Table of Contents

                        Executive Summary                                                              

1                  Introduction                                                                           

1.1                Background                                                                            

1.2                Scope of Report                                                                    

1.3                Organization Structure                                                   

1.4                Summary of Construction Works                                

1.5                Summary of EM&A Programme Requirements          

2                  EM&A RESULTS                                                                          

2.1                Air Quality                                                                                

2.2                Noise Monitoring                                                                   

2.3                Water Quality Monitoring                                                

2.4                Dolphin Monitoring                                                              

2.5                EM&A Site Inspection                                                            

2.6                Waste Management Status                                              

2.7                Environmental Licenses and Permits                         

2.8                Implementation Status of Environmental Mitigation Measures                                                                                  

2.9                Summary of Exceedances of the Environmental Quality Performance Limit                                               

2.10              Summary of Complaints, Notification of Summons and Successful Prosecutions                                                

3                  Comparison of EM&A Results with EIA Predictions and Baseline Monitoring Results                                         

3.1                Air Quality Monitoring                                                       

3.2                Noise Impact Monitoring                                                    

3.3                Water Quality Monitoring                                                

3.4                Marine Ecology                                                                     

3.5                Waste Management                                                              

3.6                Summary of Monitoring Methodology and Effectiveness                                                                         

3.7                Summary of Mitigation Measures                                  

4                  Future Key Issues                                                                 

4.1                Key Issues for the coming period                                 

5                  Conclusion and Recommendations                              


 

List of Appendices

Appendix A       Project Organization for Environmental Works

Appendix B       Implementation Schedule of Environmental Mitigation Measures (EMIS)

Appendix C       Summary of Action and Limit Levels

Appendix D       Post-Construction Water Quality Monitoring Results in Graphical Presentation

Appendix E       Event Action Plan

Appendix F      Summary of Waste Flow Table

Appendix G       Cumulative Statistics on Exceedances, Complaints, Notifications of Summons and Successful Prosecutions

 

Executive Summary

Under Contract No. HY/2012/07, Gammon Construction Limited (GCL) is commissioned by the Highways Department (HyD) to undertake the design and construction of the Southern Connection Viaduct Section of the Tuen MunChek Lap Kok Link Project (TM-CLK Link Project) while AECOM Asia Company Limited was appointed by HyD as the Supervising Officer.  For implementation of the environmental monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong, Limited (ERM) has been appointed as the Environmental Team (ET).  Ramboll Hong Kong Ltd. was employed by the HyD as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) in accordance with Environmental Permit No. EP-354/2009/A.  Further applications for variation of environmental permit (VEP), EP-354/2009/B, EP-354/2009/C and EP-354/2009/D, were granted on 28 January 2014, 10 December 2014 and 13 March 2015, respectively.

The southern landfall of TM-CLK Link lies alongside the Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary Crossing Facilities (HKBCF) where a reclamation area is constructed by Contract No. HY/2010/02 under Environmental Permit No. EP-353/2009/K and EP-354/2009/D.  Upon the agreement and confirmation between the Supervising Officer Representatives and Contractors of HY/2010/02 and HY/2012/07 in September 2015, part of the reclamation area for southern landfall under EP-353/2009/K and EP-354/2009/D was handed-over to Contract No. HY/2012/07.  Another part of the southern landfall area under EP-354/2009/D was handed-over to Contract No. HY/2012/07 after completion of reclamation works by Contract No. HY/2010/02 in June 2016.

The construction phase of the Contract commenced on 31 October 2013.  The impact monitoring of the EM&A programme, including air quality, noise, water quality and marine ecological monitoring as well as environmental site inspections, commenced on 31 October 2013.

This is the Seventh Annual EM&A Report presenting the EM&A works carried out during the period from 1 November 2019 to 16 March 2020 for the Southern Connection Viaduct Section in accordance with the Updated EM&A Manual of the TM-CLK Link Project.  As informed by the Contractor, there were no major works undertaken in the reporting period.

A summary of monitoring and audit activities conducted in the reporting period is listed below:

Post-Construction Water quality monitoring                   12 sessions

Dolphin monitoring                                                  8 sessions

Joint Environmental site inspection ([1])                          18 sessions

Breaches of Action and Limit Levels for Air Quality

No air quality monitoring was scheduled in the reporting period.  Notification of temporary suspension of air quality monitoring has been approved by EPD on 28 August 2019.

Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020.  The construction phase EM&A programme of the Contract has been terminated since 16 March 2020.

Breaches of Action and Limit Levels for Noise

No construction noise monitoring was scheduled in the reporting period.  Notification of temporary suspension of noise monitoring has been approved by EPD on 28 August 2019.

Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020.  The construction phase EM&A programme of the Contract has been terminated since 16 March 2020.

Breaches of Action and Limit Levels for Water Quality

No water quality impact monitoring was scheduled in the reporting period.  Notification of temporary suspension of water quality monitoring has been approved by EPD on 30 August 2019. 

Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020.  The construction phase EM&A programme of the Contract has been terminated since 16 March 2020. 

Impact Dolphin Monitoring

Two (2) Limit Level exceedances for both NEL and NWL regions were recorded between November 2019 and February 2020.  No unacceptable impact from the construction activities of the TM-CLKL Southern Connection Viaduct Section on Indo-Pacific humpback dolphin Sousa chinensis (i.e. Chinese White Dolphin) was noticeable from general observations during the dolphin monitoring in this reporting period.

Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020.  The construction phase EM&A programme of the Contract has been terminated since 16 March 2020.

No marine works were undertaken since July 2019, therefore, daily 250 m marine mammal exclusion zone monitoring was not undertaken since July 2019.  No Passive Acoustic Monitoring (PAM) was implemented as the marine piling works were not carried out outside the daylight hours in this reporting period. 

Environmental Complaints, Non-compliance & Summons

There was no environmental complaints, notification of summons or successful prosecution recorded in the reporting period.

Reporting Change

Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020.  The construction phase EM&A programme of the Contract has been terminated since 16 March 2020.

Future Key Issues

As informed by the Contractor, there were no major works to be undertaken for the Contract in the coming period.

               

1                                                         Introduction

1.1                                                    Background

According to the findings of the Northwest New Territories (NWNT) Traffic and Infrastructure Review conducted by the Transport Department, Tuen Mun Road, Ting Kau Bridge, Lantau Link and North Lantau Highway would be operating beyond capacity after 2016.  This forecast has been based on the estimated increase in cross boundary traffic, developments in the Northwest New Territories (NWNT), and possible developments in North Lantau, including the Airport developments, the Lantau Logistics Park (LLP) and the Hong Kong – Zhuhai – Macao Bridge (HZMB).  In order to cope with the anticipated traffic demand, two new road sections between NWNT and North Lantau – Tuen MunChek Lap Kok Link (TM-CLKL) and Tuen Mun Western Bypass (TMWB) are proposed.

An Environmental Impact Assessment (EIA) of TM-CLKL (the Project) was prepared in accordance with the EIA Study Brief (No. ESB-175/2007) and the Technical Memorandum of the Environmental Impact Assessment Process (EIAO-TM).  The EIA Report was submitted under the Environmental Impact Assessment Ordinance (EIAO) in August 2009.  Subsequent to the approval of the EIA Report (EIAO Register Number: AEIAR-146/2009), an Environmental Permit (EP-354/2009) for TM-CLKL was granted by the Director of Environmental Protection (DEP) on 4 November 2009, and EP variation (EP-354/2009/A) was issued on 8 December 2010.  

Under Contract No. HY/2012/07, Gammon Construction Limited (GCL) is commissioned by the Highways Department (HyD) to undertake the design and construction of the Southern Connection Viaduct Section of TM-CLKL (“the Contract”) while AECOM Asia Company Limited was appointed by HyD as the Supervising Officer.  For implementation of the environmental monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong, Limited (ERM) has been appointed as the Environmental Team (ET).  Ramboll Hong Kong Ltd. was employed by HyD as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) in accordance with Environmental Permit No. EP-354/2009/A.  Further applications for variation of environmental permit (VEP), EP-354/2009/B, EP-354/2009/C and EP-354/2009/D, were granted on 28 January 2014, 10 December 2014 and 13 March 2015, respectively.

The southern landfall of TM-CLK Link lies alongside the Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary Crossing Facilities (HKBCF) where a reclamation area is constructed by Contract No. HY/2010/02 under Environmental Permit No. EP-353/2009/K and EP-354/2009/D.  Upon the agreement and confirmation between the Supervising Officer Representatives and Contractors of HY/2010/02 and HY/2012/07 in September 2015, part of the reclamation area for southern landfall under EP-353/2009/K and EP-354/2009/D was handed-over to Contract No. HY/2012/07.  Another part of the southern landfall area under EP-354/2009/D was handed-over to Contract No. HY/2012/07 after completion of reclamation works by Contract No. HY/2010/02 in June 2016.

The construction phase of the Contract commenced on 31 October 2013.  The impact monitoring phase of the EM&A programme, including air quality, noise, water quality and marine ecological monitoring as well environmental site inspections, commenced on 31 October 2013.

The general layout plan of the Contract components is presented in Figures 1.1 & 1.2a to l.

1.2                                                    Scope of This Report

This is the Seventh Annual EM&A Report under the Contract No. HY/2012/07 Tuen MunChek Lap Kok Link – Southern Connection Viaduct Section.  This report presents a summary of the environmental monitoring and audit works from 1 November 2019 to 16 March 2020.

1.3                                                    Organization Structure

The organization structure of the Contract is shown in Appendix A.  The key personnel contact names and contact details are summarized in Table 1.1 below.

Table 1.1 Contact Information of Key Personnel

Party

Position

Name

Telephone

Fax

HyD (Highways Department)

Project Coordinator

Stanley Chan

2762 3406

3188 6614

 

Senior Engineer

Steven Shum

 

2762 4133

3188 6614

SOR

(AECOM Asia Company Limited)

 

Chief Resident Engineer

Daniel Ip

3553 3800

2492 2057

 

Resident Engineer

 

Chan Wah Fu

2293 6434

3691 2899

 

 

 

 

 

ENPO / IEC

(Ramboll Hong Kong Ltd.)

ENPO Leader

 

Y.H. Hui

3465 2850

3465 2899

IEC

 

Dr. F.C. Tsang

3465 2851

3465 2899

Environmental Officer

 

Roy Leung

3520 0387

3520 0486

 

24-hour Complaint Hotline

 

 

9738 4332

 

ET (ERM-HK)

ET Leader

Dr. Jasmine Ng

2271 3311

2723 5660

1.4                                                    Summary of Construction Works

As informed by the Contractor, there were no major works undertaken in the reporting period.

The Environmental Sensitive Receivers in the vicinity of the Project are shown in Figure 1.3

The environmental mitigation measures implementation schedule is presented in Appendix B.


1.5                                                    Summary of EM&A Programme Requirements

The EM&A programme required environmental monitoring for air quality, noise, water quality and marine ecology as well as environmental site inspections for air quality, noise, water quality, waste management, marine ecology and landscape and visual impacts.  The EM&A requirements and related findings for each component are described in the following sections, which include:

                        ·              Monitoring parameters;

                        ·              Action and Limit levels for all environmental parameters;

                        ·              Event Action Plan;

                        ·              Tested environmental impact hypotheses;

                        ·              Environmental mitigation measures, as recommended in the approved EIA Report; and

                        ·              Environmental requirement in contract documents.

2                                                         EM&A RESULTS

The EM&A programme required environmental monitoring for air quality, noise, water quality and marine ecology as well as environmental site inspections for air quality, noise, water quality, waste management, marine ecology and landscape and visual impacts.  The EM&A requirements and related findings for each component are summarized in the following sections.

2.1                                                    Air Quality

No air quality monitoring was undertaken in the reporting period.  Notification of temporary suspension of air quality monitoring has been approved by EPD on 28 August 2019. 

Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020.  The construction phase EM&A programme of the Contract has been terminated since 16 March 2020.

2.2                                                    Noise Monitoring

No noise monitoring was undertaken in the reporting period.  Notification of temporary suspension of noise monitoring has been approved by EPD on 28 August 2019.

Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020.  The construction phase EM&A programme of the Contract has been terminated since 16 March 2020.

2.3                                                    Water Quality Monitoring

2.3.1                                          Monitoring Requirements and Equipment

No water quality impact monitoring was undertaken in the reporting period.  Notification of temporary suspension of water quality monitoring has been approved by EPD on 30 August 2019. 

Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020.  The construction phase EM&A programme of the Contract has been terminated since 16 March 2020.

According to the Updated EM&A Manual, a post-construction water quality monitoring shall be carried out upon completion of all marine-based construction activities.  Post-construction water quality monitoring was undertaken three days per week for at least 4 weeks in accordance with the Updated EM&A Manual.  The proposal for post-construction water quality monitoring was approved by EPD on 19 November 2019.    The post-construction water quality monitoring commenced on 27 November 2019 and completed on 23 December 2019.

Details of monitoring stations are provided in Figure 2.1 and Table 2.1.

Table 2.1   Locations of Water Quality Monitoring Stations and the Corresponding Monitoring Requirements

Station ID

Type

Coordinates

*Parameters, unit

Depth

Frequency

 

 

Easting

Northing

 

 

 

IS(Mf)9

Impact Station (Close to HKBCF construction site)

 

813273

818850

Ÿ Temperature(°C)

Ÿ pH(pH unit)

Ÿ Turbidity (NTU)

Ÿ Water depth (m)

Ÿ Salinity (ppt)

Ÿ Dissolved

Oxygen (DO) (mg/L and % of

saturation)

·    Suspended Solid   

(SS) (mg/L)

3 water depths: 1m

below sea surface,

mid-depth and 1m

above sea bed.  If the water depth is less than 3m, mid-depth sampling only.  If water depth less than 6m, mid-depth may be omitted.

Post-construction monitoring: 3 days per week, at mid-flood and mid-ebb tides for 4 weeks.

IS(Mf)16

Impact Station (Close to HKBCF construction site)

 

814328

819497

IS8(N)

Impact Station(Close to HKBCF construction site)

 

814413

818570

SR4(N2)

Sensitive receiver (Tai Ho)

 

815688

817996

SR4a

Sensitive receiver

 

815247

818067

CS(Mf)3(N)

 

Control Station

 

808814

822355

CS(Mf)5

Control Station

817990

821129

Notes:

In addition to the parameters presented monitoring location/position, time, water depth, sampling depth, tidal stages, weather conditions and any special phenomena or works underway nearby were also recorded.

Water Quality Monitoring Station CS(Mf)3 was relocated to CS(Mf)3(N) since 2 May 2017.

Water Quality Monitoring Station SR4 was relocated to SR4(N) since 2 March 2018.

Water Quality Monitoring Station SR4(N) was relocated to SR4(N2) since 12 June 2019.

Water Quality Monitoring Station IS8 was relocated to IS8(N) since 12 June 2019.

Details of the equipment deployed in water quality monitoring are provided in Table 2.2.

Table 2.2     Water Quality Monitoring Equipment

Equipment

Brand and Model

Multi-parameters

(Dissolved Oxygen, Salinity, Turbidity, Temperature, pH)

YSI ProDSS / YSI 6920 V2

 

 

Positioning Equipment

Furuno GP-170

Water Depth Detector

Lowrance Mark 5x / Garmin Striker 4

Water Sampler

WildCo Vertical Alpha Bottles 1120-2.2L /1120-3.2L

Aquatic Research Instrument Vertical/Horizontal Point Water Sampler 2.2L / 3.0L

2.3.2                                          Monitoring Schedule for the Reporting Period

The schedules for water quality monitoring in the reporting period are provided in the Seventy-third to Seventy-fourth Monthly EM&A Reports.  

2.3.3                                          Results and Observations

In this reporting period, a total of 12 monitoring events were undertaken.     Post-construction water quality monitoring was conducted at all designated monitoring stations in the reporting period.  The detailed post-construction water quality monitoring data are presented graphically in Appendix D and was reported in the Seventy-third to Seventy-fourth Monthly EM&A Reports.

2.4                                                  Dolphin Monitoring

2.4.1                                          Monitoring Requirements

Impact dolphin monitoring is required to be conducted by a qualified dolphin specialist team to evaluate whether there have been any effects on the Indo-Pacific humpback dolphin Sousa chinensis (i.e. Chinese White Dolphin) from the Contract.  In order to fulfil the EM&A requirements and make good use of available resources, the impact line transect dolphin monitoring data collected by HyD’s Contract No. HY/2012/08 TMCLKL Northern Connection Sub-Sea Tunnel Section on monthly basis is adopted to avoid duplicates of survey effort between November 2019 and February 2020.

Responsibility for the implementation of dolphin monitoring was changed from Contract No. HY/2011/03 HZMB HKLR Section between Scenic Hill and HKBCF to Contract No. HY/2012/08 TMCLKL Northern Connection Sub-Sea Tunnel Section since October 2019.  The on-going impact line transect dolphin monitoring data collected by HyD’s Contract No. HY/2012/08 TMCLKL Northern Connection Sub-Sea Tunnel Section on the monthly basis is adopted since October 2019.

Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020.  The construction phase EM&A programme of the Contract has been terminated since 16 March 2020.

2.4.2                                          Monitoring Equipment

Table 2.3 summarizes the equipment used for the impact dolphin monitoring.

Table 2.3   Dolphin Monitoring Equipment

Equipment

Model

Global Positioning System (GPS)

 

 

Camera

 

 

Laser Binoculars

 

Marine Binocular

 

 

Vessel for Monitoring

 

Garmin 18X-PC

Geo One Phottix

 

Nikon D90 300m 2.8D fixed focus

Nikon D90 20-300m zoom lens

 

Infinitor LRF 1000

 

Bushell 7 x 50 marine binocular with compass and reticules

 

65 foot single engine motor vessel with viewing platform 4.5m above water level

2.4.3                                          Monitoring Parameter, Frequencies & Duration

The dolphin monitoring covered all transect lines in Northeast Lantau (NEL) and the Northwest Lantau (NWL) survey areas twice per month throughout the entire construction period.  The monitoring data were compatible with, and should be made available for, long-term studies of small cetacean ecology in Hong Kong.  In order to provide a suitable long-term dataset for comparison, identical methodology and line transects employed in baseline dolphin monitoring was followed in the impact dolphin monitoring.

2.4.4                                          Monitoring Location

The impact dolphin monitoring was carried out in the NEL and NWL along the line transect as depicted in Figure 2.2.  The co-ordinates of all transect lines are shown in Table 2.4 ([2]) below.

Table 2.4   Impact Dolphin Monitoring Line Transect Co-ordinates

Line No.

Easting

Northing

Line No.

Easting

Northing

1

Start Point

804671

815456

13

Start Point

816506

819480

1

End Point

804671

831404

13

End Point

816506

824859

2

Start Point

805476

820800

14

Start Point

817537

820220

2

End Point

805476

826654

14

End Point

817537

824613

3

Start Point

806464

821150

15

Start Point

818568

820735

3

End Point

806464

822911

15

End Point

818568

824433

4

Start Point

807518

821500

16

Start Point

819532

821420

4

End Point

807518

829230

16

End Point

819532

824209

5

Start Point

808504

821850

17

Start Point

820451

822125

5

End Point

808504

828602

17

End Point

820451

823671

6

Start Point

809490

822150

18

Start Point

821504

822371

6

End Point

809490

825352

18

End Point

821504

823761

7

Start Point

810499

822000*

19

Start Point

822513

823268

7

End Point

810499

824613

19

End Point

822513

824321

8

Start Point

811508

821123

20

Start Point

823477

823402

8

End Point

811508

824254

20

End Point

823477

824613

9

Start Point

812516

821303

21

Start Point

805476

827081

9

End Point

812516

824254

21

End Point

805476

830562

10

Start Point

813525

821176

22

Start Point

806464

824033

10

End Point

813525

824657

22

End Point

806464

829598

11

Start Point

814556

818853

23

Start Point

814559

821739

11

End Point

814556

820992

23

End Point

814559

824768

12

Start Point

815542

818807

24

Start Point

805476

815900

12

End Point

815542

824882

24

End Point

805476

819100

2.4.5                                          Action & Limit Levels

The Action and Limit levels of dolphin impact monitoring are shown in Appendix C.  The Event Action Plan is presented in Appendix E.

2.4.6                                          Monitoring Schedule for the Reporting Period

The dolphin monitoring schedules for the reporting period are provided in the Seventy-third to Seventy-sixth Monthly EM&A Reports.

2.4.7                                          Results & Observations

In this reporting period, a total of 8 monitoring events were undertaken.     The detailed dolphin monitoring data was reported in the Seventy-third to Seventy-sixth Monthly EM&A Reports.

Two (2) Limit Level exceedances for both NEL and NWL regions were recorded between November 2019 and February 2020.  In this reporting period, no unacceptable impact from the activities of this Contract on Chinese White Dolphins was noticeable from general observations.

2.4.8                                          Marine Mammal Exclusion Zone Monitoring

No marine works were undertaken since July 2019, therefore, daily 250 m marine mammal exclusion zone monitoring was not undertaken since July 2019.  

Passive Acoustic Monitoring (PAM) was not undertaken in this reporting period as no marine piling works was carried out outside the daylight hours since September 2015. 

2.5                                                  EM&A Site Inspection

Site inspections were carried out on weekly basis to monitor the implementation of proper environmental pollution control and mitigation measures under the Contract.  Eighteen (18) site inspections were carried out in the reporting period.  Key observations were summarized in the section of EM&A Site Inspection in the Seventy-third to Seventy-seventh Monthly EM&A Reports.  The Contractor has rectified all of the observations identified during environmental site inspections in the reporting period.

2.6                                                  Waste Management Status

The Contractor had submitted application form for registration as chemical waste producer under the Contract.  Sufficient numbers of receptacles were available for general refuse collection and sorting.

Wastes generated during this reporting period include mainly construction wastes (inert and non-inert), recyclable materials and chemical waste.  Reference has been made to the waste flow table prepared by the Contractor (Appendix F).  The quantities of different types of wastes are summarized in Table 2.5.


 

Table 2.5   Quantities of Different Waste Generated in the Reporting Period

Month/

Year

Inert Construction Waste (a) (m3)

Imported Fill

(m3)

Inert Construction Waste Re-used

(m3)

Non-inert Construction Waste (b) (kg)

Recyclable Materials (c)  (kg)

Chemical Wastes (kg)

Marine Sediment (m3)

Category L

Category M

(Mp & Mf)

Category H

Nov 2019

0

0

0

19,670

0

0

0

0

0

Dec 2019

0

0

0

0

0

0

0

0

0

Jan 2020

0

0

0

12,260

0

0

0

0

0

Feb 2020

48

0

0

0

0

0

0

0

0

Mar 2020

38

0

0

0

0

0

0

0

0

Total

86

0

0

31,930

0

0

0

0

0

Notes:

(a)    Inert construction wastes include hard rock and large broken concrete, and materials disposed as public fill.

(b)    Non-inert construction wastes include general refuse disposed at landfill.

(c)    Recyclable materials include metals, paper, cardboard, plastics, timber and others.

The Contractor was advised to properly maintain on site C&D materials and waste collection, sorting and recording system, dispose of C&D materials and wastes at designated ground and maximize reuse/ recycle of C&D materials and wastes.  The Contractor was also reminded to properly maintain the site tidiness and dispose of the wastes accumulated on site regularly and properly.

For chemical waste containers, the Contractor was reminded to treat properly and store temporarily in designated chemical waste storage area on site in accordance with the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes.

2.7                                                  Environmental Licenses and Permits

The status of environmental licensing and permit is summarized in Table 2.6 below.


Table 2.6   Summary of Environmental Licensing and Permit Status

License/ Permit

License or Permit No.

Date of Issue

Date of Expiry

License/ Permit Holder

Remarks

Environmental Permit

EP-353/2009/K

11-Apr-16

N/A

HyD

Hong Kong Boundary Crossing Facilities

Environmental Permit

EP-354/2009/D

13-Mar-15

N/A

HyD

Tuen Mun- Chek Lap Kok Link

Chemical Waste Registration

5213-951-G2380-17

12-Jun-14

N/A

GCL

Viaducts A, B, C, D & E

Chemical Waste Registration

5213-961-G2380-13

10-Oct-13

N/A

GCL

Chemical waste produced in Contract HY/2012/07 (Area 1 adjacent to Cheng Tung Road, Siu Ho Wan)

Chemical Waste Registration

5213-961-G2380-14

10-Oct-13

N/A

GCL

Chemical waste produced in Contract HY/2012/07 (Area 2 adjacent to Cheung Tung Road, Pak Mong Village)

Chemical Waste Registration

5213-974-G2588-03

04-Nov-13

N/A

GCL

Chemical waste produced in Contract HY/2012/07  (WA5 adjacent to Cheung Tung Road, Yam O)

Construction Dust Notification

361571

05-Jul-13

N/A

GCL

 

Construction Dust Notification

362093

17-Jul-13

N/A

GCL

For Area 23

Construction Waste Disposal Account

7017735

10-Jul-13

N/A

GCL

-

Construction Waste Disposal Account

7019470

03-Mar-14

N/A

GCL

Vessel CHIT Account

Construction Noise Permit for night works and works in general holidays

GW-RW0266-19

21-Jun-19

13-Dec-19

GCL

General works at WA5

Construction Noise Permit for night works and works in general holidays

GW-RW0592-19

18-Dec-19

13-Jun-20

GCL

General works at WA5

Construction Noise Permit for night works and works in general holidays

GW-RS0507-19

13-Jun-19

11-Dec-19

GCL

Broad Permit for Whole Site Areas

Construction Noise Permit for night works and works in general holidays

GW-RS1108-19

12-Dec-19

11-Jun-20

GCL

Broad Permit for Whole Site Areas

Construction Noise Permit for night works and works in general holidays

GW-RS0977-19

7-Nov-19

16-Dec-19

GCL

Defect Repairing at under-bridge of Viaduct A, B, C and D

Construction Noise Permit for night works and works in general holidays

GW-RS1214-19

16-Jan-20

14-Feb-20

GCL

Defect Repairing at under-bridge of Viaduct B and C

Construction Noise Permit for night works and works in general holidays

GW-RS0153-20

19-Mar-20

31-Mar-20

GCL

Defect Repairing at under-bridge of Viaduct B and C

Construction Noise Permit for night works and works in general holidays

GW-RS1067-19

2-Dec-19

31-Dec-19

GCL

Resurfacing Works at Pak Mong


2.8                                                  Implementation Status of Environmental Mitigation Measures

A summary of the Environmental Mitigation and Enhancement Measure Implementation Schedules (EMIS) is presented in Appendix B.  The necessary mitigation measures were implemented properly for this Contract.

2.9                                                  Summary of Exceedances of the Environmental Quality Performance Limit

No air quality and noise impact monitoring was conducted in the reporting period.

Post-construction water quality monitoring was completed on 23 December 2019

Two (2) Limit Level exceedances for both NEL and NWL regions were recorded for impact dolphin monitoring for both NEL and NWL regions.  No unacceptable impact from the construction activities of the TM-CLKL Southern Connection Viaduct Section on Chinese White Dolphins was noticeable from general observations during the dolphin monitoring in this reporting period.  Detailed investigation reports were presented in Appendix J of Twenty-fourth to Twenty-fifth Quarterly EM&A Reports.

2.10                                              Summary of Complaints, Notification of Summons and Successful Prosecutions

The Environmental Complaint Handling Procedure is provided in Figure 2.3.

There was no environmental complaints, notification of summons or successful prosecution received in the reporting period.

Statistics on complaints, notifications of summons, successful prosecutions are summarized in Appendix G.

3                                                         Comparison of EM&A Results with EIA Predictions and Baseline Monitoring Results

The EM&A results in the reporting period are compared to the predictions from EIA Report and baseline monitoring result in order to review the validity of EIA predictions.

3.1                                                  Air Quality Monitoring

No air quality monitoring was undertaken in the reporting period.  Notification of temporary suspension of air quality monitoring has been approved by EPD on 28 August 2019. 

Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020.  The construction phase EM&A programme of the Contract has been terminated since 16 March 2020.

3.2                                                  Noise Impact Monitoring

No noise monitoring was undertaken in the reporting period.  Notification of temporary suspension of noise monitoring has been approved by EPD on 28 August 2019.

Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020.  The construction phase EM&A programme of the Contract has been terminated since 16 March 2020.

3.3                                                  Water Quality Monitoring

No water quality impact monitoring was scheduled in the reporting period.  Notification of temporary suspension of water quality monitoring has been approved by EPD on 30 August 2019. 

Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020.  The construction phase EM&A programme of the Contract has been terminated since 16 March 2020.

3.4                                                  Marine Ecology

According to the baseline results in the Appendix F of the approved EIA Report, the dolphin groups were largely sighted near waters around Lung Kwu Chau and Sha Chau.  There was no dolphin sighted along the alignment of this Contract. 

In this reporting period, a total of 8 monitoring events were undertaken.     The detailed dolphin monitoring data was reported in the Seventy-third to Seventy-fourth Monthly EM&A Reports.

Two (2) Limit Level exceedances for both NEL and NWL regions were recorded between November 2019 and February 2020.  In this reporting period, no unacceptable impact from the activities of this Contract on Chinese White Dolphins was noticeable from general observations.

3.5                                                  Waste Management

In general, wastes generated from the construction activities including C&D materials (inert and non-inert), chemical wastes, marine sediment and recyclable materials.  The summary of waste generation amount is presented in Table 2.5.

Waste monitoring and audit programme has been undertaken during this reporting period.  Wastes arising from this Project have been managed in accordance with the recommendations in the EIA Report, the EM&A Manual, the Waste Management Plan and other relevant statutory requirements.

The requirements for construction waste management have been reviewed and were considered as adequate.  No change to the requirements was considered to be necessary.

3.6                                                  Summary of Monitoring Methodology and Effectiveness

The EM&A monitoring programme has been reviewed and was considered effective and adequate to cater for the nature of works in progress.  No further change to the monitoring programme was considered to be necessary.

3.7                                                  Summary of Mitigation Measures

The mitigation measures stipulated in the Updated EM&A Manual were undertaken by the Contractor in the reporting period.  The mitigation measures were reviewed and considered effective. 

4                                                         Future Key Issues

4.1                                                  Key Issues for the coming period

As informed by the Contractor, there were no major works to be undertaken for the Contract in the coming period.

5                                                         Conclusion and Recommendations

This Seventh Annual EM&A Report presents findings of the EM&A activities undertaken during the period from 1 November 2019 to 16 March 2020, in accordance with the Updated EM&A Manual and the requirements of the Environmental Permits (EP-354/2009/D and EP-353/2009/K).

No Air quality (1-hour TSP and 24-hour TSP) and noise monitoring were carried out in the reporting period. 

Post-construction water quality monitoring (DO, turbidity and SS) and dolphin monitoring were carried out in the reporting period.

Two (2) Limit Level exceedances for both NEL and NWL regions were recorded between November 2019 and February 2020, whilst no unacceptable impact from the activities of this Contract on Chinese White Dolphins was noticeable from the general observations. 

Environmental site inspection was carried out eighteen (18) times in the reporting period.  Recommendations on remedial actions were given to the Contractor for the deficiencies identified during the site audits.

There was no environmental complaints, notification of summons or successful prosecution received during the reporting period.

The review of monitoring data suggested that the construction works under this Contract have proceeded in an environmentally acceptable manner in this reporting period.  In general, the monitoring results were in line with EIA predictions.

The monitoring programme has been reviewed and was considered as adequate to cater for the nature of works in progress. 

Termination proposal for construction EM&A programme was approved by EPD on 16 March 2020.  The construction phase EM&A programme of the Contract has been terminated since 16 March 2020.

 

 



([1])      The joint environmental site inspection scheduled on 31 January 2020 was cancelled due to site closure during outbreak of novel coronavirus (COVID-19) caused by severe acute respiratory syndrome coronavirus 2 (SARS-CoV-2).

([2])        Proposal on the changes of transect lines for dolphin monitoring was approved by EPD on

          28 July 2017 (Reference number: (19) in EP2/G/A/129 Pt. 8).