table of Contents

                        Executive Summary                                                              

1                      Introduction                                                                           

1.1                   Background                                                                            

1.2                   Scope of Report                                                                    

1.3                   Organization Structure                                                   

1.4                   Summary of Construction Works                                

2                      EM&A Results                                                                          

2.1                   Air quality                                                                               

2.2                   Water Quality Monitoring                                               

2.3                   Dolphin Monitoring                                                              

2.4                   EM&A Site Inspection                                                           

2.5                   Waste Management Status                                              

2.6                   Environmental Licenses and Permits                         

2.7                   Implementation Status of Environmental Mitigation Measures   

2.8                   Summary of Exceedances of the Environmental Quality Performance Limit                                                                                             

2.9                   Summary of Complaints, Notification of Summons and Successful Prosecutions                                                                          

3                      Future Key Issues                                                                 

3.1                   Construction Activities for the Coming Quarter

3.2                   Key Issues for the Coming Quarter                             

3.3                   Monitoring Schedule for the Coming Quarter      

4                      Conclusions                                                                            

 

 

Appendix A       Project Organization

Appendix B       Construction Programme

Appendix C       Environmental Mitigation And Enhancement Measure Implementation Schedules (EMIS)

Appendix D       Action And Limit Levels

Appendix E        Monitoring Schedule

Appendix F        Air Quality Monitoring Results

Appendix G       Water Quality Monitoring Results

Appendix H      Impact Dolphin Monitoring

Appendix I         Event And Action Plan                                                 

Appendix J    Cumulative Statistics On Exceedance And Complaint

Appendix K       Waste Flow Table

 

Executive Summary

Under Contract No. HY/2012/08, Dragages – Bouygues Joint Venture (DBJV) is commissioned by the Highways Department (HyD) to undertake the design and construction of the Northern Connection Sub-sea Tunnel Section of the Tuen Mun – Chek Lap Kok Link Project (TM-CLK Link Project) while AECOM Asia Company Limited was appointed by HyD as the Supervising Officer.  For implementation of the environmental monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong, Limited (ERM) has been appointed as the Environmental Team (ET) in accordance with Environmental Permit No. EP-354/2009/A. Ramboll Hong Kong Ltd. was employed by HyD as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO).  Subsequent applications for variation of environmental permits (VEP), EP-354/2009/B, EP-354/2009/C and EP-354/2009/D, were granted on 28 January 2014, 10 December 2014 and 13 March 2015, respectively.  

The construction phase of the Contract commenced on 1 November 2013 and will tentatively be completed in early 2020.  The impact monitoring of the EM&A programme, including air quality, water quality, marine ecological monitoring and environmental site inspections, were commenced on 1 November 2013.

This is the Twenty-fourth Quarterly EM&A report presenting the EM&A works carried out during the period from 1 September 2019 to 30 November 2019 for the Contract No. HY/2012/08 Northern Connection Sub-sea Tunnel Section (the “Contract”) in accordance with the Updated EM&A Manual of the TM-CLK Link Project.  As informed by the Contractor, the major activities in the reporting quarter included:

Land-based Works

·         Construction of Thermal barrier – TBM tunnel;

·         Construction of Walkway Corbel & Cover – TBM Tunnel;

·         Road & Drainage works – Portion N-A and Portion S-C;

·         Gantry Crane Removal – Portion N-A;

·         RC structure – Portion S-A;

·         E&M Platform Installation – Portion S-A;

·         Backfilling – Portion S-A & S-C;

·         Water Treatment Facilities Dismantling – Portion S-C; and

·         Cut & Cover Tunnel RC structure – Portion S-C

 

Marine-based Works

·         Seawall Modification Works – Portion S-B

A summary of monitoring and audit activities conducted in the reporting period is listed below:

                           

24-hour TSP Monitoring                            30 sessions

1-hour TSP Monitoring                              30 sessions

Water Quality Monitoring                          39 sessions

Impact Dolphin Monitoring                        6 sessions

Joint Environmental Site Inspection         13 sessions

Implementation of Marine Mammal Exclusion Zone

Daily marine mammal exclusion zone was in effect during the period of silt curtain installation in open waters under this Contract.  No sighting of the Indo-Pacific humpback dolphin (i.e. Chinese White Dolphin) was recorded in the reporting period during the exclusion zone monitoring.

Summary of Breaches of Action/Limit Levels

Breaches of Action and Limit Levels for Air Quality

Eight (8) Action level and four (4) Limit Level exceedances of 1-hour TSP and were recorded in this reporting period.  Investigation reports are provided in Appendix J.

Breaches of Action and Limit Levels for Water Quality

Thirty-five (35) Action level of Dissolved Oxygen were recorded in this reporting period.  Four (4) Action Level exceedance for Depth-averaged suspended solids was recorded.  Investigation reports are provided in Appendix J.

Dolphin Monitoring

Whilst one (1) Limit Level exceedance was observed for the quarterly dolphin monitoring data between September and November 2019, no unacceptable impact from the construction activities of the TM-CLKL Northern Connection Sub-sea Tunnel Section on Chinese White Dolphins was noticeable from general observations during the dolphin monitoring in this reporting quarter.

Environmental Complaints, Non-compliance & Summons

No non-compliance with EIA recommendations, EP conditions and other requirements associated with the construction of this Contract was recorded in this reporting period.

No environmental complaint was received in this reporting period.

No environmental summons was received in this reporting period.

 

Reporting Change

Water quality monitoring was carried out in the reporting period in view of the commencement of seawall modification works since 12 August 2019.  

Contract No. HY/2012/08 has taken over the responsibility for implementation of dolphin monitoring from HZMB HKLR Contract No. HY/2011/03 since October 2019.

Upcoming Works for the Next Reporting Period

Works to be undertaken in the coming quarterly period include the following:

Land-based Works

·         Construction of Thermal barrier – TBM tunnel;

·         Construction of Walkway Corbel & Cover – TBM Tunnel;

·         Road & Drainage works – Portion N-A

·         Gantry Crane Removal – Portion N-B & Portion S-C;

·         RC structure – Portion S-A;

·         E&M Platform Installation – Portion S-A

·         Backfilling – Portion S-A & S-C;

·         Water Treatment Facilities Dismantling – Portion S-C;

·         Cut & Cover Tunnel RC structure – Portion S-C

·         Tower Crane Removal – Portion S-C

 

Marine-based Works

·         Seawall Modification Works – Portion S-B

 

Future Key Issues

Potential environmental impacts arising from the above upcoming construction activities in the coming quarterly period are expected to be mainly associated with dust, marine ecology, marine water quality and waste management issues.

                                     


1                             Introduction

1.1                         Background

According to the findings of the Northwest New Territories (NWNT) Traffic and Infrastructure Review conducted by the Transport Department, Tuen Mun Road, Ting Kau Bridge, Lantau Link and North Lantau Highway would be operating beyond capacity after 2016.  This forecast has been based on the estimated increase in cross boundary traffic, developments in the Northwest New Territories (NWNT), and possible developments in North Lantau, including the Airport developments, the Lantau Logistics Park (LLP) and the Hong Kong – Zhuhai – Macao Bridge (HZMB).  In order to cope with the anticipated traffic demand, two new road sections between NWNT and North Lantau – Tuen Mun – Chek Lap Kok Link (TM-CLKL) and Tuen Mun Western Bypass (TMWB) are proposed.

An Environmental Impact Assessment (EIA) of TM-CLKL (the Project) was prepared in accordance with the EIA Study Brief (No. ESB-175/2007) and the Technical Memorandum of the Environmental Impact Assessment Process (EIAO-TM).  The EIA Report was submitted under the Environmental Impact Assessment Ordinance (EIAO) in August 2009.  Subsequent to the approval of the EIA Report (EIAO Register Number AEIAR-146/2009), an Environmental Permit (EP-354/2009) for TM-CLKL was granted by the Director of Environmental Protection (DEP) on 4 November 2009, and EP variation (VEP) (EP-354/2009/A) was issued on 8 December 2010.  Subsequent applications for variation of environmental permits (VEP), EP-354/2009/B, EP-354/2009/C and EP-354/2009/D, were granted on 28 January 2014, 10 December 2014 and 13 March 2015, respectively.

Under Contract No. HY/2012/08, Dragages – Bouygues Joint Venture (DBJV) is commissioned by the Highways Department (HyD) to undertake the design and construction of the Northern Connection Sub-sea Tunnel Section of TM-CLKL while AECOM Asia Company Limited was appointed by HyD as the Supervising Officer.  For implementation of the environmental monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong, Limited (ERM) has been appointed as the Environmental Team (ET) in accordance with Environmental Permit No. EP-354/2009/A.  Ramboll Hong Kong Ltd. was employed by HyD as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO).

Layout of the Contract components is presented in Figure 1.1.

                  

The construction phase of the Contract commenced on 1 November 2013 and will tentatively be completed in early 2020.  The impact monitoring phase of the EM&A programme, including air quality, water quality, marine ecological monitoring and environmental site inspections, were commenced on 1 November 2013.

1.2                         Scope of Report

This is the Twenty-fourth Quarterly EM&A Report under the Contract No. HY/2012/08 Tuen Mun – Chek Lap Kok Link – Northern Connection Sub-sea Tunnel Section.  This report presents a summary of the environmental monitoring and audit works from 1 September 2019 to 30 November 2019.

1.3                         Organization Structure

The organization structure of the Contract is shown in Appendix A.  The key personnel contact names and contact details are summarized in Table 1.1 below.

Table 1.1        Contact Information of Key Personnel

Party

Position

Name

Telephone

Fax

Highways Department

 

Engr 24/SD

Ken T.M. Cheng

2762 4062

3188 6614

SOR

(AECOM Asia Company Limited)

 

Chief Resident Engineer

Roger Man

 

Andrew Westmoreland

 

2293 6388

 

2293 6360

2293 6300

 

2293 6300

ENPO / IEC

(Ramboll Hong Kong Ltd.)

ENPO Leader

 

Y.H. Hui

3465 2850

3465 2899

IEC

 

Dr. F.C. Tsang

3465 2851

3465 2899

Contractor

(Dragages – Bouygues Joint Venture)

Deputy Environmental Manager

Bryan Lee

 

2293 7323

 

2293 7499

 

24-hour hotline

 

 

2293 7330

 

ET (ERM-HK)

ET Leader

Jasmine Ng

2271 3311

2723 5660

1.4                         Summary of Construction Works

The construction phase of this Contract was commenced on 1 November 2013.  The construction programme is shown in Appendix B.

As per DBJV’s information, details of major construction works carried out in this reporting period are summarized in Table 1.2.

The general layout plan of the site showing the detailed works areas is shown in Figure 1.2.  The Environmental Sensitive Receivers in the vicinity of the Contract are shown in Figure 1.3.

The implementation schedule of environmental mitigation measures is presented in Appendix C.

Table 1.2        Summary of Construction Activities Undertaken during the Reporting Period

Construction Activities Undertaken

Land-based Works

·         Construction of Thermal barrier – TBM tunnel;

·         Construction of Walkway Corbel & Cover – TBM Tunnel;

·         Road & Drainage works – Portion N-A;

·         Gantry Crane Removal – Portion N-A;

·         RC structure – Portion S-A;

·         Backfilling – Portion S-A & S-C;

·         Water Treatment Facilities Dismantling – Portion S-C;

·         Road & Drainage - Portion S-C

 

Marine-based Works

·         Seawall Modification Works – Portion S-B

 

 

Figure 1.2      Locations of Construction Activities – September to November 2019

 

 

 

2                             EM&A Results

The EM&A programme required environmental monitoring for air quality, water quality and marine ecology as well as environmental site inspections for air quality, noise, water quality, waste management, marine ecology and landscape and visual impacts.  The EM&A requirements and related findings for each component are summarized in the following sections

2.1                         Air quality

As per the requirements under Condition 2.4 of EP-354/2009/D, the Enhanced TSP Monitoring Plan has been prepared under Contract No. HY/2012/08.  Details of the monitoring plan are presented in the Enhanced TSP Monitoring Plan ([1]).  

2.1.1                     Monitoring Requirements and Equipment

In accordance with the Updated EM&A Manual and the Enhanced TSP Monitoring Plan, impact 1-hour TSP monitoring was conducted three (3) times in every six (6) days and impact 24-hour TSP monitoring was carried out once in every six (6) days when the highest dust impact was expected.  1-hr and 24-hr TSP monitoring frequency was increased to three times per day every three days and daily every three days respectively as excavation works for launching shaft commenced on 24 October 2014.

High volume samplers (HVSs) were used to carry out the 1-hour and 24-hour TSP monitoring in the reporting quarter at the five (5) air quality monitoring stations in accordance with the requirements stipulated in the Updated EM&A Manual (Figure 2.1; Table 2.1).  Wind anemometer was installed at the rooftop of ASR5 for logging wind speed and wind direction.  Details of the equipment deployed are provided in Table 2.2.

Table 2.1        Locations of Impact Air Quality Monitoring Stations and Monitoring Dates in this Reporting Period

Monitoring Station

Monitoring Dates

Location

Description

Parameters & Frequency

ASR1

2, 5, 8, 11, 14, 17, 20, 23, 26 and 29 September 2019

Tuen Mun Fireboat Station

 

Office

TSP monitoring

Ÿ  1-hour Total Suspended Particulates (1-hour TSP, µg/m3), 3 times in every 6 days

Ÿ  24-hour Total Suspended Particulates (24-hour TSP, µg/m3), daily for 24-hour in every 6 days

Enhanced TSP monitoring (commenced on 24 October 2014)

Ÿ  1-hour Total Suspended Particulates (1-hour TSP, µg/m3), 3 times in every 3 days

Ÿ  24-hour Total Suspended Particulates (24-hour TSP, µg/m3), daily for 24-hour in every 3 days

ASR5

2, 5, 8, 11, 14, 17, 20, 23, 26 and 29 October 2019

Pillar Point Fire Station

 

Office

AQMS1

1, 4, 7, 10, 13, 16, 19, 22, 25 and 28 November 2019

Previous River Trade Golf

 

Bare ground

ASR6

 

Butterfly Beach Laundry

 

Office

ASR10

 

Butterfly Beach Park

Recreational uses

Table 2.2      Air Quality Monitoring Equipment

Equipment

Brand and Model

High Volume Sampler
(1-hour TSP and 24-hour TSP)

Tisch Environmental Mass Flow Controlled Total Suspended Particulate (TSP) High Volume Sampler (Model No. TE-5170)

Wind Meter

Davis (Model: Vantage Pro 2 (S/N: AS160104014)

Wind Anemometer for calibration

Lutron (Model No. AM-4201)

2.1.2                     Action & Limit Levels

The Action and Limit Levels of the air quality monitoring is provided in Appendix D.  The Event and Action plan is presented in Appendix H.

2.1.3                     Monitoring Schedule for the Reporting Quarter

The schedules for air quality monitoring in the reporting quarter are provided in Appendix E.

2.1.4                     Results and Observations

Impact air quality monitoring was conducted at all designated monitoring stations in the reporting period under favourable weather conditions.  The major dust sources in the reporting period include construction activities under the Contract as well as nearby traffic emissions. 

The monitoring results for 1-hour TSP and 24-hour TSP are summarized in Tables 2.3 and 2.4, respectively.  Monitoring results are presented graphically in Appendix F and detailed impact air quality monitoring data were reported in the Seventy-first to Seventy-third Monthly EM&A Report

Table 2.3        Summary of 1-hour TSP Monitoring Results in this Reporting Period

Month/Year

Station

Average (µg/m3)

Range (µg/m3)

Action Level  (µg/m3)

Limit Level  (µg/m3)

September to November 2019

ASR 1

162

23 - 626

331

500

ASR 5

183

25 - 534

340

500

AQMS1

108

14 - 204

335

500

ASR6

111

14 - 216

338

500

ASR10

66

13 - 143

337

500

 

Table 2.4        Summary of 24-hour TSP Monitoring Results in this Reporting Period

Month/Year

Station

Average (µg/m3)

Range (µg/m3)

Action Level  (µg/m3)

Limit Level  (µg/m3)

September to November 2019

ASR 1

104

28 - 207

213

260

ASR 5

111

55 - 196

238

260

AQMS1

71

25 - 108

213

260

ASR6

81

32 - 145

238

260

ASR10

54

22 - 95

214

260

Eight (8) Action level and four (4) Limit Level exceedances of 1-hour TSP and were recorded in this reporting period.  Investigation reports are provided in Appendix J.  Summary of Exceedances for Air Quality Impact Monitoring in this Reporting Quarter is detailed in Table 2.15.

2.2                         Water Quality Monitoring

Seawall Modification Works at Portion S-B was carried out in this reporting period.

2.2.1                     Monitoring Requirements & Equipment

In accordance with the approved Environmental Review Report dated 21 March 2018 for the Change in Design of Vertical Seawall to Sloping Seawall on Southern Landfall, Updated Impact water quality monitoring programme and water quality monitoring stations IS17, SR7 and IS(Mf)11 specified under the EM&A Manual for HZMB HKBCF project will be adopted.  (Figure 2.2; Table 2.5).  

Results of water quality monitoring were adopted from the published EM&A data of Contract No. HY/2012/07 Tuen Mun-Chek Lap Kok Link – Southern Connection Viaduct Section.

The Action and Limit Levels of the water quality monitoring were adopted from the EM&A Manual for HZMB HKBCF project.  The Action and Limit Levels are provided in Appendix D

Table 2.5        Locations of Water Quality Monitoring Stations and the Corresponding Monitoring Requirements

Station ID

Type

Coordinates

*Parameters, unit

Depth

Frequency

 

 

Easting

Northing

 

 

 

IS(Mf)11

Impact Station (Close to HKBCF construction site)

 

813562

820716

Ÿ Temperature(°C)

Ÿ pH(pH unit)

Ÿ Turbidity (NTU)

Ÿ Water depth (m)

Ÿ Salinity (ppt)

Ÿ DO (mg/L and % of

saturation)

·    SS (mg/L)

3 water depths: 1m

below sea surface,

mid-depth and 1m

above sea bed.  If the water depth is less than 3m, mid-depth sampling only.  If water depth less than 6m, mid-depth may be omitted.

 

 

Impact monitoring: 3 days per week, at mid-flood and mid-ebb tides during the construction period of the Contract.

IS17

Impact Station (Close to HKBCF construction site)

814539

820391

SR7

Sensitive receivers (Tai Mo Do)

814293

821431

IS(Mf)9

Impact Station (Close to HKBCF construction site)

813273

818850

 

 

 

IS(Mf)16

Impact Station (Close to HKBCF construction site)

814328

819497

 

 

 

IS8(N)

Impact Station (Close to HKBCF construction site)

814413

818570

 

 

 

 

SR4(N2)

Sensitive receiver (Tai Ho Inlet)

814688

817996

 

 

 

 

SR4a

Sensitive receiver

815247

818067

 

 

 

CS(Mf)3(N)

Control Station

808814

822355

 

 

 

CS(Mf)5

Control Station

817990

821129

 

 

 

*Notes:

In addition to the parameters presented monitoring location/position, time, water depth, sampling depth, tidal stages, weather conditions and any special phenomena or works underway nearby were also recorded.

Water Quality Monitoring Station CS(Mf)3 was relocated to CS(Mf)3(N) since 2 May 2017.

Water Quality Monitoring Station SR4 was relocated to SR4(N) since 2 March 2018.

Water Quality Monitoring Station SR4(N) was relocated to SR4(N2) since 12 June 2019

Water Quality Monitoring Station IS8 was relocated to IS8(N) since 12 June 2019.

Table 2.6 summarizes the equipment used in the impact water quality monitoring programme. 

Table 2.6     Water Quality Monitoring Equipment

Equipment

Model

Multi-Parameters

YSI ProDss 18A104824

Multi-Parameters

YSI ProDss 15M100005

Multi-Parameters

Multi-Parameters

Multi-Parameters

Multi-Parameters

Multi-Parameters

YSI ProDss 0001C6A7

YSI ProDss 17H105557

YSI ProDss 00019CB2

YSI ProDss 17E100747

YSI ProDss 16H104233

Positioning Equipment

Furuno GP-170

Water Depth Detector

Lowrance Mark 5x / Garmin Striker 4

2.2.2                     Action & Limit Levels

The Action and Limit levels of water quality impact monitoring are shown in Appendix D.  The Event and Action plan is presented in Appendix I.

2.2.3                     Monitoring Schedule for the Reporting Period

The schedules for water quality monitoring in the reporting quarter are provided in Appendix E.

2.2.4                     Results and Observations

Impact water quality monitoring was conducted at all designated monitoring stations in the reporting quarter.  Results and graphical presentations of impact water quality monitoring are presented in Appendix G.  Detailed water quality monitoring data were reported in the Seventy-first and Seventy-third Monthly EM&A Report.

2.3                         Dolphin Monitoring

2.3.1                     Monitoring Requirements

Impact dolphin monitoring is required to be conducted by a qualified dolphin specialist team to evaluate whether there have been any effects on the dolphins.  In order to fulfil the EM&A requirements and make good use of available resources, Contract No. HY/2012/08 has taken over the responsibility for implementation of dolphin monitoring from HZMB HKLR Contract No. HY/2011/03 since October 2019.

2.3.2                     Monitoring Equipment

Table 2.7 summarizes the equipment used for the impact dolphin monitoring.

Table 2.7         Dolphin Monitoring Equipment

Equipment

Model

Global Positioning System (GPS)

 

Camera

 

Laser Binoculars

Marine Binocular

 

Vessel for Monitoring

 

Garmin 18X-PC

Geo One Phottix

Nikon D90 300m 2.8D fixed focus

Nikon D90 20-300m zoom lens

Infinitor LRF 1000

Bushell 7 x 50 marine binocular with compass and reticules

65 foot single engine motor vessel with viewing platform 4.5m above water level

 

2.3.3                     Monitoring Parameter, Frequencies & Duration

Dolphin monitoring should cover all transect lines in Northeast Lantau (NEL) and the Northwest Lantau (NWL) survey areas twice per month throughout the entire construction period.  The monitoring data should be compatible with, and should be made available for, long-term studies of small cetacean ecology in Hong Kong.  In order to provide a suitable long-term dataset for comparison, identical methodology and line transects employed in baseline dolphin monitoring was followed in the impact dolphin monitoring.

2.3.4                     Monitoring Location

The impact dolphin monitoring was carried out in the NEL and NWL along the line transect as depicted in Figure 2.3.  The co-ordinates of all transect lines are shown in Table 2.8 below.

Table 2.8        Impact Dolphin Monitoring Line Transect Co-ordinates

Line No.

Easting

Northing

Line No.

Easting

Northing

1

Start Point

804671

815456

13

Start Point

816506

819480

1

End Point

804671

831404

13

End Point

816506

824859

2

Start Point

805476

820800*

14

Start Point

817537

820220

2

End Point

805476

826654

14

End Point

817537

824613

3

Start Point

806464

821150*

15

Start Point

818568

820735

3

End Point

806464

822911

15

End Point

818568

824433

4

Start Point

807518

821500*

16

Start Point

819532

821420

4

End Point

807518

829230

16

End Point

819532

824209

5

Start Point

808504

821850*

17

Start Point

820451

822125

5

End Point

808504

828602

17

End Point

820451

823671

6

Start Point

809490

822150*

18

Start Point

821504

822371

6

End Point

809490

825352

18

End Point

821504

823761

7

Start Point

810499

822000*

19

Start Point

822513

823268

7

End Point

810499

824613

19

End Point

822513

824321

8

Start Point

811508

821123

20

Start Point

823477

823402

8

End Point

811508

824254

20

End Point

823477

824613

9

Start Point

812516

821303

21

Start Point

805476

827081

9

End Point

812516

824254

21

End Point

805476

830562

10

Start Point

813525

821176

22

Start Point

806464

824033

10

End Point

813525

824657

22

End Point

806464

829598

11

Start Point

814556

818853

23

Start Point

814559

821739

11

End Point

814556

820992

23

End Point

814559

824768

12

Start Point

815542

818807

24*

Start Point

805476*

815900*

12

End Point

815542

824882

24*

End Point

805476*

819100*

Remarks: The coordinates of several starting and ending points have been revised since August 2017 due to the presence of a work zone to the north of the airport platform with intense construction activities in association with the construction of the third runway expansion for the Hong Kong International Airport.  Co-ordinates in red and marked with asterisk are revised co-ordinates of transect line.

2.3.5                     Action & Limit Levels

The Action and Limit levels of dolphin impact monitoring are shown in Appendix D.  The Event and Action plan is presented in Appendix I.

2.3.6                     Monitoring Schedule for the Reporting Period

The dolphin monitoring schedules for the reporting period are shown in Appendix E.

2.3.7                     Results & Observations

A total of 796.79 km of survey effort was conducted, with 97.9% of the total survey effort being conducted under favourable weather conditions (ie Beaufort Sea State 3 or below with good visibility) in this reporting quarter.  Amongst the two areas, 293.68 km and 503.11 km of survey effort were conducted from NEL and NWL survey areas, respectively.  The total survey effort conducted on primary and secondary lines were 572.39 km and 224.40 km, respectively.  The survey efforts are summarized in Appendix H.

A total of 4 groups of 7 Chinese White Dolphins sightings were recorded during the six sets of surveys in this reporting quarter.  All four dolphin sightings were made during on-effort search, and three of the four on-effort dolphin sightings were made on primary lines.  During this reporting quarter, all dolphin groups were sighted in NWL, while no dolphin was sighted in NEL.

Encounter rates of Chinese White Dolphins are deduced from the survey effort and on-effort sighting data made under favourable conditions (Beaufort 3 or below with good visibility) in the reporting quarter with the results and comparison with baseline results present in Tables 2.9 and 2.10.

Table 2.9        Individual Survey Event Encounter Rates

 

Encounter rate (STG)     (no. of on-effort dolphin sightings per 100 km of survey effort)

Encounter rate (ANI)            (no. of dolphins from all on-effort sightings per 100 km of survey effort)

Primary Lines Only

Primary Lines Only

NEL

Set 1 (4 & 11 Sep 2019)

0.00

0.00

Set 2 (17 & 23 Sep 2019)

0.00

0.00

Set 3 (8 & 9 Oct 2019)

0.00

0.00

Set 4 (14 & 29 Oct 2019)

0.00

0.00

Set 5 (5 & 19 Nov 2019)

0.00

0.00

Set 6 (27 & 28 Nov 2019)

0.00

0.00

NWL

Set 1 (4 & 11 Sep 2019)

1.64

3.28

Set 2 (17 & 23 Sep 2019)

0.00

0.00

Set 3 (8 & 9 Oct 2019)

1.68

1.68

Set 4 (14 & 29 Oct 2019)

0.00

0.00

Set 5 (5 & 19 Nov 2019)

1.67

1.67

Set 6 (27 & 28 Nov 2019)

0.00

0.00

Note: Dolphin Encounter Rates are deduced from the Two Sets of Surveys (Two Surveys in Each Set) in the reporting quarter in Northeast (NEL) and Northwest Lantau (NWL)

Table 2.10      Quarterly Average Encounter Rates

 

Encounter rate (STG)

(no. of on-effort dolphin sightings per 100 km of survey effort)

Encounter rate (ANI)            (no. of dolphins from all on-effort sightings per 100 km of survey effort)

September –         November 2019

September – November 2011

September –         November 2019

September – November 2011

Northeast Lantau

0.0

6.00 ± 5.05

0.0

22.19 ± 26.81

Northwest Lantau

0.83 ± 0.91

9.85 ± 5.85

1.10 ± 1.34

44.66 ± 29.85

Note: Encounter rates deduced from the baseline monitoring period have been recalculated based only on survey effort and on-effort sighting data made along the primary transect lines under favourable conditions.

Table d 4.6

nd limit levels of dolphin impact monitoring are shown in Table  

Group size of Chinese White Dolphins ranged from 1 – 3 individuals per group in North Lantau region during September to November 2019.  The average dolphin group sizes from these three months were compared with the ones deduced from the baseline period in September to November 2011, as shown in Table 2.11.

 

Table 2.11      Average Dolphin Group Size

 

Average Dolphin Group Size

September – November 2019

September – November 2011

Overall

1.75 ± 0.96 (n = 4)

3.72 ± 3.13 (n = 66)

Northeast Lantau

---

3.18 ± 2.16 (n = 17)

Northwest Lantau

1.75 ± 0.96 (n = 4)

3.92 ± 3.40 (n = 49)

Whilst one limit level exceedance was observed for the quarterly dolphin monitoring data between September and November 2019, no unacceptable impact from the construction activities of this Contract was recorded from the general observations.

Although the dolphins infrequently occurred along the alignment of TM-CLKL Northern Connection Sub-Sea Tunnel Section in the past and during the baseline monitoring period, it is apparent that dolphin usage has been significantly reduced in NEL.

It is critical to monitor the dolphin usage in North Lantau region in the upcoming quarters to determine whether the dolphins are continuously affected by the various construction activities in relation to the HZMB-related works, and whether suitable mitigation measure can be applied to revert the situation.

2.3.8                     Implementation of Marine Mammal Exclusion Zone

Daily marine mammal exclusion zone was in effect during the period of silt curtain installation in open waters under this Contract.  No sighting of the Indo-Pacific humpback dolphin (i.e. Chinese White Dolphin) was recorded in the reporting period during the exclusion zone monitoring.

2.4                         EM&A Site Inspection

Site inspections were carried out on a weekly basis to monitor the implementation of proper environmental pollution control and mitigation measures under the Contract.  Thirteen (13) site inspections were carried out in the reporting quarter on 4, 11, 18 and 25 September 2019; 2, 9, 16, 23 and 30 October 2019; 7, 14, 21 and 28 November 2019.

Key observations during the site inspections in this reporting period are summarized in Table 2.12.

                                    

Table 2.12      Specific Observations and Recommendations during the Weekly Site Inspection in this Reporting Period

Inspection Date

Environmental Observations

Recommendations/ Remarks

4 September 2019

Works Area – Portion N-A

Ÿ  Food waste in the skip should be removed.

Ÿ  Drip tray should be provided for the chemical containers.

Ÿ  The faded NRMM label should be replaced.

Ÿ  The broken water barrier should be removed.

Works Area - Portion S-A

Ÿ  Food waste should be removed.

Works Area – Portion N-A

Ÿ  The Contractor was reminded to Remove the food waste in the skip.

Ÿ  The Contractor was reminded to provide drip tray for the chemical containers.

Ÿ  The Contractor was reminded to replace the NRMM label.

Ÿ  The Contractor was reminded to remove the broken water barrier.

Works Area - Portion S-A

Ÿ  The Contractor was reminded to remove the food waste.

11 September 2019

Works Area – TBM tunnel

Ÿ  Better housekeeping should be maintained.

Ÿ  The broken water barrier should be removed.

Ÿ  Water spraying should be applied for dust control.

Works Area - Portion S-A

Ÿ  Food waste should be removed.

Works Area – Portion S-B

Ÿ  Oil spillage on the floor should be cleaned up.

Works Area – TBM tunnel

Ÿ  The Contractor was reminded to maintain better housekeeping.

Ÿ  The Contractor was reminded to remove the broken water barrier.

Ÿ  The Contractor was reminded to apply water spraying for dust control.

Works Area - Portion S-A

Ÿ  The Contractor was reminded to remove the food waste.

Works Area – Portion S-B

Ÿ  The Contractor was reminded to clean up the oil spillage on the floor.

18 September 2019

Works Area – Portion N-B

Ÿ  Waste should be removed and better housekeeping should be maintained.

Ÿ  Drip tray should be provided for the chemical containers.

Reminder from the SOR

Works Area – Portion S-B

Ÿ  Stagnant water and rubbish should be cleared.

Ÿ  Stagnant water should be cleared.

Works Area – Portion N-B

Ÿ  The Contractor was reminded to remove the waste and maintain better housekeeping.

Ÿ  The Contractor was reminded to provide drip tray for the chemical containers.

Reminder from the SOR

Works Area – Portion S-B

Ÿ  The Contractor was reminded to clear the stagnant water and rubbish.

Ÿ  The Contractor was reminded to clear the stagnant water.

25 September 2019

Works Area – Portion S-B

Ÿ  Waste and stagnant water should be cleared.

Works Area - Portion N-B

Ÿ  Waste should be cleared and better housekeeping should be maintained.

Ÿ  Drip tray should be provided for the chemical containers.

Reminder from the SOR

Works Area – Portion S-B

Ÿ  Stagnant water should be cleared.

Works Area – Portion S-B

Ÿ  The Contractor was reminded to clear the waste and stagnant water.

Works Area - Portion N-B

Ÿ  The Contractor was reminded to clear the waste and maintain better housekeeping.

Ÿ  The Contractor was reminded to provide drip tray for the chemical containers.

Reminder from the SOR

Works Area – Portion S-B

Ÿ  The Contractor was reminded to clear the stagnant water.

2 October 2019

Works Area – Portion N-A

Ÿ  Water spraying should be applied on main haul road.

Ÿ  NRMM label on machine should be fixed.

Works Area – Portion S-B

Ÿ  Water spraying should be applied on main haul road.

Ÿ  Food waste in the waste skip should be cleared.

Reminder from the SOR

Works Area - Portion S-B

Cover of the water barrier should be provided.

Works Area – Portion N-A

Ÿ  The Contractor was reminded to apply water spraying on the main haul road.

Ÿ  The Contractor was reminded to fix the NRMM label on machine.

Works Area – Portion S-B

Ÿ  The Contractor was reminded to apply water sraying on the main haul road.

Ÿ  The Contractor was reminded to clear the food waste in the waste skip.

Reminder from the SOR

Works Area - Portion S-B

The Contractor was reminded to provide the cover of the water barrier.

9 October 2019

Works Area – TBM tunnel

Ÿ  Food waste should be removed and better housekeeping should be maintained.

Works Area – Portion S-A

Ÿ  Cement bages should be covered with tarpaulin sheets.

Reminder from the SOR

Works Area – TBM tunnel

Ÿ  Stagnant water should be cleared.

Works Area - Portion S-A

Ÿ  Stagnant water should be cleared.

Works Area – TBM tunnel

Ÿ  The Contractor was reminded to remove the food waste and maintain better housekeeping.

Works Area – Portion S-A

Ÿ  The Contractor was reminded to cover the cement bags with tarpaulin sheets.

Reminder from the SOR

Works Area – TBM tunnel

Ÿ  The Contractor was reminded to clear the stagnant water.

Works Area - Portion S-A

Ÿ  The Contractor was reminded to clear the stagnant water.

16 October 2019

Works Area – Portion S-A

Ÿ  Faded NRMM label should be replaced.

Works Area – Portion S-B

Ÿ  Food waste in the skip should be cleared.

Works Area – Portion N-A

Ÿ  Drip tray should be provided for the chemical containers.

Reminder from the SOR

Works Area – Portion S-A

Ÿ  Stagnant water should be cleared.

Works Area – Portion N-A

Ÿ  Lifting eyes should be filled with sand.

Works Area – Portion S-A

Ÿ  The Contractor was reminded to replace the faded NRMM label.

Works Area – Portion S-B

Ÿ  The Contractor was reminded to clear the food waste in the skip.

Works Area – Portion N-A

Ÿ  The Contractor was reminded to provide drip tray for the chemical containers.

Reminder from the SOR

Works Area – Portion S-A

Ÿ  The Contractor was reminded to clear the stagnant water.

Works Area – Portion N-A

Ÿ  The Contractor was reminded to fill the lifting eyes with sand.

23 October 2019

Works Area – Portion S-A

Ÿ  Cement batching station should be sheltered on top and 3 sides.

Ÿ  Cement bags should be covered with tarpaulin sheets.

Works Area – TBM tunnel

Ÿ  Cement bages should be covered with tarpaulin sheets.

Reminder from the SOR

Works Area – TBM tunnel

Covers of the water barrier should be provided.

Works Area – Portion S-A

Ÿ  The Contractor was reminded to shelter the cement batching station on top and 3 sides.

Ÿ  The Contractor was reminded to cover the cement bags with tarpaulin sheets.

Works Area – TBM tunnel

Ÿ  The Contractor was reminded to cover the cement bags with tarpaulin sheets.

Reminder from the SOR

Works Area – TBM tunnel

The Contractor was reminded to provide covers for the water barrier.

30 October 2019

Works Area – Portion S-A

Ÿ  The faded NRMM label on the air compressor should be replaced.

Works Area – Portion S-B

Ÿ  Food waste should be removed.

Works Area – Poriton N-A

Ÿ  Food waste from the skip should be removed.

Ÿ  The damaged NRMM label should be replaced.

Reminder from the SOR

Works Area – Portion N-A

Ÿ  The oil leakage should be fixed.

Ÿ   

Works Area – Portion S-A

Ÿ  The Contractor was reminded to replace the faded NRMM label on the air compressor.

Works Area – Portion S-B

Ÿ  The Contractor was reminded to remove the food waste.

Works Area – Poriton N-A

Ÿ  The Contractor was reminded to remove the food waste from the skip.

Ÿ  The Contractor was reminded to replace the damaged NRMM label.

Reminder from the SOR

Works Area – Portion N-A

Ÿ  The Contractor was reminded to fix the oil leakage.

Ÿ   

7 November 2019

Works Area – TBM tunnel

Ÿ  The cement batching station should be sheltered on top and 3 sides.

Works Area – Portion S-A

Ÿ  Drip tray should be provided for the chemical containers.

Ÿ  Broken water barrier should be removed.

Reminder from the SOR

Works Area - Portion S-A

Ÿ  The lifting eyes should be filled with sand.

Works Area – TBM tunnel

Ÿ  The Contractor was reminded to shelter the cement batching station on top and 3 sides.

Works Area – Portion S-A

Ÿ  The Contractor was reminded to provide drip tray for the chemical containers.

Ÿ  The Contractor was reminded to remove the broken barrier.

Reminder from the SOR

Works Area - Portion S-A

Ÿ  The Contractor was reminded to fill the lifting eyes with sand.

14 November 2019

Works Area – Portion S-B

Ÿ  The damaged NRMM label for the excavator should be replaced.

Works Area – Portion N-A

Ÿ  Water spraying should be applied on main haul raod.

Ÿ  Drip tray should be provided for the chemical containers.

Reminder from the SOR

Works Area – Portion S-B

Ÿ  Stagnant water should be cleared.

Works Area – Portion S-B

Ÿ  The Contractor was reminded to replace the damaged NRMM label for the excavator.

Works Area – Portion N-A

Ÿ  The Contractor was reminded to apply water spraying on main haul road.

Ÿ  The Contractor was reminded to provide drip tray for the chemical containers.

Reminder from the SOR

Works Area – Portion S-B

Ÿ  The Contractor was reminded to clear the stagnant water.

21 November 2019

Works Area – TBM tunnel

Ÿ  The NRMM label should be replaced.

Ÿ  Food waste from the skip should be removed and better housekeeping should be maintained.

Works Area – Portion S-B

Ÿ  Drip tray should be provided for the chemical containers.

Reminder from the SOR

Works Area – Portion S-A

Ÿ  Broken water barrier should be replaced.

Works Area – TBM tunnel

Ÿ  The Contractor was reminded to replace the NRMM label.

Ÿ  The Contractor was reminded to remove the food waste from the skip and maintain better housekeeping.

Works Area – Portion S-B

Ÿ  The Contractor was reminded to provide drip tray for the chemical containers.

Reminder from the SOR

Works Area – Portion S-A

Ÿ  The Contractor was reminded to replace the broken water barrier.

28 November 2019

Works Area – Portion S-A

Ÿ  Food waste should be removed.

Works Area – TBM tunnel

Ÿ  The faded NRMM label should be replaced.

Works Area – Portion S-A

Ÿ  The Contractor was reminded to remove the food waste.

Works Area – TBM tunnel

Ÿ  The Contractor was reminded to replace the NRMM label.

The Contractor has rectified all of the observations as identified during environmental site inspections in the reporting quarter.

2.5                         Waste Management Status

The Contractor had submitted application form for registration as chemical waste producer under the Contract.  Sufficient numbers of receptacles were available for general refuse collection and sorting.

Wastes generated during this reporting period include mainly construction wastes (inert and non-inert). Reference has been made to the waste flow table prepared by the Contractor (Appendix K).  The quantities of different types of wastes are summarized in Table 2.13.     

Table 2.13      Quantities of Different Waste Generated in the Reporting Period

Month/Year

Inert Construction Waste (a) (tonnes)

Inert Construction Waste Re-used

(tonnes)

Non-inert Construction Waste (b) (tonnes)

Recyclable Materials (c)  (kg)

Chemical Wastes (kg)

Marine Sediment (m3)

Category L

Category M

(Mp & Mf)

Mixed

(L+M)

September 2019

4,191(d)

0

737(d)

399,320

8,000

0

0

0

October 2019

8,366

0

754

524,090

5,800

0

0

0

November 2019

6,215

0

525

273,630

1,000

0

0

0

Notes:

 

(a)  Inert construction wastes include hard rock and large broken concrete, and materials disposed as public fill.

(b)  Non-inert construction wastes include general refuse disposed at landfill.

(c)   Recyclable materials include metals, paper, cardboard, plastics, timber and others.

(d)  Updated figure and waste flow table is presented in this quarterly report.

 

The Contractor was advised to properly maintain on site C&D materials and waste collection, sorting and recording system, dispose of C&D materials and wastes at designated ground and maximize reuse/ recycle of C&D materials and wastes.  The Contractor was also reminded to properly maintain the site tidiness and dispose of the wastes accumulated on site regularly and properly.

For chemical waste containers, the Contractor was reminded to treat properly and store temporarily in designated chemical waste storage area on site in accordance with the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes.

2.6                         Environmental Licenses and Permits

The status of environmental licensing and permit is summarized in Table 2.14 below.  


Table 2.14      Summary of Environmental Licensing and Permit Status

License/ Permit

License or Permit No.

Date of Issue

Date of Expiry

License/ Permit Holder

Remarks

Environmental Permit

EP-354/2009/D

13 March 2015

Throughout the Contract

HyD

Application for VEP on 3 March 2015 to supersede EP-354/2009/C

Construction Dust Notification

363510

19 August 2013

Throughout the Contract

DBJV

Northern Landfall

Construction Dust Notification

 

403620

10 June 2016

Throughout the Contract

DBJV

Southern Landfall

Chemical Waste Registration

5213-422-D2516-02

18 January 2017

Throughout the Contract

DBJV

Northern Landfall

 

Chemical Waste Registration

5213-951-D2591-01

25 May 2016

Throughout the Contract

DBJV

Southern Landfall

Construction Waste Disposal Account

7018108

28 August 2013

Throughout the Contract

DBJV

Waste disposal in Contract No. HY/2012/08

Construction Waste Disposal Account

7021715

4 July 2019

14 October 2019

DBJV

Vessel Disposal

Construction Waste Disposal Account

7021715

4 October 2019

14 January 2020

DBJV

Vessel Disposal

Waste Water Discharge License

WT00031435-2018

2 August 2018

31 August 2023

DBJV

Southern Landfall

Waste Water Discharge License

WT00034060-2019

25 July 2019

30 June 2024

DBJV

Northern Landfall (4 Discharge Point)

Marine Dumping Permit

EP/MD/20-013

19 May 2019

18 November 2019

DBJV

Type 1 (Open Sea Disposal)

Construction Noise Permit

GW-RW0406-18

27 April 2019

15 October 2019

DBJV

Urmston Road in front of Pillar Point

Construction Noise Permit

GW-RW0406-18

17 October 2019

15 April 2020

DBJV

Urmston Road in front of Pillar Point

Construction Noise Permit

GW-RW0374-19

20 August 2019

19 February 2020

DBJV

WA23 @ Tsing Yi

Construction Noise Permit

GW-RS0766-19

2 September 2019

25 February 2020

DBJV

Southern Landfall

Construction Noise Permit

GW-RS0224-19

25 March 2019

24 September 2019

DBJV

Southern Landfall

Construction Noise Permit

GW-RW0179-19

27 April 2019

15 October 2019

DBJV

Urmston Road in front of Pillar Point

Notes:

HyD = Highways Department

DBJV = Dragages – Bouygues Joint Venture

VEP = Variation of Environmental Permit


2.7                         Implementation Status of Environmental Mitigation Measures

In response to the site audit findings, the Contractors carried out all corrective actions.

A summary of the Implementation Schedule of Environmental Mitigation Measures (EMIS) is presented in Appendix C.  The necessary mitigation measures relevant to this Contract were implemented properly.

2.8                         Summary of Exceedances of the Environmental Quality Performance Limit

For air quality impact monitoring, a total of thirty monitoring events for both 1-hour TSP and 24-hour TSP were undertaken in which Eight (8) Action level and four (4) Limit Level exceedances of 1-hour TSP and were recorded      (Table 2.15).

Table 2.15      Summary of Exceedances for Air Quality Impact Monitoring in this Reporting Quarter

Station

Exceedance Level

Date of Exceedances

Number of Exceedances

1-hr TSP

24-hr TSP

1-hr TSP

24-hr TSP

AQMS1

Action Level

-

-

-

-

Limit Level

-

-

-

-

ASR1

Action Level

2019-10-14

2019-10-17

2019-10-17

2019-11-28

2019-11-28

-

-

-

Limit Level

2019-09-20

2019-11-04

2019-11-28

-

-

-

ASR5

Action Level

2019-11-04

2019-11-07

2019-11-28

-

-

-

Limit Level

2019-11-28

-

-

-

ASR6

Action Level

-

-

-

-

Limit Level

-

-

-

-

ASR10

Action Level

-

-

-

-

Limit Level

-

-

-

-

Total number of Action level Exceedances:

8

0

Total number of Limit level Exceedances:

4

0


For marine water quality impact monitoring, a total of thirty-nine monitoring events were undertaken in which Thirty-five (35) Action level of Dissolved Oxygen were recorded in this reporting period.  Four (4) Action Level exceedance for Depth-averaged suspended solids was recorded. (Table 2.16).  

 


Table 2.16   Summary of Exceedances for Marine Water Quality Impact Monitoring in this Reporting Quarter

Station

Exceedance Level (a)

DO (Surface and Middle)

DO (Bottom)

Turbidity (depth-averaged)

SS (depth-averaged)

Mid-ebb

Mid-flood

Mid-ebb

Mid-flood

Mid-ebb

Mid-flood

Mid-ebb

Mid-flood

IS17

AL

2019-09-18

2019-09-20

2019-09-16

2019-09-18

2019-09-20

2019-09-16

2019-09-18

2019-09-20

2019-09-16

2019-09-18

2019-09-20

-

-

-

-

LL

-

-

-

-

-

-

-

-

IS(Mf)11

AL

2019-09-18

2019-09-16

2019-09-18

2019-09-20

2019-09-18

2019-09-18

2019-09-20

-

-

-

-

LL

-

-

-

-

-

-

-

-

SR7

AL

-

2019-09-16

2019-09-18

2019-09-20

-

2019-09-18

-

-

-

2019-10-02

2019-10-28

LL

-

-

-

-

-

-

-

-

CS(Mf)5

AL

-

-

-

-

-

-

-

-

LL

-

-

-

-

-

-

-

-

CS(Mf)3(N)

AL

-

-

-

-

-

-

-

-

LL

-

-

-

-

-

-

-

-

IS(Mf)16

AL

-

2019-09-18

-

-

-

-

2019-11-01

-

LL

-

-

-

-

-

-

-

-

SR4a

AL

-

2019-09-18

2019-09-16

2019-09-06

-

-

-

-

LL

-

-

-

-

-

-

-

-

SR4(N2)

AL

2019-09-23

2019-09-18

2019-09-23

2019-09-18

2019-09-20

-

-

-

-

LL

-

-

-

-

-

-

-

-

IS8(N)

AL

2019-09-16

2019-09-18

-

-

-

-

-

-

-

LL

-

-

-

-

-

-

-

-

IS(Mf)9

AL

2019-09-18

2019-09-18

-

-

-

-

2019-09-09

-

LL

-

-

-

-

-

-

-

-

Total AL Exceedances:

7

13

6

9

0

0

2

2

Total LL Exceedances:

0

0

0

0

0

0

0

0

Notes:

(a) AL = Action Level; LL = Limit Level


One (1) Limit Level exceedance was observed for the quarterly dolphin monitoring data between September and November 2019, whilst no unacceptable impact from the construction activities of the TM-CLKL Northern Connection Sub-sea Tunnel Section on Chinese White Dolphins was noticeable from general observations.

Cumulative statistics are provided in Appendix J.

2.9                         Summary of Complaints, Notification of Summons and Successful Prosecutions

The Environmental Complaint Handling Procedure is provided in Figure 2.4.

No environmental complaint was received in this reporting period.

No environmental summons was received in this reporting period.

Statistics on complaints, notifications of summons and successful prosecutions are summarized in Appendix J.

 

 

3                             Future Key Issues

3.1                         Construction Activities for the Coming Quarter

As informed by the Contractor, the major works for the Contract in the coming quarter are summarized in Table 3.1.

Table 3.1        Construction Works to Be Undertaken in the Coming Quarter

Works to be undertaken

Land-based Works

·         Construction of Thermal barrier – TBM tunnel;

·         Construction of Walkway Corbel & Cover – TBM Tunnel;

·         Road & Drainage works – Portion N-A

·         Gantry Crane Removal – Portion N-B & Portion S-C;

·         RC structure – Portion S-A;

·         E&M Platform Installation – Portion S-A

·         Backfilling – Portion S-A & S-C;

·         Water Treatment Facilities Dismantling – Portion S-C;

·         Cut & Cover Tunnel RC structure – Portion S-C

·         Tower Crane Removal – Portion S-C

 

Marine-based Works

·         Seawall Modification Works – Portion S-B

 

3.2                      Key Issues for the Coming Quarter

Potential environmental impacts arising from the above upcoming construction activities in the coming quarterly period are expected to be mainly associated with dust, marine ecology, marine water quality and waste management issues.

3.3                         Monitoring Schedule for the Coming Quarter

Impact monitoring for air quality and marine ecology (include dolphin monitoring) are scheduled to continue for the next reporting period.

The monitoring programme has been reviewed and was considered as adequate to cater for the nature of works in progress.  Change to the monitoring programme was thus not considered to be necessary at this stage.  The monitoring programme will be evaluated as appropriate in the next reporting period. 

 

4                             Conclusions

This Twenty-fourth Quarterly EM&A Report presents the findings of the EM&A activities undertaken during the period from 1 September 2019 to 30 November 2019, in accordance with the Updated EM&A Manual and the requirements of EP-354/2009/D.   

Air quality (including 1-hour TSP and 24-hour TSP), water quality and dolphin monitoring were carried out in the reporting period.  Eight (8) Action level and four (4) Limit Level exceedances of 1-hour TSP and were recorded in this reporting period.

Thirty-five (35) Action level of Dissolved Oxygen were recorded in this reporting period.  Four (4) Action Level exceedance for Depth-averaged suspended solids was recorded.

A total of 4 groups of 7 Chinese White Dolphins sightings were recorded during the six sets of surveys in this reporting quarter.  All four dolphin sightings were made during on-effort search, and three of the four on-effort dolphin sightings were made on primary lines.  Whilst one limit level exceedance was observed for the quarterly dolphin monitoring data between September to November 2019, no unacceptable impact from the construction activities of this Contract was recorded from the general observations.  Although the dolphins infrequently occurred along the alignment of TM-CLKL Northern Connection Sub-Sea Tunnel Section in the past and during the baseline monitoring period, it is apparent that dolphin usage has been significantly reduced in NEL.  It is critical to monitor the dolphin usage in North Lantau region in the upcoming quarters, to determine whether the dolphins are continuously affected by the various construction activities in relation to the construction works of the Contract, and whether suitable mitigation measure can be applied to improve the situation.

Thirteen weekly environmental site inspections were carried out in the reporting period.  Recommendations on remedial actions provided for the deficiencies identified during the site audits were properly implemented by the Contractor.  No non-compliance event was recorded during the reporting period.

The monitoring programme has been reviewed and was considered as adequate to cater for the nature of works in progress.  Change to the monitoring programme was thus not recommended at this stage.  The monitoring programme will be evaluated as appropriate in the next reporting period.  The ET will keep track on the construction works to confirm compliance of environmental requirements and the proper implementation of all necessary mitigation measures. 


 

 



([1])     ERM (2013) Enhanced TSP Monitoring Plan.  Submitted on 28 October 2013 and subsequently approved by EPD on 1 November 2013.