5-12-2014 |
---|
Item 1. Existing trees on boundary of the Project Area have been protected carefully during construction. |
5-12-2014 |
Item 4. Hydro-seeding provided at stockpile. |
5-12-2014 | |
Item 5. Hoarding around works area. | |
5-12-2014 | |
Item 7. Ensure no run-off into water body. |
12-12-2014 | |
Item 1. Existing trees on boundary of the Project Area have been protected carefully during construction. | |
12-12-2014 | |
Item 4. Hydro-seeding or sheeting provided at stockpile. |
12-12-2014 |
---|
Item 5. Hoarding around works area. |
12-12-2014 |
Item 7. Ensure no run-off into water body. |
19-12-2014 |
---|
Item 1. Existing trees on boundary of the Project Area have been protected carefully during construction. |
19-12-2014 |
Item 4. Sheeting of soil stockpile was provided. |
19-12-2014 | |
Item 5. Hoardings around works area. | |
19-12-2014 | |
Item 7. Ensure no run-off into water body. |
24-12-2014 |
---|
Item 1. Existing trees on boundary of the Project Area have been protected carefully during construction. |
24-12-2014 |
Item 4. Hydro-seeding or sheeting provided at stockpile. |
24-12-2014 |
---|
Item 5. Water Barrier with panel around works area. |
24-12-2014 |
Item 7. Ensure no run-off into water body. |