AUES Job No.: TCS00715/14

 

 

 

 

 

 

 

 

 

Tuen Mun - Chek Lap Kok Link

Contract No. HY/2013/12 ¡V

Northern Connection Toll Plaza and Associated Works

 

 

 

 

 

 

 

 

 

 

2nd Annual Environmental Monitoring and Audit (EM&A) Review Report ¡V November 2015 to October 2016

 

 

 

 

 

 

 

 

 

 

Prepared For

CRBC and Kaden Joint Venture

 

 

 

 

 

 

 

 

 

 

 

 

 

Date

Reference No.

Prepared By

Certified By

3 March 2017

TCS00715/14/600/R0261v3

Ben Tam

(Environmental

Consultant)

T.W. Tam

(Environmental Team

Leader)

 

 


 

 

 

 

 

 

 

 

 

EXECUTIVE SUMMARY

ES01       In August 2014, CRBC-Kaden Joint Venture (hereafter ¡§CRBC-Kaden JV¡¨) has been awarded the Contract No. HY/2013/12 -Northern Connection Toll Plaza and Tunnel Section of the Tuen Mun ¡V Chek Lap Kok Link (hereinafter called ¡§the Contract¡¨) by the Highways Department (HyD).  The construction phase of the Contract was commenced on 23 October 2014.

 

ES02       Before the Contract commencement, the baseline air quality monitoring was carried out by the ET of HY/2012/08 from 16th to 31st October 2013.  A set of Action and Limit Levels (A/L Levels) of air quality performance criteria was proposed by ET of HY/2012/08 which has been verified by IEC and endorsed by EPD.  The Action and Limit Levels of the air quality adopted for the Contract is shown in Table ES-01.

Table ES-01    Action and Limit Levels of Air Quality Monitoring

Monitoring Station

24-hour TSP, (mg /m3)

1-hour TSP, (mg/m3)

Action Level

Limit Level

Action Level

Limit Level

ASR1

213

260

331

500

ASR5

238

260

340

500

AQMS1

213

260

335

500

ASR6

238

260

338

500

ASR10

214

260

337

500

 

ES03       In September 2013, baseline survey for Pitcher Plant has been conducted within the project area by a suitably qualified ecologist.  In mid-September 2014, Contract HY/2013/12 has also conducted a one-off survey to confirm the number of existing Pitcher Plant.  For cultural heritage, a condition survey for the grave was conducted on 23 September 2014.  The Baseline Monitoring Report for the Contract was submitted on 7 October 2014 for IEC¡¦s verification and 25 November 2014 for EPD¡¦s endorsement.

 

ES04       This is the 2nd Annual EM&A Review Report for the ¡§Tuen Mun - Chek Lap Kok Link - Northern Connection Toll Plaza and Associated Works¡¨ under Environmental Permit No. EP-354/2009/D (hereinafter ¡¥¡¥the EP¡¦¡¦), covering the period from 1 November 2015 to 31 October 2016 (hereinafter ¡§Reporting Period¡¨).

 

Summary of EM&A activities for the Reporting Period

ES05       In the Reporting Period, the EM&A activities is summarized in Table ES-02.

Table ES-02     Summary EM&A Activities Undertaken in the Reporting Period

Environmental Aspect

Environmental Monitoring Parameters / Inspection

Sub-total Occasions

Total

1st Quarter

2nd Quarter

3rd Quarter

4th Quarter

Air Quality

1-hour TSP

465

435

465

435

1800

24-hour TSP

155

145

155

145

600

Cultural heritage inspection

Grave G1

13

13

13

13

52

Landfill Gas Monitoring

Oxygen; Methane & Carbon Dioxide

75 days

70 days

75 days

75 days

295 days

Landscape &Visual

Landscape & Visual Monitoring

13

13

13

13

52

Joint Site Inspection / Audit

IEC, ET, the Contractor and RE joint site Environmental Inspection and Auditing

13

13

13

13

52

 

Breach of Action and Limit (A/L) Levels

ES06       In according with the air quality measurement results by the ET of Contract HY/2012/08 in the Reporting Period, no exceedances in 24-hour and 1-hour TSP were recorded.

 

ES07       For landfill gas monitoring, the concentration of all parameters were detected within the acceptable levels.  Moreover, no noise complaint was received in the Reporting Period.  Table ES-03 is summarized breach of environmental performance criteria.

Table ES-03    Action and Limit (A/L) Levels Breach Summarized in the Reporting Period

Environmental Aspect

Monitoring Parameters

Action Level

Limit Level

Event & Action

NOE Issued

Investigation

Corrective Actions

Air Quality

1-hour TSP

0

0

0

0

0

24-hour TSP

0

0

0

0

0

Landfill Gas Monitoring

Oxygen

0

0

0

0

0

Methane

0

0

0

0

0

Carbon Dioxide

0

0

0

0

0

 

Environmental Complaint

ES08       In the First Quarter of Reporting Period, no environmental complaints were received by either the RE or ENPO or HyD or the Main Contractor.  However, one (1) environmental complaint which received the Second Quarter of Reporting Period on 28 April 2016 regarding to dust and smoke emission from a drilling rig was observed on the slope near Pillar Point, Tuen Mun. An also, two (2) environmental complaints which regarding to white color effluent discharging outfall behind sawmill at Ho Yeung Street, Tuen Mun, were received on 9 May and 7 July 2016 at the Third Quarter of Reporting Period. In the Fourth Quarter of Reporting period, one (1) environmental complaint which regarding to muddy water entering the drainage system near site entrance-Hand-key attendance system at Pillar Point, Tuen Mun at around 03:00 to 04:00 after the rainstorm, were received on 3 October 2016. The statistical of environmental complaint is listed in Table ES-04.

Table ES-04    Statistical Summary of Environmental Complaints

Reporting Period

Complaint Nature

Total Registered

Water Quality

Construction Dust

Construction Noise

1 November 2015 ¡V 31 October 2016

Ÿ  9 May 2016

Ÿ  7 July 2016

Ÿ  3 October 2016

Ÿ  28 April 2016

NA

4

 

ES09       Complaint investigation has conducted by the Contractor or ET and the corresponding investigation reports for the complaint have been submitted to relevant parties.  Based on investigation results, the contractor has enhanced the management to comply the Contract requirements.

 

Notification of Summons and Successful Prosecutions

ES10       No environmental summons or successful prosecutions were recorded in the Reporting Period.

 

Site Inspection

ES11       For past twelve months, total 52 occasions joint site inspection were carried out by the RE, IEC, ET and the Contractor.  For joint site inspections, no non-compliance was observed. However, 102 observations/reminders were recorded within the past twelve months.

 

ES12       During each occasion of site inspection, Pitcher Plants of ecology and grave of culture heritage were also to inspect and audit.

 

Future Key Issues

ES13       Construction dust emission would be a key environmental issue during construction work of the Contract at dry season.  Dust mitigation measures such as watering at least 12 times per day on all exposed soil within the Project site and associated work areas in Tuen Mun area throughout the construction period should be implemented in accordance with the EP requirement.

 

ES14       Muddy water or other water pollutants from sites surface flow to public area should properly avoided.  Water quality mitigation measures to prevent surface runoff to impact public areas should be fully implemented.

 

 

 

 


Table of Contents

1     Introduction                                                                                                                       1

1.1            Contract Background                                                                                    1

1.2            Report Structure                                                                                                1

2     Contract Organization and Construction progress and Environmental Submissions                                                                                                                            2

2.1            Contract Organization                                                                                   2

2.2            Construction Progress                                                                                    2

2.3            Summary of Environmental Submissions                                                 2

3     Summary of Impact Monitoring Requirements Under the Contract  4

3.1            General                                                                                                                   4

3.2            Air Quality Monitoring Parameters                                                          4

3.3            Monitoring Location                                                                                        4

3.4            Monitoring Frequency                                                                                     4

3.5            Derivation of Action/Limit (A/L) Levels                                                      5

3.6            Other Environmental Aspects                                                                      5

4     Air Quality Monitoring                                                                                                 8

4.1            General                                                                                                                   8

4.2            Air Quality Monitoring Results in Reporting Period                         8

4.3            Summary of Action and Limit (A/L) Levels Exceedance (non-compliance)         8

4.4            Air Quality Exceedance Investigation                                                     8

5     Ecology Monitoring                                                                                                       9

5.1            General                                                                                                                   9

5.2            Pitcher Plants Inspection                                                                               9

6     CULTURAL HERITAGE                                                                                                         10

6.1            General                                                                                                                 10

6.2            Grave Inspection                                                                                               10

7     LandscAPe and Visual                                                                                                    11

7.1            General                                                                                                                 11

7.2            Landscape and Visual Inspection                                                              11

8     Landfill Gas Hazard Monitoring                                                                           12

8.1            General                                                                                                                 12

8.2            Landfill Gas Monitoring Result                                                                12

9     Waste Management                                                                                                         14

9.1            General Waste Management                                                                        14

9.2            Records of Waste Quantities                                                                       14

10   Inspection and Auditing                                                                                               15

10.1          Site Inspection                                                                                                    15

11   Environmental Complaint and Non-compliance                                           16

11.1          Environmental Complaint, Summons and Prosecution                   16

11.2          Summary record of all complaints, action and working procedures 16

12   Implementation Status of Mitigation Measures                                            18

12.1          General Requirements                                                                                   18

13   Conclusions and Recommendations                                                                     19

13.1          Conclusions                                                                                                        19

13.2          Recommendations                                                                                             19

 


 

List of TABLES

Table 2-1      Status of Environmental Licenses and Permits of the Contract

Table 3-1      Designated Air Quality Monitoring Stations under the Contract

Table 3-2      Enhanced TSP Monitoring Plan ¡V Construction Phase

Table 3-3      TSP Action and Limit Levels for Impact Air Quality Monitoring

Table 3-4      Actions in the Event of Landfill Gas being Detected in Excavation / Confined Area

Table 4-1      Summary of Air Quality Monitoring Exceedance

Table 8-1      Landfill Gas Monitoring Zone

Table 8-2      Summary of Landfill Gas Measurement Results in this Annual for RW-B & RW-F

Table 8-3      Summary of Landfill Gas Measurement Results in this Annual for TD1 & LMR

Table 9-1      Summary of Quantities of Inert C&D Materials

Table 9-2      Summary of Quantities of C&D Wastes

Table 10-1    Summary of Reminders/Observations of Site Inspection for the Annual

Table 11-1    Statistical Summary of Environmental Exceedance

Table 11-2    Statistical Summary of Environmental Complaints

Table 11-3    Statistical Summary of Environmental Summons

Table 11-4    Statistical Summary of Environmental Prosecution

Table 12-1    Environmental Mitigation Measures

 

 

 

List of Appendices

Appendix A  Project Layout Plan

Appendix B Layout Plan of the Contract

Appendix C  Organization of the Contract

Appendix D Master Construction Program

Appendix E  Monitoring Locations for the Contract

Appendix F  Event and Action Plan

Appendix G Graphical Plots

Appendix H Investigation Report for Exceedance

Appendix I Environmental Mitigation Measures Implementation Schedule (EMMIS)

 

 

 



1                             Introduction

1.1                       Contract Background

1.1.1                 CRBC-Kaden Joint Venture (hereafter ¡§CRBC-Kaden JV¡¨) is commissioned by the Highways Department (HyD) as the Main Contractor of the Contract No. HY/2013/12 ¡V Northern Connection Toll Plaza and Tunnel Section ((hereafter ¡§the Contract¡¨) and this Contract is part of the Tuen Mun ¡V Chek Lap Kok Link (TM-CLK Link Project).  TM-CLK Link Project is a Designated Project under the latest Environmental Permit number VEP-354/2009D issued on 13 March 2015.  The layout Plan of the Project and the Contract are showed in Appendix A and Appendix B respectively.

 

1.1.2                 The works of the Contract mainly include:-

a.              construction of an approximately 5.4 hectares toll plaza and an associated footbridge;

b.             construction of associated carriageways including approximately 0.74 kilometre land viaducts, and an approximately 230 metres vehicular underpass to connect the toll plaza and the roundabout at Lung Mun Road/Lung Fu Road;

c.              site formation for the construction of the toll plaza, including associated slope works and natural terrain hazard mitigation measures;

d.             modification and realignment of the existing Lung Mun Road and Lung Fu Road; and

e.              associated waterworks, drainage, sewerage and landscaping works, etc..

 

1.1.3                 AECOM Asia Company Limited as the Resident Engineer (RE) and Ramboll Environ Hong Kong Limited as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) were employed by the HyD.  For implementation of the environmental monitoring and audit (EM&A) programme under the Contract, CRBC-Kaden JV has appointed Action-United Environmental Services & Consulting (AUES) as the Environmental Team (ET) to responsible relevant environmental monitoring work.

 

1.1.4                 Construction phase of the Contract was commenced on 23 October 2014.  This is the Secomd (2nd) Annual EM&A Review Report to summarize the monitoring results and inspection findings with the Contractor performance from 1 November 2015 to 31 October 2016 (hereinafter ¡§Reporting Period¡¨) for the past twelve months.

 

1.2                       Report Structure

1.2.1                 The Annual Environmental Monitoring and Audit (EM&A) Review Report is structured into the following sections:-

Section 1     Introduction

Section 2     Contract Organization and Construction Progress and Environmental Submissions

Section 3     Summary of Impact Monitoring Requirements under the Contract

Section 4     Air Quality Monitoring

Section 5     Ecology Monitoring

Section 6     Cultural Heritage

Section 7     Landscape and Visual

Section 8     Landfill gas hazard Monitoring

Section 9     Waste Management

Section 10   Inspection and Auditing

Section 11   Environmental Complaint and Non-Compliance

Section 12   Implementation Status of Mitigation Measures

Section 13   Conclusions and Recommendations


2                             Contract Organization and Construction progress and Environmental Submissions

2.1                       Contract Organization

2.1.1                 The Contract organization and contact details of key personnel are shown in Appendix C.

 

2.2                       Construction Progress

2.2.1                 In the Reporting Period, the major construction activity conducted under the Contract is summarized in below.  Moreover, the master construction program of the Contract is enclosed in Appendix D.

Ÿ   Instrumentation and Monitoring

Ÿ   Site Formation ¡V Retaining Structure for RW_A, Slope TP_F, TP_G, TP_A and Associated Works, TP_B and Associated Works, TP_C and Associated Works, TP_D and Associated Works, TP_E and Associated Works and Slope Upgrading Works

Ÿ   Site Formation ¡V Earthwork on Slope D and E; surface drainage on slope C, D & E and Portion H

Ÿ   Toll Plaza Decking TD1, TD2

Ÿ   Toll Plaza Footbridge

Ÿ   Retaining Structure RW_B, RW_F, RW_F and Slope TP_F¡¨

Ÿ   Bridge G1, G2,Bridge H1

Ÿ   Toll Collector Subway & Associated Works ¡V Section 1

Ÿ   Sewer Culvert 1 (TBM) ¡V Stage 4, Culvert 2 & Culvert 3

Ÿ   Natural Terrain Hazard Mitigation Measures

Ÿ   Vehicular Underpass TN-01

Ÿ   Blasting and Excavation of Underpass from East Portal

Ÿ   Road and Drainage Works for Lung Fu Road Roundabout

Ÿ   Sewer Culvert at FC1 and FC2, and the existing Box Culvert

Ÿ   Road and Drainage Works at Butterfly Bay, +11mPD, +19mPD and Portion H

Ÿ   Construction of Bored pile at central median

Ÿ   Box-culvert construction near MH2

Ÿ   Sewer culvert by hand shield method at FC1, FC2, MH6, MH3 and MH7

Ÿ   Cascade A construction

Ÿ   Portal beam formwork erection at Lung Mun Road Central medium

Ÿ   Concreting for portal beam at Lung Mun Road Central medium

Ÿ   Precast Beam installation at Lung Mun Road

Ÿ   Precast Panel Installation at RW_B & TD 1

Ÿ   Fabrication of form traveler at fire station

Ÿ   Assembly of Form Traveller at Bridge H1E and load test.

Ÿ   Stitching of TD1 decking

Ÿ   Waterproofing and lining at Vehicular Underpass

Ÿ   Construction of Retaining Wall A and B

Ÿ   Blast door installation at West Portal

 

2.3                       Summary of Environmental Submissions

2.3.1                 In according to the EP, the required documents have submitted to EPD for retention which listed in below:

Ÿ   Monitoring Plan on construction dust (submission refer to Contract HY/2012/08)

Ÿ   Landscape and Visual Plan (not yet endorsed by EPD)

Ÿ   Waste Management Plan (endorsed by the EPD on 16 March 2015)

Ÿ   Baseline Monitoring Report (not yet endorsed by EPD)

 

2.3.2                 Summary of the relevant permits, licenses, and/or notifications on environmental protection as obtained by the Contract in the past twelve months is presented in Table 2-1.

Table 2-1      Status of Environmental Licenses and Permits of the Contract

No.

Type of Permit/ License

Submission Date

Reference/

License No.

Date of Issue

Date of Expiry

1

Air pollution Control (Construction Dust) Regulation

06-08-2014

377719

06-08-2014

N/A

2

Chemical Waste Producer Registration - Waste Producers Number

06-08-2014

5117422C389301

03-09-2014

N/A

3

Water Pollution Control Ordinance - Discharge License

13-08-2014

WT00020065-2014

29-09-2014

30-09-2019

4

Variation of Effluent Discharge License

22-08-15

WT00023973-2016

14-03-16

30-09-2019

5

Waste Disposal Regulation - Billing Account for Disposal of Construction Waste

21-07-2014

7020460

01-08-2014

N/A

6

Permission to Transplant Pitcher Plant

15-6-2015

(30) in AF CON 11/13 pt.4

23-6-2015

22-12-2015

7

CNP for Multiple Task

24-04-2015

GW-RW0225-15

13-05-2015

04-11-2015

7-10-2015

GW-RW0520-15

05-11-2015

04-05-2016

21-04-2016

GW-RW0520-16

05-05-2016

04-11-2016

8

CNP for MH5

05-05-2015

GW-RW0226-15

18-05-2015

17-11-2015

23-10-2015

GW-RW0563-15

18-11-2015

17-05-2016

25-04-2016

GW-RW0563-16

18-05-2016

17-11-2016

9

CNP for Tunnel

13-11-2015

 GW-RW0582-15

23-11-2015

22-05-2016

25-04-2016

 GW-RW0582-16

23-05-2016

22-11-2016

10

CNP for falsework erection

01-02-2016

 GW-RW0076-16

15-02-2016

21-04-2016

07-04-2016

GW-RW0215-16

26-04-2016

21-06-2016

18-05-2016

GW-RW0289-16

22-06-2016

19-08-2016

27-07-2016

GW-RW0472-16

22-08-2016

21-12-2016

                      Note: CNP is Control Noise Permit

 

 

 

 


3                             Summary of Impact Monitoring Requirements Under the Contract

3.1                       General

3.1.1                 In view of the construction works under the Contract, the major construction activities are land-based.  In accordance with the Project EM&A Manual requirements, environmental aspect monitoring should be conducted including air quality, ecological (Pitcher plant), cultural heritage and site inspections during construction period.  In addition, landscape and visual (L&V) monitoring, landfill gas monitoring and audit of the contractor¡¦s implementation of the construction noise and land-based water quality pollution control measures are also required for the Contract.

 

3.1.2                 A summary of construction phase EM&A requirements are presented in the sub-sections below.

 

3.2                       Air Quality Monitoring Parameters

3.2.1                 The construction phase air quality monitoring shall cover the following parameters:

                     1-hour TSP; and

                     24-hour TSP

 

3.3                       Monitoring Location

3.3.1                 The air quality monitoring stations for impact monitoring are listed in Table 3.1 and illustrated in Appendix E.

Table 3-1      Designated Air Quality Monitoring Stations under the Contract

ID

Location

Air monitoring station Description

ASR1

Tuen Mun Fireboat Station

EM&A Manual

ASR5

Pillar Point Fire Station

EM&A Manual

AQMS1

Previous River Trade Golf

Enhanced TSP Level under EP condition 2.4

ASR6

Butterfly Beach Laundry

Enhanced TSP Level under EP condition 2.4

ASR10

Butterfly Beach Park

Enhanced TSP Level under EP condition 2.4

 

3.4                       Monitoring Frequency

General Requirement

3.4.1                 For regular impact monitoring, the sampling frequency of at least once in every six days shall be strictly observed at five of the designated monitoring stations for 24-hr TSP monitoring.  For 1-hr TSP monitoring, the sampling frequency of at least three times in every six days should be undertaken at five locations when the highest dust impact occurs.  The stations to be monitored should be selected based on the prevailing wind direction and their proximity to the active construction works.

 

Special Requirement

3.4.2                 As per Condition 2.4 of the EP of TM-CLKL, an enhanced monitoring plan on TSP level at Tuen Mun (¡§the Enhanced TSP Monitoring Plan¡¨) is required to be submitted to the DEP for approval at least 1 month before the commencement of construction of the Project.  Details of the Enhanced TSP Monitoring Plan under Contract No. HY/2012/08 could be found from the project website.  The air quality monitoring work under this Contract will follow the monitoring requirement of enhanced TSP monitoring under the project.

 

3.4.3                 The air quality monitoring requirements for the Contract is shown in Table 3-2.


Table 3-2  Enhanced TSP Monitoring Plan ¡V Construction Phase

Condition

Monitoring Parameter

Monitoring Location

Frequency

Monitoring Requirement

General

1-hour TSP

ASR1, ASR5, AQMS1, ASR6, ASR10

3 times per day every six days

Throughout the Northern Connection, toll plaza and tunnel buildings construction works

24-hour TSP

ASR1, ASR5, AQMS1, ASR6, ASR10

Daily every six days

Special

1-hour TSP

ASR1, ASR5, AQMS1, ASR6, ASR10

3 times per day every three days

Northern Connection

During excavation works for launching shaft, excavation work for Cut and Cover Tunnel and Cut and Cover Tunnel Construction

Toll Plaza

During excavation, slope works, construction of road and superstructures and wind erosion from open sites and stockpiling areas

Tunnel Buildings

During excavation, foundation works, construction of superstructures and wind erosion from open sites and stockpiling areas

24-hour TSP

ASR1, ASR5, AQMS1, ASR6, ASR10

Daily every three days

 

3.5                       Derivation of Action/Limit (A/L) Levels

3.5.1                 The baseline monitoring results formed the basis for determining the air quality criteria for the impact monitoring. The ET shall compare the impact monitoring results with air quality criteria set up for 24-hour TSP and 1-hour TSP.  Based on results of the approved Baseline Monitoring Report of HyD Contract HY/2012/08, the proposed Action and Limit Levels are shown in Tables 3-3.

Table 3-3      TSP Action and Limit Levels for Impact Air Quality Monitoring

Air Quality Monitoring Stations

24-hour TSP (£gg/m3)

1-hour TSP (£gg/m3)

Action Level

Limit Level

Action Level

Limit Level

ASR1

213

260

331

500

ASR5

238

260

340

500

AQMS1

213

260

335

500

ASR6

238

260

338

500

ASR10

214

260

337

500

 

3.5.2                 Should non-compliance of the environmental quality criteria occurs, remedial actions will be triggered according to the Event and Action Plan which presented in Appendix F.

 

3.6                       Other Environmental Aspects

Noise

3.6.1                 The TM-CLKL EIA study concluded that no existing noise sensitive receiver (NSR) was identified within the Study Area at Tuen Mun.  Therefore, no planned NSR designated at the Project sites of Tuen Mun.  Based upon this, no noise monitoring is necessary for construction phase under the Contract.

 

3.6.2                 Regular site inspections and audits will be carried out during the construction phase in order to confirm compliance with the regulatory requirements and conformity of the Contractor with regard to noise control and contract conditions.

 

Water Quality

3.6.3                 No marine works will be undertaken under the Contract.  Based upon this, no water quality monitoring is necessary for construction phase.

 

Ecology

3.6.4                 Since the Works of the Contract would not be to generate the marine ecological impact, no dolphin monitoring under the Contract to conduct.

 

3.6.5                 During construction phase, the ET will perform Pitcher Plants inspection at least once every week to report the growth condition (only undertaken at Establish period) and protection measures.

 

Landscape and Visual

3.6.6                 According to EIA recommendation, site inspection and audit shall be required to be undertaken in the operation stage. Measures to mitigate landscape and visual impacts during construction should be checked and monitored by a Registered Landscape Architect to ensure compliance with the intended aims of the mitigation measures in accordance with the EM&A Manual.

 

Cultural Heritage

3.6.7                 Grave G1 of heritage resources is situated near the proposed toll plaza in Tuen Mun.  Site inspections should be undertaken at least once per week throughout the construction period to ensure compliance with the intended aims of recommended mitigation measures.

 

Monitoring and Measurement of Landfill Gas

3.6.8                 During EIA study, landfill gas hazards are likely to be generated from the Pillar Point Valley (PPV) Landfill. Hence, regular landfill gas monitoring is recommended during construction of the proposed toll plaza.  Safety Officer or an approved and appropriated qualified person should be carried out the monitoring works to make sure the area free of landfill gas before any man enters in the area.

 

3.6.9                 Depending on the results of the measurements, actions required will vary and should be set down by the Safety Officer or other appropriately qualified person. As a minimum these should encompass those actions specified as follow:

Table 3-4      Actions in the Event of Landfill Gas being Detected in Excavation / Confined Area

Parameter

Measurement

Action

Oxygen

< 19%

- Ventilate to restore oxygen to > 19%

< 18%

- Stop work

- Evacuate personnel / prohibit entry

- Increase ventilation to restore to > 19%

Methane

> 10% LEL (> 0.5% v/v)

- Prohibit hot work

- Ventilate to restore methane to < 10% LEL

> 20% LEL (>1% v/v)

- Stop work

- Evacuate personnel / prohibit entry

- Increase ventilation to restore to < 10%

Carbon Dioxide

> 0.5%

- Ventilate to restore oxygen to < 0.5%

> 1.5%

- Stop work

- Evacuate personnel / prohibit entry

- Increase ventilation to restore to < 0.5%


 

4                             Air Quality Monitoring

4.1                       General

4.1.1                 According to the Updated EM&A Manual and the Enhanced Total Suspended Particulates (TSP) Monitoring Plan, the air quality impact monitoring was conducted at the five air quality monitoring stations during the Reporting Period by the ET of Contract HY/2012/08.  Sharing of impact air quality monitoring data between HY/2012/08 and HY/2013/12 is agreed by all relevant parties.  Therefore the Contract is not required to conduct its own dust monitoring exercise until the Contract HY/2012/08 is ended.

 

4.2                       Air Quality Monitoring Results in Reporting Period

4.2.1                 In the Reporting Period, total 1,800 of 1-hr TSP measurements and 600 events of 24-hours TSP monitoring at five proposed locations were carried out by the ET of Contract HY/2012/08.  Detailed air quality monitoring results and statistical analysis of the trends of air quality data during the Reporting Period can be referred to the Monthly EM&A Reports (from November 2015 to October 2016) and the Third Annual EM&A Review Report (November 2015 to October 2016) prepared by the ET of Contract HY/2012/08.

 

4.3                       Summary of Action and Limit (A/L) Levels Exceedance (non-compliance)

4.3.1                 According to the air quality monitoring result provided by Contract HY/2012/08, no exceedances in 1-hour and 24-hour TSP were recorded in the Reporting Period.  No Notification on Exceedances (NOEs) was issued by the ET of Contract HY/2012/08.  The summary of air quality exceedance is shown in Table 4-1.

Table 4-1      Summary of Air Quality Monitoring Exceedance

Date of Exceedance

Monitoring Station

Air Quality Parameter

Result

Exceed

NA

NA

NA

--

--

 

4.4                       Air Quality Exceedance Investigation

4.4.1                 No investigation for exceedance is required for the Reporting Period.

 

 


 

5                             Ecology Monitoring

5.1                       General

5.1.1                 According to the EM&A Manual requirements, regularly inspection for Pitcher Plants at least once every week to report it growth and protection measure situation shall be conducted during construction period.

 

5.1.2                 Total 181 pitcher plants were transplanted to final receptor site and the rest of the Pitcher Plant individuals (certified dead by the specialist) were not transplanted and were treated as general refuse. All the transplantation of pitcher plant from the nursery site to final receptor site was completed on 10th September 2015.

 

5.2                       Pitcher Plants Inspection

5.2.1                 A total 52 occasions of inspection were carried out by the Contractor and ET in the past twelve months.

 

5.2.2                 During each inspection, the transplanted pitcher plant was performed random checking at the final receptor area.  It was observed that the transplanted pitcher plants were properly protected and the growth was normally in fair condition except three individuals which appeared poor condition in May 2016 were certified dead by the specialist.  It is considered that the Pitcher Plant were establishing after transplanting shock and adapting to the condition of the Final Receptor Site and frequent watering is recommended. Besides, no construction activities were observed to be carried out at the surrounding of the final receptor area.  The condition of chain link fence is good and no repair or maintenance is required.

 

5.2.3                 Establish period for the pitcher plants was completed at the end of September 2016, therefore the join site completion of establish period visit with AFCD was undertaken on 23 September 2016 and the advance copy of final pitcher report was submitted to AFCD on 11 November 2016. Therefore after 23 September 2016, only the integrity of the protection fence was checked to fulfil the EIA requirement.

 

5.2.4                 No matters the completion of establish period, the Contractor should properly maintain the fencing along the receptor area to avoid disturbance to the pitcher plants under the EIA requirement.

 

 


 

6                             CULTURAL HERITAGE

6.1                       General

6.1.1                 According to the EM&A Manual requirements, regular inspection for heritage resource Grave G1 shall be audited by the ET at least once every week to ensure recommended mitigation measures implemented during construction period.  The aim of the survey is prevention of any possible damage to the grave and to ensure that proposed mitigation measures are implemented. The broad scope of the audit will involve supervision of the following:

 

Ÿ   Non-contact effects of the engineering works, such as vibration from pneumatic drills which could cause damage, such as foundation or wall cracks and loosening of tiles or fixtures; and

Ÿ   Contact between the historic structures and equipment and materials associated with the engineering works.

 

6.1.2                 Specifically, the monitoring programme will entail the following tasks:

 

Ÿ   The extent of the agreed works areas should be regularly checked during the construction phase to ensure the buffer is being maintained; and

Ÿ   Ensure no stockpiling or equipment storage is affecting the structure.

 

6.1.3                 In the event of non-compliance the responsibilities of the relevant parties is detailed in the Event/ Action Plan in Appendix F.

 

6.2                       Grave Inspection

6.2.1                 In this Reporting Period, there are total 52 occasions to carry out the Grave G1 inspection.  During site inspection, buffer zone was observed between the working area and the Grave and no construction material or equipment was stored nearby the Grave.

 

6.2.2                 Mitigation measures had been fully implemented by the Contractor in accordance with the requirements of the EM&A Manual.

 


 

7                             LandscAPe and Visual

7.1                       General

7.1.1                 According to EM&A Manual requirements, monitoring of Contractor¡¦s operations during construction period to report on Contractor¡¦s compliance should be carried out on weekly basis.  Measure to mitigate landscape and visual impact during construction should be checked and monitored by a Registered Landscape Architect to ensure compliance with the intended aims of the mitigation measures.  Moreover, the progress of the engineering works shall be regularly reviewed on site to identify the earliest practical opportunities for the landscape works to be undertaken.

 

7.2                       Landscape and Visual Inspection

7.2.1                 In this Reporting Period, Registered Landscape Architect with the Contractor had undertaken a total of 52 occasions of inspection.  

 

7.2.2                 In the past twelve months, most of the landscape work such as planting was not yet commenced, existing tree on boundary of the project area was properly protected and no damage of the existing tree was record in this reporting period. Felled tree under construction was collected by license collected for recycling.  The detailed inspection checklists can be referred to relevant Monthly EM&A Reports of the Contract.

 

 

 

 


 

8                             Landfill Gas Hazard Monitoring

8.1                       General

8.1.1                 During EIA study, landfill gas hazards are likely to be generated from the Pillar Point Valley (PPV) Landfill. Hence, regular landfill gas monitoring is recommended during construction of the proposed toll plaza.

 

8.1.2                 During construction, a Safety Officer should be appointed to carry out the monitoring works. The monitoring frequency and areas to be monitored should be set down prior to commencement of ground-works either by the Safety Officer or an approved and appropriated qualified person. The routine monitoring should be carried out in all excavations, manholes, chambers, relocation of monitoring wells and any other confined spaces that may have been created. All measurements in excavations should be made with the extended monitoring tube located not more than 10 mm from the exposed ground surface. Monitoring should be performed properly to make sure that the area is free of landfill gas before any man enters in the area.

 

8.1.3                 For excavations deeper than 1m, measurements should be carried out:

Ÿ   at the ground surface before excavation commences;

Ÿ   immediately before any worker enters the excavation;

Ÿ   at the beginning of each working day for the entire period the excavation remains open; and

Ÿ   periodically through the working day whilst workers are in the excavation.

 

8.1.4                 For excavations between 300mm and 1m deep, measurements should be carried out:

Ÿ   directly after the excavation has been completed; and

Ÿ   periodically whilst the excavation remains open

 

8.1.5                 For excavations less than 300mm deep, monitoring may be omitted, at the discretion of the Safety Officer or other appropriately qualified person.

 

8.1.6                 To ensure the accuracy of the monitoring data, zeroing of the gas analyser shall be undertaken at the start of each day¡¦s monitoring.  As part of the QA/QC, calibration of the gas analyser shall be conducted at least once every two weeks according to the specification of the manufacturer¡¦s operation manual.

 

8.1.7                 The landfill consultation zone was divided into 6 monitoring zones. The landfill gas monitoring zones are summarized in Table 8-1 and the layout plan for the monitoring zone is illustrated in Appendix E.

Table 8-1      Landfill Gas Monitoring Zone

ID

Location

TD1

TD1, Retaining Wall A and Subway

RW-B

Retaining Wall B

RW-F

Retaining Wall F

S&U

Slope and Underpass

BW

Bridge Works

LMR

Lung Mun Road

 

8.2                       Landfill Gas Monitoring Result

8.2.1                 In the past twelve months, landfill gas monitoring was conducted at monitoring zone RW-B & RW-F between November 2015 and September 2016. For October 2016 landfill gas monitoring was conducted at the zone TD1 and LMR due to the excavated area have been backfilled at the end of September 2016 for zone RW-B & RW-F. A BIOGAS 5000 gas analyser was used for the landfill gas monitoring.

 

8.2.2                 There were total 295 monitoring days carried out by the Safety Officer or an approved and qualified persons.  Landfill gas measurement results in the past twelve months are summarized in Table 8-2 & 8-3.  Moreover, graphical plot are attached in Appendix G.

Table 8-2      Summary of Landfill Gas Measurement Results in this Annual for RW-B & RW-F

Para.

Action Level

Limit Level

In Period

Detectable at Retaining Wall B

Detectable at Retaining Wall F

Min

Max

Min

Max

Methane

>10% LEL (>0.5% v/v)

>20% LEL (>1% v/v)

Nov 2015 to Jan 2016

0%

0.1%

0%

0.1%

Feb 2016 to Apr 2016

0%

0.2%

0%

0.1%

May 2016 to Jul 2016

0%

0.1%

0%

0.1%

Aug 2016 to Sep 2016

0.0%

0.2%

0.0%

0.2%

Oxygen

<19%

<18%

Nov 2015 to Jan 2016

21.0%

21.2%

21.0%

21.2%

Feb 2016 to Apr 2016

21.0%

21.1%

21.0%

21.1%

May 2016 to Jul 2016

21.0%

21.2%

21.0%

21.1%

Aug 2016 to Sep 2016

21.0%

21.1%

21.0%

21.1%

Carbon Dioxide

>0.5%

>1.5%

Nov 2015 to Jan 2016

0%

0.2%

0%

0.2%

Feb 2016 to Apr 2016

0.1%

0.2%

0.1%

0.2%

May 2016 to Jul 2016

0.1%

0.2%

0.1%

0.2%

Aug 2016 to Sep 2016

0.1%

0.2%

0.1%

0.2%

 

Table 8-3    Summary of Landfill Gas Measurement Results in this Annual for TD1 & LMR

Para.

Action Level

Limit Level

In Period

Detectable at Retaining Wall B

Detectable at Retaining Wall F

Min

Max

Min

Max

Methane

>10% LEL (>0.5% v/v)

>20% LEL (>1% v/v)

Oct 2016

0.1%

0.1%

0.1%

0.1%

Oxygen

<19%

<18%

Oct 2016

21.0%

21.1%

21.0%

21.1%

Carbon Dioxide

>0.5%

>1.5%

Oct 2016

0.1%

0.2%

0.1%

0.2%

 

8.2.3                 The measurement results shown that slightly methane concentration was detected and all oxygen concentration was measured between 21.0% and 21.2% and Carbon Dioxide was between 0 and 0.2 %.  No corrective action was required accordingly.

 


 

9                             Waste Management

9.1                       General Waste Management

9.1.1                 Waste management was carried out by an on-site Environmental Officer or an Environmental Supervisor from time to time. The effective management of waste arisings during the construction phase will be monitored through the site audit programme. The aims of the waste audit are:

l  to ensure the waste arising from the works are handled, stored, collected, transferred and disposed of in an environmentally acceptable manner; and

l  to encourage the reuse and recycling of material.

 

9.1.2                 In addition to the site inspections, the ET shall review the documentation procedures prepared by the Waste Coordinator once a week to ensure proper records are being maintained and procedures undertaken in accordance with the Waste Management Plan.

 

9.2                       Records of Waste Quantities

9.2.1                 All types of waste arising from the construction work are classified into the following:

l  Construction & Demolition (C&D) Material;

l  Chemical Waste;

l  General Refuse; and

l  Excavated Soil.

 

9.2.2                 In the past twelve months, total quantities of waste disposal are summarized in Tables 9-1 and 9-2.

Table 9-1      Summary of Quantities of Inert C&D Materials

Type of Waste

Quantity

Total

Disposal Location

Nov 2015 ¡V Jan 2016

Feb 2016 ¡V Apr 2016

May 2016 ¡V Jul 2016

Aug 2016 ¡V Oct 2016

Reused in this Contract (Inert) (`000m3)

35.186

39.413

31.747

15.353

121.699

-

Reused in other Projects (Inert) (`000m3)

73.010

17.086

8.727

26.678

125.501

    TM-CLKL C2 HY/2012/08

    Lam Tei Quarry

    Eco Park K.wah Recycle Facilities

    Lung Kwu Tan Tailor Recycled Aggregates

    Laintang BCP

Disposal as Public Fill (Inert) (`000m3)

3.989

1.603

1.539

0.487

7.618

Tuen Mum Area 38

 

Table 9-2      Summary of Quantities of C&D Wastes

Type of Waste

Quantity

Total

Disposal Location

Nov 2015 ¡V Jan 2016

Feb 2016 ¡V Apr 2016

May 2016 ¡V Jul 2016

Aug 2016 ¡V Oct 2016

Recycled Metal (`000kg)

0

0

0

0

0

-

Recycled Paper / Cardboard Packing (`000kg)

0.07

0

0

0

0.07

Recycle Collector

Recycled Plastic (`000kg)

0

0

0

0

0

-

Chemical Wastes (`000kg)

0

0

0

0

0

-

General Refuses (`000m3)

0.257

0.309

0.283

0.401

1.250

WENT

 

9.2.3                 Whenever possible, materials were reused on-site as far as practicable.

 

 

 

10                         Inspection and Auditing

10.1                   Site Inspection

10.1.1             According to the approved EM&A Manual, the environmental site inspection shall be formulation by ET Leader.  Weekly environmental site inspections should carry out to confirm the environmental performance.

 

Findings / Deficiencies During Reporting Period

10.1.2             In the past twelve months, total 52 events of joint site inspection to evaluate site environmental performance has been carried out by the RE, ET and the Contractor.  Moreover, IEC or ENPO attended total 12 occasion¡¦s joint site inspection.  The quantity of reminders/observations is summarized in Table 10-1.

Table 10-1         Summary of Reminders/Observations of Site Inspection for the Annual

Reporting Period

Date of site inspection

Nos. of findings / reminders

Follow-Up Status

November 2015

3rd, 10th, 17th and 24th November 2015

9

Completed

December 2015

1st, 8th, 15th, 22nd and 29th December 2015.

14

Completed

January 2016

5th, 12th, 19th and 26th January 2016

8

Completed

February 2016

2nd, 12th, 16th and 23rd February 2016

5

Completed

March 2016

1st, 8th, 15th, 22nd and 29th March 2016.

12

Completed

April 2016

6th, 12th, 19th and 26th April 2016

3

Completed

May 2016

3rd, 10th, 17th, 24th and 31st May 2016

7

Completed

June 2016

8th, 15th, 21st and 28th June 2016

6

Completed

July 2016

6th, 12th, 20th and 26th July 2016

6

Completed

August 2016

3rd, 9th, 16th, 23rd and 30th August 2016

11

Completed

September 2016

6th, 13th, 21st and 27th September 2016

8

Completed

October 2016

4th, 12th, 18th and 25th October 2016

13

Completed

 

10.1.3             In the past twelve months, there are no non-compliance recorded, however, 102 observations/ reminders were recorded during the site inspections.  The minor deficiencies found in the weekly site inspections were in general rectified within the specified deadlines.  The environmental performance of the Project was therefore considered satisfactory.

 

 

 

 

 


11                         Environmental Complaint and Non-compliance

11.1                   Environmental Complaint, Summons and Prosecution

11.1.1             For the Contract, no summons and prosecution was received in the Reporting Period.  However, there are four environmental complaints and no exceedances of action / limit levels recorded during the Reporting Period.  The statistical summary table of environmental exceedance, complaint, summons and prosecution is presented in Tables 11-1, 11-2, 11-3 and 11-4.

Table 11-1    Statistical Summary of Environmental Exceedance

Reporting Period

Environmental Aspect

Exceedance Statistics

Action

Limit

1 November 2015 ¡V

31 October 2016

Air Quality

1-hour TSP

0

0

24-hour TSP

0

0

Landfill Gas

Methane

0

0

Oxygen

0

0

Carbon Dioxide

0

0

Table 11-2    Statistical Summary of Environmental Complaints

Reporting Period

Environmental Complaint Statistics

Cumulative

Complaint Nature

Air

Noise

Water

1 November 2015 ¡V

31 October 2016

4

Ÿ  28 April 2016

NA

Ÿ  9 May 2016

Ÿ  7 July 2016

Ÿ  3 October 2016

 

Table 11-3    Statistical Summary of Environmental Summons

Reporting Period

Environmental Summons Statistics

Cumulative

Complaint Nature

Air

Noise

Water

1 November 2015 ¡V

31 October 2016

0

NA

NA

NA

 

Table 11-4    Statistical Summary of Environmental Prosecution

Reporting Period

Environmental Prosecution Statistics

Cumulative

Complaint Nature

Air

Noise

Water

1 November 2015 ¡V

31 October 2016

0

NA

NA

NA

 

11.2                   Summary record of all complaints, action and working procedures

11.2.1             During the complaint investigation work, the Contractor was co-operated with the ET in providing all the necessary information and assistance for completion of the investigation. Investigation reports for the complaints have completed by the ET and submitted to all relevant parties and they are summarized in below.

Ÿ   28 April 2016 - A complaint was received from the EPD on 28 April 2016.  The complainant complained that dust and smoke emission from a drilling rig was observed on the slope near Pillar Point, Tuen Mun.  It was suspected that the heavy dust was generated from the construction activities under the Contractor.

 

Ÿ   9 May 2016 - A complaint was received from the EPD on 9 May 2016.  The complainant complained that white color effluent discharging outfall behind sawmill at Ho Yeung Street, Tuen Mun.  It cannot confirm the source of the white color effluent therefore it considered that the above complaint is not related to the project.

 

Ÿ   7 June 2016 - A complaint was received from the EPD on 7 June 2016.  The complainant complained that white color effluent discharging outfall at storm outfall of No.33 Ho Yeung Street, Tuen Mun at around 18:00 and this is a follow up of the complaint EP/RW/0000368066 which received on 9 May 2016 and defecated as not project related complain. EPD visit the upstream area and open the cover of manhole at Ho Fuk Street on 21 June 2016. No water discharge was observed and the manhole was clean and dry in condition. During the joint investigation and inspection by EPD, Aecom and the Contractor, it was found that the white water might came from other facilities or site located at Ho Yeung Street which is not related to this project.

 

Ÿ   3 October 2016 - A complaint was received via EPD hotline on 3 October 2016, claimed that muddy water entering the drainage system near site entrance-Hand-key attendance system Pillar Point, Tuen Mun at around 03:00 to 04:00 after the rainstorm. Refer to tele-conversation with EPD and Contractor, the complaint was actually mentioning the muddy water entering the drainage system was occurred on 1 October 2016 03:00 to 04:00 at the bus station nearby the site entrance. According to the site record, the works carried out during the concerned time period was maintenance works of TTA include maintenances of flashlight, water barrier and road marking, there is no ponding water was observed nearby the concerned locations. Also during the weekly site inspection on 4 October 2016, no water discharged from site and ponding at the bus station nearby the site entrance was observed. Earth bund was also provided at the slope near the site entrance to divert the surface run-off to the de-silting system. Moreover, the record from the Hong Kong Observatory also stated there was no rainfall recorded at Tuen Mun between 30 September 2016 and 1 October 2016 04:45 a.m. Therefore for the above result, it is considered that the above complaint is not related to the project.

 

Inspection Checklist for Vulnerable to Contaminated Water Discharge

11.2.2             Following to the complaint about discharge of milky water to Bufferfuly Beach on 2 September 2015. The Contractor proposed to carry out daily inspection of wastewater treatment facilities, concerned discharge points, drainage inlets and outlets during typhoon or wet season. 

 

11.2.3             In addition, specific inspections would also be conducted before and after adverse weather to ensure necessary remedial works would be carried out timely. Should incidental contaminated water discharge be found at the inlet of the associated drainage system, a specific inspection of the relevant drainage pipes would be conducted for traces of deposit, and follow up actions would be taken when necessary.

 

11.2.4             The daily inpsection for vulnerable to contaminated water discharge was conducted by the Contractor between 1 to 30 November 2015 and 11 April to 31 October 2016 . As requested by the EPD, the associated inspection checklist should be presented in the respective Monthly EM&A Report.

 


 

12                         Implementation Status of Mitigation Measures

12.1                   General Requirements

12.1.1             The environmental mitigation measures that recommended in the Environmental Mitigation Measures Implementation Schedule (EMMIS) in the Project EM&A Manual covered the issues of Air Quality, Cultural Heritage, Ecology, Landfill Gas Hazard, Landscape & Visual, Noise, Water and Waste and they are presented in Appendix I.

 

12.1.2             In the past twelve months, environmental mitigation measures generally implemented by the Contract are listed in Table 12-1.

Table 12-1    Environmental Mitigation Measures

Issues

Environmental Mitigation Measures

Air Quality

¡P       Maintain damp / wet surface on access road

¡P       Keep slow speed in the sites

¡P       All vehicles must use wheel washing facility before off site

¡P       Sprayed water during rock breaking works

¡P       During transportation by truck, materials loaded lower than the side and tail boards, and covered before transport

¡P       Compacted all soil stockpiles

¡P       Part of the exposed slopes covered geotextile net

Cultural Heritage

¡P       Set a buffer zone between the working area and the Grave

¡P       All construction materials and equipment store far from the Grave

¡P       Inspection the Grave to ensure provision mitigation measures effective

Ecology

¡P       Wire fencing provided for temporary protect Pitcher Plants

¡P       Undertake weekly inspection of Pitcher Plants

Landfill Gas Hazard

¡P       Landfill Gas measurement undertake during trench excavation

Water Quality

¡P       Temporary drainage system provide for surface runoff prevent discharge to public area

¡P       Wastewater to be treated by sedimentation tank before discharge.

Noise

¡P       Restrain operation time of plants from 07:00 to 19:00 on any working day except for Public Holiday and Sunday.

¡P       Keep good maintenance of plants

¡P       The noisy plants or works provide mobile noise barriers

¡P       Shut down the plants when not in used

Waste and Chemical Management

¡P       On-site sorting prior to disposal

¡P       Follow requirements and procedures of the ¡§Trip-ticket System¡¨

¡P       Predict required quantity of concrete accurately

¡P       Collect the unused fresh concrete at designated locations in the sites for subsequent disposal

General

¡P       The site was generally kept tidy and clean.

 

 


13                         Conclusions and Recommendations

13.1                   Conclusions

13.1.1             This is 2nd Annual EM&A Review Report presenting the monitoring results and inspection findings for the Reporting Period from 1 November 2015 to 31 October 2016.

 

13.1.2             No air quality monitoring including 1-hour and 24-hour TSP exceedance was recorded in the Reporting Period.

 

13.1.3             In this Reporting Period, no noise complaint was received by RE, the Contractor, ENPO or HyD.  No Action Level exceedances were triggered and no NOE or the associated corrective actions were therefore issued.

 

13.1.4             Site inspection for landscape and visual was conducted on weekly basis by the Landscape Architect to ensure the compliance of the intended aims of the mitigation measures. Most of the landscape works such as planting was not yet commenced.

 

13.1.5             Landfill gas monitoring was conducted at RW-B & RW-F between November 2015 and September 2016 and at the TD1 and Lung Mun Road works area on October 2016 by the Safety Officer.  The monitoring results shown no exceedances were triggered.

 

13.1.6             No notifications of summons or successful prosecution were received during the Reporting Period.  However, three complaints about the water quality issues and one complaint about the air quality issues were received during the Reporting Period.  Investigations were conducted and the follow-up actions corresponding to the mitigation measures recommended were undertaken by the Contractor to resolve the environmental deficiencies

 

13.1.7             Joint site inspection by the RE, ET and CRBC-Kaden JV was carried in accordance with the EM&A Manual.  Moreover, the IEC attended a total of 12 joint site inspections during the Reporting Period.  No non-compliance was recorded during the site inspection but total 102 observations/reminders were recorded in the past twelve months.  All the deficiencies were rectified before next site inspection date.  

 

13.1.8             A total 52 occasions of Pitcher Plant inspection were carried out by the Contractor and ET in the past twelve months at the final receptor site.  It was observed that the transplanted pitcher plants were properly protected and the growth was normally in fair condition except three individuals which appeared poor condition in May 2016 were certified dead by the specialist.  It is considered that the Pitcher Plant were establishing after transplanting shock and adapting to the condition of the Final Receptor Site and establish period for the pitcher plants was completed at the end of September 2016.

 

13.1.9             For cultural heritage in the past twelve months, the buffer zone between the working area and the Grave was observed and no construction material or equipment was stored nearby.

 

13.2                   Recommendations

13.2.1             The construction phase monitoring programme ensured that any environmental impact to the receivers would be readily detected and timely actions could be taken to rectify any non-compliance.  Assessment and analysis of monitoring results collected demonstrated the environmental acceptability of the Project.  The regular site inspection and waste audit ensured that all the mitigation measures on waste management were effectively implemented.

 

13.2.2             The EM&A programme effectively monitored the environmental impacts from the construction phase of the Project and no particular recommendation was advised for the improvement of the programme.

 

13.2.3             It is considered that the environmental acceptability of the Contract in the past twelve months was satisfactory and acceptable.