table of
Contents
Executive
Summary
1.1 Background
1.2 Scope of Report
1.3 Organization Structure
1.4 Summary of Construction Works
2.1 Air quality
2.2 Water Quality Monitoring
2.3 Dolphin Monitoring
2.4 Post-Translocation Coral
Monitoring
2.5 EM&A Site Inspection
2.6 Waste Management Status
2.7 Environmental Licenses and
Permits
2.8 Implementation Status of
Environmental Mitigation Measures
2.9 Summary of Exceedances of the
Environmental Quality Performance Limit
2.10 Summary of Complaints,
Notification of Summons and Successful Prosecutions
2.11 Comparison of EM&A Data
with EIA Predictions
2.12 Summary of Monitoring
Methodology and Effectiveness
2.13 Summary of Mitigation
Measures
3.1 Site Inspections & Audits
3.2 Air Quality Monitoring
3.3 Marine Water Quality Monitoring
3.4 Waste Management
3.5 Marine Ecology Monitoring
3.6 Summary of Recommendations
Under Contract No. HY/2012/08,
Dragages – Bouygues Joint Venture (DBJV) is
commissioned by the Highways Department (HyD) to
undertake the design and construction of the Northern Connection Sub-sea Tunnel
Section of the Tuen Mun – Chek Lap Kok Link Project (TM-CLK
Link Project) while AECOM Asia Company Limited was appointed by HyD as the Supervising Officer. For implementation of the environmental
monitoring and audit (EM&A) programme under the
Contract, ERM-Hong Kong, Limited (ERM) has been appointed as the Environmental
Team (ET) in accordance with Environmental
Permit No. EP-354/2009/A. ENVIRON Hong Kong Ltd. was employed by HyD as the Independent Environmental Checker (IEC) and
Environmental Project Office (ENPO). Another
application for VEP (EP-354/2009/B) was granted on 28 January 2014.
The construction phase of the Project commenced on 1
November 2013 and will tentatively be completed by the end of 2018. The impact monitoring of the EM&A programme, including air quality, water quality, marine
ecological monitoring and environmental site inspections, commenced on 1
November 2013.
This
is the First Annual EM&A report presenting the EM&A works carried out
during the period from 1 November 2013 to 31 October 2014 for the Contract No. HY/2012/08 Northern Connection
Sub-sea Tunnel Section (the “Project”) in
accordance with the Updated EM&A Manual of the TM-CLK
Link Project. As informed by the
Contractor, the major activities in the reporting year included:
Construction
Activities Undertaken |
Marine-based
Works |
Marine Works Area – Portions N-A, N-B, N-C ·
Dredging ·
Vertical
and Sloping Seawall construction ·
Reclamation
filling Marine Works Area – Portion N-A ·
Marine
Sheet Piling for box culvert extension ·
Box
Culvert extension ·
Removal
of existing seawall and temporary pontoon installation at River Trade
Terminal (RTT) |
Construction
Activities Undertaken |
Land-based
Works |
Works Area - WA 23 ·
Sorting
of rock material Works Area – WA 18 ·
Site
formation works ·
Site
office construction ·
Completion
of chain-link fence ·
Site
hoarding works Works Area – N6 ·
CLP
substation construction ·
Pile
Cap Construction ·
Land
Bored Piling Reclamation Works Area – Portion N-A ·
Construction
of temporary access ·
Diaphragm
Wall Construction ·
Excavation
for North Launching Shaft ·
Land
Bored Piling Works Reclamation Works Area – Portions N-B and N-C ·
Vibro-Compaction ·
Surcharge
set up |
A summary of monitoring and audit activities conducted
in the reporting period is listed below:
24-hour TSP Monitoring 68
sessions
1-hour TSP Monitoring 68
sessions
Impact Water Quality Monitoring 155 sessions
Impact Dolphin Monitoring 24 sessions
Joint Environmental Site Inspection 52 sessions
Post Translocation Coral Monitoring 4 sessions
Implementation
of Marine Mammal Exclusion Zone
Daily
marine mammal exclusion zone was in effect during the period of dredging, reclamation or marine sheet
piling works in open waters under
this Contract. Passive Acoustic
Monitoring (PAM) was also implemented for the detection of marine mammal when
dredging, reclamation
or marine sheet piling works were
carried out outside the daylight hours under this Contract. One sighting of the Indo-Pacific humpback
dolphin Sousa chinensis
was recorded on 20 February 2014 during the exclusion zone monitoring. The marine dredging work was subsequently
suspended until the
observer has confirmed that the area is continuously clear of dolphins for a
period of 30 minutes.
Summary of Breaches of Action/Limit Levels
Breaches of
Action and Limit Levels for Air Quality
Twenty-six Action Level and two Limit Level
exceedances for 1-hour TSP; five Action Level and one Limit Level exceedances
for 24-hour TSP were recorded from the air quality monitoring in this reporting
period. The exceedances were considered
to be due to the sporadic events from cumulative anthropogenic activities in
this area of Hong Kong.
Breaches of
Action and Limit Levels for Water Quality
Six Action Level and one Limit
Level for depth-averaged suspended solids (SS) exceedances were recorded from
the water quality monitoring in this reporting period. The exceedances were well within the natural
range and were unlikely to be due to the construction works of this Contract
upon further investigation.
Dolphin Monitoring
Whilst five (5) Action Level exceedances were recorded
for 3 sets of quarterly dolphin monitoring data between October 2013 and August
2014, no unacceptable impact from the construction activities of the TM-CLKL
Northern Connection Sub-sea Tunnel Section on Chinese White Dolphins was
noticeable from general observations during the dolphin monitoring in this
reporting period. The exceedances are
considered to be the natural variation of Chinese White Dolphin ranging
pattern.
Post Translocation Coral Monitoring
Four
(4) Post-Translocation Coral Monitoring Surveys were conducted on 17 January 2014,
16 April 2014, 24 July 2014 and 23 October 2014 and the results were provided
in the First to Fourth Quarterly Post-Translocation Coral Monitoring
Reports. No exceedances
were recorded from the four post-translocation coral monitoring surveys in this
reporting period.
Environmental
Complaints, Non-compliance & Summons
No
non-compliance with Environmental Impact Assessment (EIA) recommendations, EP conditions and other
requirements associated with the construction of this Contract was recorded in
this reporting period.
Two (2) environmental complaint cases
were received in this reporting period.
The interim reports were submitted to EPD and reported in the subsequent
EM&A reports. The investigation
findings showed that the cases were considered not related to the works under
this Contract and is thus invalid.
No
environmental summons was received in this reporting period.
Review of EM&A programme
The EM&A requirements have been reviewed and were
considered as adequate and effective. No
change to the requirements was considered to be necessary. The recommended environmental mitigation
measures are also considered to be effective and efficient in reducing the
potential environmental impacts associated with the construction of the
Project. No change was thus considered
necessary.
Overall, the EM&A results indicated that the
Project has not caused unacceptable environmental impacts. This is in agreement with the assessment
presented in the EIA Report
According to the findings of the Northwest New
Territories (NWNT) Traffic and Infrastructure Review conducted by the Transport
Department, Tuen Mun Road,
Ting Kau Bridge, Lantau Link and North Lantau Highway
would be operating beyond capacity after 2016.
This forecast has been based on the estimated increase in cross boundary
traffic, developments in the Northwest New Territories (NWNT), and possible
developments in North Lantau, including the Airport developments, the Lantau
Logistics Park (LLP) and the Hong Kong – Zhuhai – Macao Bridge (HZMB). In order to cope with the anticipated traffic
demand, two new road sections between NWNT and North Lantau – Tuen Mun – Chek
Lap Kok Link (TM-CLKL) and Tuen
Mun Western Bypass (TMWB) are proposed.
An Environmental Impact Assessment (EIA) of TM-CLKL
(the Project) was prepared in accordance with the EIA Study Brief (No. ESB-175/2007) and the Technical
Memorandum of the Environmental Impact Assessment Process (EIAO-TM). The EIA Report was submitted under the
Environmental Impact Assessment Ordinance (EIAO) in August 2009. Subsequent to the approval of the EIA Report
(EIAO Register Number AEIAR-146/2009), an Environmental Permit (EP-354/2009)
for TM-CLKL was granted by the Director of Environmental Protection (DEP) on 4
November 2009, and EP variation (VEP) (EP-354/2009A) was issued on 8 December
2010. Another application for VEP
(EP-354/2009/B) was granted on 28 January 2014.
Under Contract No. HY/2012/08,
Dragages – Bouygues Joint Venture (DBJV) is
commissioned by the Highways Department (HyD) to
undertake the design and construction of the Northern Connection Sub-sea Tunnel
Section of TM-CLKL while AECOM Asia Company Limited was appointed by HyD as the Supervising Officer. For implementation of the environmental
monitoring and audit (EM&A) programme under the
Contract, ERM-Hong Kong, Limited (ERM) has been appointed as the Environmental
Team (ET). ENVIRON Hong Kong Ltd. was employed by HyD as the Independent Environmental Checker (IEC) and
Environmental Project Office (ENPO).
Layout of the Contract components is
presented in Figure 1.1.
The organization structure of the Contract is shown in
Appendix A. The
key personnel contact names and contact details are summarized in Table 1.1 below.
Table 1.1 Contact Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
Highways
Department |
Engr
16/HZMB |
Kenneth Lee |
2762 4996 |
3188 6614 |
SOR (AECOM Asia
Company Limited) |
Chief
Resident Engineer |
Edwin Ching Andrew
Westmoreland |
2450 3111 2450 3511 |
2450 3099 2450 3099 |
ENPO / IEC (ENVIRON
Hong Kong Ltd.) |
ENPO Leader |
Y.H. Hui |
3547 2133 |
3465 2899 |
IEC |
F. C. Tsang |
3547 2134 |
3465 2899 |
|
Contractor (Dragages – Bouygues Joint Venture) |
Environmental
Manager |
C.F. Kwong |
2293 7322 |
2670 2798 |
Environmental
Officer 24-hour
complaint hotline |
Bryan Lee Rachel Lam |
2293 7323 2293 7330 |
2670 2798 |
|
ET (ERM-HK) |
ET Leader |
Jovy Tam |
2271 3113 |
2723 5660 |
The general layout plan of the site showing the
detailed works areas is shown in Figure 1.2. The
Environmental Sensitive Receivers in the vicinity of the Project are shown in Figure 1.3.
Table 1.2 Summary of Construction Activities Undertaken during the Reporting
Period
|
Figure 1.2 Locations of Construction Activities –
November 2013 to October 2014
Contract no. HY/2013/12, Toll Plaza at Tuen Mun Area 46 |
||
|
||
Land-based
Works at Site WA-23 |
||
|
The EM&A programme
required environmental monitoring for air quality, water quality and marine
ecology as well as environmental site inspections for air quality, noise, water
quality, waste management, marine ecology and landscape and visual impacts. The EM&A requirements and related
findings for each component are summarized in the following sections
As per Condition 2.4 of EP-354/2009/B,
the Enhanced TSP Monitoring Plan ([1]) has been prepared under Contract No. HY/2012/08
which describes the air quality monitoring programme
for the Project.
In accordance with the Updated EM&A Manual and the
Enhanced
TSP Monitoring Plan, impact 1-hour TSP monitoring was conducted three (3)
times in every six (6) days and impact 24-hour TSP monitoring was carried out
once in every six (6) days when the highest dust impact was expected. 1-hour and 24-hour TSP monitoring frequency
were increased to three times per day in every three days and continuously for
24 hours for one day in every three days, respectively, as excavation works for
launching shaft commenced on 24 October 2014.
High volume samplers (HVSs) were used to carry out the
1-hour and 24-hour TSP monitoring in the reporting period at the five (5) air
quality monitoring stations in accordance with the requirements stipulated in
the Updated EM&A Manual (Figure 2.1; Table 2.1). Wind anemometer was installed at the rooftop
of ASR5 for logging wind speed and wind direction. Details of the equipment deployed are
provided in Table 2.2.
Table 2.1 Locations of Impact Air Quality Monitoring Stations and
Monitoring Dates in this Reporting Period
Monitoring Station |
Location |
Description |
Parameters
& Frequency |
ASR1 |
Tuen Mun Fireboat Station |
Office |
TSP monitoring
1-hour Total
Suspended Particulates (1-hour TSP, µg/m3), 3 times in every 6
days
24-hour Total
Suspended Particulates (24-hour TSP, µg/m3), daily for 24-hour in
every 6 days Enhanced TSP monitoring (commenced on 24 October 2014)
1-hour Total
Suspended Particulates (1-hour TSP, µg/m3), 3 times in every 3
days
24-hour Total
Suspended Particulates (24-hour TSP, µg/m3), daily for 24-hour in
every 3 days |
ASR5 |
Pillar
Point Fire Station |
Office |
|
AQMS1 |
Previous
River Trade Golf |
Bare
ground |
|
AQMS2/ASR6 |
Bare
ground at Ho Suen Street /Butterfly Beach Laundry |
Bare
ground/Office |
|
ASR10 |
Butterfly
Beach Park |
Recreational
uses |
*Notes:
AQMS2
was relocated and HVS was re-installed at ASR6 (Butterfly Beach Laundry) on 17
January 2014. AQMS2 was then superseded
by ASR6 for the impact air quality monitoring.
Impact air quality monitoring at ASR6 commenced on 21 January 2014.
Table 2.2 Air
Quality Monitoring Equipment
Equipment |
Brand and Model |
High Volume Sampler |
Tisch Environmental Mass Flow Controlled Total Suspended
Particulate (TSP) High Volume Sampler (Model No. TE-5170) |
Wind Meter |
MetPak (Model: MetPak II (S/N:
13130002) |
Wind Anemometer for calibration |
Lutron (Model No. AM-4201) |
The Action and Limit Levels of the air quality
monitoring are provided in Appendix C. The Event and Action plan is presented in Appendix G.
Impact air quality monitoring was conducted at all
designated monitoring stations in the reporting period under favourable weather conditions. The major dust sources in the reporting
period include construction activities under the Contract as well as nearby
traffic emissions.
The monitoring results for 1-hour TSP and 24-hour TSP
are summarized in Tables 2.3 and 2.4, respectively. Baseline and impact monitoring results are
presented graphically in Appendix D. The detailed impact air quality monitoring
data and meteorological information were reported in the First to Twelve Monthly
EM&A Report.
Table 2.3 Summary of 1-hour TSP Monitoring Results in this Reporting
Period
Month/Year |
Station |
Average (µg/m3) |
Range (µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
November
2013 to October 2014 |
ASR 1 |
178 |
56
– 474 |
331 |
500 |
ASR 5 |
194 |
43
– 559 |
340 |
500 |
|
AQMS1 |
142 |
38
– 431 |
335 |
500 |
|
AQMS2/ASR6 |
163 |
52
– 425 |
338 |
500 |
|
ASR10 |
121 |
43
– 645 |
337 |
500 |
Table 2.4 Summary of 24-hour TSP Monitoring Results in this Reporting
Period
Month/Year |
Station |
Average (µg/m3) |
Range (µg/m3) |
Action Level (µg/m3) |
Limit Level (µg/m3) |
November
2013 to October 2014 |
ASR 1 |
101 |
32
– 249 |
213 |
260 |
ASR 5 |
106 |
39
– 258 |
238 |
260 |
|
AQMS1 |
86 |
38
– 228 |
213 |
260 |
|
AQMS2/ASR6 |
94 |
38
– 269 |
238 |
260 |
|
ASR10 |
72 |
33
– 166 |
214 |
260 |
In this reporting period, a total of 68 monitoring
events were undertaken in which 26 Action Level exceedances and two (2) Limit
Level exceedances for 1-hour TSP as well as five (5) Action Level exceedances
and one (1) Limit Level exceedances for 24-hour TSP were recorded. Summary of Exceedances for Air Quality Impact
Monitoring in this reporting period is detailed in Table 2.24.
As shown in Table
2.5, the annual average 24-hour TSP levels in the reporting period were
generally lower than the corresponding average levels baseline at most
monitoring stations, whilst the annual average 1-hour TSP levels in the
reporting period were generally higher than the corresponding average baseline
levels at most monitoring stations, except for ASR 10.
In order to determine any significant air quality
impacts caused by construction activities from this Contract, One-way ANOVA
(with α set at 0.05) was conducted to examine any significant difference
in average TSP levels between the impact monitoring in this reporting period
and the baseline monitoring before commencement of construction
activities. For 1-hour TSP, the average
levels at monitoring stations AQMS2/ASR6, ASR1 and ASR5 in the reporting period
were significantly higher than the average levels recorded in the baseline
monitoring while there were no significant differences for other stations
(AQMS1: F 1, 244 = 0.93, p = 0.34, AQMS2/ASR6: F 1, 244 = 5.08, p < 0.05, ASR1: F 1, 244 = 18.83, p
< 0.01, ASR10: F 1,244
= 1.34, p = 0.25 and ASR5: F 1, 244 = 18.4, p < 0.01). For 24-hour TSP, the average levels at all
monitoring stations in the reporting period were significantly lower than the
average levels of baseline monitoring (AQMS1: F 1, 80 = 9.93, p
< 0.01, AQMS2/ASR6: F 1, 80
= 26.69, p < 0.01, ASR1: F 1, 80 = 5.15, p < 0.05, ASR10: F 1, 80 = 37.72, p
< 0.01 and ASR5: F 1, 80
= 19.41, p < 0.01). In the reporting period, levels of 1-hour and
24-hour TSP varied across sampling months (see Appendix D)
and these variations were, however, not consistent throughout the reporting
period.
Table 2.5 Summary of Average Levels of TSP Level of Baseline Monitoring
and Reporting Period (in µg/m3)
Monitoring Station |
Average
Baseline Monitoring |
Average
Impact Monitoring |
ASR1 (1-hour TSP) |
125 |
178 |
ASR1 (24-hour
TSP) |
128 |
101 |
ASR5 (1-hour TSP) |
138 |
194 |
ASR5 (24-hour
TSP) |
167 |
106 |
AQMS1 (1-hour TSP) |
131 |
141 |
AQMS1 (24-hour
TSP) |
127 |
86 |
AQMS2/ASR6 (1-hour TSP) |
135 |
163 |
AQMS2/ASR6 (24-hour
TSP) |
166 |
94 |
ASR10 (1-hour TSP) |
134 |
121 |
ASR10 (24-hour
TSP) |
129 |
72 |
Further to the One-way ANOVA, Linear Regression was
conducted to examine any relationship between TSP levels and time (i.e. number
of days after construction works commencement) during this yearly monitoring
period at each monitoring station.
Linear regression analysis makes assumptions of equal variance and
normal distribution of data. Therefore,
the significance level of the test was set at 1 % (i.e. p = 0.01) to reduce the chance of committing a Type 1 error. If a significant regression relationship was
found between TSP level and time (i.e. p <
0.01), r2 value from the analysis would be further assessed. This value represents the proportion of the
total variation in the dependent variable (i.e. TSP level) that is accounted
for by the fitted regression line and is referred to as the coefficient of
determination. An r2 value of
1 indicates a perfect relationship (or fit) whereas a value of 0 indicates that
there is no relationship (or no fit) between the dependent and independent
variables. As there are no specific
criteria to indicate how meaningful an r2 value is, for the purposes
of this EM&A programme a value of 0.60 was
adopted to indicate a meaningful regression.
If r2 < 0.60 then it was considered that there was a weak
relationship between TSP level and time or none at all. If the regression analysis indicated r2
> 0.60 then it had been interpreted that there was in fact a strong
relationship between the dependent and independent variables (i.e. a strong
temporal trend of increasing / decreasing TSP level with time).
As shown in Table
2.6, results of the regression analysis indicated that there was no
significant (r2 < 0.60) relationship between TSP level and time
during this yearly monitoring period. As
such, it is considered that there is no apparent trend of increasing /
decreasing TSP level since commencement of constructions works.
Table 2.6 Linear Regression Result of TSP Monitoring
Parameter |
Station |
R2 |
F-ratio |
p-value |
Intercept |
Coefficient |
1-hour TSP |
AQMS1 |
0.079 |
F1,202 = 17.4 |
<0.001 |
175.0 |
-0.182 |
AQMS2/ASR6 |
0.061 |
F1,202 = 13.2 |
<0.001 |
195.3 |
-0.177 |
|
ASR1 |
0.017 |
F1,202 = 3.39 |
0.07 |
195.7 |
-0.094 |
|
ASR10 |
0.129 |
F1,202 = 30.0 |
<0.001 |
163.3 |
-0.229 |
|
ASR5 |
0.060 |
F1,202 = 12.8 |
<0.001 |
229.1 |
-0.190 |
|
24-hour TSP |
AQMS1 |
0.262 |
F1,66 = 23.4 |
<0.001 |
126.1 |
-0.217 |
AQMS2/ASR6 |
0.236 |
F1,66 = 20.4 |
<0.001 |
135.2 |
-0.222 |
|
|
ASR1 |
0.108 |
F1,66 = 8.02 |
<0.001 |
123.8 |
-0.125 |
|
ASR10 |
0.120 |
F1,66 = 9.03 |
<0.001 |
90.6 |
-0.102 |
|
ASR5 |
0.242 |
F1,66 = 21.1 |
<0.001 |
145.7 |
-0.217 |
Note:
1. Dependent variable is set as TSP levels (in µg/m3) and
independent variable is set as number of day of construction works.
2. R2 <0.6 and p-value >0.01 (i.e. showing the
regression insignificant) are underlined.
3. By setting α at 0.01, insignificant coefficient is underlined.
The baseline water quality monitoring undertaken by
the Hong Kong – Zhuhai – Macao Bridge Hong Kong Projects (HKZMB) between 6 and
31 October 2011 has included all monitoring stations for the Project. Thus, the baseline monitoring results and
Action/Limit Levels presented in HKZMB Baseline Monitoring Report ([2])
are adopted for this Project.
In accordance with the Updated EM&A Manual, impact
water quality monitoring was carried out three days per week during the
construction period at nine (9) water quality monitoring stations (Figure 2.2; Table
2.7).
Table 2.7 Locations of Water Quality Monitoring Stations and the Corresponding
Monitoring Requirements
Station ID |
Type |
Coordinates |
*Parameters,
unit |
Depth |
Frequency |
|
|
|
Easting |
Northing |
|
|
|
IS12 |
Impact Station |
813218 |
823681 |
Temperature(°C) pH(pH unit) Turbidity (NTU) Water depth (m) Salinity (ppt) DO (mg/L and % of saturation) · SS (mg/L) |
3 water depths:
1m below sea
surface, mid-depth and 1m above sea bed. If the water depth is less than 3m,
mid-depth sampling only. If water
depth less than 6m, mid-depth may be omitted. |
Impact monitoring: 3 days
per week, at mid-flood and mid-ebb tides during the construction period of
the Contract. |
IS13 |
Impact
Station |
813667 |
824325 |
|||
IS14 |
Impact
Station |
812592 |
824172 |
|||
IS15 |
Impact
Station |
813356 |
825008 |
|||
CS4 |
Control /
Far Field Station |
810025 |
824004 |
|||
CS6 |
Control /
Far Field Station |
817028 |
823992 |
|||
SR8 |
Sensitive receiver (Gazettal beaches in Tuen Mun) |
816306 |
825715 |
|||
SR9 |
Sensitive receiver |
813601 |
825858 |
|||
SR10A |
Sensitive receiver |
823741 |
823495 |
|||
*Notes: In addition to the parameters presented
monitoring location/position, time, water depth, sampling depth, tidal
stages, weather conditions and any special phenomena or works underway nearby
were also recorded. |
Table 2.8
summarizes the equipment used in the impact water quality monitoring programme.
Table 2.8 Water Quality Monitoring Equipment
Equipment |
Model |
Qty. |
Water Sampler |
Kahlsico Water-Bottle Model 135DW 150 |
1 |
Dissolved Oxygen Meter |
YSI Pro 2030 |
1 |
pH Meter |
HANNA HI 8314 |
1 |
Turbidity Meter |
HACH 2100Q |
1 |
Monitoring Position Equipment |
“Magellan” Handheld GPS Model explorist GC |
4 |
DGPS Koden KGP913MK2 (1) |
1 |
The Action and Limit Levels of the water quality
monitoring is provided in Appendix C. The Event and Action plan is presented in Appendix G.
During this reporting period, major marine works
included dredging, seawall construction and reclamation filling. A closed grab dredger was used and silt
curtains (cage-type and single floating type) were deployed during dredging
works in accordance with the EP. The
level of dredging activities was within the working rate described in the EP
and the approved EIA Report. In
addition, reclamation filling was undertaken between the 200 m of leading
seawalls using filling materials specified in the EP and the approved EIA
Report with a single layer silt curtain being deployed as a precautionary
measure to reduce dispersion of suspended solids. It is useful to note that heavy marine
traffic (not associated with the Project) was commonly observed nearby the
Project site and its vicinity. On 6
August 2014, dredging at Northern Landfall was fully completed.
Impact water quality monitoring was conducted at all
designated monitoring stations in the reporting period under favourable weather conditions. Baseline and impact monitoring results are
presented graphically in Appendix E and
detailed impact water quality monitoring data were reported in the First to Twelve Monthly EM&A Report.
In this reporting period, a total of 155 monitoring
events were undertaken in which six (6) Action Level and one (1) Limit Level
exceedances were recorded for depth-averaged suspended solids (SS). Summary of Exceedances for Water Quality Impact
Monitoring in this Reporting Period is detailed in Table 2.25.
One-way ANOVA (with α setting at 0.05) was
conducted to examine any significant difference in DO, turbidity and SS levels
between this reporting period and the baseline monitoring period. The annual average levels and statistical
analysis results are presented in Tables
2.9 to 2.11 and Tables 2.12 to 2.14,
respectively. In general, the DO levels
recorded during the reporting period were mostly comparable to the results
obtained during the baseline monitoring period, except for SR 8, SR 9, SR10A
and SR15 in which DO levels during this reporting period in mid-flood tide were
significantly higher than the corresponding average baseline levels. The annual depth-averaged turbidity and SS
levels at all impact stations in the reporting period were significantly lower
than the average levels in baseline monitoring.
Whilst DO, turbidity and suspended solids levels varied across sampling
months (see Appendix E), these
variations were, however, not consistent throughout the reporting period.
Table 2.9 Summary of Average DO Level of Baseline Monitoring and the
current Reporting Period (in mg/L)
Tide |
Station |
Depth |
Average DO of baseline monitoring |
Average DO of reporting period |
Mid-ebb |
IS12 |
Surface |
6.1 |
6.3 |
IS13 |
Surface |
6.1 |
6.3 |
|
IS14 |
Surface |
6.1 |
6.3 |
|
IS15 |
Surface |
6.1 |
6.3 |
|
SR10A |
Surface |
6.0 |
6.4 |
|
SR8 |
Surface |
6.2 |
6.4 |
|
SR9 |
Surface |
6.0 |
6.3 |
|
Mid-flood |
IS12 |
Surface |
6.1 |
6.4 |
IS13 |
Surface |
6.1 |
6.4 |
|
IS14 |
Surface |
6.1 |
6.4 |
|
IS15 |
Surface |
6.2 |
6.4 |
|
SR10A |
Surface |
6.0 |
6.4 |
|
SR8 |
Surface |
6.2 |
6.4 |
|
SR9 |
Surface |
6.0 |
6.4 |
|
Mid-ebb |
IS12 |
Middle |
5.9 |
6.2 |
IS13 |
Middle |
6.0 |
6.2 |
|
IS14 |
Middle |
6.0 |
6.2 |
|
IS15 |
Middle |
6.0 |
6.2 |
|
SR10A |
Middle |
5.9 |
6.2 |
|
Mid-flood |
IS12 |
Middle |
5.9 |
6.3 |
IS13 |
Middle |
6.0 |
6.3 |
|
IS14 |
Middle |
5.9 |
6.2 |
|
IS15 |
Middle |
6.1 |
6.2 |
|
SR10A |
Middle |
5.9 |
6.3 |
|
Mid-ebb |
IS12 |
Bottom |
5.9 |
6.1 |
IS13 |
Bottom |
5.9 |
6.1 |
|
IS14 |
Bottom |
5.9 |
6.0 |
|
IS15 |
Bottom |
5.9 |
6.0 |
|
SR10A |
Bottom |
5.7 |
6.1 |
|
SR8 |
Bottom |
6.0 |
6.2 |
|
SR9 |
Bottom |
5.8 |
6.1 |
|
Mid-flood |
IS12 |
Bottom |
5.9 |
6.2 |
IS13 |
Bottom |
5.9 |
6.1 |
|
IS14 |
Bottom |
5.9 |
6.1 |
|
IS15 |
Bottom |
6.0 |
6.1 |
|
SR10A |
Bottom |
5.8 |
6.1 |
|
SR8 |
Bottom |
5.8 |
6.2 |
|
SR9 |
Bottom |
5.9 |
6.2 |
Table 2.10 Summary of
Average Depth-averaged Turbidity Level of Baseline Monitoring and the current
Reporting Period (in NTU)
Tide |
Station |
Average depth-averaged turbidity of baseline monitoring |
Average depth-averaged turbidity of reporting period |
Mid-ebb |
IS12 |
10.7 |
5.1 |
IS13 |
9.2 |
5.1 |
|
IS14 |
9.3 |
5.0 |
|
IS15 |
9.8 |
5.1 |
|
SR10A |
7.1 |
4.9 |
|
|
SR8 |
11.0 |
5.0 |
|
SR9 |
7.2 |
4.9 |
Mid-flood |
IS12 |
9.8 |
5.1 |
IS13 |
9.5 |
5.0 |
|
IS14 |
9.4 |
5.0 |
|
IS15 |
9.8 |
5.1 |
|
SR10A |
7.0 |
4.8 |
|
|
SR8 |
10.1 |
5.0 |
|
SR9 |
8.5 |
4.9 |
Table 2.11 Summary of Average Depth-averaged SS Level of Baseline
Monitoring and the current Reporting Period (in mg/L)
Tide |
Station |
Average depth-averaged SS of baseline monitoring |
Average depth-averaged SS of reporting period |
Mid-ebb |
IS12 |
9.2 |
5.3 |
IS13 |
10.0 |
5.2 |
|
IS14 |
10.4 |
5.3 |
|
IS15 |
9.6 |
5.3 |
|
SR10A |
10.3 |
5.3 |
|
|
SR8 |
10.1 |
5.2 |
|
SR9 |
8.8 |
5.2 |
Mid-flood |
IS12 |
9.5 |
5.4 |
IS13 |
10.5 |
5.2 |
|
IS14 |
9.7 |
5.3 |
|
IS15 |
11.0 |
5.4 |
|
SR10A |
10.2 |
5.2 |
|
|
SR8 |
11.3 |
5.3 |
|
SR9 |
9.9 |
5.3 |
Table 2.12 One-way ANOVA Results for DO Comparison between Impact and
Baseline Periods
Tide |
Station |
Depth |
F ratio |
p-value |
Mid-ebb |
IS12 |
Surface |
F1,164
= 2.51 |
0.12 |
Mid-ebb |
IS13 |
Surface |
F1,164
= 2.72 |
0.10 |
Mid-ebb |
IS14 |
Surface |
F1,164
= 1.27 |
0.26 |
Mid-ebb |
IS15 |
Surface |
F1,164
= 1.46 |
0.23 |
Mid-ebb |
SR10A |
Surface |
F1,164
= 4.02 |
0.05 |
Mid-ebb |
SR8 |
Surface |
F1,164
= 0.45 |
0.50 |
Mid-ebb |
SR9 |
Surface |
F1,164
= 3.40 |
0.07 |
Mid-flood |
IS12 |
Surface |
F1,164
= 3.47 |
0.06 |
Mid-flood |
IS13 |
Surface |
F1,164
= 2.43 |
0.12 |
Mid-flood |
IS14 |
Surface |
F1,164
= 2.90 |
0.09 |
Mid-flood |
IS15 |
Surface |
F1,164
= 1.12 |
0.29 |
Mid-flood |
SR10A |
Surface |
F1,164
= 6.01 |
0.02 |
Mid-flood |
SR8 |
Surface |
F1,164
= 1.86 |
0.17 |
Mid-flood |
SR9 |
Surface |
F1,164
= 5.54 |
0.02 |
Mid-ebb |
IS12 |
Middle |
F1,164
= 3.20 |
0.08 |
Mid-ebb |
IS13 |
Middle |
F1,164
= 1.53 |
0.22 |
Mid-ebb |
IS14 |
Middle |
F1,164
= 1.18 |
0.28 |
Mid-ebb |
IS15 |
Middle |
F1,164
= 0.76 |
0.38 |
Mid-ebb |
SR10A |
Middle |
F1,164
= 2.99 |
0.09 |
Mid-flood |
IS12 |
Middle |
F1,164
= 3.79 |
0.05 |
Mid-flood |
IS13 |
Middle |
F1,164
= 2.10 |
0.15 |
Mid-flood |
IS14 |
Middle |
F1,164
= 2.52 |
0.11 |
Mid-flood |
IS15 |
Middle |
F1,164
= 0.60 |
0.44 |
Mid-flood |
SR10A |
Middle |
F1,164
= 4.97 |
0.03 |
Mid-ebb |
IS12 |
Bottom |
F1,164
= 1.82 |
0.18 |
Mid-ebb |
IS13 |
Bottom |
F1,164
= 1.12 |
0.29 |
Mid-ebb |
IS14 |
Bottom |
F1,164
= 0.18 |
0.67 |
Mid-ebb |
IS15 |
Bottom |
F1,164
= 1.07 |
0.30 |
Mid-ebb |
SR10A |
Bottom |
F1,164
= 3.13 |
0.08 |
Mid-ebb |
SR8 |
Bottom |
F1,164
= 0.42 |
0.52 |
Mid-ebb |
SR9 |
Bottom |
F1,164
= 2.97 |
0.09 |
Mid-flood |
IS12 |
Bottom |
F1,164
= 2.78 |
0.10 |
Mid-flood |
IS13 |
Bottom |
F1,164
= 1.88 |
0.17 |
Mid-flood |
IS14 |
Bottom |
F1,164
= 0.95 |
0.33 |
Mid-flood |
IS15 |
Bottom |
F1,164
= 0.43 |
0.51 |
Mid-flood |
SR10A |
Bottom |
F1,164
= 2.04 |
0.15 |
Mid-flood |
SR8 |
Bottom |
F1,164
= 4.67 |
0.03 |
Mid-flood |
SR9 |
Bottom |
F1,164
= 2.12 |
0.15 |
Note: By setting
α at 0.05, significant differences (p-value
< 0.05) are bold. |
Table 2.13 One-way ANOVA Results for Depth-averaged Turbidity Comparison
between Impact and Baseline Periods
Tide |
Station |
F ratio |
p-value |
Mid-ebb |
IS12 |
F1,164
= 51.79 |
<0.01 |
Mid-ebb |
IS13 |
F1,164
= 28.76 |
<0.01 |
Mid-ebb |
IS14 |
F1,164
= 31.68 |
<0.01 |
Mid-ebb |
IS15 |
F1,164
= 31.09 |
<0.01 |
Mid-ebb |
SR10A |
F1,164
= 11.34 |
<0.01 |
Mid-ebb |
SR8 |
F1,164
= 49.82 |
<0.01 |
Mid-ebb |
SR9 |
F1,164
= 9.10 |
<0.01 |
Mid-flood |
IS12 |
F1,164
= 31.15 |
<0.01 |
Mid-flood |
IS13 |
F1,164
= 31.63 |
<0.01 |
Mid-flood |
IS14 |
F1,164
= 33.05 |
<0.01 |
Mid-flood |
IS15 |
F1,164
= 30.16 |
<0.01 |
Mid-flood |
SR10A |
F1,164
= 9.80 |
<0.01 |
Mid-flood |
SR8 |
F1,164
= 31.40 |
<0.01 |
Mid-flood |
SR9 |
F1,164
= 20.43 |
<0.01 |
Note: By setting
α at 0.05, significant differences (p-value
< 0.05) are bold. |
Table 2.14 One-way ANOVA Results for Depth-averaged SS Comparison between
Impact and Baseline Periods
Tide |
Station |
F ratio |
p-value |
Mid-ebb |
IS12 |
F1,164
= 16.90 |
<0.01 |
Mid-ebb |
IS13 |
F1,164
= 30.28 |
<0.01 |
Mid-ebb |
IS14 |
F1,164
= 28.55 |
<0.01 |
Mid-ebb |
IS15 |
F1,164
= 17.37 |
<0.01 |
Mid-ebb |
SR10A |
F1,164
= 27.43 |
<0.01 |
Mid-ebb |
SR8 |
F1,164
= 25.82 |
<0.01 |
Mid-ebb |
SR9 |
F1,164
= 14.14 |
<0.01 |
Mid-flood |
IS12 |
F1,164
= 12.75 |
<0.01 |
Mid-flood |
IS13 |
F1,164
= 34.13 |
<0.01 |
Mid-flood |
IS14 |
F1,164
= 19.18 |
<0.01 |
Mid-flood |
IS15 |
F1,164
= 29.62 |
<0.01 |
Mid-flood |
SR10A |
F1,164
= 31.47 |
<0.01 |
Mid-flood |
SR8 |
F1,164
= 39.65 |
<0.01 |
Mid-flood |
SR9 |
F1,164
= 21.20 |
<0.01 |
Note: By setting
α at 0.05, significant differences (p-value < 0.05) are bold. In addition,
linear regression was conducted to examine any relationship between DO /
Turbidity / SS levels and time (i.e. number of days after construction works
commencement) during this yearly monitoring period at each monitoring
station. The method of data
interpretation followed the same method as indicated in Section 2.1.3 for TSP monitoring.
As shown in Tables 2.15 to 2.17,
results of the regression analysis indicated that there was no significant (r2
< 0.60) relationship between DO / Turbidity / SS level and time during
this yearly monitoring period. As
such, it is considered that there is no apparent trend of increasing or
decreasing DO / Turbidity / SS level since commencement of constructions
works. |
Table
2.15 Linear Regression Result of DO
Parameter |
Station |
R2 |
F1,152 |
p-value |
Intercept |
Coefficient of days of construction |
Mid-ebb
Surface DO |
IS12 |
0.325 |
73.1 |
<0.001 |
6.898 |
-0.003 |
IS13 |
0.291 |
62.6 |
<0.001 |
6.866 |
-0.003 |
|
IS14 |
0.315 |
69.9 |
<0.001 |
6.858 |
-0.003 |
|
IS15 |
0.330 |
75.0 |
<0.001 |
6.920 |
-0.003 |
|
SR10A |
0.293 |
63.0 |
<0.001 |
6.945 |
-0.003 |
|
SR8 |
0.322 |
72.3 |
<0.001 |
6.955 |
-0.003 |
|
SR9 |
0.368 |
88.7 |
<0.001 |
6.953 |
-0.003 |
|
Parameter |
Station |
R2 |
F1,153 |
p-value |
Intercept |
Coefficient of days of construction |
Mid-flood
surface DO |
IS12 |
0.331 |
75.7 |
<0.001 |
6.969 |
-0.003 |
IS13 |
0.311 |
69.0 |
<0.001 |
6.957 |
-0.003 |
|
IS14 |
0.333 |
76.5 |
<0.001 |
6.929 |
-0.003 |
|
IS15 |
0.359 |
85.8 |
<0.001 |
6.999 |
-0.003 |
|
SR10A |
0.302 |
66.1 |
<0.001 |
7.010 |
-0.003 |
|
SR8 |
0325 |
73.8 |
<0.001 |
7.015 |
-0.003 |
|
SR9 |
0.384 |
95.3 |
<0.001 |
7.043 |
-0.003 |
|
Parameter |
Station |
R2 |
F1,152 |
p-value |
Intercept |
Coefficient of days of construction |
Mid-ebb
middle DO |
IS12 |
0.351 |
82.3 |
<0.001 |
6.826 |
-0.003 |
IS13 |
0.307 |
67.5 |
<0.001 |
6.791 |
-0.003 |
|
IS14 |
0.407 |
104.5 |
<0.001 |
6.821 |
-0.004 |
|
IS15 |
0.357 |
84.5 |
<0.001 |
6.800 |
-0.003 |
|
SR10A |
0.317 |
70.6 |
<0.001 |
6.815 |
-0.003 |
|
Parameter |
Station |
R2 |
F1,153 |
p-value |
Intercept |
Coefficient of days of construction |
Mid-flood
middle DO |
IS12 |
0.341 |
79.3 |
<0.001 |
6.913 |
-0.003 |
IS13 |
0.320 |
71.9 |
<0.001 |
6.875 |
-0.003 |
|
IS14 |
0.402 |
102.9 |
<0.001 |
6.880 |
-0.004 |
|
IS15 |
0.355 |
84.2 |
<0.001 |
6.881 |
-0.003 |
|
SR10A |
0.329 |
75.1 |
<0.001 |
6.871 |
-0.003 |
|
Parameter |
Station |
R2 |
F1,152 |
p-value |
Intercept |
Coefficient of days of construction |
Mid-ebb
bottom DO |
IS12 |
0.353 |
83.0 |
<0.001 |
6.786 |
-0.004 |
IS13 |
0.306 |
67.1 |
<0.001 |
6.703 |
-0.003 |
|
IS14 |
0.425 |
112.3 |
<0.001 |
6.758 |
-0.004 |
|
IS15 |
0.380 |
93.2 |
<0.001 |
6.739 |
-0.004 |
|
SR10A |
0.372 |
90.1 |
<0.001 |
6.771 |
-0.004 |
|
SR8 |
0.368 |
88.4 |
<0.001 |
6.876 |
-0.004 |
|
SR9 |
0.368 |
88.7 |
<0.001 |
6.798 |
-0.004 |
|
Parameter |
Station |
R2 |
F1,153 |
p-value |
Intercept |
Coefficient of days of construction |
Mid-flood
bottom DO |
IS12 |
0.362 |
86.7 |
<0.001 |
6.883 |
-0.004 |
IS13 |
0.309 |
68.6 |
<0.001 |
6.779 |
-0.004 |
|
IS14 |
0.422 |
111.8 |
<0.001 |
6.842 |
-0.004 |
|
IS15 |
0.379 |
93.4 |
<0.001 |
6.811 |
-0.004 |
|
SR10A |
0.391 |
98.1 |
<0.001 |
6.863 |
-0.004 |
|
SR8 |
0.387 |
96.5 |
<0.001 |
6.945 |
-0.004 |
|
SR9 |
0.371 |
90.4 |
<0.001 |
6.903 |
-0.004 |
Note:
1. Dependent variable is set as DO (in mg/L) and independent variable is
set as number of day of construction works.
2. R2 <0.6 and p-value >0.01 (i.e. showing the
regression insignificant) are underlined.
3. By setting α at 0.01, insignificant coefficient is underlined.
Table 2.16 Linear Regression
Result of Turbidity
Parameter |
Station |
R2 |
F1,152 |
p-value |
Intercept |
Coefficient of days of construction |
|||
Mid-ebb
depth -average
turbidity |
IS12 |
0.011 |
1.67 |
0.199 |
4.644 |
0.002 |
|||
IS13 |
0.001 |
0.23 |
0.636 |
4.895 |
0.001 |
||||
IS14 |
0.008 |
1.16 |
0.283 |
4.634 |
0.002 |
||||
IS15 |
<0.001 |
0.03 |
0.856 |
5.010 |
<0.001 |
||||
SR10A |
0.014 |
2.17 |
0.143 |
4.442 |
0.002 |
||||
SR8 |
<0.001 |
<0.001 |
0.996 |
5.048 |
<0.001 |
||||
SR9 |
<0.001 |
0.06 |
0.808 |
4.859 |
<0.001 |
||||
Parameter |
Station |
R2 |
F1,153 |
p-value |
Intercept |
Coefficient of days of construction |
|||
Mid-flood
depth -average
turbidity |
IS12 |
0.002 |
0.4 |
0.529 |
4.858 |
0.001 |
|||
IS13 |
0.003 |
0.42 |
0.518 |
4.792 |
0.001 |
||||
IS14 |
0.004 |
0.654 |
0.420 |
4.706 |
0.001 |
||||
IS15 |
<0.001 |
0.002 |
0.965 |
5.117 |
<0.001 |
||||
SR10A |
0.009 |
1.42 |
0.235 |
4.479 |
0.002 |
||||
SR8 |
<0.001 |
0.019 |
0.890 |
5.069 |
<0.001 |
||||
SR9 |
<0.001 |
0.008 |
0.927 |
4.901 |
<0.001 |
||||
Note:
1. Dependent variable is set as Turbidity (in mg/L) and independent
variable is set as number of day of construction works.
2. R2 <0.6 and p-value >0.01 (i.e. showing the
regression insignificant) are underlined.
3. By setting α at 0.01, insignificant coefficient is underlined.
Table 2.17 Linear Regression
Result of SS
Parameter |
Station |
R2 |
F1,152 |
p-value |
Intercept |
Coefficient of days of construction |
|||
Mid-ebb
depth -average
SS |
IS12 |
0.019 |
2.94 |
0.088 |
4.563 |
0.004 |
|||
IS13 |
0.013 |
2.00 |
0.160 |
4.651 |
0.003 |
||||
IS14 |
0.013 |
2.06 |
0.153 |
4.633 |
0.003 |
||||
IS15 |
<0.001 |
0.14 |
0.704 |
5.142 |
0.001 |
||||
SR10A |
0.009 |
1.39 |
0.240 |
4.762 |
0.003 |
||||
SR8 |
0.002 |
0.29 |
0.593 |
4.965 |
0.001 |
||||
SR9 |
0.004 |
0.55 |
0.461 |
4.888 |
0.002 |
||||
Parameter |
Station |
R2 |
F1,153 |
p-value |
Intercept |
Coefficient of days of construction |
|||
Mid-flood
depth -average
SS |
IS12 |
0.006 |
0.87 |
0.354 |
4.876 |
0.003 |
|||
IS13 |
0.008 |
1.17 |
0.281 |
4.754 |
0.002 |
||||
IS14 |
0.004 |
0.63 |
0.430 |
4.984 |
0.002 |
||||
IS15 |
<0.001 |
0.13 |
0.717 |
5.200 |
<0.001 |
||||
SR10A |
0.01 |
1.48 |
0.226 |
4.666 |
0.003 |
||||
SR8 |
0.006 |
0.85 |
0.359 |
4.886 |
0.002 |
||||
SR9 |
0.002 |
0.35 |
0.555 |
5.049 |
0.001 |
||||
Note:
1. Dependent variable is set as Turbidity (in mg/L) and independent
variable is set as number of day of construction works.
2. R2 <0.6 and p-value >0.01 (i.e. showing the
regression insignificant) are underlined.
3. By setting α at 0.01, insignificant coefficient is underlined.
Impact dolphin monitoring is required to be conducted
by a qualified dolphin specialist team to evaluate whether there have been any
effects on the dolphins. In order to
fulfil the EM&A requirements and make good use of available resources, the
on-going impact line transect dolphin monitoring data collected by HyD’s Contract No. HY/2011/03 Hong
Kong-Zhuhai-Macao Bridge. Hong Kong Link Road - Section between Scenic
Hill and Hong Kong Boundary Crossing Facilities on the monthly basis is
adopted to avoid duplicates of survey effort.
Table 2.18 summarises the equipment used for the impact dolphin
monitoring.
Table 2.18 Dolphin Monitoring Equipment
Equipment |
Model |
Global Positioning
System (GPS) Camera Laser Binoculars Marine Binocular Vessel for
Monitoring |
Garmin 18X-PC Geo One Phottix Nikon D90 300m 2.8D fixed focus Nikon D90 20-300m zoom lens Infinitor LRF 1000 Bushell 7 x 50 marine binocular with compass and reticules 65 foot single engine motor vessel with viewing platform 4.5m above
water level |
|
|
Dolphin monitoring should cover all transect lines in
Northeast Lantau (NEL) and the Northwest Lantau (NWL) survey areas twice per
month throughout the entire construction period. The monitoring data should be compatible
with, and should be made available for, long-term studies of small cetacean ecology
in Hong Kong. In order to provide a
suitable long-term dataset for comparison, identical methodology and line
transects employed in baseline dolphin monitoring was followed in the impact
dolphin monitoring.
The impact dolphin monitoring was carried out in the
NEL and NWL along the line transect as depicted in Figure 2.3. The co-ordinates of all transect lines are
shown in Table 2.19 below.
Table 2.19 Impact Dolphin Monitoring Line Transect Co-ordinates
Line No. |
Easting |
Northing |
Line No. |
Easting |
Northing |
||
1 |
Start
Point |
804671 |
814577 |
13 |
Start
Point |
816506 |
819480 |
1 |
End
Point |
804671 |
831404 |
13 |
End
Point |
816506 |
824859 |
2 |
Start
Point |
805475 |
815457 |
14 |
Start
Point |
817537 |
820220 |
2 |
End
Point |
805477 |
826654 |
14 |
End
Point |
817537 |
824613 |
3 |
Start
Point |
806464 |
819435 |
15 |
Start
Point |
818568 |
820735 |
3 |
End
Point |
806464 |
822911 |
15 |
End
Point |
818568 |
824433 |
4 |
Start
Point |
807518 |
819771 |
16 |
Start
Point |
819532 |
821420 |
4 |
End
Point |
807518 |
829230 |
16 |
End
Point |
819532 |
824209 |
5 |
Start
Point |
808504 |
820220 |
17 |
Start
Point |
820451 |
822125 |
5 |
End
Point |
808504 |
828602 |
17 |
End
Point |
820451 |
823671 |
6 |
Start
Point |
809490 |
820466 |
18 |
Start
Point |
821504 |
822371 |
6 |
End
Point |
809490 |
825352 |
18 |
End
Point |
821504 |
823761 |
7 |
Start
Point |
810499 |
820690 |
19 |
Start
Point |
822513 |
823268 |
7 |
End
Point |
810499 |
824613 |
19 |
End
Point |
822513 |
824321 |
8 |
Start
Point |
811508 |
820847 |
20 |
Start
Point |
823477 |
823402 |
8 |
End
Point |
811508 |
824254 |
20 |
End
Point |
823477 |
824613 |
9 |
Start
Point |
812516 |
820892 |
21 |
Start
Point |
805476 |
827081 |
9 |
End
Point |
812516 |
824254 |
21 |
End
Point |
805476 |
830562 |
10 |
Start
Point |
813525 |
820872 |
22 |
Start
Point |
806464 |
824033 |
10 |
End
Point |
813525 |
824657 |
22 |
End
Point |
806464 |
829598 |
11 |
Start
Point |
814556 |
818449 |
23 |
Start
Point |
814559 |
821739 |
11 |
End
Point |
814556 |
820992 |
23 |
End
Point |
814559 |
824768 |
12 |
Start
Point |
815542 |
818807 |
|
|
|
|
12 |
End
Point |
815542 |
824882 |
|
|
|
|
The Action and Limit levels of dolphin impact
monitoring are shown in Appendix C. The Event and Action plan is presented in Appendix G.
A total of 3,520.41 km of survey effort was collected,
with 93.2% of the total survey effort being conducted under favourable
weather conditions (ie Beaufort Sea State 3 or below
with good visibility) in this reporting year.
Amongst the two areas, 1,353.42 km and 2,166.99 km of survey effort were
collected from NEL and NWL survey areas, respectively. The total survey effort conducted on primary
and secondary lines were 2,569.49 km and 950.92 km, respectively. The survey efforts are summarized in Appendix F.
A total of 136 groups of 512 Chinese White
Dolphin sightings were recorded during the 24 sets of surveys
in this reporting year. All except eight sighting were made during on-effort search. A hundred and ten on-effort sightings were
made on primary lines, while eighteen other on-effort sightings were made on
secondary lines.
Dolphin sighting distribution of the present impact
phase monitoring period (November 2013 to October 2014) was compared to the
ones during the baseline phase (February 2011 to January 2012) and transitional
phase (November 2012 to October 2013).
As TMCLKL construction works commenced in November 2013, a 12-month
period between baseline phase and impact phase is defined as transitional
phase.
In this 12-month period, 97% of the dolphin sightings
were made in NWL, while only 4 groups of 20 dolphins were sighted in NEL. The majority of dolphin sightings made in the
12-month period were concentrated in the northwestern end of the North Lantau
region.
During the present 12-month impact phase monitoring
period, the average daily encounter rates of Chinese White Dolphins were deduced
in NEL and NWL survey areas, and compared to the ones deduced from the baseline
and transitional phases as shown in Table
2.20.
Table 2.20 Average Dolphin Encounter Rates
|
Encounter rate (STG) (no. of
on-effort dolphin sightings per 100 km of survey effort) |
Encounter rate (ANI) (no. of dolphins from all
on-effort sightings per 100 km of survey effort) |
||
Northeast Lantau |
Northwest Lantau |
Northeast Lantau |
Northwest Lantau |
|
Impact Phase (2013-2014) |
0.22 ± 0.74 |
6.93 ± 4.08 |
0.76 ± 2.59 |
26.31 ± 17.56 |
Transitional Phase (2012-2013) |
1.70 ± 2.26 |
7.68 ± 4.36 |
4.75 ± 7.61 |
27.51 ± 18.06 |
Baseline Phase (2011-2012) |
6.05 ± 5.04 |
7.75 ± 5.69 |
19.91 ± 21.30 |
29.57 ± 26.96 |
Note:
Comparison of average daily
dolphin encounter rates from impact phase (November 2013 – October 2014),
transitional phase (November 2012 – October 2013) and baseline phase monitoring
periods (February 2011 – January 2012). ± denotes the
standard deviation of the value.
Group size of Chinese White
Dolphins ranged from one to thirteen (1-13) individuals per group in North
Lantau region during November 2013 - October 2014. The average dolphin group sizes from the
12-month impact phase monitoring period were compared with the ones deduced
from baseline and transitional phases, as shown in Table 2.21.
Table 2.21 Comparison of Average Dolphin Group Sizes from Impact
Monitoring Period and Baseline Monitoring Period
|
Average Dolphin Group Size |
||
Overall |
Northeast Lantau |
Northwest Lantau |
|
Impact Phase (2013-2014) |
3.76 ± 2.57 (n = 136) |
5.00 ± 2.71 (n = 4) |
3.73 ± 2.57 (n = 132) |
Transitional Phase (2012-2013) |
3.37 ± 2.98 (n = 186) |
2.64 ± 2.38 (n = 22) |
3.47 ± 3.05 (n = 164) |
Baseline Phase (2011-2012) |
3.32 ± 2.86 (n = 288) |
2.80 ± 2.35 (n = 79) |
3.52 ± 3.01 (n = 209) |
Note: Comparison of average
dolphin group sizes from impact phase (November 2013 –October 2014),
transitional phase (November 2012 – October 2013) and baseline phase monitoring
periods (February 2011 – January 2012).
(± denotes the standard deviation of the average value)
Whilst three and two Action Level exceedances for
Northeast Lantau and Northwest Lantau were recorded in the reporting period
respectively. No Limit Level exceedance
was observed for the quarterly dolphin monitoring data between November 2013
and October 2014. In this reporting
period, no unacceptable impact from the activities of this Contract on Chinese
White Dolphins was noticeable from the general observations.
Photos
IDs of sighted dolphin are presented in Appendix
J of the First to Twelfth Monthly
EM&A Report.
Daily
marine mammal exclusion zone was in effect during the period of dredging, reclamation or marine sheet
piling works in open waters under
this Contract. Passive Acoustic
Monitoring (PAM) was also implemented for the detection of marine mammal when
dredging, reclamation
or marine sheet piling works were
carried out outside the daylight hours under this Contract. One sighting of the Indo-Pacific humpback
dolphin Sousa chinensis
was recorded on 20 February 2014 during the exclusion zone monitoring. The marine dredging work was subsequently
suspended until the
observer has confirmed that the area is continuously clear of dolphins for a
period of 30 minutes.
Four
(4) Post-Translocation Coral Monitoring Surveys were conducted on 17 January
2014, 16 April 2014, 24 July 2014 and 23 October 2014 and the results were
provided in the First to Fourth Quarterly
Post-Translocation Coral Monitoring Report.
The findings indicated that no Action or Limit Levels
exceedances was recorded for coral monitoring as increase in percentage of
partial mortality was not detected for both the tagged translocated and natural
coral colonies when comparing to the pre-translocation dataset.
Site inspections were carried out on a weekly basis to
monitor the implementation of proper environmental pollution control and
mitigation measures under the Contract.
Fifty-two (52) site inspections were carried out in the reporting
period.
Key observations were summarized in the First to Twelfth Monthly EM&A Reports.
The Contractor had submitted application form for
registration as chemical waste producer under the Contract. Sufficient numbers of receptacles were
available for general refuse collection and sorting.
Wastes generated during this reporting period include
mainly construction wastes (inert and non-inert), imported fill, recyclable
materials, chemical wastes and marine sediments. Reference has been made to the waste flow
table prepared by the Contractor (Appendix I). The quantities of different types of wastes
are summarized in Table 2.22.
Table 2.22 Quantities of Different Waste Generated in the Reporting Period
Month/Year |
Inert Construction Waste (a)
(tonnes) |
Imported Fill (tonnes) |
Inert
Construction Waste Re-used (tonnes) |
Non-inert Construction Waste (b)
(tonnes) |
Recyclable Materials (c) (kg) |
Chemical Wastes (kg) |
Marine Sediment (m3) |
|
Category L |
Category M |
|||||||
November
2013 |
2,835 |
47,449 |
0 |
152 |
130 |
0 |
21,100 |
13,200 |
December
2013 |
883 |
204,421 |
0 |
12 |
130 |
0 |
40,500 |
5,000 |
January 2014 |
9,012 |
314,306 |
0 |
45 |
130 |
0 |
34,000 |
12,500 |
February
2014 |
0 |
258,383 |
0 |
28 |
0 |
20 |
18,500 |
24,500 |
March 2014 |
105 |
516,400 |
0 |
36 |
0 |
0 |
37,300 |
40,450 |
April 2014 |
22 |
467,867 |
0 |
26 |
160 |
0 |
28,600 |
15,400 |
May 2014 |
1,016 |
516,368 |
0 |
42 |
0 |
0 |
18,700 |
29,150 |
June 2014 |
4,393 |
407,489 |
0 |
30 |
0 |
30 |
40,700 |
7,700 |
July 2014 |
14,405 |
428,392 |
0 |
33 |
300 |
0 |
37,950 |
7,150 |
August 2014 |
12,728 |
623,029 |
0 |
22 |
0 |
0 |
12,100 |
0 |
September
2014 |
6,843 |
676,219 |
0 |
39 |
0 |
0 |
0 |
0 |
October 2014 |
1,228 |
527,237 |
0 |
33 |
80 |
60 |
0 |
0 |
Total |
53,470 |
4,987,560 |
0 |
498 |
930 |
110 |
289,450 |
155,050 |
Notes: |
||||||||
(a) Inert
construction wastes include hard rock and large broken concrete, and
materials disposed as public fill. (b) Non-inert
construction wastes include general refuse disposed at landfill. (c) Recyclable
materials include metals, paper, cardboard, plastics, timber and others. |
The Contractor was advised to properly maintain on
site C&D materials and waste collection, sorting and recording system,
dispose of C&D materials and wastes at designated ground and maximize
reuse/ recycle of C&D materials and wastes.
The Contractor was also reminded to properly maintain the site tidiness
and dispose of the wastes accumulated on site regularly and properly.
For chemical waste containers, the Contractor was
reminded to treat properly and store temporarily in designated chemical waste
storage area on site in accordance with the Code of Practice on the Packaging,
Labelling and Storage of Chemical Wastes.
The status of environmental licensing and permit is
summarized in Table 2.23 below.
Table 2.23 Summary of Environmental Licensing and Permit Status
License/ Permit |
License or Permit No. |
Date of Issue |
Date of Expiry |
License/ Permit Holder |
Remarks |
|
Environmental
Permit |
EP-354/2009/A |
8
December 2010 |
Throughout
the Contract |
HyD |
Tuen Mun-Chek Lap Kok
Link |
|
Environmental
Permit |
EP-354/2009/B |
28 January 2014 |
Throughout the Contract |
HyD |
Application
for VEP on 20 January 2014 to replace EP-354/2009/A |
|
Construction
Dust Notification |
363510 |
19
August 2013 |
Throughout
the Contract |
DBJV |
- |
|
Chemical
Waste Registration |
5213-422-D2516-01 |
10
September 2013 |
Throughout
the Contract |
DBJV |
- |
|
Construction
Waste Disposal Account |
7018108 |
19
August 2013 |
Throughout
the Contract |
DBJV |
Waste disposal in Contract HY/2012/08 |
|
Waste
Water Discharge License |
WT00017707-2013 |
18
November 2013 |
30
November 2018 |
DBJV |
For works in site WA18 |
|
Waste
Water Discharge License |
WT00018433-2014 |
6
March 2014 |
31
March 2019 |
DBJV |
For works in site Portion N6 |
|
Construction
Noise Permit |
GW-RW0691-13 |
15
October 2013 |
14
April 2014 |
DBJV |
For
Dredging and Reclamation Works |
|
Construction Noise Permit |
GW-RW0035-13 |
27 January 2014 |
26 July 2014 |
DBJV |
For
Dredging and Reclamation Works |
|
Construction Noise Permit |
GW-RW0095-14 |
10 February 2014 |
9 August 2014 |
DBJV |
For
Dredging and Reclamation Works |
|
Construction
Noise Permit |
GW-RW0822-13 |
14
November 2013 |
10
May 2014 |
DBJV |
For
works in site WA18 |
|
Construction
Noise Permit |
GW-RS0814-13 |
15
November 2013 |
10
May 2014 |
DBJV |
For
works in site WA23 |
|
Construction Noise Permit |
GW-RW0029-14 |
27 January 2014 |
26 July 2014 |
DBJV |
For Portion N6 |
|
Construction Noise Permit |
GW-RW0077-14 |
17 February 2014 |
16 August 2014 |
DBJV |
For Portion N6 |
|
Construction Noise Permit |
GW-RW0223-14 |
29 March 2014 |
28 September 2014 |
DBJV |
For works in site Portion N6 |
|
Construction Noise Permit |
GW-RW0234-14 |
29 March 2014 |
28 September 2014 |
DBJV |
For Dredging and Reclamation Works |
|
Construction Noise Permit |
GW-RS0362-14 |
11 May 2014 |
10 November 2014 |
DBJV |
For works in site WA23 |
|
Construction Noise Permit |
GW-RW0550-14 |
25 July 2014 |
24 January 2015 |
DBJV |
For Dredging and Reclamation Works |
|
Construction Noise Permit |
GW-RW0223-14 |
29
September 2014 |
28 March 2015 |
DBJV |
For works in site Portion N6 |
|
Construction
Noise Permit |
GW-RS0674-14 |
18 September 2014 |
17
March 2015 |
DBJV |
For
GI works at Southern Landfall |
|
Marine
Dumping Permit |
EP/MD/14-072 |
1 November 2013 |
30
April 2014 |
DBJV |
For
Type 1 |
|
Marine
Dumping Permit |
EP/MD/14-140 |
1 March 2014 |
31
March 2014 |
DBJV |
For
Type 1 (dedicated site) and Type 2 |
|
Marine
Dumping Permit |
EP/MD/14-157 |
3 April 2014 |
30
April 2014 |
DBJV |
For
Type 1 (dedicated site) and Type 2 |
|
Marine
Dumping Permit |
EP/MD/15-007 |
1 May 2014 |
31
May 2014 |
DBJV |
For
Type 1 (dedicated site) and Type 2 |
|
Marine
Dumping Permit |
EP/MD/14-071 |
1 December 2013 |
31
December 2013 |
DBJV |
For
Type 1 (dedicated site) and Type 2 |
|
Marine
Dumping Permit |
EP/MD/14-108 |
1 January 2014 |
31
January 2014 |
DBJV |
For
Type 1 (dedicated site) and Type 2 |
|
Marine
Dumping Permit |
EP/MD/14-124 |
1 February 2014 |
28
February 2014 |
DBJV |
For
Type 1 (dedicated site) and Type 2 |
|
Marine
Dumping Permit |
EP/MD/15-006 |
1 May 2014 |
31
October 2014 |
DBJV |
For
Type 1 |
|
Marine
Dumping Permit |
EP/MD/15-026 |
31 May 2014 |
29
June 2014 |
DBJV |
For
Type 1 (dedicated site) and Type 2 |
|
Marine
Dumping Permit |
EP/MD/15-045 |
30 June 2014 |
29
July 2014 |
DBJV |
For
Type 1 (dedicated site) and Type 2 |
|
Marine
Dumping Permit |
EP/MD/15-061 |
1 August 2014 |
31
August 2014 |
DBJV |
For
Type 1 (dedicated site) and Type 2 |
|
Marine
Dumping Permit |
EP/MD/15-100 |
20
October 2014 |
19
November 2014 |
DBJV |
For
Type 1 (dedicated site) and Type 2 |
|
Notes: |
|
|
|
|
|
|
HyD
= Highways Department DBJV
= Dragages – Bouygues Joint Venture VEP
= Variation of Environmental Permit |
||||||
In response to the EM&A site audit findings
mentioned in Section 2.5 of this
report, the Contractor has carried out the corrective actions.
A summary of the Implementation Schedule of
Environmental Mitigation Measures (EMIS) is presented in Appendix B. The necessary mitigation measures relevant to
this Contract were implemented properly.
For air quality impact monitoring, a total of
sixty-eight monitoring events were undertaken in which twenty-six Action Level
exceedances and two Limit Level exceedances for 1-hour TSP; five Action Level
exceedances and one Limit Level exceedance for 24-hour TSP were recorded (Table 2.24). Further to the investigation, the recorded
exceedance for air quality monitoring was considered to be sporadic event from
the cumulative anthropogenic activities (eg traffic
emissions from River Trade Terminal) in this area of Hong Kong. The investigation findings are detailed in the First to Twelfth EM&A Monthly Report.
Table 2.24 Summary of Exceedances for Air Quality Impact Monitoring in
this Reporting Year
Station |
Exceedance Level |
Date of Exceedances |
Number of Exceedances |
||
1-hour TSP |
24-hour TSP |
1-hour TSP |
24-hour TSP |
||
AQMS1 |
Action Level |
2013-11-07 |
2014-01-03 |
3 |
1 |
Limit Level |
- |
- |
0 |
0 |
|
ASR1 |
Action Level |
2013-11-19 2014-01-03 2014-03-24 |
2013-12-11 |
7 |
2 |
Limit Level |
- |
- |
0 |
0 |
|
ASR5 |
Action Level |
2013-11-07 2014-03-24 |
2013-12-11 |
8 |
2 |
Limit Level |
2013-12-11 |
- |
1 |
0 |
|
AQMS2/ASR6 |
Action Level |
2013-12-11 2013-12-23 |
- |
6 |
0 |
Limit Level |
- |
2013-12-23 |
0 |
1 |
|
ASR10 |
Action Level |
2013-12-28 2014-04-03 |
- |
2 |
0 |
Limit Level |
2013-11-07 |
- |
1 |
0 |
|
Total number of Action level Exceedances: |
26 |
5 |
|||
Total number of Limit level Exceedances: |
2 |
1 |
|||
*Notes: |
|
|
|||
Two
exceedances were recorded on 2013-12-11. |
|
|
For marine water quality impact monitoring, a total of
a hundred and fifty-five monitoring events were undertaken in which six Action
Level exceedances and one Limit Level exceedance were recorded (Table 2.25).
Table 2.25 Summary of Exceedances for Marine Water Quality Impact
Monitoring in this Reporting Period
Station |
Exceedance Level (a) |
DO (Surface and Middle) |
DO (Bottom) |
Turbidity (depth-averaged) |
SS (depth-averaged) |
||||
Mid-ebb |
Mid-flood |
Mid-ebb |
Mid-flood |
Mid-ebb |
Mid-flood |
Mid-ebb |
Mid-flood |
||
CS4 |
AL |
- |
- |
- |
- |
- |
- |
- |
- |
LL |
- |
- |
- |
- |
- |
- |
- |
- |
|
CS6 |
AL |
- |
- |
- |
- |
- |
- |
- |
- |
LL |
- |
- |
- |
- |
- |
- |
- |
- |
|
IS12 |
AL |
- |
- |
- |
- |
- |
- |
- |
- |
LL |
- |
- |
- |
- |
- |
- |
- |
2014-03-31 |
|
IS13 |
AL |
- |
- |
- |
- |
- |
- |
- |
- |
LL |
- |
- |
- |
- |
- |
- |
- |
- |
|
IS14 |
AL |
- |
- |
- |
- |
- |
- |
- |
2014-03-31 |
LL |
- |
- |
- |
- |
- |
- |
- |
- |
|
IS15 |
AL |
- |
- |
- |
- |
- |
- |
2013-12-06 |
2013-12-04 |
LL |
- |
- |
- |
- |
- |
- |
- |
- |
|
SR8 |
AL |
- |
- |
- |
- |
- |
- |
- |
2013-12-06 |
LL |
- |
- |
- |
- |
- |
- |
- |
- |
|
SR9 |
AL |
- |
- |
- |
- |
- |
- |
2013-12-06 |
2013-12-06 |
LL |
- |
- |
- |
- |
- |
- |
- |
- |
|
SR10 |
AL |
- |
- |
- |
- |
- |
- |
- |
- |
LL |
- |
- |
- |
- |
- |
- |
- |
- |
|
Total AL Exceedances: |
0 |
0 |
0 |
0 |
0 |
0 |
2 |
4 |
|
Total LL Exceedances: |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
|
Notes: |
|||||||||
(a) AL = Action Level; LL = Limit Level |
For the dolphin impact monitoring, three (3) and two
(2) Action Level exceedances for Northeast Lantau and Northwest Lantau were
recorded in the reporting period respectively.
Following the review of monitoring data and marine works details in
accordance with the procedures stipulated in the Event and Action Plan of the
Updated EM&A Manual, the recorded exceedances were considered to be due to
natural variation of dolphin ranging pattern.
Detailed investigation findings are presented in the First to Third Quarterly EM&A Report.
Cumulative statistics are provided in Appendix H.
The Environmental Complaint Handling Procedure is
provided in Figure 2.4.
No non-compliance event was recorded during the
reporting period.
Two complaints were recorded during this reporting
period. The first complaint/ enquiry case was
notified by the Contractor on 25 April 2014.
The investigation findings showed that the case was considered not
related to the works under this Contract and is thus invalid. Another complaint case was referred by EPD on 29 October
2014. The interim report was submitted
to EPD on 6 November 2014. The
investigation findings showed that the case was considered not related to the
works under this Contract and is thus invalid.
Detailed investigation findings are provided in Appendix L of the Seventh and Thirteenth EM&A Monthly
Reports.
No summons/ prosecution was
received during the reporting period.
Statistics on complaints, notifications of summons and
successful prosecutions are summarized in Appendix H.
Findings of the EM&A activities undertaken during
the period from 1 November 2013 to 31 October 2014 were compared with the
relevant EIA predictions where appropriate to provide a review of the validity
of the EIA predictions and identify potential shortcomings in the EIA
recommendations.
Impact monitoring for air quality, water quality and marine
ecology were undertaken during the reporting period. Whilst occasional Action Level exceedances on
air quality and water quality were observed in the reporting period, the
exceedances were considered not related to this Contract upon further investigation.
The impact monitoring results for air quality and water quality are considered
to be in line with the EIA predictions.
Based
on the findings presented in TM-CLKL EIA study, the major sources of dust
nuisance arising from the Northern Connection are related to excavation, wind
erosion from reclaimed areas, open sites and stockpiling areas. Therefore during these construction
activities, the TSP monitoring frequency will be increased at all air quality
monitoring stations such that any deteriorating air quality can be readily
detected and timely action taken to rectify the situation. Comparison of EIA prediction,
average baseline monitoring and average impact monitoring results of TSP is
presented in Table 2.26.
Table 2.26 Comparison of EIA prediction and EM&A Results on Air
Quality (µg/m3)
Station |
EIA Predicted Maximum |
Maximum
Impact Monitoring |
Average
Impact Monitoring |
Maximum
Baseline Monitoring |
Average
Baseline Monitoring
|
ASR1 (1-hour) |
195 |
474 |
178 |
182 |
125 |
ASR1 (24-hour) |
148 |
249 |
101 |
173 |
128 |
ASR5 (1-hour) |
235 |
559 |
194 |
211 |
138 |
ASR5 (24-hour) |
133 |
258 |
106 |
249 |
167 |
AQMS1 (1-hour) |
N/A |
431 |
141 |
196 |
131 |
AQMS1 (24-hour) |
N/A |
228 |
86 |
211 |
127 |
AQMS2/ASR6 (1-hour) |
226 |
425 |
163 |
226 |
135 |
AQMS2/ASR6 (24-hour) |
153 |
269 |
94 |
221 |
166 |
ASR10 (1-hour) |
189 |
645 |
121 |
215 |
134 |
ASR10 (24-hour) |
112 |
166 |
72 |
181 |
129 |
As shown in Table
2.26, maximum 1-hour and 24-hour TSP impact monitoring levels at ASR1,
ASR5, ASR6 and ASR10 were higher than their corresponding EIA predicted maximum
levels. In baseline monitoring, maximum
baseline levels of 1-hour TSP at ASR10 and 24-hour TSP at ASR1, ASR5, ASR6 and
ASR10 were also higher than EIA maximum prediction. These recorded maximum monitoring values during
both impact and baseline monitoring periods are thus considered as sporadic
events and fluctuation of regional air quality. Overall, most of the monitoring results were
within EIA predicted levels during impact monitoring period. It thus appeared that the construction
activities of the Contract did not cause significant impact on air quality with
similar average TSP levels between the baseline and impact monitoring. The EIA has concluded that no adverse
residual construction dust impacts will occur after implementation of
mitigation measures. Thus, the
monitoring results are considered to be in line with the EIA prediction.
As identified in the EIA Report, key
water quality issues during construction phase will be dredging and filling
works for the reclamation. Thus, Marine
water quality monitoring shall be carried out during the construction phase to
ensure that any unacceptable increase in suspended solids / turbidity and
decrease in dissolved oxygen due to dredging and filling activities could be
readily detected and timely action be taken to rectify the situation.
According to the EIA prediction, no SS
exceedance is anticipated from this Project at the water sensitive receivers
nearby the vicinity of Contract (WSR 12, WSR 13 and WSR 47a). Although six (6) Action Level exceedances and
one (1) Limit Level exceedance on depth-averaged SS were recorded in the
reporting period, the exceedances were considered not related to this Contract
upon further investigation. Furthermore,
the construction impact on depth-averaged SS was assessed to compare the
annual mean values of depth-averaged SS with the relevant ambient mean
values. Results showed that the annual
mean values of depth-averaged SS at all monitoring stations are well below the
ambient mean values (Table 2.27),
thus the impact monitoring results are considered to in line with the EIA
prediction.
DO levels from surface, mid-depth and bottom waters
were generally similar amongst Control, Impact stations and Sensitive
Receivers, and DO levels were variable throughout the reporting period which
represented natural background fluctuation in water quality. Similar to DO levels, turbidity and SS levels
were generally comparable amongst Control, Impact stations and Sensitive
Receivers and variable throughout the monitoring period. High levels of turbidity and SS were
occasionally recorded during both mid-ebb and mid-flood tides. Such fluctuations were also observed during
baseline monitoring and are considered to be sporadic events and characteristic
of water quality in this area of Hong Kong.
The annual means of DO levels during impact period
were higher than the means of DO levels measured during baseline period. The annual means of depth-averaged SS and
Turbidity during impact period were lower than the means of depth-averaged SS and
Turbidity measured during baseline period.
One way Analysis of Variance (ANOVA) was conducted to test for the
differences between the baseline and impact monitoring data of Dissolved
Oxygen, Turbidity and Suspended Solids at the designated water quality
monitoring locations. The detailed statistical
and graphical results, as presented in Section
2.2.3 and Appendix E respectively,
show that depth-averaged SS and Turbidity levels were significantly lower
between baseline period and impact period.
Thus, the impact monitoring results are considered to in line with the
EIA prediction.
Table 2.27 Comparison between Annual Mean and Ambient Mean Values of
Depth-averaged Suspended Solids (mg/L)
Station |
Baseline
Mean |
Ambient
Mean (a) |
Annual Mean (November 2013 to
October 2014) |
|||
Mid-ebb |
Mid-flood |
Mid-ebb |
Mid-flood |
Mid-ebb |
Mid-flood |
|
CS4 |
10.2 |
9.0 |
13.3 |
11.7 |
5.3 |
5.2 |
CS6 |
10.9 |
11.7 |
14.1 |
15.2 |
5.1 |
5.3 |
IS12 |
9.2 |
9.5 |
12.0 |
12.3 |
5.3 |
5.4 |
IS13 |
10.0 |
10.5 |
13.0 |
13.7 |
5.2 |
5.2 |
IS14 |
10.4 |
9.7 |
13.5 |
12.6 |
5.3 |
5.3 |
IS15 |
9.6 |
11.0 |
12.5 |
14.2 |
5.3 |
5.4 |
SR10A |
10.3 |
10.2 |
13.3 |
13.3 |
5.3 |
5.2 |
SR8 |
10.1 |
11.3 |
13.1 |
14.7 |
5.2 |
5.3 |
SR9 |
8.8 |
9.9 |
11.4 |
12.8 |
5.2 |
5.3 |
Grand Total |
10.0 |
10.3 |
13.0 |
13.4 |
5.2 |
5.3 |
Notes: |
||||||
(a) Ambient mean value is defined as a 30%
increase of the baseline mean value |
Impact monitoring on marine ecology was undertaken
during the monitoring period. Post-Translocation Coral
Monitoring is considered to be undertaken successfully as the
translocated corals did not show any sign of deterioration in condition at the
receptor site during the First to Forth Quarterly Post-translocation Coral
Monitoring survey. The results are
considered to be in line with the EIA prediction.
According to the baseline results in the Appendix F of the approved EIA Report, the dolphin
groups were largely sighted near Lung Kwu Chau and
the waters between Lung Kwu Chau and Black Points and
infrequently along the alignment of this Contract. Two-way ANOVAs with repeated measures were
conducted to compare results of average encounter rate of sightings (STG) and
average encounter rate of dolphins (ANI) between baseline and impact
periods. Although the STG and ANI in
impact monitoring period were lower than that before the commencement of this
Contract (see Section 2.3.6), the
distribution pattern was similar between the impact monitoring period and
before the commencement (i.e. transition period in 2012 – 2013) of this
Contract. In addition, the habitat use
pattern between impact monitoring in this reporting period and before the
commencement of this contract is largely similar, in which dolphins are
observed heavily utilized area around Lung Kwu Chau
and less frequently in the North Lantau region where the works area of this
Contract is situated. The monitoring
results in this reporting period are considered to be in line with the EIA
predictions, and the review of monitoring data suggested that no unacceptable
impacts was noted from the marine dredging and reclamation activities under
this Contract. It is essential to
monitor the dolphin usage in North Lantau region for the rest of impact
monitoring period to keep track on the trend of dolphin ranging pattern.
For wastes generated from the construction activities
include C&D materials (inert and non-inert), chemical wastes, recyclable
materials and marine sediments (both categories L and M), the wastes generated
were in line with the EIA predictions.
For dredged sediment, the quantity of sediments generated was in line
with CEDD’s allocated disposal volumes as per the marine dumping permit (see
Table 2.22). The wastes were also disposed of in accordance with the
recommendations of the EIA
The EM&A monitoring programme has been reviewed
and was considered effective and adequate to cater for the nature of works in
progress. No change to the monitoring
programme was considered to be necessary.
The EM&A programme will
be evaluated as appropriate in the next reporting period
and improvements in the EM&A programme will be
recommended if deemed necessary.
The mitigation measures stipulated in the Updated
EM&A Manual were undertaken by the Contractor in the reporting period. The mitigation measures were reviewed and
considered effective. No addition or
change on mitigation measures was considered to be necessary.
Weekly joint environmental site
inspections have been conducted in the reporting period to assess the effectiveness
of the environmental controls established by the Contractor and the
implementation of the environmental mitigation measures recommended in the EIA
Report.
Findings of the site inspections confirmed that the environmental
mitigation measures recommended in the EIA Report were properly implemented by
the Contractor, and the recommended mitigation measures have been working
effectively. There was no non-compliance recorded
during the site inspections and environmental performance complied
with environmental requirements.
The
requirements for site inspections and audits have been reviewed and were
considered as adequate. No change to the
requirements was considered to be necessary.
The
recommended environmental mitigation measures are also considered to be
effective and efficient in reducing the potential environmental impacts
associated with the construction phase of the Project. No change was thus considered necessary.
Construction
phase air quality monitoring was conducted during this reporting period when
land-based construction works were undertaken.
Whilst occasional exceedances of Action and Limit Levels for air quality
were recorded, following the review of monitoring data and construction works
details in accordance with the procedures stipulated in the Event and Action
Plan of Updated EM&A Manual, these exceedances were unlikely to be due to
the Project’s construction works.
The
monitoring programme has been reviewed and was considered to be adequate to
cater for the nature of works. No change
to the requirements was considered to be necessary.
Construction phase water quality monitoring
was conducted during this reporting period when dredging and reclamation works
were undertaken. Whilst occasional
exceedances of Action and Limit Levels for water quality were recorded,
following the review of monitoring data and marine works details in accordance
with the procedures stipulated in the Event and Action Plan of Updated EM&A
Manual, these exceedances were considered to be due to natural variation in
water quality characteristic of western Hong Kong waters and were unlikely to be
due to the Project’s marine works.
The monitoring programme has been
reviewed and was considered to be adequate to cater for the nature of
works. No change to the requirements was
considered to be necessary.
The
waste inspection and audit programme has been implemented during this reporting
period. Wastes generated from
construction activities have been managed in accordance with the
recommendations in the EIA Report, the EM&A Manual, the WMP and other
relevant legislative requirements.
The
requirements for construction waste management have been reviewed and were
considered as adequate. No change to the
requirements was considered to be necessary.
Post-Translocation
Coral Monitoring has been carried out as per the requirements stipulated in the
Detailed Coral Translocation Methodology.
Daily marine mammal exclusion zone monitoring and dolphin monitoring
during the reporting period were conducted.
The monitoring programme has been reviewed and was considered to be
adequate to cater for the nature of works.
No change to the requirements was considered to be necessary.
Findings
of the EM&A programme indicate that the recommended mitigation measures
have been properly implemented and working effectively. The EM&A programme has
been reviewed and was considered as adequate and effective. No change to the EM&A programme was
considered to be necessary.
The
EM&A programme will be evaluated as appropriate in the next reporting
period and improvements in the EM&A programme will be recommended if deemed
necessary.
This First Annual EM&A Report presents the
findings of the EM&A activities undertaken during the period from 1
November 2013 to 31 October 2014, in accordance with the Updated EM&A
Manual and the requirements of EP-354/2009/B.
Air quality (including 1-hour TSP and 24-hour TSP),
marine water quality, coral and dolphin monitoring were carried out in the
reporting period. Twenty-six Action
Level and two Limit Level exceedances for 1-hour TSP, and five Action Level and
one Limit Level exceedances for 24-hour TSP were recorded during the reporting
period. Six Action Level and one Limit
Level exceedances were recorded in marine water quality impact monitoring
during the reporting period. No Action
Level or Limit Level exceedances were recorded in the post-translocation coral
monitoring in the reporting period.
Investigation findings suggested that the observed exceedances for
air quality monitoring were considered to be sporadic event from the cumulative
anthropogenic activities (e.g. traffic emissions from River Trade Terminal) in
this area of Hong Kong. The review of
water quality monitoring data suggested that no unacceptable impact was
resulting from the construction activities under this Contract in the reporting
period. Nevertheless, the Contractor was
reminded to ensure that all dust mitigation measures are provided at the
construction sites.
A total of one hundred and thirty-six (136) groups of
five hundred and twelve (512) Chinese White Dolphins (CWDs) were sighted. Whilst five (5) Action Level exceedances were
recorded for 3 sets of quarterly dolphin monitoring data between October 2013
and August 2014, no unacceptable impact from the activities of this Contract on
Chinese White Dolphins was noticeable from the general observations. It is essential to monitor the dolphin usage
in North Lantau region for the rest of impact monitoring period to keep track
on the trend of dolphin ranging pattern.
Fifty-two weekly environmental site inspections were
carried out in the reporting period.
Recommendations on remedial actions provided for the deficiencies
identified during the site audits were properly implemented by the Contractor. No non-compliance event was
recorded during the reporting period.
One
potential complaint/ enquiry case was notified by the Contractor on 25 April
2014. The investigation findings showed
that the case was considered not related to the works under this Contract and
is thus invalid.
One
potential environmental complaint case was referred by EPD on 29 October
2014. The investigation findings showed
that the case was considered not related to the works under this Contract and
is thus invalid.
No summons/ prosecution was
received during the reporting period.
The review of monitoring data suggested that the
construction works under this Contract have proceeded in an environmentally
acceptable manner in this reporting period.
The monitoring programme has
been reviewed and was considered as adequate to cater for the nature of works
in progress. Change to the
monitoring programme was thus not recommended at this stage. The monitoring programme will be evaluated as
appropriate in the next reporting period.
The ET will keep track on the construction works to confirm compliance
of environmental requirements and the proper implementation of all necessary
mitigation measures.