TABLE OF CONTENTS

                        Executive Summary                                                              

1                      Introduction                                                                           

1.1                   Background                                                                            

1.2                   Scope of Report                                                                    

1.3                   Organization Structure                                                   

1.4                   Summary of Construction Works                                

1.5                   Summary of EM&A Programme Requirements          

2                      EM&A RESULTS                                                                          

2.1                   Air Quality                                                                               

2.2                   Noise Monitoring                                                                   

2.3                   Water Quality Monitoring                                               

2.4                   Dolphin Monitoring                                                              

2.5                   EM&A Site Inspection                                                           

2.6                   Waste Management Status                                              

2.7                   Environmental Licenses and Permits                         

2.8                   Implementation Status of Environmental Mitigation Measures   

2.9                   Summary of Exceedances of the Environmental Quality Performance Limit                                                                                             

2.10                 Summary of Complaints, Notification of Summons and Successful Prosecutions                                                                          

3                      Future Key Issues                                                                 

3.1                   Construction Activities for the Coming Quarter

3.2                   Key Issues for the Coming Quarter                             

3.3                   Monitoring Schedule for the Coming Quarter      

4                      Conclusions and recommendations                           

4.1                   Conclusions                                                                            

                                                  


List of Appendices

 

Appendix A       Project Organization for Environmental Works

Appendix B       Three Month Rolling Construction Programmes

Appendix C       Implementation Schedule of Environmental Mitigation Measures (EMIS)

Appendix D       Summary of Action and Limit Levels

Appendix E       EM&A Monitoring Schedules

Appendix F       Impact Air Quality Monitoring Results and Graphical Presentation

Appendix G       Impact Noise Monitoring Results and Graphical Presentation

Appendix H      Impact Water Quality Monitoring Results and Graphical Presentation

Appendix I         Impact Dolphin Monitoring Survey Results

Appendix J        Event Action Plan

Appendix K       Quarterly Summary of Waste Flow Table

Appendix L        Cumulative Statistics on Exceedances, Complaints, Notifications of Summons and Successful Prosecutions

 

Executive Summary

Under Contract No. HY/2012/07, Gammon Construction Limited (GCL) is commissioned by the Highways Department (HyD) to undertake the design and construction of the Southern Connection Viaduct Section of the Tuen Mun – Chek Lap Kok Link Project (TM-CLK Link Project) while AECOM Asia Company Limited was appointed by HyD as the Supervising Officer.  For implementation of the environmental monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong, Limited (ERM) has been appointed as the Environmental Team (ET).  Ramboll Hong Kong Ltd. was employed by the HyD as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) in accordance with Environmental Permit No. EP-354/2009/A.  Further applications for variation of environmental permit (VEP), EP-354/2009/B, EP-354/2009/C and EP-354/2009/D, were granted on 28 January 2014, 10 December 2014 and 13 March 2015, respectively.

The southern landfall of TM-CLK Link lies alongside the Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary Crossing Facilities (HKBCF) where a reclamation area is constructed by Contract No. HY/2010/02 under Environmental Permit No. EP-353/2009/K and EP-354/2009/D.  Upon the agreement and confirmation between the Supervising Officer Representatives and Contractors of HY/2010/02 and HY/2012/07 in September 2015, part of the reclamation area for southern landfall under EP-353/2009/K and EP-354/2009/D was handed-over to Contract No. HY/2012/07.  Another part of the southern landfall area under EP-354/2009/D was handed-over to Contract No. HY/2012/07 after completion of reclamation works by Contract No. HY/2010/02 in June 2016.

The construction phase of the Contract commenced on 31 October 2013 and will be tentatively completed by 2019.  The impact monitoring of the EM&A programme, including air quality, noise, water quality and marine ecological monitoring as well as environmental site inspections, commenced on 31 October 2013.

This is the Twenty-third Quarterly EM&A Report presenting the EM&A works carried out during the period from 1 June to 31 August 2019 for the Southern Connection Viaduct Section in accordance with the Updated EM&A Manual of the TM-CLK Link Project.  As informed by the Contractor, major activities in the reporting period included:

June 2019

Marine-based Works

·             Reinstatement of seawall at Seafront

Land-based Works

·             At-grade works at HKBCF; and

·             Landscaping softwork.

July 2019

Land-based Works

·             Reinstatement of seawall at Seafront.

August 2019

There are no major works undertaken in August 2019.

A summary of monitoring and audit activities conducted in the reporting period is listed below:

24-hour TSP monitoring                            16 sessions

1-hour TSP monitoring                              17 sessions

Noise monitoring                                  17 sessions

Water quality monitoring                            36 sessions

Dolphin monitoring                                     6 sessions

Joint Environmental site inspection      13 sessions

 

Breaches of Action and Limit Levels for Air Quality

One (1) Limit Level exceedance of 1-hour TSP was recorded for construction air quality monitoring in the reporting period.  No exceedance of Action and Limit Levels of 24-hour TSP was recorded in the reporting period.

Breaches of Action and Limit Levels for Noise

No exceedance of Action and Limit Levels was recorded for construction noise monitoring in the reporting period.

Breaches of Action and Limit Levels for Water Quality

A total of thirty one (31) Action Level exceedances and three (3) Limit Level exceedances of bottom-depth dissolved oxygen (DO) and fifteen (15) Action Level exceedance of surface and middle-depth DO were recorded for water quality impact monitoring in the reporting period.

Impact Dolphin Monitoring

One (1) Limit Level exceedance was observed for the quarterly dolphin monitoring data between June to August 2019.  No unacceptable impact from the construction activities of the TM-CLKL Southern Connection Viaduct Section on Indo-Pacific humpback dolphin Sousa chinensis (i.e. Chinese White Dolphins) was noticeable from general observations during the dolphin monitoring in this reporting quarter. 

Daily marine mammal exclusion zone monitoring was undertaken during the period of marine works under this Contract.  Exclusion zone monitoring was undertaken in June 2019 and no sighting of the Chinese White Dolphin was recorded.  No marine works were undertaken in July and August 2019, therefore, daily 250m marine mammal exclusion zone monitoring was not undertaken in July and August 2019.  No Passive Acoustic Monitoring (PAM) was implemented as the marine piling works were not carried out outside the daylight hours in this reporting period. 

Environmental Complaints, Non-compliance & Summons

There was no environmental complaint, notification of summons or successful prosecution recorded in the reporting period.

Reporting Change

There was no reporting change in this reporting period.

Upcoming Works for the Next Reporting Period

Works to be undertaken in the coming quarter include the following:

September 2019

There are no major works to be undertaken in the next monitoring period of September 2019.

October 2019

There are no major works to be undertaken in the next monitoring period of October 2019.

November 2019

There are no major works to be undertaken in the next monitoring period of November 2019.

Future Key Issues

Potential environmental impacts arising from the above upcoming construction activities in the coming quarterly period are mainly associated with waste management issue.

 


1             Introduction

1.1         Background

According to the findings of the Northwest New Territories (NWNT) Traffic and Infrastructure Review conducted by the Transport Department, Tuen Mun Road, Ting Kau Bridge, Lantau Link and North Lantau Highway would be operating beyond capacity after 2016.  This forecast has been based on the estimated increase in cross boundary traffic, developments in the Northwest New Territories (NWNT), and possible developments in North Lantau, including the Airport developments, the Lantau Logistics Park (LLP) and the Hong Kong – Zhuhai – Macao Bridge (HZMB).  In order to cope with the anticipated traffic demand, two new road sections between NWNT and North Lantau – Tuen Mun – Chek Lap Kok Link (TM-CLKL) and Tuen Mun Western Bypass (TMWB) are proposed.

An Environmental Impact Assessment (EIA) of TM-CLKL (the Project) was prepared in accordance with the EIA Study Brief (No. ESB-175/2007) and the Technical Memorandum of the Environmental Impact Assessment Process (EIAO-TM).  The EIA Report was submitted under the Environmental Impact Assessment Ordinance (EIAO) in August 2009.  Subsequent to the approval of the EIA Report (EIAO Register Number: AEIAR-146/2009), an Environmental Permit (EP-354/2009) for TM-CLKL was granted by the Director of Environmental Protection (DEP) on 4 November 2009, and EP variation (EP-354/2009A) was issued on 8 December 2010.  Further applications for variation of environmental permit (VEP), EP-354/2009/B, EP-354/2009/C and EP-354/2009/D, were granted on 28 January 2014, 10 December 2014 and 13 March 2015, respectively.

Under Contract No. HY/2012/07, Gammon Construction Limited (GCL) is commissioned by the Highways Department (HyD) to undertake the design and construction of the Southern Connection Viaduct Section of TM-CLKL (“the Contract”) while AECOM Asia Company Limited was appointed by HyD as the Supervising Officer.  For implementation of the environmental monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong, Limited (ERM) has been appointed as the Environmental Team (ET).  Ramboll Hong Kong Ltd. was employed by HyD as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) in accordance with Environmental Permit No. EP-354/2009/A.

The southern landfall of TM-CLK Link lies alongside the Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary Crossing Facilities (HKBCF) where a reclamation area is constructed by Contract No. HY/2010/02 under Environmental Permit No. EP-353/2009/K and EP-354/2009/D.  Upon the agreement and confirmation between the Supervising Officer Representatives and Contractors of HY/2010/02 and HY/2012/07 in September 2015, part of the reclamation area for southern landfall under EP-353/2009/K and EP-354/2009/D was handed-over to Contract No. HY/2012/07.  Another part of the southern landfall area under EP-354/2009/D was handed-over to Contract No. HY/2012/07 after completion of reclamation works by Contract No. HY/2010/02 in June 2016.

The construction phase of the Contract commenced on 31 October 2013 and will be tentatively be completed by 2019.  The impact monitoring phase of the EM&A programme, including air quality, noise, water quality and marine ecological monitoring as well environmental site inspections, commenced on 31 October 2013.

The general layout plan of the Contract components is presented in Figures 1.1 & 1.2a to l.

1.2         Scope of Report

This is the Twenty-third Quarterly EM&A Report under the Contract No. HY/2012/07 Tuen Mun – Chek Lap Kok Link – Southern Connection Viaduct Section.  This report presents a summary of the environmental monitoring and audit works from 1 June to 31 August 2019.

1.3         Organization Structure

The organization structure of the Contract is shown in Appendix A.  The key personnel contact names and contact details are summarized in Table 1.1 below.

Table 1.1 Contact Information of Key Personnel

Party

Position

Name

Telephone

Fax

HyD (Highways Department)

Project Coordinator

Stanley Chan

2762 3406

3188 6614

 

Senior Engineer

Steven Shum

 

2762 4133

3188 6614

SOR

(AECOM Asia Company Limited)

 

Chief Resident Engineer

Daniel Ip

3553 3800

2492 2057

 

Resident Engineer

 

Chan Wah Fu

2293 6434

3691 2899

 

Resident Engineer

Ivan Yim

3691 3950

3691 2899

 

 

 

 

 

ENPO / IEC

(Ramboll Hong Kong Ltd.)

ENPO Leader

 

Y.H. Hui

3465 2850

3465 2899

IEC

Dr. F.C. Tsang

3465 2851

3465 2899

Contractor

(Gammon Construction Limited)

Environmental Officer

 

Roy Leung

3520 0387

3520 0486

 

24-hour Complaint Hotline

 

 

9738 4332

 

ET (ERM-HK)

ET Leader

Dr. Jasmine Ng

2271 3311

2723 5660

1.4         Summary of Construction Works

The construction phase of the Contract commenced on 31 October 2013.  The rolling construction programme for the period of June to August 2019 is shown in Appendix B.

As informed by the Contractor, details of the major works carried out in this reporting period are listed below:

June 2019

Marine-based Works

·           Reinstatement of seawall at Seafront

Land-based Works

·           At-grade works at HKBCF; and

·           Landscaping softwork.

July 2019

Land-based Works

·           Reinstatement of seawall at Seafront.

August 2019

There are no major works undertaken in August 2019.

The locations of the construction activities are shown in Figure 1.3.  The Environmental Sensitive Receivers in the vicinity of the Project are shown in Figure 1.4.

The environmental mitigation measures implementation schedule is presented in Appendix C.

1.5         Summary of EM&A Programme Requirements

The EM&A programme required environmental monitoring for air quality, noise, water quality and marine ecology as well as environmental site inspections for air quality, noise, water quality, waste management, marine ecology and landscape and visual impacts.  The EM&A requirements and related findings for each component are described in the following sections, which include:

·           Monitoring parameters;

·           Monitoring schedules for the reporting months and forthcoming months;

·           Action and Limit levels for all environmental parameters;

·           Event Action Plan;

·           Results and observations;

·           Environmental mitigation measures, as recommended in the approved EIA Report; and

·           Environmental requirement in contract documents.

Figure 1.3       Locations of Construction Activities in the Reporting Period


2              EM&A RESULTS

The EM&A programme required environmental monitoring for air quality, noise, water quality and marine ecology as well as environmental site inspections for air quality, noise, water quality, waste management, marine ecology and landscape and visual impacts.  The EM&A requirements and related findings for each component are summarized in the following sections.

2.1         Air Quality

The baseline air quality monitoring undertaken by the HZMB Projects during October 2011 included the two monitoring stations ASR9A and ASR9C for this Project.  Thus, the baseline monitoring results and Action/Limit Level presented in HZMB Baseline Monitoring Report ([1]) are adopted for this Project.

2.1.1                     Monitoring Requirements and Equipment

In accordance with the Updated EM&A Manual, impact 1-hour TSP monitoring was conducted three (3) times every six (6) days while the highest dust impact was expected.  Impact 24-hour TSP monitoring was carried out once every six (6) days.  The Action and Limit Levels of the air quality monitoring is provided in Appendix D.

1-hour TSP and 24-hour TSP monitoring were conducted at 2 alternative air quality monitoring stations, ASR8A (Area 4) and ASR9 (entrance of MTR Depot) during the reporting period in accordance with the requirement of the Updated EM&A Manual.  The monitoring stations are indicated in Figure 2.1 and details are presented in Table 2.1.

High Volume Samplers (HVSs) were used for carrying out 1-hour and 24-hour TSP monitoring during the reporting period.  The HVSs meets all requirements of the Updated EM&A Manual.  Brand and model of the equipment are given in Table 2.2.

Wind data monitoring equipment was installed at Area 4 during the reporting period for logging wind speed and wind direction.  The wind sensor was setup such that it was clear of obstructions or turbulence caused by building.  The wind data monitoring equipment is recalibrated at least once every six months.

 

Table 2.1        Locations of Impact Air Quality Monitoring Stations and Monitoring Dates in this Reporting Period

Monitoring Station (1)

Monitoring Period (2)

Location

Description

Parameters & Frequency

ASR8A

4, 10, 13, 19, 25 and 28 June 2019

4, 10, 16, 22, 25 and 31 July 2019

6, 12, 15, 21 and 27 August 2019

Area 4

On ground at the works area, Area 4

Ÿ  1-hour Total Suspended Particulates (1-hour TSP, µg/m3), 3 times per day every 6 days

Ÿ  24-hour Total Suspended Particulates (24-hour TSP, µg/m3), daily for 24-hour every 6 days

ASR9

4, 10, 13, 19, 25 and 28 June 2019

4, 10 and 16 July 2019

MTR Depot

On the ground nearby MTR Depot entrance

Note: 

(1)  Air Quality Monitoring Stations ASR9A and ASR9C at Siu Ho Wan MTRC Depot proposed in accordance with the Updated EM&A were relocated to ASR9 and ASR8A respectively.

(2)  Air quality monitoring of 1-hour and 24-hour TSP at ASR9 was cancelled on 22, 25, 31 July and in August due to power shortage while air quality monitoring of 24-hour TSP at ASR8A was cancelled on 31 July 2019 due to adverse weather.

Table 2.2      Air Quality Monitoring Equipment

Equipment

Brand and Model

High Volume Sampler
(1-hour TSP and 24-hour TSP)

Tisch Environmental Mass Flow Controlled Total Suspended Particulate (TSP) High Volume Sampler (Model No. TE-5170)

 

Wind Sensor

Global Water (Wind Speed Sensor: WE550; Wind Direction Sensor: WE570)

 

Wind Anemometer for calibration

Lutron (Model No. AM-4201)

2.1.2                     Action & Limit Levels

The Action and Limit Levels of the air quality monitoring are provided in Appendix D.  The Event and Action plan is presented in Appendix J.

2.1.3                     Monitoring Schedule for the Reporting Quarter

The schedules for air quality monitoring in the reporting quarter are provided in Appendix E.  Air quality monitoring of 1-hour and 24-hour TSP at ASR9 was cancelled on 22, 25, 31 July and in August due to power shortage while air quality monitoring of 24-hour TSP at ASR8A was cancelled on 31 July 2019 due to adverse weather.  There are no construction works under this Contract starting in August 2019.  EPD have approved the temporary suspension of Air Quality Monitoring on 28 August 2019.

2.1.4                     Results and Observations

The monitoring results for 1-hour TSP and 24-hour TSP are summarized in Tables 2.3 and 2.4, respectively.  Monitoring results are presented graphically in Appendix F.  Detailed impact air quality monitoring results and meteorological information were reported in the Sixty-eighth to Seventieth Monthly EM&A Reports.

Table 2.3        Summary of 1-hour TSP Monitoring Results in this Reporting Period

Month

Station

Average (µg/m3)

Range (µg/m3)

Action Level  (µg/m3)

Limit Level  (µg/m3)

June 2019

ASR 8A

35

14-95

394

500

ASR 9

109

14-752

393

500

July 2019

ASR 8A

48

14-138

394

500

ASR 9

63

15-96

393

500

August 2019

ASR 8A

53

14-144

394

500

Table 2.4        Summary of 24-hour TSP Monitoring Results in this Reporting Period

Month

Station

Average (µg/m3)

Range (µg/m3)

Action Level  (µg/m3)

Limit Level  (µg/m3)

June 2019

ASR 8A

25

16-39

178

260

ASR 9

62

22-152

178

260

July 2019

ASR 8A

29

19-42

178

260

ASR 9

41

33-48

178

260

August 2019

ASR 8A

34

26-39

178

260

The major dust sources in the reporting period include construction activities under the Contract as well as nearby traffic emissions.

One (1) Limit Level exceedance of 1-hour TSP was recorded for air quality monitoring in this reporting period.  No exceedance of Action and Limit Levels of 24-hour TSP was recorded in the reporting period.  The exceedance was considered not related to this Contract upon further investigation and the investigation report is presented in Appendix L.  No action is thus required to be undertaken in accordance with the Event Action Plan presented in Appendix J.


2.2         Noise Monitoring

The baseline noise monitoring undertaken by the HZMB Projects during the period of 18 October to 1 November 2011 included the monitoring station NSR1 for this Project.  Thus, the baseline monitoring results and Action/ Limit Level presented in HZMB Baseline Monitoring Report ([2]) are adopted for this Project.

2.2.1                     Monitoring Requirements and Equipment

In accordance with the Updated EM&A Manual, impact noise monitoring should be conducted once per week during the construction phase of the Contract.

Noise monitoring was conducted at the alternative noise monitoring station, NSR1A (Pak Mong Village Pavilion) during the reporting period in accordance with the requirement of Updated EM&A Manual.  Figure 2.2 shows the location of the monitoring station.  Table 2.5 describes the details of the monitoring station.

Noise monitoring was performed using sound level meter at the designated monitoring station in the reporting quarter.  The deployed sound level meter complies with the International Electrotechnical Commission Publications (IEC) 651:1979 (Type 1) and 804:1985 (Type 1) specifications.  Acoustic calibrator was deployed to check the sound level meter at a known sound pressure level.  Brand and model of the equipment is given in Table 2.6.


Table 2.5      Location of Impact Noise Monitoring Station and Monitoring Dates in this Reporting Period

Monitoring Station

Monitoring Period

Location

Parameters & Frequency

NSR1A

4, 10, 13, 19, 25 and 28 June 2019

4, 10, 16, 22, 25 and 31 July 2019

6, 12, 15, 21 and 27 August 2019

Pak Mong Village Pavilion

Ÿ   30-mins measurement at each monitoring station between 0700 and 1900 on normal weekdays (Monday to Saturday). Leq, L10 and L90 would be recorded.

Ÿ   At least once a week

Note:

(1)    Noise Monitoring Station NSR1 at Pak Mong Village proposed in accordance with the Updated EM&A Manual was relocated to NSR1A.

Table 2.6      Noise Monitoring Equipment

2.2.2                     Action and Limit Levels

The Action and Limit levels of the noise monitoring are provided in Appendix D.  The Event and Action plan is presented in Appendix J.

2.2.3                     Monitoring Schedule for the Reporting Quarter

The schedule for construction noise monitoring in the reporting period is provided in Appendix E.  EPD have approved the temporary suspension of Impact Noise Monitoring on 28 August 2019. 

2.2.4                     Results and Observations

The monitoring results for noise monitoring are summarized in Table 2.7.  Monitoring results are presented graphically in Appendix G and detailed impact noise monitoring results are reported in the Sixty-eighth to Seventieth Monthly EM&A Reports.

Table 2.7         Summary of Construction Noise Monitoring Results at NSR1A in the Reporting Period

Month

Average , dB(A), Leq (30mins)

Range, dB(A), Leq (30mins)

Limit Level, dB(A), Leq (30mins)

June 2019

63

62-63

75

July 2019

63

62-65

75

August 2019

63

62-63

75

Major noise sources during the noise monitoring included noise from nearby traffic noise and aircraft noise.
All noise monitoring results were below the Action and Limit Levels in the reporting period.  No action is thus required to be undertaken in accordance with the Event Action Plan presented in Appendix J.

2.3         Water Quality Monitoring

The baseline water quality monitoring undertaken by the HZMB Projects between 6 and 31 October 2011 included all monitoring stations except SR4a for the Project.  Thus, the baseline monitoring results except for station SR4a and Action/Limit Level presented in HZMB Baseline Monitoring Report ([3]) are adopted for this Project.  Baseline water quality monitoring was conducted at station SR4a from 29 August to 24 September 2013.

2.3.1                     Monitoring Requirements and Equipment

Impact water quality monitoring was carried out to ensure that any deterioration of water quality was detected, and that timely action was taken to rectify the situation.  Impact water quality monitoring was undertaken three days per week during the construction period at seven water quality monitoring stations in accordance with the Updated EM&A Manual.

Results of water quality monitoring were adopted from the published EM&A data of Contract No. HY/2012/08 Tuen Mun-Chek Lap Kok Link – Northern Connection Sub-sea Tunnel Section ([4]) in July and August 2019.

The locations of the monitoring stations under the Contract are shown in Figure 2.3 and Table 2.8.

Table 2.8        Locations of Water Quality Monitoring Stations and the Corresponding Monitoring Requirements

Station ID

Type

Coordinates

*Parameters, unit

Depth

Frequency

 

 

Easting

Northing

 

 

 

IS(Mf)9

Impact Station (Close to HKBCF construction site)

813273

818850

Ÿ Temperature(°C)

Ÿ pH(pH unit)

Ÿ Turbidity (NTU)

Ÿ Water depth (m)

Ÿ Salinity (ppt)

Ÿ Dissolved Oxygen (DO) (mg/L and % of

saturation)

·    Suspended Solid (SS) (mg/L)

3 water depths: 1m

below sea surface,

mid-depth and 1m

above sea bed.  If the water depth is less than 3m, mid-depth sampling only.  If water depth less than 6m, mid-depth may be omitted.

 

 

Impact monitoring: 3 days per week, at mid-flood and mid-ebb tides during the construction period of the Contract.

IS(Mf)16

Impact Station (Close to HKBCF construction site)

814328

819497

IS8

Impact Station(Close to HKBCF construction site)

814251

818412

IS8 (N)

Impact Station (Close to HKBCF construction site)

814413

818570

SR4(N)

Sensitive receiver (Tai Ho Inlet)

814705

817859

SR4(N2)

Sensitive receiver (Tai Ho Inlet)

814688

817996

SR4a

Sensitive receiver

815247

818067

CS(Mf)3(N)

 

Control Station

808814

822355

CS(Mf)5

Control Station

817990

821129

Notes:

In addition to the parameters presented monitoring location/position, time, water depth, sampling depth, tidal stages, weather conditions and any special phenomena or works underway nearby were also recorded.

Water Quality Monitoring Station CS(Mf)3 was relocated to CS(Mf)3(N) since 2 May 2017.

Water Quality Monitoring Station SR4 was relocated to SR4(N) since 2 March 2018.

Water Quality Monitoring Station SR4(N) was relocated to SR4(N2) since 12 June 2019

Water Quality Monitoring Station IS8 was relocated to IS8(N) since 12 June 2019.

Table 2.9 summarizes the equipment used in the impact water quality monitoring programme.

Table 2.9        Water Quality Monitoring Equipment

Equipment

Brand and Model

Multi-parameters

(Dissolved Oxygen, Salinity, Turbidity, Temperature, pH)

YSI ProDSS

Positioning Equipment

Furuno GP-170

 

Water Depth Detector

Lowrance Mark 5x / Garmin Striker 4

 

Water Sampler

WildCo Vertical Alpha Bottles 1120-2.2L /1120-3.2L

Aquatic Research Instrument Vertical/Horizontal Point Water Sampler 2.2L / 3.0L

 

2.3.2                     Action & Limit Levels

The Action and Limit Levels of the water quality monitoring are provided in Appendix D.

2.3.3                     Monitoring Schedule for the Reporting Quarter

The schedules for water quality monitoring in the reporting quarter are provided in Appendix EWater quality monitoring on 7 June 2019 was cancelled due to suspension of marine works during holiday.  EPD have approved the temporary suspension of Water Quality Monitoring on 30 August 2019 as all marine-based construction activities under this Contract has been completed.

2.3.4                     Results and Observations

In this reporting period, a total of 36 monitoring events for impact water quality monitoring were conducted at monitoring stations in the reporting period.  Monitoring results are presented graphically in Appendix H and detailed impact water quality monitoring results were reported in the Sixty-eighth to Seventieth Monthly EM&A Reports.

A total of thirty one (31) Action Level exceedances and three (3) Limit Level exceedances of bottom-depth dissolved oxygen (DO) and fifteen (15) Action Level exceedance of surface and middle-depth DO were recorded for water quality impact monitoring in the reporting period.  The exceedances were considered not related to this Contract upon further investigation and the investigation report is presented in Appendix L.  No actions was required to be undertaken in accordance with the Event Action Plan as presented in Appendix J.

2.4         Dolphin Monitoring

2.4.1                     Monitoring Requirements

Impact dolphin monitoring is required to be conducted by a qualified dolphin specialist team to evaluate whether there have been any effects on the Indo-Pacific humpback dolphin Sousa chinensis (i.e. Chinese White Dolphin) from the Contract.  In order to fulfil the EM&A requirements and make good use of available resources, the on-going impact line transect dolphin monitoring data collected by HyD’s Contract No. HY/2011/03 Hong Kong-Zhuhai-Macao Bridge. Hong Kong Link Road - Section between Scenic Hill and Hong Kong Boundary Crossing Facilities on the monthly basis is adopted to avoid duplicates of survey effort.

2.4.2                     Monitoring Equipment

Table 2.10 summarizes the equipment used for the impact dolphin monitoring.

Table 2.10      Dolphin Monitoring Equipment

Equipment

Model

Global Positioning System (GPS)

 

Camera

 

Laser Binoculars

Marine Binocular

Vessel for Monitoring

 

Garmin 18X-PC

Geo One Phottix

Nikon D90 300m 2.8D fixed focus

Nikon D90 20-300m zoom lens

Infinitor LRF 1000

Bushell 7 x 50 marine binocular with compass and reticules

65 foot single engine motor vessel with viewing platform 4.5m above water level

2.4.3                     Monitoring Parameter, Frequencies & Duration

Dolphin monitoring should cover all transect lines in Northeast Lantau (NEL) and the Northwest Lantau (NWL) survey areas twice per month throughout the entire construction period.  The monitoring data should be compatible with, and should be made available for, long-term studies of small cetacean ecology in Hong Kong.  In order to provide a suitable long-term dataset for comparison, identical methodology and line transects employed in baseline dolphin monitoring was followed in the impact dolphin monitoring.

2.4.4                     Monitoring Location

The impact dolphin monitoring was carried out in the NEL and NWL along the line transect as depicted in Figure 2.4.  The co-ordinates of all transect lines are shown in Table 2.11 below ([5]).


Table 2.11      Impact Dolphin Monitoring Line Transect Co-ordinates

Line No.

Easting

Northing

Line No.

Easting

Northing

1

Start Point

804671

815456

13

Start Point

816506

819480

1

End Point

804671

831404

13

End Point

816506

824859

2

Start Point

805476

820800

14

Start Point

817537

820220

2

End Point

805476

826654

14

End Point

817537

824613

3

Start Point

806464

821150

15

Start Point

818568

820735

3

End Point

806464

822911

15

End Point

818568

824433

4

Start Point

807518

821500

16

Start Point

819532

821420

4

End Point

807518

829230

16

End Point

819532

824209

5

Start Point

808504

821850

17

Start Point

820451

822125

5

End Point

808504

828602

17

End Point

820451

823671

6

Start Point

809490

822150

18

Start Point

821504

822371

6

End Point

809490

825352

18

End Point

821504

823761

7

Start Point

810499

822000

19

Start Point

822513

823268

7

End Point

810499

824613

19

End Point

822513

824321

8

Start Point

811508

821123

20

Start Point

823477

823402

8

End Point

811508

824254

20

End Point

823477

824613

9

Start Point

812516

821303

21

Start Point

805476

827081

9

End Point

812516

824254

21

End Point

805476

830562

10

Start Point

813525

821176

22

Start Point

806464

824033

10

End Point

813525

824657

22

End Point

806464

829598

11

Start Point

814556

818853

23

Start Point

814559

821739

11

End Point

814556

820992

23

End Point

814559

824768

12

Start Point

815542

818807

24 

Start Point

805476

815900

12

End Point

815542

824882

 24

End Point

805476

819100

2.4.5                     Action & Limit Levels

The Action and Limit levels of dolphin impact monitoring are shown in Appendix D.  The Event and Action plan is presented in Appendix J.

2.4.6                     Monitoring Schedule for the Reporting Period

The dolphin monitoring schedules for the reporting period are shown in Appendix E

.

2.4.7                     Results & Observations

A total of 785.23 km of survey effort was collected, with 96.0% of the total survey effort being conducted under favourable weather conditions (i.e. Beaufort Sea State 3 or below with good visibility).  Among the two areas, 287.33 km and 497.90 km of survey effort were conducted in NEL and NWL survey areas respectively.  The total survey effort conducted on primary lines was 577.21 km, while the effort on secondary lines was 208.02 km.  Survey effort conducted on both primary and secondary lines were considered as on-effort survey data.  The survey efforts are summarized in Appendix I.

During the six sets of monitoring surveys in June to August 2019, a total of four (4) groups of eight (8) Chinese White Dolphins were sighted.  Three (3) dolphin sightings were made during on-effort and two (2) on-effort dolphin sightings were made on primary lines.  In this quarterly period, all dolphin groups were sighted in NWL, no sighting of dolphin was sighted in NEL.  Summary table of the dolphin sightings is shown in Appendix II of Appendix I.

Encounter rates of Chinese White Dolphins deduced from the survey effort and on-effort sighting data from the primary transect lines under favourable conditions (Beaufort 3 or below) in the reporting period with the results presented in Tables 2.12 and 2.13.

Table 2.12      Individual Survey Event Encounter Rates

Survey Area

Survey period

Encounter rate (STG)     (no. of on-effort dolphin sightings per 100 km of survey effort)

Encounter rate (ANI)            (no. of dolphins from all on-effort sightings per 100 km of survey effort)

Primary Lines Only

Primary Lines Only

NEL

Set 1: 3rd / 6th Jun 2019

0.0

0.0

Set 2: 10th / 13th Jun 2019

0.0

0.0

Set 3: 16th /18th Jul 2019

0.0

0.0

Set 4: 22nd/ 24th Jul 2019

0.0

0.0

Set 5: 13th / 14th Aug 2019

0.0

0.0

Set 6: 20th/ 26th/ 29th Aug 2019

0.0

0.0

NWL

Set 1: 3rd / 6th Jun 2019

3.73

9.32

Set 2: 10th / 13th Jun 2019

0.00

0.00

Set 3: 16th /18th Jul 2019

0.00

0.00

Set 4: 22nd/ 24th Jul 2019

0.00

0.00

Set 5: 13th / 14th Aug 2019

0.00

0.00

Set 6: 20th/ 26th/ 29th Aug 2019

0.00

0.00

Note:  Dolphin Encounter Rates are deduced from the six sets of surveys (two surveys in each set) in the reporting period in Northeast (NEL) and Northwest Lantau (NWL)


Table 2.13      Quarterly Average Encounter Rates

Survey Area

Encounter rate (STG)        (no. of on-effort dolphin sightings per 100 km of survey effort)

Encounter rate (ANI)            (no. of dolphins from all on-effort sightings per 100 km of survey effort)

June - August 2019

September -November 2011

June - August 2019

September -November 2011

Northeast Lantau

0.0

6.00 ± 5.05

0.0

22.19 ± 26.81

Northwest Lantau

0.62 ± 1.52

9.85 ± 5.85

1.55 ± 3.80

44.66 ± 29.85

Note: encounter rates deduced from the baseline monitoring period (September – November 2011) have been recalculated based only on survey effort and on-effort sighting data made along the primary transect lines under favourable conditions

Group size of Chinese White Dolphins ranged from one (1) to four (4) individuals per group in North Lantau region during June to August 2019.  The average dolphin group sizes from these three months were compared with the ones deduced from the baseline period in September to November 2011, as shown in Table 2.14.

Table 2.14      Comparison of Quarterly Average Group Sizes

 

Average Dolphin Group Size

June to August 2019

September - November 2011

Overall

2.00 ± 1.41 (n = 4)

3.72 ± 3.13 (n = 66)

Northeast Lantau

---

3.18 ± 2.16 (n = 17)

Northwest Lantau

2.00 ± 1.41 (n = 4)

3.92 ± 3.40 (n = 49)

One (1) Limit Level exceedance was observed for the quarterly dolphin monitoring data between June to August 2019.
During this quarter of dolphin monitoring, no unacceptable impact from the activities of this Contract on Chinese White Dolphins was noticeable from the general observations.

Although the dolphins infrequently occurred along the alignment of TM-CLKL Southern Connection Viaduct in the past and during the baseline monitoring period, it is apparent that dolphin usage has been significantly reduced in both NEL and NWL, and many individuals have shifted away from the important habitat around the Brothers Islands.

It is critical to monitor the dolphin usage in North Lantau region in the upcoming quarters, to determine whether the dolphins are continuously affected by the various construction activities in relation to the HZMB-related works, and whether suitable mitigation measure can be applied to revert the situation.

2.4.8                     Marine Mammal Exclusion Zone Monitoring

Daily marine mammal exclusion zone monitoring was undertaken in June 2019.  No sighting of Chinese White Dolphin was recorded in the monitoring period during the exclusion zone monitoring.  No marine works were undertaken in July and August 2019, therefore, daily 250 m marine mammal exclusion zone monitoring was not undertaken in July and August 2019.

Passive Acoustic Monitoring (PAM) was decommissioned in this reporting period as no marine piling works was carried out outside the daylight hours since September 2015.  Daytime marine mammal exclusion zone was still in effect to cater for temporary staging installation and uninstallation works.

2.5         EM&A Site Inspection

Site inspections were carried out on a weekly basis to monitor the implementation of proper environmental pollution control and mitigation measures under the Contract.  Thirteen (13) site inspections were carried out in the reporting quarter on 5, 12, 18 and 27 June, 4, 10, 17, 25 and 29 July and 7, 15, 22 and 29 August 2019.

Key observations during the site inspections in this reporting period are summarized in Table 2.15.

Table 2.15        Specific Observations Identified during the Weekly Site Inspection in this Reporting Period

Inspection Date

Location & Environmental Observations

Recommendations/ Remarks

5 June 2019

Viaduct D

Ÿ   General refuse was observed.

Ÿ   Silt was observed in the U-channel

Viaduct D

Ÿ   The Contractor was reminded to clear general refuse.

Ÿ   The Contractor was reminded to clear the silt inside U-channel.

12 June 2019

WA4

Ÿ   Chemical without drip tray.

 

WA4

Ÿ   The Contractor was reminded to place chemicals in drip tray and remove empty chemical container off site.

18 June 2019

Seafront

Ÿ   The silt curtain should be properly extended.

Viaduct D

Ÿ   Accumulated refuse should be cleared.

Ÿ   Chemical without drip tray.

Seafront

Ÿ   The Contractor was reminded to properly extend the silt curtain.

Viaduct D

Ÿ   The Contractor was reminded to clear accumulated refuse.

Ÿ   The Contract was reminded to place chemical in drip tray.

27 June 2019

Seafront

Ÿ   NRMM label should be displayed on the excavator.

 

Seafront

Ÿ   The Contractor was reminded to display

the NRMM label on the excavator.

4 July 2019

WA1

Ÿ   Tyre marks were observed at the exit of the works area.

Ÿ   Accumulated waste should be cleared.

WA2

Ÿ   Rubbish and dirt was observed in the U-channel.

WA1

Ÿ  The Contractor was reminded to clear the tyre marks at the exit of the works area.

Ÿ  The Contractor was reminded to clear the accumulated waste.

WA2

Ÿ  The Contractor was reminded to clear the rubbish and dirt in the U-channel.

10 July 2019

No observation.

No observation.

17 July 2019

Viaduct D

Ÿ   General refuse is observed on the ground.

Viaduct D

Ÿ   The Contractor was reminded to clear general refuse on the ground.

25 July 2019

BCF

Ÿ   Accumulated general refuse should be cleared or disposed in rubbish bin.

BCF

Ÿ   The Contractor was reminded to clear accumulated general refuse or dispose them in the rubbish bin.

29 July 2019

CEDD Track

Ÿ   Soil stockpile should be covered with tarpaulin or removed.

CEDD Track

Ÿ   The Contractor was reminded to cover soil stockpile with tarpaulin or to remove the soil stockpile.

7 August 2019

BCF

Ÿ   Accumulated water in the drip tray should be discharged.

BCF

Ÿ   The Contractor was reminded to discharge accumulated water in the drip tray.

15 August 2019

Seafront

Ÿ   Chemical container was observed without drip tray.

Ÿ   General refuse was observed on the ground.

 

Seafront

Ÿ   The Contractor was reminded to place chemical container in drip tray.

Ÿ   The Contractor was reminded to place general refuse in capped rubbish bin.

22 August 2019

WA1

Ÿ   Accumulated waste should be cleared.

Ÿ   Chemical container should be placed in drip tray.

 

WA1

Ÿ   The Contractor was reminded to clear accumulated refuse.

Ÿ   The Contractor was reminded to place chemical container in drip tray.

29 August 2019

BCF

Ÿ   Accumulated refuse should be cleared or disposed in capped rubbish bin.

BCF

Ÿ   The Contractor was reminded to clear accumulated refuse or disposed refuse in capped rubbish bin.

The Contractor has rectified all of the observations identified during environmental site inspections in the reporting period.

2.6         Waste Management Status

The Contractor has submitted application form for registration as chemical waste producer under the Contract.  Sufficient numbers of receptacles were available for general refuse collection and sorting.

Wastes generated during this reporting period include mainly construction wastes (inert and non-inert), recyclable materials, chemical waste and marine sediment.  Reference has been made to the waste flow table prepared by the Contractor (Appendix K).  The quantities of different types of wastes are summarized in Table 2.16.

Table 2.16                 Quantities of Different Waste Generated in the Reporting Period

Month/

Year

Inert C&D Materials (a) (m3)

Imported Fill (m3)

Inert Construction Waste Re-used

(m3)

Non-inert Construction Waste (b) (kg)

Recyclable Materials (c)  (kg)

Chemical Wastes (kg)

Marine Sediment (m3)

Category L

Category M

(Mp & Mf)

Category H

June 2019

356

0

315

39,960

0

0

0

0

0

July 2019

0

0

0

17,100

0

0

0

0

0

August 2019

0

0

0

31,050

0

0

0

0

0

Notes:

(a)  Inert construction wastes include hard rock and large broken concrete, and materials disposed as public fill.

(b)  Non-inert construction wastes include general refuse disposed at landfill.

(c)   Recyclable materials include metals, paper, cardboard, plastics, timber, felled trees and others.

The Contractor was advised to properly maintain on site C&D materials and waste collection, sorting and recording system, dispose of C&D materials and wastes at designated ground and maximize reuse/ recycle of C&D materials and wastes.  The Contractor was also reminded to properly maintain the site tidiness and dispose of the wastes accumulated on site regularly and properly.

For chemical waste containers, the Contractor was reminded to treat properly and store temporarily in designated chemical waste storage area on site in accordance with the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes.

2.7         Environmental Licenses and Permits

The status of environmental licensing and permit is summarized in Table 2.17 below.

Table 2.17        Summary of Environmental Licensing and Permit Status

License/ Permit

License or Permit No.

Date of Issue

Date of Expiry

License/ Permit Holder

Remarks

Environmental Permit

EP-353/2009/K

11-Apr-16

N/A

HyD

Hong Kong Boundary Crossing Facilities

Environmental Permit

EP-354/2009/D

13-Mar-15

N/A

HyD

Tuen Mun- Chek Lap Kok Link

Construction Dust Notification

361571

05-Jul-13

N/A

GCL

 

Construction Dust Notification

362093

17-Jul-13

N/A

GCL

For Area 23

Chemical Waste Registration

5213-951-G2380-17

12-Jun-14

N/A

GCL

Viaducts A, B, C, D & E

Chemical Waste Registration

5213-961-G2380-13

10-Oct-13

N/A

GCL

Chemical waste produced in Contract No. HY/2012/07  (Area 1 adjacent to Cheng Tung Road, Siu Ho Wan)

Chemical Waste Registration

5213-961-G2380-14

10-Oct-13

N/A

GCL

Chemical waste produced in Contract No. HY/2012/07  (Area 2 adjacent to Cheung Tung Road, Pak Mong Village)

Chemical Waste Registration

5213-974-G2588-03

04-Nov-13

N/A

GCL

Chemical waste produced in Contract No. HY/2012/07  (WA5 adjacent to Cheung Tung Road, Yam O)

Construction Waste Disposal Account

7017735

10-Jul-13

N/A

GCL

-

Construction Waste Disposal Account

7019470

03-Mar-14

N/A

GCL

Vessel CHIT Account

Construction Noise Permit for night works and works in general holidays

GW-RS0149-19

19 February 2019

15 July 2019

GCL

Broad Permit for Whole Site Areas

Construction Noise Permit for night works and works in general holidays

GW-RS0507-19

13 June 2019

11 December 2019

GCL

Broad Permit for Whole Site Areas

Construction Noise Permit for night works and works in general holidays

GW-RW012-19

23 January 2019

13 June 2019

GCL

General works at WA5

Construction Noise Permit for night works and works in general holidays

GW-RW0266-19

21 June 2019

13 December 2019

GCL

General works at WA5

Construction Noise Permit for night works and works in general holiday            

GW-RS0728-19

16 August 2019

25 October 2019

GCL

Defect repairing at under-bridge of Viaduct A, B, C and D

 

Equipment

Brand and Model

Integrated Sound Level Meter

Rion NL-52

 

Acoustic Calibrator

Rion NC-73


2.8         Implementation Status of Environmental Mitigation Measures

In response to the site audit findings, the Contractor has carried out corrective actions.

A summary of the Environmental Mitigation and Enhancement Measure Implementation Schedules (EMIS) is presented in Appendix C.  The necessary mitigation measures were implemented properly for this Contract.

2.9         Summary of Exceedances of the Environmental Quality Performance Limit

One (1) Limit Level exceedance of 1-hour TSP was recorded for construction air quality monitoring in the reporting period.  No exceedance of Action and Limit Levels of 24-hour TSP was recorded in the reporting period.

No Action or Limit Level exceedance for construction noise monitoring was recorded during the reporting period.

A total of thirty one (31) Action Level exceedances and three (3) Limit Level exceedances of bottom-depth dissolved oxygen (DO) and fifteen (15) Action Level exceedance of surface and middle-depth DO were recorded for water quality impact monitoring in the reporting period.

The construction impact on depth-averaged SS was assessed by comparing the quarterly mean values of depth-averaged SS with the relevant ambient mean values (Table 2.18).  The monitoring results showed that the quarterly means of depth-averaged SS at all sampling stations during both mid-ebb and mid-flood tides were well below the corresponding ambient means.  The depth-averaged SS results suggest that the Contract did not cause unacceptable impact on water quality in the reporting period.

Table 2.18        Comparison between Quarterly Mean and Ambient Mean Values of Depth-averaged Suspended Solids

Station

Baseline Mean

Ambient Mean (a)

Quarterly Mean (June to August 2019)

Mid-ebb

Mid-flood

Mid-ebb

Mid-flood

Mid-ebb

Mid-flood

CS(Mf)3(N) (b)

9.2

12.8

12.0

16.6

5.6

6.5

CS(Mf)5

9.2

11.5

11.9

14.9

5.8

5.1

SR4(N)/

SR4(N2) (c)(d)

10.3

12.3

13.4

16.0

7.6

6.6

SR4a

9.1

9.8

11.9

12.7

6.9

6.3

IS8/

IS8(N) (e)

11.3

13.5

14.6

17.6

7.8

6.6

IS(Mf)9

10.9

14.3

14.2

18.5

6.6

6.5

IS(Mf)16

11.4

10.3

14.8

13.4

7.8

7.1

Notes:

(a)  Ambient mean value is defined as a 30% increase of the baseline mean value

(b)  Water Quality Monitoring Station CS(Mf)3 was relocated to CS(Mf)3(N) since 2 May 2017.

(c)   Water Quality Monitoring Station SR4 was relocated to SR4(N) since 2 March 2018.

(d)  Water Quality Monitoring Station SR4(N) was relocated to SR4(N2) since 12 June 2019.

(e)  Water Quality Monitoring Station IS8 was relocated to IS8(N) since 12 June 2019.

One (1) Limit Level exceedance was recorded for impact dolphin monitoring in this reporting quarter.  Following the review of the monitoring data and marine works details as per the procedure stipulated in the Event and Action Plan of the Updated EM&A Manual, no unacceptable impact was associated with the construction works under this Contract that may have affected the dolphin usage in the North Lantau region.  Investigation findings were detailed in Appendix L.

2.10       Summary of Complaints, Notification of Summons and Successful Prosecutions

The Environmental Complaint Handling Procedure is provided in Figure 2.5.

There was no complaint, notification of summons or successful prosecution recorded in the reporting period.

Statistics on complaint, notification of summons of successful prosecution are summarized in Appendix L.

 

3              Future Key Issues

3.1         Construction Activities for the Coming Quarter

As informed by the Contractor, the major works for the Contract in the coming quarter are summarized below:

September 2019

There are no major works to be undertaken in the next monitoring period of September 2019.

October 2019

There are no major works to be undertaken in the next monitoring period of October 2019.

November 2019

There are no major works to be undertaken in the next monitoring period of November 2019.

3.2         Key Issues for the Coming Quarter

Potential environmental impacts arising from the above upcoming construction activities are mainly associated with waste management issues.

3.3         Monitoring Schedule for the Coming Quarter

Impact monitoring for dolphin monitoring is scheduled to continue for the next reporting period.

Impact monitoring for air quality and noise were temporarily suspended.  EPD have approved the temporary suspension of Air Quality Monitoring and Impact Noise Monitoring on 28 August 2019.

Impact monitoring for marine water quality was temporarily suspended.  EPD have approved the temporary suspension of Water Quality Monitoring on 30 August 2019.

The monitoring programme has been reviewed and was considered as adequate to cater for the nature of works in progress.

 

 

4              Conclusions and recommendations

4.1         Conclusions

The Twenty-third Quarterly EM&A Report presents the findings of the EM&A activities undertaken during the period from 1 June to 31 August 2019, in accordance with the Updated EM&A Manual and the requirements of the Environmental Permits (EP-354/2009/D and EP-353/2009/K).

One (1) Limit Level exceedance of 1-hour TSP was recorded for construction air quality monitoring in the reporting period.  No exceedance of Action and Limit Levels of 24-hour TSP was recorded in the reporting period.

No Action or Limit Level exceedance for construction noise monitoring was recorded during the reporting period.

A total of thirty one (31) Action Level exceedances and three (3) Limit Level exceedances of bottom-depth dissolved oxygen (DO) and fifteen (15) Action Level exceedance of surface and middle-depth DO were recorded for water quality impact monitoring in the reporting period.

A total of four (4) groups of eight (8) Chinese White Dolphins were sighted during the six sets of survey from June to August 2019.  One (1) Limit Level exceedance was recorded for the quarterly dolphin monitoring data between June to August 2019, no unacceptable impact from the activities of this Contract on Chinese White Dolphins was noticeable from the general observations.  It is critical to monitor the dolphin usage in North Lantau region in the upcoming quarters, to determine whether the dolphins are continuously affected by the various construction activities in relation to the HZMB-related works, and whether suitable mitigation measure can be applied to revert the situation.

Environmental site inspection was carried out thirteen (13) times in the reporting period.  Recommendations on remedial actions were given to the Contractor for the deficiencies identified during the site audits.

There was no complaint, notification of summons or successful prosecution recorded in the reporting period.

The monitoring programme has been reviewed and was considered as adequate to cater for the nature of works in progress.  Change to the monitoring programme was thus not recommended at this stage.  The monitoring programme will be evaluated as appropriate in the next reporting period.  The ET will keep track on the construction works to confirm compliance of environmental requirements and the proper implementation of all necessary mitigation measures.

 


([1])      Agreement No. CE 35/2011 (EP) Baseline Environmental Monitoring for Hong Kong - Zhuhai - Macao Bridge Hong Kong Projects - Investigation.  Baseline Environmental Monitoring Report (Version C).  Submitted on 8 March 2012 and subsequently approved by EPD.

([2])    Agreement No. CE 35/2011 (EP) Baseline Environmental Monitoring for Hong Kong - Zhuhai - Macao Bridge Hong Kong Projects - Investigation.  Baseline Environmental Monitoring Report (Version C).  Submitted on 8 March 2012 and subsequently approved by EPD.

([3])     Agreement No. CE 35/2011 (EP) Baseline Environmental Monitoring for Hong Kong - Zhuhai - Macao Bridge Hong Kong Projects - Investigation.  Baseline Environmental Monitoring Report (Version C).  Submitted on 8 March 2012 and subsequently approved by EPD.

([4])     Published EM&A data for water quality monitoring by Contract No. HY/2012/08 are available at: http://www.hzmbenpo.com/

([5])      Proposal on the changes of transect lines for dolphin monitoring was approved by EPD on

          28 July 2017 (Reference number: (19) in EP2/G/A/129 Pt. 8).