04-11-2016
Item 1. Existing trees on boundary of the Project Area should be protected carefully during construction.
04-11-2016
Item 4. Hydro-seeding or sheeting provided at stockpile.
04-11-2016
Item 5. Hoarding with panel around works area & Item 6. Temporary traffic management lighting.
04-11-2016
Item 7. Ensure no run-off into water body.
19-08-2016
Item 9. Recycle of felled trees as facilities to reuse.
11-11-2016
Item 1. Existing trees on boundary of the Project Area should be protected carefully during construction.
11-11-2016
Item 4. Hydro-seeding or sheeting provided at stockpile.
11-11-2016
Item 5. Hoarding with panel around works area & Item 6. Temporary traffic management lighting.
11-11-2016
Item 7. Ensure no run-off into water body.
19-08-2016
Item 9. Recycle of felled trees as facilities to reuse.
18-11-2016
Item 1. Existing trees on boundary of the Project Area should be protected carefully during construction.
18-11-2016
Item 4. Hydro-seeding or sheeting provided at stockpile.
18-11-2016
Item 5. Hoarding with panel around works area & Item 6. Temporary traffic management lighting.
18-11-2016
Item 7. Ensure no run-off into water body.
19-08-2016
Item 9. Recycle of felled trees as facilities to reuse.
25-11-2016
Item 1. Existing trees on boundary of the Project Area should be protected carefully during construction.
25-11-2016
Item 4. Hydro-seeding or sheeting provided at stockpile.
25-11-2016
Item 5. Hoarding with panel around works area & Item 6. Temporary traffic management lighting.
25-11-2016
Item 7. Ensure no run-off into water body.
19-08-2016
Item 9. Recycle of felled trees as facilities to reuse.