AUES Job No.: TCS00715/14

 

 

 

 

 

 

 

 

 

Tuen Mun - Chek Lap Kok Link

Contract No. HY/2013/12 ¡V

Northern Connection Toll Plaza and Associated Works

 

 

 

 

 

 

 

 

 

 

1st Monthly Environmental Monitoring and Audit (EM&A) Report ¡V November 2014

 

 

 

 

 

 

 

 

 

 

Prepared For

CRBC and Kaden Joint Venture

 

 

 

 

 

 

 

 

 

 

 

 

 

Date

Reference No.

Prepared By

Certified By

31 Dec 2014

TCS00715/14/600/R0043v4

Nicola Hon

(Environmental Consultant)

T.W. Tam

(Environmental Team Leader)

 

 

 

 

 

 

 


EXECUTIVE SUMMARY

ES01       CRBC-Kaden Joint Venture (hereafter ¡§CRBC-Kaden JV¡¨) has been awarded the Contract No. HY/2013/12 -Northern Connection Toll Plaza and Tunnel Section of the Tuen Mun ¡V Chek Lap Kok Link (hereinafter called ¡§the Contract¡¨) by the Highways Department (HyD) in August 2014.  This is a Designated Project to be implemented under Environmental Permit number EP-354/2009/B (hereinafter referred as ¡§the EP¡¨).

 

ES02       AECOM Asia Company Limited as the Resident Engineer (RE) and ENVIRON Hong Kong Ltd as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) were employed by the HyD.  Moreover, CRBC-Kaden JV has appointed Action-United Environmental Services & Consulting (AUES) as the Environmental Team (ET) to implement the related environmental monitoring and audit (EM&A) programme under the Contract.

 

ES03       In view of the construction works under the Contract, the major construction activities are land-based works.  Hence, the EM&A programme including water quality and marine ecological monitoring should not related the Contract works.  Moreover, all designated noise monitoring locations are located in Lantau and noise monitoring is therefore not required under the Contract.  In accordance with the Project EM&A Manual requirements included air quality, ecological (Pitcher Plant) monitoring, cultural heritage and site inspections should be conducted.  In addition, landscape and visual (L&V) monitoring, landfill gas monitoring and audit of the contractor¡¦s implementation of the construction noise and land-based water quality pollution control measures are also required for the Contract.

 

ES04       The baseline air quality monitoring was carried out by the ET of HY/2012/08 from 16th to 31st October 2013.  A set of Action and Limit Levels (A/L Levels) of air quality performance criteria was proposed by ET of HY/2012/08 which has been verified by IEC and endorsed by EPD.  The Action and Limit Levels of the air quality adopted for the Contract is shown in Table ES-1.

Table ES-1      Action and Limit Levels of Air Quality Monitoring

Monitoring Station

24-hour TSP, (mg /m3)

1-hour TSP, (mg/m3)

Action Level

Limit Level

Action Level

Limit Level

ASR1

213

260

331

500

ASR5

238

260

340

500

AQMS1

213

260

335

500

ASR6

238

260

338

500

ASR10

214

260

337

500

 

ES05       In September 2013, baseline survey for Pitcher Plant has been conducted within the project area by a suitably qualified ecologist.  In mid-September 2014, Contract HY/2013/12 has also conducted a one-off survey to confirm the number of existing Pitcher Plant.  For cultural heritage, a condition survey for the grave was conducted on 23 September 2014.  The Baseline Monitoring Report for the Contract was submitted on 7 October 2014 for IEC¡¦s verification and 25 November 2014 for EPD¡¦s endorsement.

 

ES06       The construction phase of the Contract was commenced on 23 October 2014.  This is the 1st Monthly EM&A Report presenting the air quality monitoring results and inspection findings for the reporting period from 23 October 2014 to 30 November 2014 (hereinafter ¡¥the Reporting Period¡¦).

 

Summary of EM&A activities for the Reporting Period

ES07       In the Reporting Period, the EM&A activities are summary in below.

Ÿ     24-hour TSP monitoring ¡V 50 events

Ÿ     1-hour TSP monitoring ¡V 150 events

Ÿ     Cultural heritage inspection ¡V 5 events

Ÿ     Landfill Gas Monitoring ¡V 32 days

Ÿ     Landscape &Visual Monitoring ¡V 5 events

Ÿ     Joint Environmental site inspection ¡V 5 events

 

Breach of Action and Limit (A/L) Levels

ES08       In the Reporting Period, 2 Action Level exceedances of 1-hour TSP were recorded at ASR01 on 14 November.  Statistics of air quality including exceedance, NOE issued and investigation are summarized in the following table

 

Environmental Aspect

Monitoring Parameters

Action Level

Limit Level

Event & Action

NOE Issued

Investigation

Corrective Actions

Air Quality

1-hour TSP

2

0

1

Not related the Contract

Not require

24-hour TSP

0

0

0

0

0

 

ES09       No noise complaint was received in the Reporting Period.

 

Environmental Complaint

ES10       No environmental complaints were received by either the RE or ENPO or HyD or the Main Contractor in the Reporting Period.

 

Notification of Summons and Successful Prosecutions

ES11       No environmental summons or successful prosecutions were recorded in the Reporting Period.

 

Reporting Change

ES12       As this is the first Monthly EM&A Report, no reporting changes were made in the Reporting Period.

 

Site Inspection

ES13       In the Reporting Period, joint site inspection by the RE, IEC, ET and the Contractor was carried out on 28th October 2014, 4th, 11th, 19th and 25th November 2014.  No non-compliance observed during the site inspection.

 

ES14       In addition, inspection for Pitcher Plants of ecology and grave of culture heritage were also carried out during the weekly site inspection.

 

Future Key Issues

ES15       Construction dust emission would be a key environmental issue during construction work of the Contract.  Dust mitigation measures such as watering at least 12 times per day on all exposed soil within the Project site and associated work areas in Tuen Mun area throughout the construction period should be implemented in accordance with the EP requirement.

 

ES16       Muddy water or other water pollutants from sites surface flow to public area should properly avoided.  Water quality mitigation measures to prevent surface runoff to impact public areas should be fully implemented.

 

ES17       Construction noise would be another environmental issue during construction works of the Contract.  Noise mitigation measures such as using of quiet plants should be implemented in accordance with the EM&A requirement.

 

 

 


Table of Contents

 

1     Introduction                                                                                                                     1

1.1            Project Background                                                                                       1

1.2            Contract Background                                                                                  1

1.3            Report Structure                                                                                             2

2     Contract Organization and Construction progress and Environmental Submissions                                                                                                                          3

2.1            Contract Organization                                                                                 3

2.2            Construction Progress                                                                                 5

2.3            Summary of Environmental Submissions                                               5

3     Summary of Impact Monitoring Requirements Under the Contract 6

3.1            General                                                                                                                 6

3.2            Air Quality Monitoring Parameters                                                        6

3.3            Monitoring Location                                                                                      6

3.4            Monitoring Frequency                                                                                  6

3.5            Monitoring Equipment                                                                                   7

3.6            Derivation of Action/Limit (A/L) Levels                                                    8

3.7            Other Environmental Aspects                                                                    8

4     Air Quality Monitoring                                                                                            10

4.1            General                                                                                                               10

4.2            Air Quality Monitoring Results in Reporting Period                     10

4.3            Action and Limit (A/L) Levels Exceedance                                           10

4.4            Air Quality Exceedance Investigation                                                 10

5     Ecology Monitoring                                                                                                   11

5.1            General                                                                                                               11

5.2            Pitcher Plants Inspection                                                                           11

6     CULTURAL HERITAGE                                                                                                       12

6.1            General                                                                                                               12

6.2            Grave Inspection                                                                                             12

7     Landscpae and Visual                                                                                                  13

7.1            General                                                                                                               13

7.2            Landscape and Visual Inspection                                                            13

8     Landfill Gas Hazard Monitoring                                                                        14

8.1            General                                                                                                               14

8.2            Landfill Gas Monitoring Result                                                              14

9     Waste Management                                                                                                       16

9.1            General Waste Management                                                                      16

9.2            Records of Waste Quantities                                                                     16

10   Inspection and Auditing                                                                                            17

10.1          Site Inspection                                                                                                  17

11   Environmental Complaint and Non-compliance                                         19

11.1          Environmental Complaint, Summons and Prosecution                 19

12   Implementation Status of Mitigation Measures                                          20

12.1          General Requirements                                                                                 20

12.2          Tentative Construction Activities in the Coming Month             20

12.3          Key Environmental Issues for the Coming Month                           21

13   Conclusions and Recommendations                                                                   22

13.1          Conclusions                                                                                                      22

13.2          Recommendations                                                                                           22

 


 

List of TABLES

Table 2-1      Status of Environmental Licenses and Permits of the Contract

Table 3-1      Designated Air Quality Monitoring Stations under the Contract

Table 3-2      Enhanced TSP Monitoring Plan ¡V Construction Phase

Table 3-3      TSP Action and Limit Levels for Impact Air Quality Monitoring

Table 3-4      Actions in the Event of Landfill Gas being Detected in Excavation / Confined Area

Table 4-1      Detailed Air Quality Monitoring Result Exceedance

Table 8-1      Summary of Landfill Gas Measurement Results in Reporting Period

Table 9-1      Summary of Quantities of Inert C&D Materials

Table 9-2      Summary of Quantities of C&D Wastes

Table 10-1    Site Observations for the Contract

Table 11-1    Statistical Summary of Environmental Exceedance

Table 11-2    Statistical Summary of Environmental Complaints

Table 11-3    Statistical Summary of Environmental Summons

Table 11-4    Statistical Summary of Environmental Prosecution

Table 12-1    Environmental Mitigation Measures

 

 

 

List of Appendices

Appendix A Project Layout Plan

Appendix B Layout Plan of the Contract

Appendix C  Organization of the Contract

Appendix D Master Construction Program and three Months roll Program

Appendix E  Monitoring Locations for the Contract

Appendix F  Event and Action Plan

Appendix G Calibration Certificates of Monitoring Equipment

Appendix H Landfill Gas Monitoring Results and Graphical Plots

Appendix I Investigation Report for Exceedance

Appendix J Checklist for Landscape and Visual Monitoring

Appendix K Monthly Summary Waste Flow Table

Appendix L Environmental Mitigation Measures Implementation Schedule (EMMIS)

 

 

 


1                    Introduction

1.1                       Project Background

1.1.1                 According to the findings of the Northwest New Territories (NWNT) Traffic and Infrastructure Review conducted by the Transport Department, Tuen Mun Road, Ting Kau Bridge, Lantau Link and North Lantau Highway would be operating beyond capacity after 2016. This forecast has been based on the estimated increase in cross boundary traffic, developments in the Northwest New Territories (NWNT), and possible developments in North Lantau, including the Airport developments, the Lantau Logistics Park (LLP) and the Hong Kong ¡V Zhuhai ¡V Macao Bridge (HZMB). In order to cope with the anticipated traffic demand, two new road sections between NWNT and North Lantau ¡V Tuen Mun ¡V Chek Lap Kok Link (TM-CLKL) and Tuen Mun Western Bypass (TMWB) are proposed.

 

1.1.2                 An Environmental Impact Assessment (EIA) of TM-CLKL (the Project) was prepared in accordance with the EIA Study Brief (No. ESB-175/2007) and the Technical Memorandum of the Environmental Impact Assessment Process (EIAOTM).  The EIA Report was submitted under the Environmental Impact Assessment Ordinance (EIAO) in August 2009.  Subsequent to the approval of the EIA Report (EIAO Register Number AEIAR-145/2009), an Environmental Permit (EP-354/2009) for TM-CLKL was granted by the Director of Environmental Protection (DEP) on 4 November 2009, the VEP (EP-354/2009B) was issued on 20 September 2012, and the latest VEP (EP-354/2009C) was issued on 10 December 2014.   The Project Layout Plan shown in Appendix A.

 

1.2                       Contract Background

1.2.1                 CRBC-Kaden Joint Venture (hereafter ¡§CRBC-Kaden JV¡¨) is commissioned by the Highways Department (HyD) as the Main Contractor of the Contract No. HY/2013/12 -Northern Connection Toll Plaza and Tunnel Section of the Tuen Mun ¡V Chek Lap Kok Link (TM-CLK Link Project).  Layout Plan of the Contract shows in Appendix B.  The works of the Contract mainly include:-

a.              construction of an approximately 5.4 hectares toll plaza and an associated footbridge;

b.             construction of associated carriageways including approximately 0.74 kilometre land viaducts, and an approximately 230 metres vehicular underpass to connect the toll plaza and the roundabout at Lung Mun Road/Lung Fu Road;

c.              site formation for the construction of the toll plaza, including associated slope works and natural terrain hazard mitigation measures;

d.             modification and realignment of the existing Lung Mun Road and Lung Fu Road; and

e.              associated waterworks, drainage, sewerage and landscaping works, etc..

 

1.2.2                 AECOM Asia Company Limited as the Resident Engineer (RE) and ENVIRON Hong Kong Ltd as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) were employed by the HyD.  For implementation of the environmental monitoring and audit (EM&A) programme under the Contract, CRBC-Kaden JV has appointed Action-United Environmental Services & Consulting (AUES) as the Environmental Team (ET) to responsible relevant environmental monitoring work.

 

1.2.3                 In view of the construction works under the Contract, the major construction activities are land-based works.  Hence, the EM&A programme including water quality and marine ecological monitoring should not related the Contract works.  Moreover, all designated noise monitoring locations are located in Lantau and noise monitoring is therefore not required under the Contract.  In accordance with the Project EM&A Manual requirements included air quality, ecological (Pitcher Plant) monitoring, cultural heritage and site inspections should be conducted. In addition, landscape and visual (L&V) monitoring, landfill gas monitoring and audit of the contractor¡¦s implementation of the construction noise and land-based water quality pollution control measures are also required for the Contract.

 

1.2.4                 As part of the EM&A program, baseline air quality monitoring has been carried out by the Environmental Team HY/2012/08 from 16th to 31st October 2013.  A set of Action and Limit Levels (A/L Levels) of air quality performance criteria as proposed by Environmental Team of HY/2012/08 would be used for this Contract.

 

1.2.5                 In September 2013, baseline survey for Pitcher Plant has been conducted within the project area by a suitably qualified ecologist.  In mid-September 2014, Contract HY/2013/12 has also conducted a one-off survey to confirm the number of existing Pitcher Plant.  For cultural heritage, a condition survey for the grave was conducted on 23 September 2014.  The Baseline Monitoring Report for the Contract was submitted on 7 October 2014 for IEC¡¦s verification and 25 November 2014 for EPD¡¦s endorsement.

 

1.2.6                 The construction phase of the Contract has been commenced on 23 October 2014.  This is 1st monthly EM&A report presenting the monitoring results and inspection findings for reporting period from 23 October 2014 to 30 November 2014.

 

1.3                       Report Structure

1.3.1                 The Monthly Environmental Monitoring and Audit (EM&A) Report is structured into the following sections:-

Section 1     Introduction

Section 2     Contract Organization and Construction Progress

Section 3     Summary of Impact Monitoring Requirements

Section 4     Air Quality Monitoring

Section 5     Ecology Monitoring

Section 6     Cultural Heritage

Section 7     Landscape and Visual

Section 8     Landfill gas hazard Monitoring

Section 9     Waste Management

Section 10   Site Inspections

Section 11   Environmental Complaints and Non-Compliance

Section 12   Implementation Status of Mitigation Measures

Section 13   Conclusions and Recommendations

 

 

 

 


2                    Contract Organization and Construction progress and Environmental Submissions

2.1                       Contract Organization

2.1.1                 The Contract organization is shown in Appendix C.  The responsibilities of respective parties are:

 

Highways Department (HyD)

2.1.2                 HyD is the Project Proponent and the Permit Holder of the EP of the development of the Project and will assume overall responsibility for the project. An Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) shall be employed by HyD to audit the results of the EM&A works carried out by the ET.

 

Environmental Protection Department (EPD

2.1.3                 EPD is the statutory enforcement body for environmental protection matters in Hong Kong.

 

Engineer or Engineers Representative (ER)

2.1.4                 The ER is responsible for overseeing the construction works and for ensuring that the works are undertaken by the Contractor in accordance with the specification and contract requirements. The duties and responsibilities of the ER with respect to EM&A are:

¡P           Monitor the Contractors¡¦ compliance with contract specifications, including the implementation and operation of the environmental mitigation measures and their effectiveness

¡P           Monitor Contractor¡¦s, ET¡¦s and IEC¡¦s compliance with the requirements in the Environmental Permit (EP) and EM&A Manual

¡P           Facilitate ET¡¦s implementation of the EM&A programme

¡P           Participate in joint site inspection by the ET and IEC or EPNO

¡P           Oversee the implementation of the agreed Event / Action Plan in the event of any exceedance

¡P           Adhere to the procedures for carrying out complaint investigation

 

The Contractor

2.1.5                 The Contractor should report to the ER.  The duties and responsibilities of the Contractor are:

¡P           Comply with the relevant contract conditions and specifications on environmental protection

¡P           Employ an Environmental Team (ET) to undertake monitoring, laboratory analysis and reporting of EM &A Facilitate ET¡¦s monitoring and site inspection activities

¡P           Participate in the site inspections by the ET and IEC, and undertake any corrective actions

¡P           Provide information / advice to the ET regarding works programme and activities which may contribute to the generation of adverse environmental impacts

¡P           Submit proposals on mitigation measures in case of exceedances of Action and Limit levels in accordance with the Event / Action Plans

¡P           Implement measures to reduce impact where Action and Limit levels are exceeded

¡P           Adhere to the procedures for carrying out complaint investigation

 

Environmental Team (ET)

2.1.6                 The ET shall not be in any way an associated body of the Contractor, and shall be employed by the Project Proponent/Contractor to conduct the EM&A programme.  The ET should be managed by the ET Leader. The ET Leader shall be a person who has at least 7 years¡¦ experience in EM&A and has relevant professional qualifications. Suitably qualified staff should be included in the ET, and resources for the implementation of the EM&A programme should be allocated in time under the Contract, to enable fulfillment of the Project¡¦s EM&A requirements as specified in the EM&A Manual during construction of the Contract.  The ET shall report to the Project Proponent and the duties shall include:

Ÿ   Sampling, analysis and statistical evaluation of monitoring parameters with reference to the EIA study recommendations and requirements in respect of noise, dust and water quality.

Ÿ   Environmental site surveillance.

Ÿ   Audit of compliance with environmental protection and pollution prevention and control regulations.

Ÿ   Monitor the implementation of environmental mitigation measures.

Ÿ   Monitor compliance with the environmental protection clauses/specifications in the Contract.

Ÿ   Review construction programme and comment as necessary.

Ÿ   Review construction methodology and comment as necessary.

Ÿ   Complaint investigation, evaluation and identification of corrective measures.

Ÿ   Audit of the EMS and recommend and implement any changes as appropriate.

Ÿ   Liaison with the Independent Environmental Checker IEC) on all environmental performance matters.

Ÿ   Advice to the Contractor on environmental improvement, awareness, enhancement matter, etc., on site.

Ÿ   Timely submission of the designated EM&A reports to the ER, the IEC, the DEP, the AFCD and the AMO as appropriate.

 

Independent Environmental Checker (IEC)

2.1.7                 The Independent Environmental Checker (IEC) should not be in any way an associated body of the Contractor(s) or the ET for the Project.  The IEC should be employed by the Permit Holder (i.e., HyD) prior to the commencement of the construction of the Project.  (IEC) shall be employed to advise the ER on environmental issues related to the project.  The role of the IEC shall be independent from the management of construction works, but the IEC shall be empowered to audit the environmental performance of the construction activities and operational mitigation. The IEC shall have project management experience in addition to the requirements of the ET specified above and the appointment of the IEC will be subject to the approval of the ER and the DEP.  The IEC may require specialist support staff in order to properly carry out his duties, which shall include the following:

Ÿ   Review and audit all aspects of the EM&A programme.

Ÿ   Validate and confirm the accuracy of monitoring results, monitoring equipment, monitoring locations, monitoring procedures and locations of sensitive receivers.

Ÿ   Carry out random sample check and audit on monitoring data and sampling procedures, etc.

Ÿ   Conduct random site inspection.

Ÿ   Audit the EIA recommendations and requirements against the status of implementation of environmental protection measures on site.

Ÿ   Review the effectiveness of environmental mitigation measures and project environmental performance.

Ÿ   Audit the Contractor¡¦s construction methodology and agree the least impact alternative in consultation with the ET and the Contractor.

Ÿ   Check complaint cases and the effectiveness of corrective measures.

Ÿ   Review EM&A report submitted by the ET.

Ÿ   Feedback audit results to ET by signing off relevant EM&A proformas.

 

Environmental Protection Office (ENPO)

2.1.8                 The responsibility of the ENPO would be similar to that of the IEC but should also include:

Ÿ   coordination of the monitoring and auditing works for all the on-going projects in the area in order to identify possible sources/causes of exceedances and recommend suitable remedial actions where appropriate;

Ÿ   identify and assess cumulative impacts including possible sources/causes of exceedance and recommending suitable remedial actions;

Ÿ   undertake liaison with the mainland project teams counterparts to identify and assess any cross-boundary cumulative impacts; and

Ÿ   coordinate the assessment and response to complaints/enquires from locals, green groups, district councils or the public at large.

2.2                       Construction Progress

2.2.1                 In the Reporting Period, the major construction activity conducted under the Contract is summarized in below.  Moreover, the master construction program of the Contract is enclosed in Appendix D.

Ÿ   Site Formation at Portion X.

Ÿ   Slope stabilization works at Portion X.

Ÿ   Surface drainage at Portion X.

Ÿ   Ground Investigation Works at various locations

Ÿ   Site Clearance at various locations

Ÿ   Erection of site office at WA18

Ÿ   Retaining Wall at Portions X and I

Ÿ   Road Works

Ÿ   Piling Works at Portion I

Ÿ   Tree Felling at Portions X and I

 

2.3                       Summary of Environmental Submissions

2.3.1                 To according with the EP stipulation, the required documents has submitted to EPD for retention as listed below:

Ÿ   Monitoring Plan on construction dust (submission refer to Contract HY/2012/08)

Ÿ   Landscape and Visual Plan (not yet endorsed by EPD)

Ÿ   Waste Management Plan  (not yet endorsed by EPD)

Ÿ   Baseline Monitoring Report (not yet endorsed by EPD)

 

2.3.2                 Summary of the relevant permits, licenses, and/or notifications on environmental protection for the Contract is presented in Table 2-1.

Table 2-1      Status of Environmental Licenses and Permits of the Contract

No.

Type of Permit/ License

Submission Date

Reference/

License No.

Date of Issue

Date of Expiry

1

Air pollution Control (Construction Dust) Regulation

06-08-2014

377719

06-08-2014

N/A

2

Chemical Waste Producer Registration - Waste Producers Number

06-08-2014

5117422C389301

03-09-2014

N/A

3

Water Pollution Control Ordinance - Discharge License

13-08-2014

WT00020065-2014

29-09-2014

30-09-2019

4

Waste Disposal Regulation - Billing Account for Disposal of Construction Waste

21-07-2014

7020460

01-08-2014

N/A

5

CNP for Construction of Site Office

15-08-2014

GW-RW0656-14

03-09-2014

22-02-2015

6

CNP for Site Formation

15-09-2014

GW-RW0761-14

29-09-2014

29-03-2015

7

CNP for Concreting

15-09-2014

GW-RW0748-14

29-09-2014

29-03-2015

 

 


3                    Summary of Impact Monitoring Requirements Under the Contract

3.1                       General

3.1.1                 In view of the construction works under the Contract, the major construction activities are land-based.  In accordance with the Project EM&A Manual requirements, environmental aspect monitoring should be conducted including air quality, ecological (Pitcher plant), cultural heritage and site inspections during construction period.  In addition, landscape and visual (L&V) monitoring, landfill gas monitoring and audit of the contractor¡¦s implementation of the construction noise and land-based water quality pollution control measures are also required for the Contract.

 

3.1.2                 A summary of construction phase EM&A requirements are presented in the sub-sections below.

 

3.2                       Air Quality Monitoring Parameters

3.2.1                 The construction phase monitoring air quality shall cover the following parameters:

                     1-hour TSP; and

                     24-hour TSP

 

3.3                       Monitoring Location

3.3.1                 The air quality monitoring stations for impact monitoring are listed in Table 3.1 and illustrated in Appendix E.

Table 3-1      Designated Air Quality Monitoring Stations under the Contract

ID

Location

Air monitoring station Description

ASR1

Tuen Mun Fireboat Station

EM&A Manual

ASR5

Pillar Point Fire Station

EM&A Manual

AQMS1

Previous River Trade Golf

Enhanced TSP Level under EP condition 2.4

ASR6

Butterfly Beach Laundry

Enhanced TSP Level under EP condition 2.4

ASR10

Butterfly Beach Park

Enhanced TSP Level under EP condition 2.4

 

3.4                       Monitoring Frequency

General Requirement

3.4.1                 For regular impact monitoring, the sampling frequency of at least once in every six days shall be strictly observed at five of the designated monitoring stations for 24-hr TSP monitoring.  For 1-hr TSP monitoring, the sampling frequency of at least three times in every six days should be undertaken at five locations when the highest dust impact occurs.  The stations to be monitored should be selected based on the prevailing wind direction and their proximity to the active construction works.

 

Special Requirement

3.4.2                 As per Condition 2.4 of the EP of TM-CLKL, an enhanced monitoring plan on TSP level at Tuen Mun (¡§the Enhanced TSP Monitoring Plan¡¨) is required to be submitted to the DEP for approval at least 1 month before the commencement of construction of the Project.  Details of the Enhanced TSP Monitoring Plan are provided in the Contract specific EM&A Manual.  The air quality monitoring work under this Contract will follow the monitoring requirement of enhanced TSP monitoring under the project.

 

3.4.3                 The air quality monitoring requirements for the Contract is shown in Table 3-2.

Table 3-2      Enhanced TSP Monitoring Plan ¡V Construction Phase

Condition

Monitoring Parameter

Monitoring Location

Frequency

Monitoring Requirement

General

1-hour TSP

ASR1, ASR5, AQMS1, ASR6, ASR10

3 times per day every six days

Throughout the Northern Connection, toll plaza and tunnel buildings construction works

24-hour TSP

ASR1, ASR5, AQMS1, ASR6, ASR10

Daily every six days

Special

1-hour TSP

ASR1, ASR5, AQMS1, ASR6, ASR10

3 times per day every three days

Northern Connection

During excavation works for launching shaft, excavation work for Cut and Cover Tunnel and Cut and Cover Tunnel Construction

Toll Plaza

During excavation, slope works, construction of road and superstructures and wind erosion from open sites and stockpiling areas

Tunnel Buildings

During excavation, foundation works, construction of superstructures and wind erosion from open sites and stockpiling areas

24-hour TSP

ASR1, ASR5, AQMS1, ASR6, ASR10

Daily every three days

 

3.5                       Monitoring Equipment

3.5.1                 The 24-hour and 1-hour TSP levels shall be measured by following the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.

 

3.5.2                 A high volume sampler in compliance with the following specifications shall be used for carrying out the 1-hr and 24-hr TSP monitoring:

(i)            0.6-1.7 m3/min (20-60 SCFM) adjustable flow range;

(ii)          equipped with a timing/control device with +/- 5 minutes accuracy for 24 hours operation;

(iii)        installed with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;

(iv)        capable of providing a minimum exposed area of 406 cm2 (63 in2);

(v)          flow control accuracy: +/- 2.5% deviation over 24-hr sampling period;

(vi)        equipped with a shelter to protect the filter and sampler;

(vii)      incorporated with an electronic mass flow rate controller or other equivalent devices;

(viii)    equipped with a flow recorder for continuous monitoring;

(ix)        provided with a peaked roof inlet;

(x)          equipped with a manometer;

(xi)        able to hold and seal the filter paper to the sampler housing in a horizontal position;

(xii)      easy to change the filter; and

(xiii)    capable of operating continuously for 24-hr period.

 

3.5.3                 Calibration of dust monitoring equipment shall be conducted by the ET upon installation and thereafter at bi-monthly intervals. The transfer standard shall be traceable to the internationally recognized primary standard and be calibrated annually. The calibration data shall be properly documented for future reference by concerned parties, such as the IEC. All the data shall be converted into standard temperature and pressure condition.

 

3.5.4                 The filter paper of 24-hour TSP measurement shall be determined by HOKLAS accredited laboratory.

 

3.5.5                 If the ET proposes to use a direct reading dust meter to measure 1-hr TSP levels on an ad hoc basis, he shall submit sufficient information to the IEC to prove that the instrument is capable of achieving a comparable result as that the High Volume Sampler (HVS) and may be used for the 1-hr sampling.  The instrument should also be calibrated regularly and the 1-hr sampling shall be checked periodically by the HVS to check the validity and accuracy of the results measured by the direct reading method.

 

3.5.6                 According to the Project EM&A Manual, wind data monitoring equipment shall also be provided and set up for logging wind speed and wind direction near the dust monitoring locations.  The equipment installation location shall be proposed by the ET and agreed with the IEC.  For installation and operation of wind data monitoring equipment, the following points shall be observed:

(i)            the wind sensors should be installed on masts at an elevated level 10 m above ground so that they are clear of obstructions or turbulence caused by the buildings;

(ii)          the wind data should be captured by a data logger to be down-loaded for processing at least once a month;

(iii)        the wind data monitoring equipment should be re-calibrated at least once every six months; and

(iv)        wind direction should be divided into 16 sectors of 22.5 degrees each.

 

3.6                       Derivation of Action/Limit (A/L) Levels

3.6.1                 The baseline monitoring results formed the basis for determining the air quality criteria for the impact monitoring. The ET shall compare the impact monitoring results with air quality criteria set up for 24-hour TSP and 1-hour TSP.  Based on results of the approved Baseline Monitoring Report of HyD Contract HY/2012/08, the proposed Action and Limit Levels are shown in Tables 3-3.

Table 3-3      TSP Action and Limit Levels for Impact Air Quality Monitoring

Air Quality Monitoring Stations

24-hour TSP (£gg/m3)

1-hour TSP (£gg/m3)

Action Level

Limit Level

Action Level

Limit Level

ASR1

213

260

331

500

ASR5

238

260

340

500

AQMS1

213

260

335

500

ASR6

238

260

338

500

ASR10

214

260

337

500

 

3.6.2                 Should non-compliance of the environmental quality criteria occurs, remedial actions will be triggered according to the Event and Action Plan which presented in Appendix F.

 

3.7                       Other Environmental Aspects

Noise

3.7.1                 The TM-CLKL EIA study concluded that no existing noise sensitive receiver (NSR) was identified within the Study Area at Tuen Mun.  Therefore, no planned NSR designated at the Project sites of Tuen Mun.  Based upon this, no noise monitoring is necessary for construction phase under the Contract.

 

3.7.2                 Regular site inspections and audits will be carried out during the construction phase in order to confirm compliance with the regulatory requirements and conformity of the Contractor with regard to noise control and contract conditions.

 

Water Quality

3.7.3                 No marine works will be undertaken under the Contract.  Based upon this, no water quality monitoring is necessary for construction phase.

 

Ecology

3.7.4                 Since the Works of the Contract would not be to generate the marine ecological impact, no dolphin monitoring under the Contract to conduct.

 

3.7.5                 During construction phase, the ET will perform Pitcher Plants regularly inspection at least once every week to report the growth and protection measure situation.

 

Landscape and Visual

3.7.6                 According to EIA recommendation, site inspection and audit shall be required to be undertaken in the operation stage. Measures to mitigate landscape and visual impacts during construction should be checked and monitored by a Registered Landscape Architect to ensure compliance with the intended aims of the mitigation measures in accordance with the EM&A Manual.

 

Cultural Heritage

3.7.7                 Grave G1 of heritage resources is situated near the proposed toll plaza in Tuen Mun.  Site inspections should be undertaken at least once per week throughout the construction period to ensure compliance with the intended aims of recommended mitigation measures.

 

Monitoring and Measurement of Landfill Gas

3.7.8                 During EIA study, landfill gas hazards are likely to be generated from the Pillar Point Valley (PPV) Landfill. Hence, regular landfill gas monitoring is recommended during construction of the proposed toll plaza.  Safety Officer or an approved and appropriated qualified person should be carried out the monitoring works to make sure the area free of landfill gas before any man enters in the area.

 

3.7.9                 Depending on the results of the measurements, actions required will vary and should be set down by the Safety Officer or other appropriately qualified person. As a minimum these should encompass those actions specified as follow:

Table 3-4      Actions in the Event of Landfill Gas being Detected in Excavation / Confined Area

Parameter

Measurement

Action

Oxygen

< 19%

- Ventilate to restore oxygen to > 19%

< 18%

- Stop work

- Evacuate personnel / prohibit entry

- Increase ventilation to restore to > 19%

Methane

> 10% LEL (> 0.5% v/v)

- Prohibit hot work

- Ventilate to restore methane to < 10% LEL

> 20% LEL (>1% v/v)

- Stop work

- Evacuate personnel / prohibit entry

- Increase ventilation to restore to < 10%

Carbon Dioxide

> 0.5%

- Ventilate to restore oxygen to < 0.5%

> 1.5%

- Stop work

- Evacuate personnel / prohibit entry

- Increase ventilation to restore to < 0.5%

 

 


 

4                    Air Quality Monitoring

4.1                       General

4.1.1                 The air quality impact monitoring and enhanced Total Suspended Particulates (TSP) level monitoring perform the five proposed locations are currently carried out by the ET of Contract HY/2012/08.  Sharing of impact air quality monitoring data between HY/2012/08 and HY/2013/12 is agreed by all relevant parties.  Therefore the Contract is not required to conduct its own dust monitoring exercise until the Contract HY/2012/08 is ended.

 

4.2                       Air Quality Monitoring Results in Reporting Period

4.2.1                 In the Reporting Period, 1-hr TSP and 24-hours TSP monitoring were carried out at five proposed locations by the ET of Contract HY/2012/08.  The detailed information of air quality monitoring could be referred to the Monthly EM&A Reports of the Contract HY/2012/08 (October 2014 and November 2014).

 

4.3                       Action and Limit (A/L) Levels Exceedance

4.3.1                 According to the air quality monitoring results provided Contract HY/2012/08, no exceedances in 24-hour TSP were recorded but a total of two (2) exceedances of 1-hour TSP were triggered in the Reporting Period.  Notification on Exceedances (NOEs) to all relevant parties has been issued by the ET of Contract HY/2012/08 upon the results was confirmed.  The summary of air quality exceedance is shown in Table 4-1.

Table 4-1      Summary of Air Quality Monitoring Exceedance

Date of Exceedance

Monitoring Station

Air Quality Parameter

Result

Exceed

14 Nov 2014

ASR1

1-hour TSP

404£gg/m3

396£gg/m3

Action Level

 

4.3.2                 Investigation report for the cause of exceedances has been completed and submitted to relevant parties and it has been shown in Appendix H.

 

4.4                       Air Quality Exceedance Investigation

1-hour TSP exceedance dated 14 November 2014

4.4.1                 Upon received the notification of exceedance, investigation has been undertaken by the ET of the Contract.  According to site information provided by CRBC-Kaden JV, site formation works was conducted on 14 November 2014.  To reduce to dust impact arises from the contract. mitigation measures for construction dust control were implementation and they are included the following:-

Ÿ   watering of haul road by water truck to keep road surface wet

Ÿ   to set speed control at 5 km/hr for all vehicles using the haul road

Ÿ   most soil stockpiles were well compacted

Ÿ   installation of auto-water sprinkler in dusty area

Ÿ   provide water spraying during rock breaking work

Ÿ   covered part of the exposed slopes by geotextile net

 

4.4.2                 During the subsequent site inspection, it was observed the above-mentioned dust mitigation measures were implemented and the site condition is acceptable.

 

4.4.3                 Moreover, the exceedance location ASR1 is located over 800m from the working area. There are other monitoring locations closer to the active site area, such as ASR5 and ASR6, and the relevant monitoring results were reviewed.  With referenced to the monitoring results collected at other stations, ASR5 is ranged 114-226£gg/m3 and ASR6 is ranged 108-130£gg/m3 and no exceedances were triggered.

 

4.4.4                 Based on above investigation, the exceedance is unlikely related to the Contract work and no corrective action was required accordingly.

5                    Ecology Monitoring

5.1                       General

5.1.1                 According to the EM&A Manual requirements, regularly inspection for Pitcher Plants at least once every week to report it growth and protection measure situation shall be conducted during construction period.

 

5.2                       Pitcher Plants Inspection

5.2.1                 In the Reporting Period, inspections for the condition of the Pitcher Plants and mitigation measures were carried out by the Contractor on 24th and 31st October 2014, 7th, 14th, 21st and 28th November 2014.  It was observed that hoarding along the works boundary for protecting the Pitcher Plants was not yet installed.  However, wire fencing has been provided as the temporary protection.  As advised by CRBC-Kaden JV, the design of the hoarding and installation is currently in progress. 

 

5.2.2                 During each occasion of site inspection, no construction activities were found to be conducted nearby the protected areas of Pitcher Plants and the growth of Pitcher Plants is kept normal condition.

 


 

6                    CULTURAL HERITAGE

6.1                       General

6.1.1                 According to the EM&A Manual requirements, regular inspection for heritage resource Grave G1 shall be audited by the ET at least once every week to ensure recommended mitigation measures implemented during construction period The aim of the survey is prevention of any possible damage to the grave and to ensure that proposed mitigation measures area implemented. The broad scope of the audit will involve supervision of the following:

 

Ÿ   Non-contact effects of the engineering works, such as vibration from pneumatic drills which could case damage, such as foundation or wall cracks and loosening of tiles or fixtures; and

Ÿ   Contact between the historic structures and equipment and materials associated with the engineering works.

 

6.1.2                 Specifically, the monitoring programme will entail the following tasks:

 

Ÿ   The extent of the agreed works areas should be regularly checked during the construction phase to ensure the buffer is being maintained; and

Ÿ   Ensure no stockpiling or equipment storage is affecting the structure.

 

6.1.3                 In the event of non compliance the responsibilities of the relevant parties is detailed in the Event/ Action Plan in Appendix F.

 

6.2                       Grave Inspection

6.2.1                 In the Reporting Period, site inspection for the Grave G1 was undertaken on 28th October 2014, 4th, 11th, 19th and 25th November 2014.  During site inspection, buffer zone was observed between the working area and the Grave and no construction material or equipment was stored nearby the Grave.

 

6.2.2                 Mitigation measures undertaken by the Contractor has fully implemented the EM&A Manual requirements.

 


 

7                    Landscpae and Visual

7.1                       General

7.1.1                 According to EM&A Manual requirements, monitoring of Contractor¡¦s operations during construction period to report on Contractor¡¦s compliance should be carried out on weekly basis.  Measure to mitigate landscape and visual impact during construction should be checked and monitored by a Registered Landscape Architect to ensure compliance with the intended aims of the mitigation measures.  Moreover, the progress of the engineering works shall be regularly reviewed on site to identify the earliest practical opportunities for the landscape works to be undertaken.

 

7.2                       Landscape and Visual Inspection

7.2.1                 In the Reporting Period, site inspection for landscape and visual mitigation measures was undertaken on 24th and 31st October 2014, 7th, 14th, 21st and 28 November 2014 by the Contractor.  During the site inspection, all the existing trees were properly protected and kept away from construction works.  Sand bags were erected at sensitive areas to ensure no runoff into water body.  Most of the landscape works such as hydro-seeding and planting were not yet commenced.  The detailed inspection checklists were provided in Appendix J.

 

 

 

 


 

8                    Landfill Gas Hazard Monitoring

8.1                       General

8.1.1                 During EIA study, landfill gas hazards are likely to be generated from the Pillar Point Valley (PPV) Landfill. Hence, regular landfill gas monitoring is recommended during construction of the proposed toll plaza.

 

8.1.2                 During construction, a Safety Officer should be appointed to carry out the monitoring works. The monitoring frequency and areas to be monitored should be set down prior to commencement of ground-works either by the Safety Officer or an approved and appropriated qualified person. The routine monitoring should be carried out in all excavations, manholes, chambers, relocation of monitoring wells and any other confined spaces that may have been created. All measurements in excavations should be made with the extended monitoring tube located not more than 10 mm from the exposed ground surface. Monitoring should be performed properly to make sure that the area is free of landfill gas before any man enters in the area.

 

8.1.3                 For excavations deeper than 1m, measurements should be carried out:

Ÿ   at the ground surface before excavation commences;

Ÿ   immediately before any worker enters the excavation;

Ÿ   at the beginning of each working day for the entire period the excavation remains open; and

Ÿ   periodically through the working day whilst workers are in the excavation.

 

8.1.4                 For excavations between 300mm and 1m deep, measurements should be carried out:

Ÿ   directly after the excavation has been completed; and

Ÿ   periodically whilst the excavation remains open

 

8.1.5                 For excavations less than 300mm deep, monitoring may be omitted, at the discretion of the Safety Officer or other appropriately qualified person.

 

8.1.6                 To ensure the accuracy of the monitoring data, zeroing of the gas analyser shall be undertaken at the start of each day¡¦s monitoring.  As part of the QA/QC, calibration of the gas analyser shall be conducted at least once every two weeks according to the specification of the manufacturer¡¦s operation manual.

 

8.2                       Landfill Gas Monitoring Result

8.2.1                 In the Reporting Period, landfill gas monitoring was conducted at the construction of Retaining Wall B and Retaining Wall F and the locations are illustrated in Appendix E. A BIOGAS 5000 gas analysis was used for the landfill gas monitoring and the valid calibration certificate is presented in Appendix G.

 

8.2.2                 There were total 32 workings days monitoring were carried by the Safety Officer or an approved and qualified persons.  Table 8-1 is summarized landfill gas measurement results.  Moreover, field data sheet and graphical plot are attached in Appendix H.

Table 8-1      Summary of Landfill Gas Measurement Results in Reporting Period

Landfill Gas Parameter

Action Level

Limit Level

Detectable at Retaining Wall B

Detectable at Retaining Wall F

Min

Max

Min

Max

Methane

>10% LEL (>0.5% v/v)

>20% LEL (>1% v/v)

0%

0%

0%

0%

Oxygen

<19%

<18%

21.0%

21.4%

21.0%

21.3%

Carbon Dioxide

>0.5%

>1.5%

0.0%

0.3%

0.0%

0.3%

 

8.2.3                 The measurement results shown no methane concentration was detected and all oxygen concentration were over 21% and Carbon Dioxide was between 0.0 and 0.3 %.  No corrective action was required accordingly.

 


 

9                    Waste Management

9.1                       General Waste Management

9.1.1                 Waste management was carried out by an on-site Environmental Officer or an Environmental Supervisor from time to time. The effective management of waste arisings during the construction phase will be monitored through the site audit programme. The aims of the waste audit are:

l  to ensure the waste arising from the works are handled, stored, collected, transferred and disposed of in an environmentally acceptable manner; and

l  to encourage the reuse and recycling of material.

 

9.1.2                 In addition to the site inspections, the ET shall review the documentation procedures prepared by the Waste Coordinator once a week to ensure proper records are being maintained and procedures undertaken in accordance with the Waste Management Plan.

 

9.2                       Records of Waste Quantities

9.2.1                 All types of waste arising from the construction work are classified into the following:

l  Construction & Demolition (C&D) Material;

l  Chemical Waste;

l  General Refuse; and

l  Excavated Soil.

 

9.2.2                 The quantities of waste for disposal in this Reporting Period are summarized in Tables 9-1 and 9-2 and the Monthly Summary Waste Flow Table is shown in Appendix K.  Whenever possible, materials were reused on-site as far as practicable.

Table 9-1      Summary of Quantities of Inert C&D Materials

Type of Waste

Quantity

Disposal Location

Reused in this Contract (Inert) (`000m3)

5.41

-

Reused in other Projects (Inert) (`000m3)

15.061

HY/2012/08

Disposal as Public Fill (Inert) (`000m3)

92.693

Tuen Mum Area 38

 

Table 9-2      Summary of Quantities of C&D Wastes

Type of Waste

Quantity

Disposal Location

Recycled Metal (`000kg)

0

-

Recycled Paper / Cardboard Packing (`000kg)

0

-

Recycled Plastic (`000kg)

0

-

Chemical Wastes (`000kg)

0

-

General Refuses (`000m3)

0.016

WENT

 

 

 


 

10                Inspection and Auditing

10.1                   Site Inspection

10.1.1             According to the approved EM&A Manual, the environmental site inspection shall be formulation by ET Leader.  Weekly environmental site inspections should carry out to confirm the environmental performance.

 

Findings / Deficiencies During Reporting Period

10.1.2             In the Reporting Period, joint site inspection to evaluate site environmental performance has been carried out by the RE, ET and the Contractor on 28th October 2014, 4th, 11th, 19th and 25th November 2014.  No non-compliance was noted but five (5) observations and five (5) reminders were recorded during site inspections. Moreover, IEC or ENPO has attended joint site inspection on 28 October 2014 and 25 November 2014.

 

10.1.3             The findings / deficiencies observed during the weekly site inspection are listed in Table 10-1.

Table 10-1    Site Observations for the Contract

Date

Findings / Deficiencies

Follow-Up Status

28 Oct 2014

Ÿ  It was reminded that properly facities should be provided for all chemical wastes and plants to prevent land contamination.

Ÿ  Not required for reminder.

 

 

 

 

Ÿ  It was reminded that Air quality mitigation measures should be provide to prevent construction dust emission during dry and windy season.

Ÿ  Not required for reminder.

 

04 Nov 2014

.

Ÿ  C&D waste scattered at the site office construction area was observed. The Contractor was should improve housekeeping on site and provide more waste skip for waste storage.

Ÿ  The deficiency has been rectified before site inspection on 19 November 2014.

Ÿ  Stockpile without any cover was observed. The Contractor was requested to provide proper dust mitigation measures for stockpile to minimize dust generation

Ÿ  The deficiency has been rectified before site inspection on 25 November 2014.

Ÿ  It was reminded that air quality mitigation measures should be provide to prevent construction dust emission during dry and windy season.

Ÿ  Not required for reminder.

11 Nov 2014

Ÿ  C&D material scattered at the site office construction area was observed.  Housekeeping should be improved to maintain the site clean and tidy.

Ÿ  The deficiency has been rectified in before site inspection on 19 November 2014.

 

Ÿ  Earth bund should be provided to prevent muddy surface run-off discharged into the stream near the wheel washing bay

Ÿ  The deficiency has been rectified in before site inspection on 25 November 2014.

 

Ÿ  Residual sand and mud was observed retain on haul road behind the wheel washing bay. The Contractor should cleaned up the wheel washing bay regularly to make sure its effective.

Ÿ  To be followed up in next reporting period.

19 Nov 2014

Ÿ  No environmental issue was observed

Ÿ  NA

25 Nov 2014

Ÿ  The Contractor was reminded that all plants using on site shall be properly maintenance to prevent smoke emission.

Ÿ  Not required for reminder.

 

Ÿ  The Contractor was reminded that during the breaking activities, dust mitigation measures should be applied to prevent dust generation.

Ÿ  Not required for reminder.

 

10.1.4             During dry and windy season, air quality mitigation measures should be provide to reduce construction dust impact.

 

10.1.5             Moreover, weekly tidiness and daily cleaniness of general housekeeping should be implemented in accordance with the EM&A Manual recommendation.  Furthermore, tree protected fences should be provided for all the retained trees and chemical waste storage area should be set-up for all chemical waste disposes on site.

 

 

 


11                Environmental Complaint and Non-compliance

11.1                   Environmental Complaint, Summons and Prosecution

11.1.1             For the Contract, no environmental complaint, summons and prosecution was received in the Reporting Period.  However, there were 2 exceedances of the environmental performance limit (Action and Limit Level).  The statistical summary table of environmental exceedance, complaint, summons and prosecution is presented in Tables 11-1, 11-2, 11-3 and 11-4.

Table 11-1    Statistical Summary of Environmental Exceedance

Reporting Period

Environmental Aspect

Frequency

Cumulative

23 October 2014 ¡V

30 November 2014

1-hr TSP

Action

2

0

2

0

Limit

0

0

0

0

24-hr TSP

Action

0

0

0

0

Limit

0

0

0

0

Table 11-2    Statistical Summary of Environmental Complaints

Reporting Period

Environmental Complaint Statistics

Frequency

Cumulative

Complaint Nature

Air

Noise

Water

23 October 2014 ¡V

30 November 2014

0

0

NA

NA

NA

 

Table 11-3    Statistical Summary of Environmental Summons

Reporting Period

Environmental Summons Statistics

Frequency

Cumulative

Complaint Nature

Air

Noise

Water

23 October 2014 ¡V

30 November 2014

0

0

NA

NA

NA

 

Table 11-4    Statistical Summary of Environmental Prosecution

Reporting Period

Environmental Prosecution Statistics

Frequency

Cumulative

Complaint Nature

Air

Noise

Water

23 October 2014 ¡V

30 November 2014

0

0

NA

NA

NA

 


 

12                Implementation Status of Mitigation Measures

12.1                   General Requirements

12.1.1             The environmental mitigation measures that recommended in the Implementation Schedule for Environmental Mitigation Measures (ISEMM) in the Project EM&A Manual covered the issues of Air Quality, Cultural Heritage, Ecology, Landfill Gas Hazard, Landscape & Visual, Noise, Water and Waste and they are presented in Appendix L.

 

12.1.2             The Contract shall be implementing the required environmental mitigation measures according to the EM&A Manual as subject to the site condition.  Environmental mitigation measures generally implemented by the Contract in this Reporting Period are summarized in Table 12-1.

 

Table 12-1    Environmental Mitigation Measures

Issues

Environmental Mitigation Measures

Air Quality

¡P       Maintain damp / wet surface on access road;

¡P       Keep slow speed in the sites;

¡P       All vehicles must use wheel washing facility before off site;

¡P       Sprayed water during rock breaking works;

¡P       During transportation by truck, materials loaded lower than the side and tail boards, and covered before transport;

¡P       Compacted all soil stockpiles; and

¡P       Part of the exposed slopes covered geotextile net

Cultural Heritage

¡P       Set a buffer zone between the working area and the Grave

¡P       All construction materials and equipment store far from the Grave

¡P       Inspection the Grave to ensure provision mitigation measures effective

Ecology

¡P       Wire fencing provided for temporary protect Pitcher Plants

¡P       Undertake weekly inspection of Pitcher Plants

Landfill Gas Hazard

¡P       Landfill Gas measurement undertake during trench excavation

Water Quality

¡P       Temporary drainage system provide for surface runoff prevent discharge to public area

¡P       Wastewater to be treated by sedimentation tank before discharge.

Noise

¡P       Restrain operation time of plants from 07:00 to 19:00 on any working day except for Public Holiday and Sunday.

¡P       Keep good maintenance of plants

¡P       The noisy plants or works provide mobile noise barriers

¡P       Shut down the plants when not in used.

Waste and Chemical Management

¡P       On-site sorting prior to disposal

¡P       Follow requirements and procedures of the ¡§Trip-ticket System¡¨

¡P       Predict required quantity of concrete accurately

¡P       Collect the unused fresh concrete at designated locations in the sites for subsequent disposal

General

¡P       The site was generally kept tidy and clean.

 

12.2                   Tentative Construction Activities in the Coming Month

12.2.1             Construction activities as undertaken in the coming month for the Contract lists below:

Ÿ   Construction of Haul Roads to Slope A, B, C, D & E

Ÿ   Excavation to Slope A, B & E

Ÿ   Slope stabilization works

Ÿ   Surface drainage

Ÿ   Ground Investigation Works

Ÿ   Site Clearance

Ÿ   Erection of ER¡¦s and CKJV¡¦s site office

Ÿ   Civil works of ER¡¦s and CKJV¡¦s site office

Ÿ   Retaining Wall B & F

Ÿ   Road Works

Ÿ   Piling Works

Ÿ   Tree Felling

 

12.3                   Key Environmental Issues for the Coming Month

12.3.1             Key environmental issues to be considered in the coming month include:

Ÿ    Implementation of dust suppression measures at all times;

Ÿ    Potential wastewater quality impact due to surface runoff;

Ÿ    Potential fugitive dust quality impact due from the dry/loose/exposure soil surface/dusty material;

Ÿ    Ensure dust suppression measures are implemented properly;

Ÿ    Sediment catch-pits and silt removal facilities should be regularly maintained;

Ÿ    Management of chemical wastes;

Ÿ    Site effluent discharge to the nearby nullah is prohibited;

Ÿ    Follow-up of improvement on general waste management issues; and

Ÿ    Implementation of construction noise preventative control measures

 


13                Conclusions and Recommendations

13.1                   Conclusions

13.1.1             This is 1st monthly EM&A report presenting the monitoring results and inspection findings for the Reporting Period from 23 October 2014 to 30 November 2014.

 

13.1.2             No exceedances of 24-hour TSP monitoring were recorded in the Reporting Period. However, there were two exceedances of 1-hour TSP measurements trigger in Action Level at ASR1 on 14 November 2014.  NOE was issued by the ET of HY/2012/08 to notify all relevant parties.  Based on investigation finding, the exceedance is unlikely related with the works under the Contract and no corrective action was required for the Contract accordingly.

 

13.1.3             In this Reporting Period, no noise complaint was received by RE, the Contractor, ENPO or HyD.  No Action Level exceedances were triggered and no NOE or the associated corrective actions were therefore issued.

 

13.1.4             Site inspections for landscape and visual have been conducted on weekly basis to check by the Contractor and ensure if the condition compliance with the intended aims of the mitigation measures.  During the site inspection, all the existing trees were properly protected and kept away from construction works.  Sand bags were erected at sensitive areas to ensure no runoff into water body.  Most of the landscape works such as hydro-seeding and planting were not yet commenced.

 

13.1.5             Landfill gas monitoring was conducted at the construction of Retaining Wall B and Retaining Wall F by the Safety Officer. The monitoring results shown no exceedances were triggered.

 

13.1.6             No documented a complaint, notification of summons or successful prosecution is received by the Contract.

 

13.1.7             Joint site inspection by the RE, ET and CRBC-Kaden JV was carried out on 28th October 2014, 4th, 11th, 19th and 25th November 2014.  Moreover, IEC or ENPO attended joint site inspection On 28 October 2014 and 25 November 2014.  No non-compliance was recorded during the site inspection but five (5) observations and five (5) reminders were recorded during site inspections.  All the deficiencies were rectified before next site inspection date.  The environmental performance of the Contract was therefore considered as satisfactory.

 

13.1.8             In the Reporting Period, hoarding along the works boundary for protecting the Pitcher Plants was not yet installed.  However, wire fencing has been provided as the temporary protection.  As advised by CRBC-Kaden JV, the design of the hoarding and installation is currently working in progress.  During each occasion of site inspection, no construction activities were found to be conducted nearby the protected areas of Pitcher Plants and the growth of Pitcher Plants is kept in normal condition.

 

13.1.9             For cultural heritage, the buffer zone between the working area and the Grave was observed and no construction material or equipment was stored nearby.

 

13.1.10         No joint site inspection was undertaken with any external parties i.e. EPD and AFCD in this Reporting Period.

 

13.2                   Recommendations

13.2.1             During dry season, special attention should be paid on the potential construction dust impact.  The Contractor should fully implement the construction dust mitigation measures properly.

 

13.2.2             Water quality mitigation measures such as prevention of muddy water and other water quality pollutants via site surface water runoff get into public area should be avoided.

 

13.2.3             It was reminded that good housekeeping practice should be maintained.  Mosquito control measures should be properly implemented to prevent mosquito breeding on site.