer. For implementation of the environmental monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong, Limited (ERM) has been appointed as the Environmental Team (ET). Ramboll Hong Kong Ltd. was employed by the HyD as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) in accordance with Environmental Permit No. EP-354/2009/A. Further applications for variation of environmental permit (VEP), EP-354/2009/B, EP-354/2009/C and EP-354/2009/D, were granted on 28 January 2014, 10 December 2014 and 13 March 2015, respectively.
The southern landfall of TM-CLK Link lies alongside the Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary Crossing Facilities (HKBCF) where a reclamation area is constructed by Contract No. HY/2010/02 under Environmental Permit No. EP-353/2009/K and EP-354/2009/D. Upon the agreement and confirmation between the Supervising Officer Representatives and Contractors of HY/2010/02 and HY/2012/07 in September 2015, part of the reclamation area for southern landfall under EP-353/2009/K and EP-354/2009/D was handed-over to Contract No. HY/2012/07. Another part of the southern landfall area under EP-354/2009/D was handed-over to Contract No. HY/2012/07 after completion of reclamation works by Contract No. HY/2010/02 in June 2016.
The construction phase of the Contract commenced on 31 October 2013. The impact monitoring of the EM&A programme, including air quality, noise, water quality and marine ecological monitoring as well as environmental site inspections, commenced on 31 October 2013.
This is the seventy-seventh Monthly EM&A report presenting the EM&A works carried out during the period from 1 to 16 March 2020 for the Southern Connection Viaduct Section in accordance with the Updated EM&A Manual of the TM-CLK Link Project. As informed by the Contractor, there are no major works to be undertaken in the monitoring period of March 2020.
A summary of monitoring and audit activities conducted in the reporting period is listed below:
Joint Environmental Site Inspection 2 sessions
Breaches of Action and Limit Levels for Air Quality
No air quality monitoring was scheduled for the reporting month as construction works was substantially completed on 31 July 2019. Notification of temporary suspension of air quality monitoring has been approved by EPD on 28 August 2019.
Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020. The construction phase EM&A programme of the Contract has been terminated since 16 March 2020. No construction air quality monitoring programme was undertaken in the reporting period.
Breaches of Action and Limit Levels for Noise
No noise monitoring was scheduled for the reporting month as construction works was substantially completed on 31 July 2019. Notification of temporary suspension of noise monitoring has been approved by EPD on 28 August 2019.
Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020. The construction phase EM&A programme of the Contract has been terminated since 16 March 2020. No construction noise monitoring programme was undertaken in the reporting period.
Impact Dolphin Monitoring
Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020. The construction phase EM&A programme of the Contract has been terminated since 16 March 2020. No dolphin impact monitoring programme was undertaken in the reporting period.
No marine works were undertaken during the reporting period, therefore, daily 250 m marine mammal exclusion zone monitoring was not undertaken during the reporting period.
Environmental Complaints, Non-compliance & Summons
No environmental complaints, notification of summons or successful prosecution recorded in the reporting period.
Reporting Change
Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020. The construction phase EM&A programme of the Contract has been terminated since 16 March 2020.
Upcoming Works for the Next Reporting Period
There are no major works to be undertaken in April 2020.
Future Key Issues
There are no major works to be undertaken in April 2020.
According to the findings of the Northwest New Territories (NWNT) Traffic and Infrastructure Review conducted by the Transport Department, Tuen Mun Road, Ting Kau Bridge, Lantau Link and North Lantau Highway would be operating beyond capacity after 2016. This forecast has been based on the estimated increase in cross boundary traffic, developments in the Northwest New Territories (NWNT), and possible developments in North Lantau, including the Airport developments, the Lantau Logistics Park (LLP) and the Hong Kong – Zhuhai – Macao Bridge (HZMB). In order to cope with the anticipated traffic demand, two new road sections between NWNT and North Lantau – Tuen Mun – Chek Lap Kok Link (TM-CLKL) and Tuen Mun Western Bypass (TMWB) are proposed.
An Environmental Impact Assessment (EIA) of TM-CLKL (the Project) was prepared in accordance with the EIA Study Brief (No. ESB-175/2007) and the Technical Memorandum of the Environmental Impact Assessment Process (EIAO-TM). The EIA Report was submitted under the Environmental Impact Assessment Ordinance (EIAO) in August 2009. Subsequent to the approval of the EIA Report (EIAO Register Number AEIAR-146/2009), an Environmental Permit (EP-354/2009) for TM-CLKL was granted by the Director of Environmental Protection (DEP) on 4 November 2009, and EP variation (EP-354/2009/A) was issued on 8 December 2010.
Under Contract No. HY/2012/07, Gammon Construction Limited (GCL) is commissioned by the Highways Department (HyD) to undertake the design and construction of the Southern Connection Viaduct Section of TM-CLKL (“the Contract”) while AECOM Asia Company Limited was appointed by HyD as the Supervising Officer. For implementation of the environmental monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong, Limited (ERM) has been appointed as the Environmental Team (ET). Ramboll Hong Kong Ltd. was employed by HyD as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) in accordance with Environmental Permit No. EP-354/2009/A. Further applications for variation of environmental permit (VEP), EP-354/2009/B, EP-354/2009/C and EP-354/2009/D, were granted on 28 January 2014, 10 December 2014 and 13 March 2015, respectively.
The southern landfall of TM-CLK Link lies alongside the Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary Crossing Facilities (HKBCF) where a reclamation area is constructed by Contract No. HY/2010/02 under Environmental Permit No. EP-353/2009/K and EP-354/2009/D. Upon the agreement and confirmation between the Supervising Officer Representatives and Contractors of HY/2010/02 and HY/2012/07 in September 2015, part of the reclamation area for southern landfall under EP-353/2009/K and EP-354/2009/D was handed-over to Contract No. HY/2012/07. Another part of the southern landfall area under EP-354/2009/D was handed-over to Contract No. HY/2012/07 after completion of reclamation works by Contract No. HY/2010/02 in June 2016.
The construction phase of the Contract commenced on 31 October 2013. The impact monitoring phase of the EM&A programme, including air quality, noise, water quality and marine ecological monitoring as well environmental site inspections, commenced on 31 October 2013.
Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020. The construction phase EM&A programme of the Contract has been terminated since 16 March 2020.
The general layout plan of the Contract components is presented in Figures 1.1 & 1.2a to l.
This is the seventy-seventh Monthly EM&A Report under the Contract No. HY/2012/07 Tuen Mun – Chek Lap Kok Link – Southern Connection Viaduct Section. This report presents a summary of the environmental monitoring and audit works during the period from 1 to 16 March 2020.
The organization structure of the Contract is shown in Appendix A. The key personnel contact names and contact details are summarized in Table 1.1 below.
Table 1.1 Contact Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
HyD (Highways Department) |
Project Coordinator |
Stanley Chan |
2762 3406 |
3188 6614 |
|
Senior Engineer |
Steven Shum
|
2762 4133 |
3188 6614 |
SOR (AECOM Asia Company Limited)
|
Chief Resident Engineer |
Daniel Ip |
3553 3800 |
2492 2057 |
|
Resident Engineer
|
Chan Wah Fu |
2293 6434 |
3691 2899 |
ENPO / IEC (Ramboll Hong Kong Ltd.) |
ENPO Leader
|
Y.H. Hui |
3465 2850 |
3465 2899 |
IEC |
Dr. F.C. Tsang |
3465 2851 |
3465 2899 |
|
Contractor (Gammon Construction Limited) |
|
|
|
|
Environmental Officer
|
Roy Leung |
3520 0387 |
3520 0486 |
|
|
24-hour Complaint Hotline
|
|
9738 4332 |
|
ET (ERM-HK) |
ET Leader |
Dr. Jasmine Ng |
2271 3311 |
2723 5660 |
The construction phase of the Contract commenced on 31 October 2013. The three-month rolling construction programme is shown in Appendix B. The jetty removal works and reinstatement was hand over to Contract No.: HY/2012/08 TMCLKL Northern Connection Sub-Sea Tunnel Section.
As informed by the Contractor, no major works were carried out in the reporting month.
The Environmental Sensitive Receivers in the vicinity of the Project are shown in Figure 1.3.
The environmental mitigation measures implementation schedule is presented in Appendix C.
The EM&A programme required environmental monitoring for air quality, noise, water quality and marine ecology as well as environmental site inspections for air quality, noise, water quality, waste management, marine ecology and landscape and visual impacts. The EM&A requirements and related findings for each component are summarized in the following sections.
No air quality monitoring was scheduled for the reporting month as construction works was substantially completed on 31 July 2019. Notification of temporary suspension of air quality monitoring has been approved by EPD on 28 August 2019.
Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020. The construction phase EM&A programme of the Contract has been terminated since 16 March 2020. No construction air quality monitoring programme was undertaken in the reporting period.
No noise monitoring was scheduled for the reporting month as construction works was substantially completed on 31 July 2019. Notification of temporary suspension of noise monitoring has been approved by EPD on 28 August 2019.
Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020. The construction phase EM&A programme of the Contract has been terminated since 16 March 2020. No construction noise monitoring programme was undertaken in the reporting period.
Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020. The construction phase EM&A programme of the Contract has been terminated since 16 March 2020. No dolphin impact monitoring programme was undertaken in the reporting period.
No marine works were undertaken during the reporting period, therefore, daily 250 m marine mammal exclusion zone monitoring was not undertaken during the reporting period.
Passive Acoustic Monitoring (PAM) had been decommissioned as no marine piling works was carried out outside the daylight hours since September 2015.
Site inspections were carried out on a weekly basis to monitor the implementation of proper environmental pollution control and mitigation measures under the Contract. In the reporting month, two (2) site inspections were carried out on 2 and 13 March 2020.
Key observations during the site inspections are summarized in Table 2.1.
Table 2.1 Specific Observations Identified during the Weekly Site Inspections in this Reporting Month
Inspection Date |
Environmental Observations |
Recommendations/ Remarks |
2 March 2020 |
Viaduct C Nil. |
Viaduct C Nil. |
13 March 2020 |
Viaduct D Nil. |
Viaduct D Nil. |
No particular observations were identified during environmental site inspections in the reporting month.
Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020. The construction phase EM&A programme of the Contract has been terminated since 16 March 2020. No weekly site audit was undertaken since 16 March 2020.
The Contractor has submitted application form for registration as chemical waste producer under the Contract. Sufficient numbers of receptacles were available for general refuse collection and sorting.
Wastes generated during this reporting period include mainly construction wastes (inert and non-inert) and recyclable materials. Reference has been made to the waste flow table prepared by the Contractor (Appendix D). The quantities of different types of wastes are summarized in Table 2.2.
Table 2.2 Quantities of Different Waste Generated in the Reporting Period
Month/ Year |
Inert C&D Materials (a) (m3) |
Imported Fill (m3) |
Inert Construction Waste Re-used (m3) |
Non-inert Construction Waste (b) (kg) |
Recyclable Materials (c) (kg) |
Chemical Wastes (kg) |
Marine Sediment (m3) |
||
Category L |
Category M (Mp & Mf) |
Category H |
|||||||
March 2020 |
38 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Notes: |
|||||||||
(a) Inert construction wastes include hard rock and large broken concrete, and materials disposed as public fill. (b) Non-inert construction wastes include general refuse disposed at landfill. (c) Recyclable materials include metals, paper, cardboard, plastics, timber, felled trees and others. |
The Contractor was advised to properly maintain on site C&D materials and waste collection, sorting and recording system, dispose of C&D materials and wastes at designated ground and maximize reuse/ recycle of C&D materials and wastes. The Contractor was also reminded to properly maintain the site tidiness and dispose of the wastes accumulated on site regularly and properly.
For chemical waste containers, the Contractor was reminded to treat properly and store temporarily in designated chemical waste storage area on site in accordance with the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes.
The status of environmental licensing and permit is summarized in Table 2.3 below.
Table 2.3 Summary of Environmental Licensing and Permit Status
License/ Permit |
License or Permit No. |
Date of Issue |
Date of Expiry |
License/ Permit Holder |
Remarks |
Environmental Permit |
EP-354/2009/D |
13 Mar 2015 |
N/A |
HyD |
Tuen Mun- Chek Lap Kok Link |
Environmental Permit |
EP-353/2009/K |
11 Apr 2016 |
N/A |
HyD |
Hong Kong Boundary Crossing Facilities |
Construction Dust Notification |
361571 |
5 Jul 2013 |
N/A |
GCL |
|
Construction Dust Notification |
362093 |
17 Jul 2013 |
N/A |
GCL |
For Area 23 |
Chemical Waste Registration |
5213-961-G2380-13 |
10 Oct 2013 |
N/A |
GCL |
Chemical waste produced in Contract No. HY/2012/07 (Area 1 adjacent to Cheng Tung Road, Siu Ho Wan) |
Chemical Waste Registration |
5213-961-G2380-14 |
10 Oct 2013 |
N/A |
GCL |
Chemical waste produced in Contract No. HY/2012/07 (Area 2 adjacent to Cheung Tung Road, Pak Mong Village) |
Chemical Waste Registration |
5213-974-G2588-03 |
4 Nov 2013 |
N/A |
GCL |
Chemical waste produced in Contract No. HY/2012/07 (WA5 adjacent to Cheung Tung Road, Yam O) |
Chemical Waste Registration |
5213-951-G2380-17 |
12 Jun 2014 |
N/A |
GCL |
Viaducts A, B, C, D & E |
Construction Waste Disposal Account |
7017735 |
10 Jul 2013 |
N/A |
GCL |
- |
Construction Waste Disposal Account |
7019470 |
3 Mar 2014 |
N/A |
GCL |
Vessel CHIT Account |
Construction Noise Permit for night works and works in general holidays |
GW-RS1108-19 |
12 December 2019 |
11 June 2020 |
GCL |
Broad Permit for Whole Site Areas |
Construction Noise Permit for night works and works in general holidays |
GW-RW0592-19 |
18 December 2019 |
13 June 2020 |
GCL |
General works at WA5 |
Construction Noise Permit for night works and works in general holidays
|
GW-RS0153-20 |
19 March 2020 |
31 March 2020 |
GCL |
Defect Repairing at under-bridge of Viaduct B and C |
In response to the site audit findings, the Contractors carried out corrective actions.
A summary of the Implementation Schedule of Environmental Mitigation Measures (EMIS) is presented in Appendix C. The necessary mitigation measures were implemented properly for this Contract.
The landscape and visual (L&V) mitigation measures were also monitored on weekly basis in the reporting period. The monitoring status is summarized in Appendix C.
Post-construction water quality monitoring was completed on 23 December 2019.
No air quality, noise and dolphin impact monitoring was conducted in the reporting period.
Cumulative statistics on exceedances is provided in Appendix E.
The Environmental Complaint Handling Procedure is provided in Figure 2.1.
There was no environmental complaint, notification of summons or successful prosecution recorded in the reporting period.
Statistics on complaints, notifications of summons, successful prosecutions are summarized in Appendix E.
As informed by the Contractor, there are no major works to be undertaken in April 2020.
As informed by the Contractor, there are no major works to be undertaken in April 2020.
Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020. The construction phase EM&A programme of the Contract has been terminated since 16 March 2020.
This Seventy-seventh Monthly EM&A Report presents the findings of the EM&A activities undertaken during the period from 1 to 16 March 2020 in accordance with the Updated EM&A Manual and the requirements of the Environmental Permits (EP-354/2009/D and EP-353/2009/K).
No Air quality (1-hour TSP and 24-hour TSP), noise and dolphin monitoring were carried out in the reporting month. Post-construction water quality monitoring (DO, turbidity and SS) was completed on 23 December 2019.
Environmental site inspections were carried out two (2) times in March 2020. Recommendations on remedial actions were given to the Contractor for the deficiencies identified during the site audits.
There was no environmental complaint, notification of summons or successful prosecution recorded in the reporting period.
Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020. The construction phase EM&A programme of the Contract has been terminated since 16 March 2020.