Pages from 0215660_7th Qtr EM&A 20151224_Page_1

Pages%20from%200215660_7th%20Qtr%20EM&A%2020151224_Page_2

Pages%20from%200215660_7th%20Qtr%20EM&A%2020151224_Page_3

 
TABLE OF CONTENTS

                        Executive Summary                                                             

1                      Introduction                                                                          

1.1                   Background                                                                           

1.2                   Scope of Report                                                                   

1.3                   Organization Structure                                                 

1.4                   Summary of Construction Works                              

1.5                   Summary of EM&A Programme Requirements        

2                      EM&A RESULTS                                                                         

2.1                   Air Quality                                                                               

2.2                   Noise Monitoring                                                                  

2.3                   Water Quality Monitoring                                              

2.4                   Dolphin Monitoring

2.5                   EM&A Site Inspection                                                           

2.6                   Waste Management Status                                             

2.7                   Environmental Licenses and Permits                        

2.8                   Implementation Status of Environmental Mitigation Measures  

2.9                   Summary of Exceedances of the Environmental Quality Performance Limit

2.10                 Summary of Complaints, Notification of Summons and Successful Prosecutions                                                                         

3                      Future Key Issues                                                                

3.1                   Construction Activities for the Coming Quarter

3.2                   Key Issues for the Coming Quarter                           

3.3                   Monitoring Schedule for the Coming Quarter   

4                      Conclusions and recommendations                         

4.1                   Conclusions                                                                           


List of Appendices

 

Appendix A     Project Organization for Environmental Works

Appendix B     Three Month Rolling Construction Programmes

Appendix C     Implementation Schedule of Environmental Mitigation Measures (EMIS)

Appendix D     Summary of Action and Limit Levels

Appendix E     EM&A Monitoring Schedules

Appendix F     Impact Air Quality Monitoring Results and Graphical Presentation

Appendix G    Impact Noise Monitoring Results and Graphical Presentation

Appendix H    Impact Water Quality Monitoring Results and Graphical Presentation

Appendix I      Impact Dolphin Monitoring Survey Results

Appendix J     Event Action Plan

Appendix K     Quarterly Summary of Waste Flow Table

Appendix L     Cumulative Statistics on Exceedances, Complaints, Notifications of Summons and Successful Prosecutions

 

 

Executive Summary

Under Contract No. HY/2012/07, Gammon Construction Limited (GCL) is commissioned by the Highways Department (HyD) to undertake the design and construction of the Southern Connection Viaduct Section of the Tuen MunChek Lap Kok Link Project (TM-CLK Link Project) while AECOM Asia Company Limited was appointed by HyD as the Supervising Officer.  For implementation of the environmental monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong, Limited (ERM) has been appointed as the Environmental Team (ET).  Ramboll Environ Hong Kong Ltd. was employed by the HyD as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) in accordance with Environmental Permit No. EP-354/2009/A.  Further applications for variation of environmental permit (VEP), EP-354/2009/B, EP-354/2009/C and EP-354/2009/D, were granted on 28 January 2014, 10 December 2014 and 13 March 2015, respectively.

The construction phase of the Contract commenced on 31 October 2013 and will be tentatively completed by 2018.  The impact monitoring of the EM&A programme, including air quality, noise, water quality and marine ecological monitoring as well as environmental site inspections, commenced on 31 October 2013.

This is the seventh quarterly EM&A report presenting the EM&A works carried out during the period from 1 June to 31 August 2015 for the Southern Connection Viaduct Section in accordance with the Updated EM&A Manual of the TM-CLK Link Project.  As informed by the Contractor, major activities in the reporting period included:

June 2015

Marine Works

·      Construction and installation of pile caps;

·      Uninstallation of marine piling platform;

·      Pier construction;

·      Launching gantry assembly;

·      Marine piling and

·      Installation of pier head segment

Land-based Works

·      Construction and installation of pile caps;

·      Pier construction;

·      Re-alignment of Cheung Tung Road;

·      Land piling;

·      Pre-drilling works;

·      Installation of pier head segment;

·      Additional land GI, trial pits & lab testing;

·      Relocation of MTRC fence; and

·      Slope work of Slopes 9SE-B/C9 and 9SE-B/F85.

July 2015

Marine Works

·      Construction and installation of pile caps;

·      Uninstallation of marine piling platform;

·      Pier construction;

·      Launching gantry assembly;

·      Marine piling; and,

·      Installation of pier head segment.

Land-based Works

·      Predrilling at Viaduct F;

·      Construction and installation of pile caps;

·      Pier construction;

·      Re-alignment of Cheung Tung Road;

·      Land piling;

·      Pre-drilling works;

·      Installation of pier head segment;

·      Additional land GI, trial pits & lab testing;

·      Relocation of MTRC fence; and,

·      Slope work of Viaducts A & B.

August 2015

Marine Works

·      Construction and installation of pile caps;

·      Uninstallation of marine piling platform;

·      Pier construction;

·      Launching gantry assembly;

·      Marine piling; and,

·      Installation of pier head segment.

Land-based Works

·      Predrilling at Viaduct F;

·      Construction and installation of pile caps;

·      Pier construction;

·      Re-alignment of Cheung Tung Road;

·      Land piling;

·      Installation of pier head segment;

·      Additional land GI, trial pits & lab testing;

·      Relocation of MTRC fence; and,

·      Slope work of Viaducts A & B.

A summary of monitoring and audit activities conducted in the reporting period is listed below:

24-hour TSP monitoring                                18 sessions

1-hour TSP monitoring                                  18 sessions

Noise monitoring                                       18 sessions

Water quality monitoring                      38 sessions

Dolphin monitoring                               6 sessions

Joint Environmental site inspection      13 sessions

Breaches of Action and Limit Levels for Air Quality

No exceedance of Action and Limit Levels was recorded for air quality monitoring in the reporting period.

Breaches of Action and Limit Levels for Noise

No exceedance of Action and Limit Levels was recorded for construction noise monitoring in the reporting period.

Breaches of Action and Limit Levels for Water Quality

No exceedance of Action and Limit Levels was recorded for water quality monitoring in the reporting period.

Impact Dolphin Monitoring

One (1) Limit Level exceedance was observed for the quarterly dolphin monitoring data between June and August 2015, whilst no unacceptable impact from the construction activities of the TM-CLKL Southern Connection Viaduct Section on Chinese White Dolphins was noticeable from general observations during the dolphin monitoring in this reporting quarter.

Daily marine mammal exclusion zone monitoring was undertaken during the period of marine works under this Contract.  No Passive Acoustic Monitoring (PAM) was implemented as the marine piling works were not carried out outside the daylight hours in this reporting period.  No sighting of the Indo-Pacific humpback dolphin Sousa chinensis (i.e. Chinese White Dolphin) was recorded in the monitoring period during the exclusion zone monitoring.

Environmental Complaints, Non-compliance & Summons

One (1) complaint with regard to dust emission from dump truck was received on 18 June 2015.

Reporting Change

There was no reporting change in this reporting period.

Upcoming Works for the Next Reporting Period

Works to be undertaken in the coming quarter include the following:

September 2015

Marine Works

·      Construction and installation of pile caps;

·      Uninstallation of marine piling platform;

·      Pier construction;

·      Launching gantry assembly;

·      Marine piling; and,

·      Installation of pier head segment.

Land-based Works

·      Predrilling at Viaduct F;

·      Construction and installation of pile caps;

·      Pier construction;

·      Re-alignment of Cheung Tung Road;

·      Land piling;

·      Installation of pier head segment;

·      Additional land GI, trial pits & lab testing;

·      Relocation of MTRC fence; and,

·      Slope work of Viaduct A.

October 2015

Marine Works

·      Construction and installation of pile caps;

·      Uninstallation of marine piling platform;

·      Pier construction;

·      Launching gantry assembly;

·      Installation of deck segment and pier head segment.

Land-based Works

·      Predrilling at Viaduct F;

·      Construction and installation of pile caps;

·      Pier construction;

·      Re-alignment of Cheung Tung Road;

·      Installation of pier head segment;

·      Additional land GI, trial pits & lab testing;

·      Relocation of MTRC fence; and,

·      Slope work of Viaduct A.

November 2015

Marine Works

·      Construction and installation of pile caps;

·      Uninstallation of marine piling platform;

·      Pier construction;

·      Launching gantry assembly; and

·      Installation of deck segment and pier head segment.

Land-based Works

·      Construction and installation of pile caps;

·      Pier construction;

·      Re-alignment of Cheung Tung Road;

·      Installation of pier head segment; and

·      Slope work of Viaduct A.

Future Key Issues

Potential environmental impacts arising from the above upcoming construction activities in the coming quarterly period are mainly associated with air quality, noise, marine water quality, marine ecology and waste management issue.


1                                            Introduction

1.1                                      Background

According to the findings of the Northwest New Territories (NWNT) Traffic and Infrastructure Review conducted by the Transport Department, Tuen Mun Road, Ting Kau Bridge, Lantau Link and North Lantau Highway would be operating beyond capacity after 2016.  This forecast has been based on the estimated increase in cross boundary traffic, developments in the Northwest New Territories (NWNT), and possible developments in North Lantau, including the Airport developments, the Lantau Logistics Park (LLP) and the Hong Kong – Zhuhai – Macao Bridge (HZMB).  In order to cope with the anticipated traffic demand, two new road sections between NWNT and North Lantau – Tuen MunChek Lap Kok Link (TM-CLKL) and Tuen Mun Western Bypass (TMWB) are proposed.

An Environmental Impact Assessment (EIA) of TM-CLKL (the Project) was prepared in accordance with the EIA Study Brief (No. ESB-175/2007) and the Technical Memorandum of the Environmental Impact Assessment Process (EIAO-TM).  The EIA Report was submitted under the Environmental Impact Assessment Ordinance (EIAO) in August 2009.  Subsequent to the approval of the EIA Report (EIAO Register Number: AEIAR-146/2009), an Environmental Permit (EP-354/2009) for TM-CLKL was granted by the Director of Environmental Protection (DEP) on 4 November 2009, and EP variation (EP-354/2009A) was issued on 8 December 2010.  Further applications for variation of environmental permit (VEP), EP-354/2009/B, EP-354/2009/C and EP-354/2009/D, were granted on 28 January 2014, 10 December 2014 and 13 March 2015, respectively.

Under Contract No. HY/2012/07, Gammon Construction Limited (GCL) is commissioned by the Highways Department (HyD) to undertake the design and construction of the Southern Connection Viaduct Section of TM-CLKL (“the Contract”) while AECOM Asia Company Limited was appointed by HyD as the Supervising Officer.  For implementation of the environmental monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong, Limited (ERM) has been appointed as the Environmental Team (ET).  Ramboll Environ Hong Kong Ltd. was employed by HyD as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) in accordance with Environmental Permit No. EP-354/2009/A.

The construction phase of the Contract commenced on 31 October 2013 and will be tentatively be completed by 2018.  The impact monitoring phase of the EM&A programme, including air quality, noise, water quality and marine ecological monitoring as well environmental site inspections, commenced on 31 October 2013.

The general layout plan of the Contract components is presented in Figures 1.1 & 1.2a to l.

1.2                                      Scope of Report

This is the Seventh Quarterly EM&A Report under the Contract No. HY/2012/07 Tuen MunChek Lap Kok Link – Southern Connection Viaduct Section.  This report presents a summary of the environmental monitoring and audit works from 1 June to 31 August 2015.

1.3                                      Organization Structure

The organization structure of the Contract is shown in Appendix A.  The key personnel contact names and contact details are summarized in Table 1.1 below.

Table 1.1        Contact Information of Key Personnel

Party

Position

Name

Telephone

Fax

SOR

(AECOM Asia Company Limited)

 

Chief Resident Engineer

Daniel Ip

3553 3800

2492 2057

 

Resident Engineer

Kingman Chan

3691 2950

3691 2899

 

ENPO / IEC

(Ramboll Environ Hong Kong Ltd.)

ENPO Leader

 

Y.H. Hui

3547 2133 

3465 2899

IEC

 

Dr. F.C. Tsang

3547 2134

3465 2899

Contractor

(Gammon Construction Limited)

Environmental Manager

 

Brian Kam

3520 0387

3520 0486

Environmental Officer

 

Roy Leung

3520 0387

3520 0486

 

24-hour Complaint Hotline

 

 

9738 4332

 

ET (ERM-HK)

ET Leader

Jovy Tam

2271 3113

2723 5660

1.4                                      Summary of Construction Works

The construction phase of the Contract commenced on 31 October 2013.  The rolling construction programme for the period of June to August 2015 is shown in Appendix B.

As informed by the Contractor, details of the major works carried out in this reporting period are listed below:

June 2015

Marine Works

·      Construction and installation of pile caps;

·      Uninstallation of marine piling platform;

·      Pier construction;

·      Launching gantry assembly;

·      Marine piling and

·      Installation of pier head segment

Land-based Works

·      Construction and installation of pile caps;

·      Pier construction;

·      Re-alignment of Cheung Tung Road;

·      Land piling;

·      Pre-drilling works;

·      Installation of pier head segment;

·      Additional land GI, trial pits & lab testing;

·      Relocation of MTRC fence; and

·      Slope work of Slopes 9SE-B/C9 and 9SE-B/F85.

July 2015

Marine Works

·      Construction and installation of pile caps;

·      Uninstallation of marine piling platform;

·      Pier construction;

·      Launching gantry assembly;

·      Marine piling; and,

·      Installation of pier head segment.

Land-based Works

·      Predrilling at Viaduct F;

·      Construction and installation of pile caps;

·      Pier construction;

·      Re-alignment of Cheung Tung Road;

·      Land piling;

·      Pre-drilling works;

·      Installation of pier head segment;

·      Additional land GI, trial pits & lab testing;

·      Relocation of MTRC fence; and,

·      Slope work of Viaducts A & B.

August 2015

Marine Works

·      Construction and installation of pile caps;

·      Uninstallation of marine piling platform;

·      Pier construction;

·      Launching gantry assembly;

·      Marine piling; and,

·      Installation of pier head segment.

Land-based Works

·      Predrilling at Viaduct F;

·      Construction and installation of pile caps;

·      Pier construction;

·      Re-alignment of Cheung Tung Road;

·      Land piling;

·      Installation of pier head segment;

·      Additional land GI, trial pits & lab testing;

·      Relocation of MTRC fence; and,

·      Slope work of Viaducts A & B.

The locations of the construction activities are shown in Figure 1.3.  The Environmental Sensitive Receivers in the vicinity of the Project are shown in Figure 1.4.



Figure 1.3     Locations of Construction Activities in the Reporting Period


The environmental mitigation measures implementation schedule is presented in Appendix C.

1.5                                      Summary of EM&A Programme Requirements

The EM&A programme required environmental monitoring for air quality, noise, water quality and marine ecology as well as environmental site inspections for air quality, noise, water quality, waste management, marine ecology and landscape and visual impacts.  The EM&A requirements and related findings for each component are described in the following sections, which include:

·      Monitoring parameters;

·      Monitoring schedules for the reporting months and forthcoming months;

·      Action and Limit levels for all environmental parameters;

·      Event Action Plan;

·      Results and observations;

·      Environmental mitigation measures, as recommended in the approved EIA Report; and

·      Environmental requirement in contract documents.

2                                            EM&A RESULTS

The EM&A programme required environmental monitoring for air quality, noise, water quality and marine ecology as well as environmental site inspections for air quality, noise, water quality, waste management, marine ecology and landscape and visual impacts.  The EM&A requirements and related findings for each component are summarized in the following sections.

2.1                                      Air Quality

The baseline air quality monitoring undertaken by the Hong Kong – Zhuhai –Macao Bridge Hong Kong Projects (HKZMB) during October 2011 has included the two monitoring stations ASR9A and ASR9C for this project.  Thus, the baseline monitoring results and Action/ Limit Level presented in HKZMB Baseline Monitoring Report ([1]) are adopted for this Project.

2.1.1                                Monitoring Requirements and Equipment

In accordance with the Updated EM&A Manual, impact 1-hour TSP monitoring was conducted three (3) times every six (6) days while the highest dust impact was expected.  Impact 24-hour TSP monitoring was carried out once every six (6) days.  The Action and Limit Levels of the air quality monitoring is provided in Appendix D.

1-hour TSP and 24-hour TSP monitoring were conducted at 2 alternative air quality monitoring stations, ASR8A (Area 4) and ASR9 (Entrance of MTR Depot) during the reporting period in accordance with the requirement of the Updated EM&A Manual.  The monitoring stations are indicated in Figure 2.1 and details are presented in Table 2.1.

High Volume Samplers (HVSs) were used for carrying out 1-hour and 24-hour TSP monitoring during the reporting period.  The HVSs meets all requirements of the Updated EM&A Manual.  Brand and model of the equipment are given in Table 2.2.

Wind data monitoring equipment was installed at Area 4 during the reporting period for logging wind speed and wind direction.  The wind sensor was setup such that it was clear of obstructions or turbulence caused by building.  The wind data monitoring equipment is recalibrated at least once every six months.

Table 2.1        Locations of Impact Air Quality Monitoring Stations and Monitoring Dates in this Reporting Period

Monitoring Station (1)

Monitoring Period

Location

Description

Parameters & Frequency

ASR8A

2, 8, 11, 17, 23 and 29 June 2015;

2, 7, 13, 16, 22 and 28 July 2015;

3, 6, 12, 18, 24 and 27 August 2015

Area 4

On ground at the Area 4

Ÿ  1-hour Total Suspended Particulates (1-hour TSP, µg/m3), 3 times per day every 6 days

Ÿ  24-hour Total Suspended Particulates (24-hour TSP, µg/m3), daily for 24-hour every 6 days

ASR9

MTR Depot

On the ground nearby MTR Depot Entrance

Note: 

(1) Air Quality Monitoring Stations ASR9A and ASR9C at Siu Ho Wan MTRC Depot proposed in accordance with the Updated EM&A were relocated to ASR9 and ASR8A respectively.

Table 2.2        Air Quality Monitoring Equipment

Equipment

Brand and Model

High Volume Sampler
(1-hour TSP and 24-hour TSP)

Tisch Environmental Mass Flow Controlled Total Suspended Particulate (TSP) High Volume Sampler (Model No. TE-5170)

 

Wind Sensor

Global Water (Wind Speed Sensor: WE550; Wind Direction Sensor: WE570)

 

Wind Anemometer for calibration

Lutron (Model No. AM-4201)

2.1.2                                Action & Limit Levels

The Action and Limit Levels of the air quality monitoring are provided in Appendix D.  The Event and Action plan is presented in Appendix J.

2.1.3                                Monitoring Schedule for the Reporting Quarter

The schedules for air quality monitoring in the reporting quarter are provided in Appendix E.

2.1.4                                Results and Observations

The monitoring results for 1-hour TSP and 24-hour TSP are summarized in Tables 2.3 and 2.4, respectively.  Monitoring results are presented graphically in Appendix F.  Detailed impact air quality monitoring results and meteorological information were reported in the Twentieth to Twenty-second Monthly EM&A Report.

Table 2.3        Summary of 1-hour TSP Monitoring Results in this Reporting Period

Month

Station

Average (µg/m3)

Range (µg/m3)

Action Level  (µg/m3)

Limit Level  (µg/m3)

June 2015

ASR 8A

59

41 - 95

394

500

ASR 9

71

48 - 119

393

500

July 2015

ASR 8A

63

41 - 139

394

500

ASR 9

73

41 - 116

393

500

August 2015

ASR 8A

88

58 - 148

394

500

ASR 9

104

60 - 165

393

500

Table 2.4        Summary of 24-hour TSP Monitoring Results in this Reporting Period

Month

Station

Average (µg/m3)

Range (µg/m3)

Action Level  (µg/m3)

Limit Level  (µg/m3)

June 2015

ASR 8A

45

42 – 47

178

260

ASR 9

47

45 – 49

178

260

July 2015

ASR 8A

51

44 – 75

178

260

 

ASR 9

56

47 – 89

178

260

August 2015

ASR 8A

61

48 – 85

178

260

 

ASR 9

68

51 – 101

178

260

The major dust sources in the reporting period include construction activities under the Contract as well as nearby traffic emissions.

In this reporting period, a total of eighteen (18) monitoring events were undertaken within the reporting period, in which no Action or Limit Level exceedance for 1-hour and 24-hour TSP for air quality was recorded during the reporting period.


2.2                                      Noise Monitoring

The baseline noise monitoring undertaken by the Hong Kong – Zhuhai – Macao Bridge Hong Kong Projects (HKZMB) during the period of 18 October to 1 November 2011 has included the monitoring station NSR1 for this project.  Thus, the baseline monitoring results and Action/ Limit Level presented in HKZMB Baseline Monitoring Report ([2]) are adopted for this Project.

2.2.1                                Monitoring Requirements and Equipment

In accordance with the Updated EM&A Manual, impact noise monitoring should be conducted once per week during the construction phase of the Contract.

Noise monitoring was conducted at the alternative noise monitoring station, NSR1A (Pak Mong Village Pavilion) during the reporting period in accordance with the requirement of Updated EM&A Manual.  Figure 2.2 shows the location of the monitoring station.  Table 2.5 describes the details of the monitoring station.

Noise monitoring was performed using sound level meter at the designated monitoring station in the reporting quarter.  The deployed sound level meter complies with the International Electrotechnical Commission Publications (IEC) 651:1979 (Type 1) and 804:1985 (Type 1) specifications.  Acoustic calibrator was deployed to check the sound level meter at a known sound pressure level.  Brand and model of the equipment is given in Table 2.6.


Table 2.5        Location of Impact Noise Monitoring Station and Monitoring Dates in this Reporting Period

Monitoring Station

Monitoring Period

Location

Parameters & Frequency

NSR1A

2, 8, 11, 17, 23 and 29 June 2015;

2, 7, 13, 16, 22 and 28 July 2015;

3, 6, 12, 18, 24 and 27 August 2015

Pak Mong Village Pavilion

Ÿ   30-mins measurement at each monitoring station between 0700 and 1900 on normal weekdays (Monday to Saturday). Leq, L10 and L90 would be recorded.

Ÿ   At least once a week

Note:

(1)    Noise Monitoring Station NSR1 at Pak Mong Village proposed in accordance with the Updated EM&A was relocated to NSR1A.

Table 2.6        Noise Monitoring Equipment

Equipment

Brand and Model

Integrated Sound Level Meter

Rion NL-31

Acoustic Calibrator

Rion NC-73

2.2.2                                Action and Limit Levels

The Action and Limit levels of the noise monitoring are provided in Appendix D.  The Event and Action plan is presented in Appendix J.

2.2.3                                Monitoring Schedule for the Reporting Quarter

The schedules for noise monitoring in the reporting quarter are provided in Appendix E.

2.2.4                                Results and Observations

The monitoring results for noise monitoring are summarized in Table 2.7.  Monitoring results are presented graphically in Appendix G and detailed impact noise monitoring results are reported in the Twentieth to Twenty-second Monthly EM&A Report.

Table 2.7        Summary of Construction Noise Monitoring Results at NSR1A in the Reporting Period

Month

Average , dB(A), Leq (30mins)

Range, dB(A), Leq (30mins)

Limit Level, dB(A), Leq (30mins)

June 2015

59

58 - 60

75

July 2015

60

53 - 61

75

August 2015

58

57 - 60

75

 

A total of eighteen (18) monitoring events were undertaken in the reporting period with no Action Level and Limit Level exceedance recorded at the monitoring station in the reporting period.  No action is thus required to be undertaken in accordance with the Event Action Plan presented in Appendix J.

Major noise sources during the noise monitoring included construction activities, nearby traffic noise and aircraft noise.


2.3                                      Water Quality Monitoring

The baseline water quality monitoring undertaken by the Hong Kong – Zhuhai – Macao Bridge Hong Kong Projects (HKZMB) between 6 and 31 October 2011 has included all monitoring stations except SR4a for the Project.  Thus, the baseline monitoring results except for station SR4a and Action/Limit Level presented in HKZMB Baseline Monitoring Report ([3]) are adopted for this Project.  Baseline water quality monitoring was conducted at station SR4a from 29 August to 24 September 2013.

2.3.1                                Monitoring Requirements and Equipment

Impact water quality monitoring was carried out to ensure that any deterioration of water quality was detected, and that timely action was taken to rectify the situation.  Impact water quality monitoring was undertaken three days per week during the construction period at seven water quality monitoring stations in accordance with the Updated EM&A Manual (Figure 2.3; Table 2.8). 

Table 2.8        Locations of Water Quality Monitoring Stations and the Corresponding Monitoring Requirements

Station ID

Type

Coordinates

*Parameters, unit

Depth

Frequency

 

 

Easting

Northing

 

 

 

IS(Mf)9

Impact Station (Close to HKBCF construction site)

813273

818850

Ÿ Temperature(°C)

Ÿ pH(pH unit)

Ÿ Turbidity (NTU)

Ÿ Water depth (m)

Ÿ Salinity (ppt)

Ÿ DO (mg/L and % of

saturation)

·    SS (mg/L)

3 water depths: 1m

below sea surface,

mid-depth and 1m

above sea bed.  If the water depth is less than 3m, mid-depth sampling only.  If water depth less than 6m, mid-depth may be omitted.

 

 

Impact monitoring: 3 days per week, at mid-flood and mid-ebb tides during the construction period of the Contract.

IS(Mf)16

Impact Station (Close to HKBCF construction site)

814328

819497

IS8

Impact Station(Close to HKBCF construction site)

814251

818412

SR4

Sensitive receiver (Tai Ho Inlet)

814760

817867

SR4a

Sensitive receiver

815247

818067

CS(Mf)3

Control Station

809989

821117

CS(Mf)5

Control Station

817990

821129

Notes:

In addition to the parameters presented monitoring location/position, time, water depth, sampling depth, tidal stages, weather conditions and any special phenomena or works underway nearby were also recorded.

Table 2.9 summarizes the equipment used in the impact water quality monitoring programme.

Table 2.9        Water Quality Monitoring Equipment

Equipment

Brand and Model

DO, Temperature meter and Salinity

YSI Pro2030

 

 

Turbidimeter

HACH Model 2100Q

 

pH meter   

HANNA HI8314 &

Thermo Scientific Orion 2 Star

 

Positioning Equipment

Koden913MK2 with KBG-3 DGPS antenna

 

Water Depth Detector

Speedtech Instrument SM-5

 

Water Sampler

Kemmerer 1520 (1520-C25) 2.2L with messenger

2.3.2                                Action & Limit Levels

The Action and Limit Levels of the water quality monitoring are provided in Appendix D.

2.3.3                                Monitoring Schedule for the Reporting Quarter

The schedules for water quality monitoring in the reporting quarter are provided in Appendix E.  The WQM on 7 July 2015 was cancelled due to adverse weather.

2.3.4                                Results and Observations

Impact water quality monitoring was conducted at all designated monitoring stations in the reporting period.  Monitoring results are presented graphically in Appendix H and detailed impact water quality monitoring results were reported in the Twentieth to Twenty-second Monthly EM&A Reports.

In this reporting period, a total of thirty-eight (38) monitoring events were undertaken with no Action Level and Limit Level exceedance recorded at the monitoring station in the reporting period.  No action is thus required to be undertaken in accordance with the Event Action Plan presented in Appendix J.

The SS levels at IS8 on 25 July 2015 and IS(Mf)16 on 1 August 2015 during mid-ebb tide were higher than the corresponding Action Level but not higher than 120% of the upstream control station at the same tide on same day.  Thus the results were not regarded as exceedances.

2.4                                      Dolphin Monitoring

2.4.1                                Monitoring Requirements

Impact dolphin monitoring is required to be conducted by a qualified dolphin specialist team to evaluate whether there have been any effects on the dolphins.  In order to fulfil the EM&A requirements and make good use of available resources, the on-going impact line transect dolphin monitoring data collected by HyD’s Contract No. HY/2011/03 Hong Kong-Zhuhai-Macao Bridge. Hong Kong Link Road - Section between Scenic Hill and Hong Kong Boundary Crossing Facilities on the monthly basis is adopted to avoid duplicates of survey effort.

2.4.2                                Monitoring Equipment

Table 2.10 summarizes the equipment used for the impact dolphin monitoring.


Table 2.10      Dolphin Monitoring Equipment

Equipment

Model

Global Positioning System (GPS)

 

Camera

 

Laser Binoculars

Marine Binocular

Vessel for Monitoring

 

Garmin 18X-PC

Geo One Phottix

Nikon D90 300m 2.8D fixed focus

Nikon D90 20-300m zoom lens

Infinitor LRF 1000

Bushell 7 x 50 marine binocular with compass and reticules

65 foot single engine motor vessel with viewing platform 4.5m above water level

2.4.3                                Monitoring Parameter, Frequencies & Duration

Dolphin monitoring should cover all transect lines in Northeast Lantau (NEL) and the Northwest Lantau (NWL) survey areas twice per month throughout the entire construction period.  The monitoring data should be compatible with, and should be made available for, long-term studies of small cetacean ecology in Hong Kong.  In order to provide a suitable long-term dataset for comparison, identical methodology and line transects employed in baseline dolphin monitoring was followed in the impact dolphin monitoring.

2.4.4                                Monitoring Location

The impact dolphin monitoring was carried out in the NEL and NWL along the line transect as depicted in Figure 2.4.  The co-ordinates of all transect lines are shown in Table 2.11 below.


Table 2.11      Impact Dolphin Monitoring Line Transect Co-ordinates

Line No.

Easting

Northing

Line No.

Easting

Northing

1

Start Point

804671

814577

(815456)

13

Start Point

816506

819480

1

End Point

804671

831404

13

End Point

816506

824859

2

Start Point

805475

815457

(815913)

14

Start Point

817537

820220

2

End Point

805477

826654

14

End Point

817537

824613

3

Start Point

806464

819435

15

Start Point

818568

820735

3

End Point

806464

822911

15

End Point

818568

824433

4

Start Point

807518

819771

16

Start Point

819532

821420

4

End Point

807518

829230

16

End Point

819532

824209

5

Start Point

808504

820220

17

Start Point

820451

822125

5

End Point

808504

828602

17

End Point

820451

823671

6

Start Point

809490

820466

18

Start Point

821504

822371

6

End Point

809490

825352

18

End Point

821504

823761

7

Start Point

810499

820690

(820880)

19

Start Point

822513

823268

7

End Point

810499

824613

19

End Point

822513

824321

8

Start Point

811508

820847

(821123)

20

Start Point

823477

823402

8

End Point

811508

824254

20

End Point

823477

824613

9

Start Point

812516

820892

(821303)

21

Start Point

805476

827081

9

End Point

812516

824254

21

End Point

805476

830562

10

Start Point

813525

820872

22

Start Point

806464

824033

10

End Point

813525

824657

22

End Point

806464

829598

11

Start Point

814556

818449

(818853)

23

Start Point

814559

821739

11

End Point

814556

820992

23

End Point

814559

824768

12

Start Point

815542

818807

 

 

 

 

12

End Point

815542

824882

 

 

 

 

Note:

Northing co-ordinates in bracket are the adjusted co-ordinates since

August 2015 due to obstruction of permanent structures associated with construction works.  Approval of the adjustments from EPD was recieved in July 2015. 

2.4.5                                Action & Limit Levels

The action and limit levels of dolphin impact monitoring are shown in Appendix D.  The Event and Action plan is presented in Appendix J.

2.4.6                                Monitoring Schedule for the Reporting Period

The dolphin monitoring schedules for the reporting period are shown in Appendix E.

2.4.7                                Results & Observations

A total of 900.64 km of survey effort was collected, with 92.8% of the total survey effort being conducted under favourable weather conditions (i.e. Beaufort Sea State 3 or below with good visibility).  Among the two areas, 345.58 km and 555.06 km of survey effort were conducted in NEL and NWL survey areas respectively.  The total survey effort conducted on primary lines was 655.74 km, while the effort on secondary lines was 244.90 km.  Survey effort conducted on both primary and secondary lines were considered as on-effort survey data.  The survey efforts are summarized in Appendix I.

During the six sets of monitoring surveys in June to August 2015, a total of twelve (12) groups of forty-two (42) Chinese White Dolphins were sighted.  All dolphin sightings were made during on-effort search, and all of them were made on primary lines.  In this quarterly period, all except one (1) dolphin groups were sighted in NWL, while one (1) group of a lone animal was sighted in NEL.  Notably, this was the first dolphin sighted in NEL since monitoring surveys in July 2014.  Summary table of the dolphin sightings is shown in Appendix I.

Encounter rates of Chinese White Dolphins deduced from the survey effort and on-effort sighting data from the primary transect lines under favourable conditions (Beaufort 3 or below) in the reporting period with the results presented in Tables 2.12 and 2.13.


Table 2.12      Individual Survey Event Encounter Rates

Survey Area

Survey period

Encounter rate (STG)     (no. of on-effort dolphin sightings per 100 km of survey effort)

Encounter rate (ANI)            (no. of dolphins from all on-effort sightings per 100 km of survey effort)

Primary Lines Only

Primary Lines Only

NEL

Set 1: 2nd & 10th Jun 2015

0.00

0.00

Set 2: 24th & 26th Jun 2015

2.64

2.64

Set 3: 2nd & 7th Jul 2015

0.00

0.00

Set 4: 22nd & 27th Jul 2015

0.00

0.00

Set 5: 10th & 14th Aug 2015

0.00

0.00

Set 6: 19th & 28th Aug 2015

0.00

0.00

NWL

Set 1: 2nd & 10th Jun 2015

1.51

15.15

Set 2: 24th & 26th Jun 2015

0.00

0.00

Set 3: 2nd & 7th Jul 2015

1.69

3.38

Set 4: 22nd & 27th Jul 2015

3.46

6.92

Set 5: 10th & 14th Aug 2015

0.00

0.00

Set 6: 19th & 28th Aug 2015

8.53

29.84

Note:  Dolphin Encounter Rates are deduced from the six sets of surveys (two surveys in each set) in the reporting period in Northeast (NEL) and Northwest Lantau (NWL)

 

Table 2.13      Quarterly Average Encounter Rates

Survey Area

Encounter rate (STG)        (no. of on-effort dolphin sightings per 100 km of survey effort)

Encounter rate (ANI)            (no. of dolphins from all on-effort sightings per 100 km of survey effort)

June - August 2015

September -November 2011

June - August 2015

September -November 2011

Northeast Lantau

0.44 ± 1.08

6.00 ± 5.05

0.44 ± 1.08

22.19 ± 26.81

Northwest Lantau

2.53 ± 3.20

9.85 ± 5.85

9.21 ± 11.57

44.66 ± 29.85

Note: encounter rates deduced from the baseline monitoring period (September – November 2011) have been recalculated based only on survey effort and on-effort sighting data made along the primary transect lines under favourable conditions

Except one (1) group of ten (10) individuals was sighted, group size of Chinese White Dolphins ranged from one (1) to five (5) individuals per group in North Lantau region during June 2015 to August 2015.  The average dolphin group sizes from these three months were compared with the ones deduced from the baseline period in September to November 2011, as shown in Table 2.14.


Table 2.14      Comparison of Quarterly Average Encounter Rates

 

Average Dolphin Group Size

June - August 2015

September - November 2011

Overall

3.50 ± 2.65 (n = 12)

3.72 ± 3.13 (n = 66)

Northeast Lantau

1.00 (n = 1)

3.18 ± 2.16 (n = 17)

Northwest Lantau

3.73 ± 2.65 (n = 11)

3.92 ± 3.40 (n = 49)

One (1) Limit Level exceedance was observed for the quarterly dolphin monitoring data between June and August 2015.  During this quarter of dolphin monitoring, no unacceptable impact from the activities of this Contract on Chinese White Dolphins was noticeable from the general observations.

Although the dolphins infrequently occurred along the alignment of TMCLKL Southern Connection Viaduct in the past and during the baseline monitoring period, it is apparent that dolphin usage has been significantly reduced in NEL, and many individuals have shifted away from the important habitat around the Brothers Islands.

It is critical to monitor the dolphin usage in North Lantau region in the upcoming quarters, to determine whether the dolphins are continuously affected by the various construction activities in relation to the HZMB-related works, and whether suitable mitigation measure can be applied to revert the situation.

2.4.8                                Marine Mammal Exclusion Zone Monitoring

Daily marine mammal exclusion zone monitoring was undertaken during the period of marine works under this Contract.  No Passive Acoustic Monitoring (PAM) was implemented as the marine piling works were not carried out outside the daylight hours in this reporting period.  No sighting of the Indo-Pacific humpback dolphin Sousa chinensis (i.e. Chinese White Dolphin) was recorded in the monitoring period during the exclusion zone monitoring.

2.5                                      EM&A Site Inspection

Site inspections were carried out on a weekly basis to monitor the implementation of proper environmental pollution control and mitigation measures under the Contract.  Thirteen (13) site inspections were carried out in the reporting quarter on 2, 10, 17 and 25 June 2015; 2, 9, 14, 22 and 30 July 2015; 7, 12, 19 and 27 August 2015.

Key observations during the site inspections in this reporting period are summarized in Table 2.15.

Table 2.15      Specific Observations Identified during the Weekly Site Inspection in this Reporting Period

Inspection Date

Location & Environmental Observations

Recommendations/ Remarks

2 June 2015

Pier E11

·         Excessive soil was found in gutter.

·         Stagnant water was accumulated in drip tray.

Pier E6

·         A label for sediment was missing on barge.

Barge G39

·         Some chemical containers were not placed in drip tray.

Pier E11

·         Gutter should be cleaned up regularly.

·         Stagnant water should be removed to avoid runoff.

Pier E6

·         Type of sediment should be properly labelled..

Barge G39

·         Chemical containers should be placed in drip tray.

10 June 2015

Area 1

·         Refuse was found in drainage.

·         Some chemical containers were not placed in drip tray

 

Area 1

·         Refuse in drainage should be cleaned up.

·         Chemical containers should be placed in drip tray.

17 June 2015

Pier E13

·         The updated dumping permit was not displayed.

·         A generator was not placed on acoustic decoupling pad.

·          A drip tray was not plugged.

Pier E13

·         The updated dumping permit should be displayed.

·         Generator on marine platform should be placed on acoustic decoupling pad.

·         Drip tray should be plugged.

 

25 June 2015

Site Entrance 4A

·          Cover of a dump truck was damaged.

·          Excessive soil was found in drainage.

·          Chemical containers were not placed in drip tray.

Barge G39

·          Chemical containers were not placed in drip tray.

Site Entrance 4A

·          Cover of a dump truck should be able to effectively cover dusty material.

·          Soil in drainage should be cleaned up. Bund or sandbag should be provided to avoid soil runoff into drainage.

·          Chemical containers should be placed in drip tray.

Barge G39

·          Chemical containers should be placed in drip tray.

2 July 2015

Area 1

Ÿ   Chemical containers were not placed in drip tray.

Ÿ   Refuse was found in drainage.

Area 2

Ÿ   EP was not displayed.

 

Area 1

Ÿ   Chemical containers should be placed in drip tray.

Ÿ   Refuse in drainage should be cleaned up regularly.

Area 2

Ÿ   EP should be displayed.

 

9 July 2015

Pier A2

Ÿ   Gutter was not properly installed.

Seafront

Ÿ   A drip tray was not plugged.

Ÿ   A power pack was not placed in drip tray.

Ÿ   Checklist for a wet sep was not displayed.

 

Pier A2

Ÿ   Gutter should be properly installed.

Seafront

Ÿ   Drip tray should be plugged.

Ÿ   Power pack should be placed in drip tray.

Ÿ   Checklist for wet sep should be displayed.

 

14 July 2015

Area 1

Ÿ   The ground was partially dry.

Ÿ   Some chemical containers were not placed in drip tray.

Ÿ   The old EP was displayed.

Site Access 4A

Ÿ   A drip tray for air compressor contained stagnant water.

Pier D12 A

Ÿ   Stagnant water was accumulated in drip tray.

Pier D10

Ÿ   The ground was partially dry.

Ÿ   Some chemical containers were not placed in drip tray.

 

Area 1

Ÿ   Unpaved area should be watered to avoid dust emission.

Ÿ   Chemical containers should be placed in drip tray.

Ÿ   The old EP was removed immediately.

Site Access 4A

Ÿ   Stagnant water in drip tray should be removed to avoid overflow.

Pier D12 A

Ÿ   Stagnant water in drip tray should be removed to avoid overflow.

Pier D10

Ÿ   Unpaved area should be watered to avoid dust emission.

Ÿ   Chemical containers should be placed in drip tray.

 

22 July 2015

Slope B/F8

Ÿ   Oil stain was found in drainage.

Ÿ   Chemical containers were not placed in drip tray.

Slope B/C9

Ÿ   Chemical containers of Aqua Sed were not labelled.

Seafront

Ÿ   Chemical containers were not placed in drip tray.

 

Slope B/F8

Ÿ   Oil stain in drainage should be removed.

Ÿ   Chemical containers should be placed in drip tray.

Slope B/C9

Ÿ   Chemical containers should be labelled.

Seafront

Ÿ   Chemical containers should be placed in drip tray.

 

30 July 2015

Pier D5

Ÿ   A drip tray for generator was not plugged.

Ÿ   A decoupling mat was damaged.

Ÿ   A part of gutter was damaged.

Barge Kiu Lik (next to Pier A7)

Ÿ   A drip tray for generator was not plugged.

Ÿ   Some chemical containers were not placed in drip tray.

Pier E12

Ÿ   A generator was not placed on acoustic decoupling mat.

 

Pier D5

Ÿ   Drip tray for generator should be plugged.

Ÿ   Damaged decoupling mat should be replaced by new decoupling mat.

Ÿ   Damaged gutter should be repaired to avoid runoff.

Barge Kiu Lik (next to Pier A7)

Ÿ   Drip tray for generator should be plugged.

Ÿ   Chemical containers should be placed in drip tray.

Pier E12

Ÿ   Generator should be placed on acoustic decoupling mat.

 

7 August 2015

Pier C3

Ÿ   Stagnant water was accumulated in drip tray

Pier E12

Ÿ   Gutter was not properly installed.

 

Pier C3

Ÿ   Stagnant water in drip tray should be cleaned up to avoid runoff.

Pier E12

Ÿ   Gutter should be properly installed to avoid runoff.

 

12 August 2015

Area 1

Ÿ   Chemical containers were placed too close to the natural habitat.

Ÿ   Chemical containers were placed without drip tray.

Ÿ   Soil stockpile next to drainage was not well covered.

Pier B14

Ÿ   Chemical containers were placed without drip tray.

 

Area 1

Ÿ   Chemical containers should be placed in drip tray and away from natural habitat.

Ÿ   Tarpaulin sheet or hydroseeding should be provided to the soil stockpile next to drainage.

Pier B14

Ÿ   Chemical containers should be placed in drip tray.

 

19 August 2015

Pier E6

Ÿ   Some chemical containers were not placed in drip tray.

Ÿ   An expired dumping permit was displayed.

Pier E12

Ÿ   A drip tray was not plugged.

Pier B13

Ÿ   Refuse was found accumulated onsite.

 

Pier E6

Ÿ   Chemical containers should be placed in drip tray.

Ÿ   Expired dumping permit should not be displayed.

Pier E12

Ÿ   Drip tray should be plugged.

Pier B13

Ÿ   Refuse should be regularly cleaned up

 

27 August 2015

Abutment D

Ÿ   A label of chemical container was damaged.

Ÿ   Checklist of wetsep was not displayed.

Ÿ   Stagnant water was found in a drip tray for air compressor.

Pier E1

Ÿ   Excessive soil was found in gutter

Pier C4

Ÿ   A generator was not well placed on decoupling pad.

 

Abutment D

Ÿ   Chemical container should be properly labeled.

Ÿ   Checklist of wetsep should be displayed.

Ÿ   Stagnant water in drip tray should be removed to avoid runoff.

Pier E1

Ÿ   Excessive soil should be cleaned up regularly.

Pier C4

Ÿ   Stationary PME should be well placed on decoupling pad.

 

The Contractor has rectified all of the observations identified during environmental site inspections in the reporting period.

2.6                                      Waste Management Status

The Contractor has submitted application form for registration as chemical waste producer under the Contract.  Sufficient numbers of receptacles were available for general refuse collection and sorting.

Wastes generated during this reporting period include mainly construction wastes (inert and non-inert), imported fill, recyclable materials, chemical wastes and marine sediments (Categories L & M).  Reference has been made to the waste flow table prepared by the Contractor (Appendix K).  The quantities of different types of wastes are summarized in Table 2.16.


Table 2.16      Quantities of Different Waste Generated in the Reporting Period

Month / Year

Inert Construction Waste (a) (m3)

Imported Fill (m3)

Inert Construction Waste Re-used

(m3)

Non-inert Construction Waste (b) (kg)

Recyclable Materials (c)  (kg)

Chemical Wastes (kg)

Marine Sediment (m3)

 

Category L

Category M

 

June 2015

7,166

0

1,351

89,930

119

17

324

287

July 2015

2,322

78

992

111,570

105

1,400

0

0

August 2015

1,265

0

105

87,760

133

1,200

0

0

Total

10,753

78

2,448

289,260

357

2,617

324

287

 

Notes:

 

(a)   Inert construction wastes include hard rock and large broken concrete, and materials disposed as public fill.

(b)   Non-inert construction wastes include general refuse disposed at landfill.

(c)    Recyclable materials include metals, paper, cardboard, plastics, timber and others.

 

The Contractor was advised to properly maintain on site C&D materials and waste collection, sorting and recording system, dispose of C&D materials and wastes at designated ground and maximize reuse/ recycle of C&D materials and wastes.  The Contractor was also reminded to properly maintain the site tidiness and dispose of the wastes accumulated on site regularly and properly.

For chemical waste containers, the Contractor was reminded to treat properly and store temporarily in designated chemical waste storage area on site in accordance with the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes.

2.7                                      Environmental Licenses and Permits

The status of environmental licensing and permit is summarized in Table 2.17 below.


Table 2.17      Summary of Environmental Licensing and Permit Status

License/ Permit

License or Permit No.

Date of Issue

Date of Expiry

License/ Permit Holder

Remarks

 

Environmental Permit

EP-354/2009/D

13-Mar-15

N/A

HyD

Tuen Mun- Chek Lap Kok Link

 

Construction Dust Notification

361571

5-Jul-13

N/A

GCL

-

 

Construction Dust Notification

362093

17-Jul-13

N/A

GCL

For Area 23

 

Chemical Waste Registration

5213-961-G2380-13

10-Oct-13

N/A

GCL

Chemical waste produced in Contract HY/2012/07 (Area 1 adjacent to Cheng Tung Road, Siu Ho Wan)

 

Chemical Waste Registration

5213-961-G2380-14

10-Oct-13

N/A

GCL

Chemical waste produced in Contract HY/2012/07 (Area 2 adjacent to Cheung Tung Road, Pak Mong Village)

 

Chemical Waste Registration

5213-974-G2588-03

4-Nov-13

N/A

GCL

Chemical waste produced in Contract HY/2012/07 (WA5 adjacent to Cheung Tung Road, Yam O)

 

Chemical Waste Registration

5213-951-G2380-17

12-Jun-14

N/A

GCL

Viaducts A, B, C, D & E

 

Construction Waste Disposal Account

7017735

10-Jul-13

N/A

GCL

-

 

Construction Waste Disposal Account

7019470

3-Mar-14

N/A

GCL

Vessel CHIT Account

 

Waste Water Discharge License

WT00019017-2014

13-May-14

31-May-19

GCL

Discharge for marine portion

 

Waste Water Discharge License

WT00019018-2014

13-May-14

31-May-19

GCL

Discharge for land portion

 

Construction Noise Permit

Nil

N/A

N/A

GCL

For Piling Works

 

Construction Noise Permit for night works and works in general holidays

GW-RW0093-15

26-Feb-15

26-Aug-15

GCL

General works at WA5

 

Construction Noise Permit for night works and works in general holidays

GW-RS0307-15

27-Mar-15

27-Sep-15

GCL

For Load unload at NLH near Viaduct D

 

Construction Noise Permit for night works and works in general holidays

GW-RS0691-15

23-Jun-15

22-Dec-15

GCL

For Broad Permit

 

Construction Noise Permit for night works and works in general holidays

GW-RS0078-15

28-Jan-15

29-Jul-15

GCL

For Plant mobilization using tractor with trailer

 

Construction Noise Permit for night works and works in general holidays

GW-RS0539-15

14-May-15

31-Jul-15

GCL

B9-B16 Pier Head Segments Erection

 

Construction Noise Permit for night works and works in general holidays

GW-RS0137-15

12-Feb-15

15-Aug-15

GCL

Pre-casted pile cap shell installation at E10-E13

 

Construction Noise Permit for night works and works in general holidays

GW-RW0695-15

30-Jun-15

30-Nov-15

GCL

Segment Erection between B6-B11 by LG1

 

Construction Noise Permit for night works and works in general holidays

GW-RS0491-15

8-May-15

30-Jun-15

GCL

TTA Case 009 Ch.2.1E-4.2E

 

Construction Noise Permit for night works and works in general holidays

GW-RS0489-15

8-May-15

7-Aug-15

GCL

B8 Pier Head Temp Works Lifting

 

Construction Noise Permit for night works and works in general holidays

GW-RS0539-15

14-May-15

31-Jul-15

GCL

B9-B16 Pier Head Segments Erection

 

Construction Noise Permit for night works and works in general holidays

GW-RS0769-15

15-Jul-15

30-Sep-15

GCL

TTA Case 009 Ch.2.1E-4.2E

 

Construction Noise Permit for night works and works in general holidays

GW-RW0422-15

21-Aug-15

25-Jan-16

GCL

General works at WA5

 

Construction Noise Permit for night works and works in general holidays

GW-RS0911-15

27-Aug-15

26-Feb-16

GCL

Broad Permit for Seg. Launching at Land Portion

 

Construction Noise Permit for night works and works in general holidays

GW-RS0855-15

12-Aug-15

11-Feb-16

GCL

Pier construction at C7, D8, D9

 

Construction Noise Permit for night works and works in general holidays

GW-RW0861-15

13-Aug-15

30-Sep-15

GCL

Portal beam installation at Pier D14

 

Marine Dumping Permit

EP/MD/16-020

22-May-15

26-Jun-15

GCL

For dumping Type I (Dedicated Site) and Type II sediment

 

Marine Dumping Permit

EP/MD/15-257

2-Apr-15

7-Oct-15

GCL

For dumping Type I sediment


2.8                                      Implementation Status of Environmental Mitigation Measures

In response to the site audit findings, the Contractor has carried out corrective actions.

A summary of the Environmental Mitigation and Enhancement Measure Implementation Schedules (EMIS) is presented in Appendix C.  The necessary mitigation measures were implemented properly for this Contract.

2.9                                      Summary of Exceedances of the Environmental Quality Performance Limit

Results for 1-hour TSP, 24-hour TSP, construction noise and water quality complied with the Action/ Limit levels in the reporting period.
The construction impact on depth-averaged SS was assessed by comparing the quarterly mean values of depth-averaged SS with the relevant ambient mean values.  Except CS(Mf)3, SR4, IS8 and IS(Mf)9 during mid-flood tide, results showed that the quarterly means of depth-averaged SS at all sampling stations during both mid-ebb and mid-flood tides were higher than the corresponding ambient means (Table 2.18).  One-way ANOVA was conducted to examine whether there is significant difference of depth-averaged SS between ambient levels and results in this quarter.  Statistical significant differences were only found at control stations CS(Mf)3 (F1,68 = 11.6, p = 0.001) and CS(Mf)5 (F1,72 = 10.6, p = 0.002) during mid-ebb tide between ambient level and impact monitoring of this quarter.  No significant difference was detected at impact monitoring stations.  The analytical results suggested that the increased SS levels are likely due to the natural fluctuation in the western waters of Hong Kong.  The ET will monitor the trend of depth-averaged SS in the upcoming quarters to determine whether there is any change in water quality associated with this Project and further mitigation measures will be recommended if deemed necessary.

Table 2.18      Comparison between Quarterly Mean and Ambient Mean Values of Depth-averaged Suspended Solids

Station

Baseline Mean

Ambient Mean (a)

Quarterly Mean (June 2015 to August 2015)

Mid-ebb

Mid-flood

Mid-ebb

Mid-flood

Mid-ebb

Mid-flood

CS(Mf)3

9.2

12.8

12.0

16.6

15.8

14.5

CS(Mf)5

9.2

11.5

11.9

14.9

15.3

14.9

SR4

10.3

12.3

13.4

16.0

15.1

14.4

SR4a

9.1

9.8

11.9

12.7

15.1

14.3

IS8

11.3

13.5

14.6

17.6

14.9

14.5

IS(Mf)9

10.9

14.3

14.2

18.5

14.8

14.3

IS(Mf)16

11.4

10.3

14.8

13.4

15.5

14.4

Notes:

(a) Ambient mean value is defined as a 30% increase of the baseline mean value

One (1) Limit Level exceedance was recorded for impact dolphin monitoring in this reporting quarter.  Following the review of the monitoring data and marine works details as per the procedure stipulated in the Event and Action Plan of the Updated EM&A Manual, there was no unacceptable impact on dolphin usage in the North Lantau region associated with construction works under this Contract.  Investigation findings were detailed in Appendix L.

2.10                                   Summary of Complaints, Notification of Summons and Successful Prosecutions

The Environmental Complaint Handling Procedure is provided in Figure 2.5.

One (1) environmental complaint with regard to dust emission from vehicles of this Project was received on 18 June 2015.  An investigation was carried out by ET on 18 June 2015.  Another investigation was conducted by EPD with SOR and Contractor on 19 June 2015.  The complaint was followed-up in accordance with the Environmental Complaint Handling Procedure.  Detailed investigation report for the complaint is presented in Appendix L.

3                                            Future Key Issues

3.1                                      Construction Activities for the Coming Quarter

As informed by the Contractor, the major works for the Contract in the coming quarter are summarized below:

September 2015

Marine Works

·      Construction and installation of pile caps;

·      Uninstallation of marine piling platform;

·      Pier construction;

·      Launching gantry assembly;

·      Marine piling; and,

·      Installation of pier head segment.

Land-based Works

·      Predrilling at Viaduct F;

·      Construction and installation of pile caps;

·      Pier construction;

·      Re-alignment of Cheung Tung Road;

·      Land piling;

·      Installation of pier head segment;

·      Additional land GI, trial pits & lab testing;

·      Relocation of MTRC fence; and,

·      Slope work of Viaduct A.

October 2015

Marine Works

·      Construction and installation of pile caps;

·      Uninstallation of marine piling platform;

·      Pier construction;

·      Launching gantry assembly;

·      Installation of deck segment and pier head segment.

Land-based Works

·      Predrilling at Viaduct F;

·      Construction and installation of pile caps;

·      Pier construction;

·      Re-alignment of Cheung Tung Road;

·      Installation of pier head segment;

·      Additional land GI, trial pits & lab testing;

·      Relocation of MTRC fence; and,

·      Slope work of Viaduct A.

November 2015

Marine Works

·      Construction and installation of pile caps;

·      Uninstallation of marine piling platform;

·      Pier construction;

·      Launching gantry assembly; and

·      Installation of deck segment and pier head segment.

Land-based Works

·      Construction and installation of pile caps;

·      Pier construction;

·      Re-alignment of Cheung Tung Road;

·      Installation of pier head segment; and

·      Slope work of Viaduct A.

3.2                                      Key Issues for the Coming Quarter

Potential environmental impacts arising from the above upcoming construction activities are mainly associated with air quality, noise, marine water quality, marine ecology and waste management issues.

3.3                                      Monitoring Schedule for the Coming Quarter

Impact monitoring for air quality, noise, marine water quality and dolphin monitoring are scheduled to continue for the next reporting period.

The monitoring programme has been reviewed and was considered as adequate to cater for the nature of works in progress.

4                                            Conclusions and recommendations

4.1                                      Conc lusions

This Seventh Quarterly EM&A Report presents the findings of the EM&A activities undertaken during the period from 1 June to 31 August 2015, in accordance with the Updated EM&A Manual and the requirements of the Environmental Permit (EP-354/2009/D).

Neither Action Level nor Limit Level exceedances were observed for air quality, noise and water quality monitoring in this reporting period.

A total of twelve (12) groups of forty-two (42) Chinese White Dolphins were sighted during the six sets of survey from June to August 2015.  Whilst one (1) Limit Level exceedance was recorded for the quarterly dolphin monitoring data between June and August 2015, no unacceptable impact from the activities of this Contract on Chinese White Dolphins was noticeable from the general observations.  It is critical to monitor the dolphin usage in North Lantau region in the upcoming quarters, to determine whether the dolphins are continuously affected by the various construction activities in relation to the HZMB-related works, and whether suitable mitigation measure can be applied to revert the situation.

Environmental site inspection was carried out thirteen (13) times in the reporting period.  Recommendations on remedial actions were given to the Contractor for the deficiencies identified during the site audits.

One (1) environmental complaint regarding dust emission from vehicles of this Project was received in the reporting period.

The monitoring programme has been reviewed and was considered as adequate to cater for the nature of works in progress.  Change to the monitoring programme was thus not recommended at this stage.  The monitoring programme will be evaluated as appropriate in the next reporting period.  The ET will keep track on the construction works to confirm compliance of environmental requirements and the proper implementation of all necessary mitigation measures.


 


([1]) Agreement No. CE 35/2011 (EP) Baseline Environmental Monitoring for Hong Kong - Zhuhai - Macao Bridge Hong Kong Projects - Investigation.  Baseline Environmental Monitoring Report (Version C).  Submitted on 8 March 2012 and subsequently approved by EPD.

([2]) Agreement No. CE 35/2011 (EP) Baseline Environmental Monitoring for Hong Kong - Zhuhai - Macao Bridge Hong Kong Projects - Investigation.  Baseline Environmental Monitoring Report (Version C).  Submitted on 8 March 2012 and subsequently approved by EPD.

([3]) Agreement No. CE 35/2011 (EP) Baseline Environmental Monitoring for Hong Kong - Zhuhai - Macao Bridge Hong Kong Projects - Investigation.  Baseline Environmental Monitoring Report (Version C).  Submitted on 8 March 2012 and subsequently approved by EPD.