AUES Job No.: TCS00715/14

 

 

 

 

 

 

 

 

 

Tuen Mun - Chek Lap Kok Link

Contract No. HY/2013/12 ¡V

Northern Connection Toll Plaza and Associated Works

 

 

 

 

 

 

 

 

 

 

Final Environmental Monitoring and Audit (EM&A) Report ¡V November 2014 to December 2020

 

 

 

 

 

 

 

 

 

 

Prepared For

CRBC and Kaden Joint Venture

 

 

 

 

 

 

 

 

 

 

 

 

 

Date

Reference No.

Prepared By

Certified By

7 September 2021

TCS00715/14/600/R0745v3

Ben Tam

(Environmental

Consultant)

T.W. Tam

(Environmental Team

Leader)

 

 


 

 

 

 

 

 

EXECUTIVE SUMMARY

ES01       In August 2014, CRBC-Kaden Joint Venture (hereafter ¡§CRBC-Kaden JV¡¨) has been awarded the Contract No. HY/2013/12 -Northern Connection Toll Plaza and Tunnel Section of the Tuen Mun ¡V Chek Lap Kok Link (hereinafter called ¡§the Contract¡¨) by the Highways Department (HyD).  The construction phase of the Contract was commenced on 23 October 2014.

 

ES02       The Project TM-CLKL had been commissioning at the end of 2020 and the termination proposal for construction EM&A programme was approved by EPD on 23 December 2020. The construction phase EM&A programme of the Contract has been terminated since 31 December 2020.

 

ES03       In view of the construction works under the Contract, the major construction activities are land-based.  In accordance with the Project EM&A Manual requirements, environmental aspect monitoring should be conducted including air quality, ecological (Pitcher plant), cultural heritage and site inspections during construction period.  In addition, landscape and visual (L&V) monitoring, landfill gas monitoring and audit of the contractor¡¦s implementation of the construction noise and land-based water quality pollution control measures are also required for the Contract.

 

ES04       This is the Final EM&A Report for the ¡§Tuen Mun - Chek Lap Kok Link - Northern Connection Toll Plaza and Associated Works¡¨ under Environmental Permit No. EP-354/2009/D (hereinafter ¡¥¡¥the EP¡¦¡¦), covering the construction phase of the contract from 23 October 2014 to 31 December 2020 (hereinafter ¡§Reporting Period¡¨).

 

Summary of EM&A activities for the Reporting Period

ES05       In the Reporting Period, the EM&A activities is summarized in Table ES-02.

Table ES-02     Summary EM&A Activities Undertaken in the Reporting Period

Environmental Aspect

Environmental Monitoring Parameters / Inspection

Total

Air Quality

1-hour TSP

10,845

24-hour TSP

3,605

Cultural heritage inspection

Grave G1

322

Landfill Gas Monitoring

Oxygen; Methane & Carbon Dioxide

1,403 days

Landscape &Visual

Landscape & Visual Monitoring

291

Joint Site Inspection / Audit

IEC, ET, the Contractor and RE joint site Environmental Inspection and Auditing

322

     

 

Breach of Action and Limit (A/L) Levels

ES06       In according with the air quality measurement results by the ET of Contract HY/2012/08 total 94 Action Level, 13 Limit Level exceedances of 1-hour TSP and total 7 Action Level, 3 Limit Level exceedances of 24-hour TSP were recorded in the Reporting Period


 

ES07       For landfill gas monitoring, the concentration of all parameters were detected within the acceptable levels.  Table ES-03 is summarized breach of environmental performance criteria.

Table ES-03    Action and Limit (A/L) Levels Breach Summarized in the Reporting Period

Environmental Aspect

Monitoring Parameters

Action Level

Limit Level

Event & Action

NOE Issued

Investigation

Corrective Actions

Air Quality

1-hour TSP

94

13

71

71

0

24-hour TSP

7

3

10

10

0

Landfill Gas Monitoring

Oxygen

0

0

0

0

0

Methane

0

0

0

0

0

Carbon Dioxide

0

0

0

0

0

 

Environmental Complaint

ES08       Total 11 complaints received during the Construction Phase of the contract. The statistics of environmental complaint is listed in Table ES-04.

Table ES-04    Statistical Summary of Environmental Complaints

Reporting Period

Complaint Nature

Total Registered

Water Quality

Construction Dust

Construction Noise

Others

23 October 2014 ¡V 31 December 2020

6

4

1

2

11

 

Notification of Summons and Successful Prosecutions

ES09       No environmental summons or successful prosecutions were recorded in the Reporting Period.

 

Conclusions

ES10        The construction phase monitoring programme ensured that any environmental impact to the receivers would be readily detected and timely actions could be taken to rectify any non-compliance.  Assessment and analysis of monitoring results collected demonstrated the environmental acceptability of the Project.  The regular site inspection and waste audit ensured that all the mitigation measures on waste management were effectively implemented.

 

ES11       The EM&A programme effectively monitored the environmental impacts from the construction phase of the Project and no particular recommendation was advised for the improvement of the programme.

 

ES12       It is considered that the environmental acceptability of the Contract during the construction phase was satisfactory and acceptable. In general, the monitoring results were in line with EIA predictions.

 

ES13       After terminated of the construction phase EM&A programme, the establishment period monitoring for planting works will be carried on till May 2022 to fulfill the EM&A Manual requirement.

 

able of Contents

1     Introduction                                                                                                                       1

1.1            Contract Background                                                                                    1

1.2            Report Structure                                                                                                1

2     Contract Organization and Construction progress and Environmental Submissions                                                                                                                            3

2.1            Contract Organization                                                                                   3

2.2            Construction Progress                                                                                    3

2.3            Summary of Environmental Submissions                                                 3

3     Summary of Impact Monitoring Requirements Under the Contract  6

3.1            General                                                                                                                   6

3.2            Air Quality Monitoring Parameters                                                          6

3.3            Monitoring Location                                                                                        6

3.4            Monitoring Frequency                                                                                     6

3.5            Derivation of Action/Limit (A/L) Levels                                                      7

3.6            Other Environmental Aspects                                                                      8

4     Air Quality Monitoring                                                                                               10

4.1            General                                                                                                                 10

4.2            Air Quality Monitoring Results in Reporting Period                       10

4.3            Summary of Action and Limit (A/L) Levels Exceedance (non-compliance)         10

4.4            Air Quality Exceedance Investigation                                                   14

5     Ecology Monitoring                                                                                                     15

5.1            General                                                                                                                 15

5.2            Pitcher Plants Inspection                                                                             15

6     CULTURAL HERITAGE                                                                                                         16

6.1            General                                                                                                                 16

6.2            Grave Inspection                                                                                               16

7     LandscAPe and Visual                                                                                                    17

7.1            General                                                                                                                 17

7.2            Landscape and Visual Inspection (Construction Phase)                 17

7.3            Establishment Works Inspection                                                               17

8     Landfill Gas Hazard Monitoring                                                                           18

8.1            General                                                                                                                 18

8.2            Landfill Gas Monitoring Result                                                                19

9     Waste Management                                                                                                         20

9.1            General Waste Management                                                                        20

9.2            Records of Waste Quantities                                                                       20

10   Inspection and Auditing                                                                                               22

10.1          Site Inspection                                                                                                    22

11   Environmental Complaint and Non-compliance                                           23

11.1          Environmental Complaint, Summons and Prosecution                   23

11.2          Summary record of all complaints, action and working procedures 23

12   Implementation Status of Mitigation Measures                                            26

12.1          General Requirements                                                                                   26

13   Conclusions and Recommendations                                                                     27

13.1          Conclusions                                                                                                        27

 


 

List of TABLES

Table 2-1      Status of Environmental Licenses and Permits of the Contract

Table 3-1      Designated Air Quality Monitoring Stations under the Contract

Table 3-2      Enhanced TSP Monitoring Plan ¡V Construction Phase

Table 3-3      TSP Action and Limit Levels for Impact Air Quality Monitoring

Table 3-4      Actions in the Event of Landfill Gas being Detected in Excavation / Confined Area

Table 4-1      Summary of Air Quality Monitoring Exceedance

Table 8-1      Landfill Gas Monitoring Zone

Table 8-2      Summary of Landfill Gas Measurement Results

Table 9-1      Summary of Quantities of Inert C&D Materials

Table 9-2      Summary of Quantities of C&D Wastes

Table 11-1    Statistical Summary of Environmental Exceedance

Table 11-2    Statistical Summary of Environmental Complaints

Table 11-3    Statistical Summary of Environmental Summons

Table 11-4    Statistical Summary of Environmental Prosecution

Table 12-1    Environmental Mitigation Measures

 

 

 

List of Appendices

Appendix A  Project Layout Plan

Appendix B Layout Plan of the Contract

Appendix C  Organization of the Contract

Appendix D Monitoring Locations for the Contract

Appendix E  Event and Action Plan

Appendix F  Graphical Plots

Appendix G Waste Flow Table

Appendix H Environmental Mitigation Measures Implementation Schedule (EMMIS)

 



1                             Introduction

1.1                          Contract Background

1.1.1                 According to the findings of the Northwest New Territories (NWNT) Traffic and Infrastructure Review conducted by the Transport Department, Tuen Mun Road, Ting Kau Bridge, Lantau Link and North Lantau Highway would be operating beyond capacity after 2016. This forecast has been based on the estimated increase in cross boundary traffic, developments in the Northwest New Territories (NWNT), and possible developments in North Lantau, including the Airport developments, the Lantau Logistics Park (LLP) and the Hong Kong ¡V Zhuhai ¡V Macao Bridge (HZMB). In order to cope with the anticipated traffic demand, two new road sections between NWNT and North Lantau ¡V Tuen Mun ¡V Chek Lap Kok Link (TM-CLKL) and Tuen Mun Western Bypass (TMWB) are proposed.

 

1.1.2                 CRBC-Kaden Joint Venture (hereafter ¡§CRBC-Kaden JV¡¨) is commissioned by the Highways Department (HyD) as the Main Contractor of the Contract No. HY/2013/12 ¡V Northern Connection Toll Plaza and Tunnel Section ((hereafter ¡§the Contract¡¨) and this Contract is part of the Tuen Mun ¡V Chek Lap Kok Link (TM-CLK Link Project).  TM-CLK Link Project is a Designated Project under the latest Environmental Permit number EP-354/2009/D issued on 13 March 2015.  The layout Plan of the Project and the Contract are showed in Appendix A and Appendix B respectively.

 

1.1.3                 AECOM Asia Company Limited as the Resident Engineer (RE) and Ramboll Hong Kong Limited as the Independent Environmental Checker (IEC) and Environmental Project Office (ENPO) were employed by the HyD.  For implementation of the environmental monitoring and audit (EM&A) programme under the Contract, CRBC-Kaden JV has appointed Action-United Environmental Services & Consulting (AUES) as the Environmental Team (ET) to responsible relevant environmental monitoring work.

 

1.1.4                 Construction phase of the Contract was commenced on 23 October 2014. According to the approved EM&A Manual, the impact monitoring for the EM&A programme including air quality, ecological monitoring, cultural heritage monitoring, landscape and visual monitoring, landfill gas hazard monitoring and environmental site inspections.

 

1.1.5                 The Project TM-CLKL had been commissioning at the end of 2020 and the termination proposal for construction EM&A programme was approved by EPD on 23 December 2020. The construction phase EM&A programme of the Contract has been terminated since 31 December 2020.

 

1.1.6                 This is the Final EM&A Report to summarize the monitoring results and inspection findings with the Contractor performance during the construction period from 23 October 2014 to 31 December 2020 (hereinafter ¡§Reporting Period¡¨).

 

1.2                          Report Structure

1.2.1                 The Final Environmental Monitoring and Audit (EM&A) Report is structured into the following sections:-

Section 1     Introduction

Section 2     Contract Organization and Construction Progress and Environmental Submissions

Section 3     Summary of Impact Monitoring Requirements under the Contract

Section 4     Air Quality Monitoring

Section 5     Ecology Monitoring

Section 6     Cultural Heritage

Section 7     Landscape and Visual

Section 8     Landfill gas hazard Monitoring

Section 9     Waste Management

Section 10   Inspection and Auditing

Section 11   Environmental Complaint and Non-Compliance

Section 12   Implementation Status of Mitigation Measures

Section 13   Conclusions and Recommendations


2                             Contract Organization and Construction progress and Environmental Submissions

2.1                          Contract Organization

2.1.1                 The Contract organization and contact details of key personnel are shown in Appendix C.

 

2.2                          Construction Progress

2.2.1                 The major construction activity conducted under the Contract is summarized in below.

a.              construction of an approximately 5.4 hectares toll plaza and an associated footbridge;

b.             construction of associated carriageways including approximately 0.74 kilometre land viaducts, and an approximately 230 metres vehicular underpass to connect the toll plaza and the roundabout at Lung Mun Road/Lung Fu Road;

c.              site formation for the construction of the toll plaza, including associated slope works and natural terrain hazard mitigation measures;

d.             modification and realignment of the existing Lung Mun Road and Lung Fu Road; and

e.              associated waterworks, drainage, sewerage and landscaping works, etc..

 

2.3                          Summary of Environmental Submissions

2.3.1                 In according to the EP, the required documents have submitted to EPD for retention which listed in below:

Ÿ   Monitoring Plan on construction dust

Ÿ   Landscape and Visual Plan

Ÿ   Waste Management Plan

Ÿ   Baseline Monitoring Report

 

2.3.2                 Summary of the relevant permits, licenses, and/or notifications on environmental protection as obtained by the Contract in the reporting period is presented in Table 2-1.

Table 2-1      Status of Environmental Licenses and Permits of the Contract

No.

Type of Permit/ License

Reference/

License No.

Date of Issue

Date of Expiry

1

Air pollution Control (Construction Dust) Regulation

377719

06-08-2014

N/A

2

Chemical Waste Producer Registration - Waste Producers Number

5117422C389301

03-09-2014

N/A

3

Water Pollution Control Ordinance ¡VOriginal / Variation of Effluent Discharge License

WT00020065-2014

29-09-2014

30-09-2019

WT00023973-2016

25-10-2017

30-09-2019

4

Waste Disposal Regulation - Billing Account for Disposal of Construction Waste

7020460

01-08-2014

N/A

5

Permission to Transplant Pitcher Plant

(7) in AF CON 11/13 pt.4

09-12-2014

08-06-2015

(30) in AF CON 11/13 pt.4

23-6-2015

22-12-2015

6

CNP for Construction of Site Office

GW-RW0656-14

03-09-2014

22-02-2015

7

CNP for Site Formation

GW-RW0761-14

29-09-2014

29-03-2015

8

CNP for Concreting

GW-RW0748-14

29-09-2014

29-03-2015

9

CNP for Multiple Task

GW-RW0949-14

05-12-2014

04-05-2015

GW-RW0225-15

13-05-2015

04-11-2015

GW-RW0520-15

05-11-2015

04-05-2016

GW-RW0520-16

05-05-2016

04-11-2016

GW-RW0619-16

05-11-2016

04-05-2017

GW-RW0230-17

08-05-2017

04-11-2017

GW-RW0605-17

25-11-2017

24-05-2018

GW-RW0154-18

25-05-2018

24-11-2018

GW-RW0480-18

25-11-2018

24-05-2019

GW-RW0230-19

30-05-2019

24-11-2019

GW-RW0555-19

25-11-2019

23-05-2020

GW-RW0202-20

24-05-2020

23-11-2020

GW-RW0532-20

24-11-2020

23-05-2021

10

CNP for GI works

GW-RW0134-15

16-03-2015

07-04-2015

11

CNP for MH5

GW-RW0226-15

18-05-2015

17-11-2015

GW-RW0563-15

18-11-2015

17-05-2016

GW-RW0563-16

18-05-2016

17-11-2016

GW-RW0650-16

18-11-2016

17-05-2017

GW-RW0242-17

22-05-2017

17-11-2017

12

CNP for Tunnel

GW-RW0582-15

23-11-2015

22-05-2016

GW-RW0582-16

23-05-2016

22-11-2016

GW-RW0653-16

23-11-2016

22-05-2017

GW-RW0243-17

23-05-2017

22-11-2017

GW-RW0567-17

26-10-2017

22-05-2018

GW-RW0140-18

23-05-2018

22-11-2018

GW-RW0478-18

23-11-2018

22-05-2019

13

CNP for falsework erection

GW-RW0076-16

15-02-2016

21-04-2016

GW-RW0215-16

26-04-2016

21-06-2016

GW-RW0289-16

22-06-2016

19-08-2016

GW-RW0472-16

22-08-2016

21-12-2016

GW-RW0724-16

28-12-2016

16-03-2017

GW-RW0117-17

09-03-2017

16-06-2017

GW-RW0205-17

25-04-2017

25-11-2017

GW-RW0563-17

26-10-2017

24-02-2018

GW-RW0066-18

26-02-2018

19-05-2018

14

CNP for Portion H

GW-RW0704-16

06-12-2016

21-02-2017

GW-RW0049-17

14-02-2017

18-08-2017

GW-RW0242-17

22-05-2017

17-11-2017

GW-RW0568-17

26-10-2017

22-05-2018

GW-RW0155-18

25-05-2018

17-11-2018

GW-RW0479-18

18-11-2018

17-05-2019

GW-RW0203-19

18-05-2019

17-11-2019

GW-RW0556-19

25-11-2019

17-05-2020

GW-RW0201-20

18-05-2020

16-11-2020

15

CNP for Road Paving Works

GW-RW0211-17

25-04-2017

01-11-2017

GW-RW0561-17

26-10-2017

01-02-2018

GW-RW0044-18

01-02-2018

28-04-2018

16

CNP for Lung Mun Road

GW-RW0174-18

20-05-2018

12-08-2018

GW-RW0334-18

13-08-2018

17-11-2018

GW-RW0475-18

19-11-2018

02-12-2018

GW-RW0530-18

25-12-2018

02-03-2019

GW-RW0103-19

15-03-2019

30-04-2019

GW-RW0200-19

16-05-2019

05-06-2019

GW-RW0344-19

27-07-2019

01-10-2019

GW-RW0491-19

11-10-2019

15-12-2019

GW-RW0004-20

09-01-2020

14-03-2020

GW-RW0123-20

27-03-2020

14-05-2020

GW-RW0261-20

12-06-2020

16-08-2020

GW-RW0382-20

04-09-2020

13-11-2020

GW-RW0506-20

13-11-2020

18-12-2020

17

CNP for Lung Fu Road

GW-RW0135-18

02-05-2018

27-07-2018

GW-RW0289-18

30-07-2018

27-10-2018

GW-RW0436-18

29-10-2018

01-12-2018

GW-RW0531-18

27-12-2018

02-03-2019

GW-RW0162-19

17-04-2019

05-06-2019

GW-RW0341-19

26-07-2019

28-09-2019

GW-RW0490-19

11-10-2019

14-12-2019

GW-RW0005-20

10-01-2020

26-03-2020

GW-RW0130-20

08-04-2020

24-06-2020

GW-RW0287-20

03-07-2020

09-09-2020

GW-RW0423-20

22-09-2020

06-11-2020

18

CNP for Lung Fu Road (Out of site boundary)

GW-RW0381-20

04-09-2020

27-09-2020

                      Note: CNP is Control Noise Permit

 

 

 

 


3                             Summary of Impact Monitoring Requirements Under the Contract

3.1                          General

3.1.1                 In view of the construction works under the Contract, the major construction activities are land-based.  In accordance with the Project EM&A Manual requirements, environmental aspect monitoring should be conducted including air quality, ecological (Pitcher plant), cultural heritage and site inspections during construction period.  In addition, landscape and visual (L&V) monitoring, landfill gas monitoring and audit of the contractor¡¦s implementation of the construction noise and land-based water quality pollution control measures are also required for the Contract.

 

3.1.2                 A summary of construction phase EM&A requirements are presented in the sub-sections below.

 

3.2                          Air Quality Monitoring Parameters

3.2.1                 The construction phase air quality monitoring shall cover the following parameters:

                     1-hour TSP; and

                     24-hour TSP

 

3.3                          Monitoring Location

3.3.1                 The air quality monitoring stations for impact monitoring are listed in Table 3.1 and illustrated in Appendix D.

Table 3-1      Designated Air Quality Monitoring Stations under the Contract

ID

Location

Air monitoring station Description

ASR1

Tuen Mun Fireboat Station

EM&A Manual

ASR5

Pillar Point Fire Station

EM&A Manual

AQMS1

Previous River Trade Golf

Enhanced TSP Level under EP condition 2.4

ASR6

Butterfly Beach Laundry

Enhanced TSP Level under EP condition 2.4

ASR10

Butterfly Beach Park

Enhanced TSP Level under EP condition 2.4

 

3.4                          Monitoring Frequency

General Requirement

3.4.1                 For regular impact monitoring, the sampling frequency of at least once in every six days shall be strictly observed at five of the designated monitoring stations for 24-hr TSP monitoring.  For 1-hr TSP monitoring, the sampling frequency of at least three times in every six days should be undertaken at five locations when the highest dust impact occurs.  The stations to be monitored should be selected based on the prevailing wind direction and their proximity to the active construction works.

 

Special Requirement

3.4.2                 As per Condition 2.4 of the EP of TM-CLKL, an enhanced monitoring plan on TSP level at Tuen Mun (¡§the Enhanced TSP Monitoring Plan¡¨) is required to be submitted to the DEP for approval at least 1 month before the commencement of construction of the Project.  Details of the Enhanced TSP Monitoring Plan under Contract No. HY/2012/08 could be found from the project website.  The air quality monitoring work under this Contract will follow the monitoring requirement of enhanced TSP monitoring under the project.

 

3.4.3                 The air quality monitoring requirements for the Contract is shown in Table 3-2.


 

Table 3-2      Enhanced TSP Monitoring Plan ¡V Construction Phase

Condition

Monitoring Parameter

Monitoring Location

Frequency

Monitoring Requirement

General

1-hour TSP

ASR1, ASR5, AQMS1, ASR6, ASR10

3 times per day every six days

Throughout the Northern Connection, toll plaza and tunnel buildings construction works

24-hour TSP

ASR1, ASR5, AQMS1, ASR6, ASR10

Daily every six days

Special

1-hour TSP

ASR1, ASR5, AQMS1, ASR6, ASR10

3 times per day every three days

Northern Connection

During excavation works for launching shaft, excavation work for Cut and Cover Tunnel and Cut and Cover Tunnel Construction

Toll Plaza

During excavation, slope works, construction of road and superstructures and wind erosion from open sites and stockpiling areas

Tunnel Buildings

During excavation, foundation works, construction of superstructures and wind erosion from open sites and stockpiling areas

24-hour TSP

ASR1, ASR5, AQMS1, ASR6, ASR10

Daily every three days

 

3.5                          Derivation of Action/Limit (A/L) Levels

3.5.1                 The baseline monitoring results formed the basis for determining the air quality criteria for the impact monitoring. The ET shall compare the impact monitoring results with air quality criteria set up for 24-hour TSP and 1-hour TSP.  Based on results of the approved Baseline Monitoring Report of HyD Contract HY/2012/08, the proposed Action and Limit Levels are shown in Tables 3-3.

Table 3-3      TSP Action and Limit Levels for Impact Air Quality Monitoring

Air Quality Monitoring Stations

24-hour TSP (£gg/m3)

1-hour TSP (£gg/m3)

Action Level

Limit Level

Action Level

Limit Level

ASR1

213

260

331

500

ASR5

238

260

340

500

AQMS1

213

260

335

500

ASR6

238

260

338

500

ASR10

214

260

337

500

 

3.5.2                 Should non-compliance of the environmental quality criteria occurs, remedial actions will be triggered according to the Event and Action Plan which presented in Appendix E.


 

3.6                          Other Environmental Aspects

Noise

3.6.1                 The TM-CLKL EIA study concluded that no existing noise sensitive receiver (NSR) was identified within the Study Area at Tuen Mun.  Therefore, no planned NSR designated at the Project sites of Tuen Mun.  Based upon this, no noise monitoring is necessary for construction phase under the Contract.

 

3.6.2                 Regular site inspections and audits will be carried out during the construction phase in order to confirm compliance with the regulatory requirements and conformity of the Contractor with regard to noise control and contract conditions.

 

Water Quality

3.6.3                 No marine works will be undertaken under the Contract.  Based upon this, no water quality monitoring is necessary for construction phase.

 

Ecology

3.6.4                 Since the Works of the Contract would not generate marine ecological impact, no dolphin monitoring under the Contract was conducted.

 

3.6.5                 During construction phase, the ET will perform Pitcher Plants inspection at least once every week to report the growth condition (only undertaken at Establish period) and protection measures.

 

Landscape and Visual

3.6.6                 According to EIA recommendation, site inspection and audit shall be required to be undertaken in the operation stage. Measures to mitigate landscape and visual impacts during construction should be checked and monitored by a Registered Landscape Architect to ensure compliance with the intended aims of the mitigation measures in accordance with the EM&A Manual.

 

Cultural Heritage

3.6.7                 Grave G1 of heritage resources is situated near the proposed toll plaza in Tuen Mun.  Site inspections should be undertaken at least once per week throughout the construction period to ensure compliance with the intended aims of recommended mitigation measures.

 

Monitoring and Measurement of Landfill Gas

3.6.8                 During EIA study, landfill gas hazards are likely to be generated from the Pillar Point Valley (PPV) Landfill. Hence, regular landfill gas monitoring is recommended during construction of the proposed toll plaza.  Safety Officer or an approved and appropriated qualified person should be carried out the monitoring works to make sure the area free of landfill gas before any man enters in the area.


 

3.6.9                 Depending on the results of the measurements, actions required will vary and should be set down by the Safety Officer or other appropriately qualified person. As a minimum these should encompass those actions specified as follow:

Table 3-4      Actions in the Event of Landfill Gas being Detected in Excavation / Confined Area

Parameter

Measurement

Action

Oxygen

< 19%

- Ventilate to restore oxygen to > 19%

< 18%

- Stop work

- Evacuate personnel / prohibit entry

- Increase ventilation to restore to > 19%

Methane

> 10% LEL (> 0.5% v/v)

- Prohibit hot work

- Ventilate to restore methane to < 10% LEL

> 20% LEL (>1% v/v)

- Stop work

- Evacuate personnel / prohibit entry

- Increase ventilation to restore to < 10%

Carbon Dioxide

> 0.5%

- Ventilate to restore oxygen to < 0.5%

> 1.5%

- Stop work

- Evacuate personnel / prohibit entry

- Increase ventilation to restore to < 0.5%


 

4                             Air Quality Monitoring

4.1                          General

4.1.1                 According to the Updated EM&A Manual and the Enhanced Total Suspended Particulates (TSP) Monitoring Plan, the air quality impact monitoring was conducted at the five air quality monitoring stations during the Reporting Period by the ET of Contract HY/2012/08.  Sharing of impact air quality monitoring data between HY/2012/08 and HY/2013/12 is agreed by all relevant parties.  Therefore the Contract is not required to conduct its own dust monitoring exercise until the Contract HY/2012/08 is ended.

 

4.2                          Air Quality Monitoring Results in Reporting Period

4.2.1                 In the Reporting Period (construction phase), total 10,845 of 1-hr TSP measurements and 3,605 events of 24-hours TSP monitoring at five proposed locations were carried out by the ET of Contract HY/2012/08.  Detailed air quality monitoring results and statistical analysis of the trends of air quality data during the Reporting Period can be referred to the Monthly EM&A Reports (from November 2014 to December 2020).

 

4.3                          Summary of Action and Limit (A/L) Levels Exceedance (non-compliance)

4.3.1                 According to the air quality monitoring result provided by Contract HY/2012/08, total 94 Action Level, 13 Limit Level exceedances of 1-hour TSP and total 7 Action Level, 3 Limit Level exceedances of 24-hour TSP were recorded in the Reporting Period.  Notification of Exceedances (NOEs) were issued after receiving the monitoring result from the Contract HY/2012/08.  The summary of air quality exceedance is shown in Table 4-1.

Table 4-1      Summary of Air Quality Monitoring Exceedance

Date of Exceedance

Monitoring Station

Air Quality Parameter

Result

Exceed

Contract Related

14 November 2014

ASR1

1-hour TSP

404£gg/m3

Action Level

No

14 November 2014

ASR1

1-hour TSP

396£gg/m3

Action Level

No

2 December 2014

ASR5

1-hour TSP

346£gg/m3

Action Level

No

17 December 2014

AQMS1

1-hour TSP

348£gg/m3

Action Level

No

29 July 2017

ASR5

1Hr TSP

370 µg/m3

Action Level

No

29 July 2017

ASR6

1Hr TSP

401 µg/m3

Action Level

No

29 July 2017

ASR10

1Hr TSP

475 µg/m3

Action Level

No

22 August 2017

ASR1

1Hr TSP

360 µg/m3

Action Level

No

12 September 2017

ASR1

1Hr TSP

332 µg/m3

Action Level

No

12 September 2017

ASR1

1Hr TSP

545 µg/m3

Limit Level

No

12 September 2017

ASR1

1Hr TSP

413 µg/m3

Action Level

No

12 September 2017

ASR5

1Hr TSP

367 µg/m3

Action Level

No

18 September 2017

AQMS1

1Hr TSP

473 µg/m3

Action Level

No

27 September 2017

ASR5

1Hr TSP

355 µg/m3

Action Level

No

27 September 2017

ASR5

1Hr TSP

456 µg/m3

Action Level

No

21 October 2017

ASR1

1Hr TSP

372 µg/m3

Action Level

No

21 October 2017

ASR1

1Hr TSP

439 µg/m3

Action Level

No

27 October 2017

ASR5

1Hr TSP

368 µg/m3

Action Level

No

27 October 2017

ASR6

1Hr TSP

388 µg/m3

Action Level

No

2 November 2017

ASR5

1Hr TSP

351 µg/m3

Action Level

No

2 November 2017

ASR10

1Hr TSP

403 µg/m3

Action Level

No

2 November 2017

ASR10

1Hr TSP

816 µg/m3

Limit Level

No

11 November 2017

ASR5

1Hr TSP

389 µg/m3

Action Level

No

29 November 2017

ASR10

1Hr TSP

455 µg/m3

Action Level

No

8 December 2017

ASR5

1Hr TSP

353 µg/m3

Action Level

No

11 December 2017

ASR1

1Hr TSP

399 µg/m3

Action Level

No

11 December 2017

ASR1

1Hr TSP

443 µg/m3

Action Level

No

11 December 2017

ASR5

1Hr TSP

417 µg/m3

Action Level

No

20 December 2017

ASR1

1Hr TSP

357 µg/m3

Action Level

No

20 December 2017

ASR5

1Hr TSP

372 µg/m3

Action Level

No

26 December 2017

ASR1

1Hr TSP

407 µg/m3

Action Level

No

13 January 2018

ASR5

1Hr TSP

345 µg/m3

Action Level

No

16 January 2018

ASR5

1Hr TSP

396 µg/m3

Action Level

No

16 January 2018

ASR5

1Hr TSP

384 µg/m3

Action Level

No

16 January 2018

ASR5

1Hr TSP

345 µg/m3

Action Level

No

22 January 2018

ASR5

1Hr TSP

363 µg/m3

Action Level

No

22 January 2018

ASR5

1Hr TSP

380 µg/m3

Action Level

No

3 February 2018

ASR1

1Hr TSP

392 µg/m3

Action Level

No

3 February 2018

ASR5

1Hr TSP

455 µg/m3

Action Level

No

2 March 2018

ASR1

1Hr TSP

460 µg/m3

Action Level

No

20 March 2018

ASR1

1Hr TSP

446 µg/m3

Action Level

No

13 April 2018

ASR5

1Hr TSP

389 µg/m3

Action Level

No

26 August 2018

ASR1

1Hr TSP

417 µg/m3

Action Level

No

29 August 2018

ASR1

1Hr TSP

403 µg/m3

Action Level

No

7 September 2018

ASR1

1Hr TSP

392 µg/m3

Action Level

No

28 September 2018

ASR1

1Hr TSP

584 µg/m3

Limit Level

No

28 September 2018

ASR1

1Hr TSP

417 µg/m3

Action Level

No

4 October 2018

ASR1

1Hr TSP

340 µg/m3

Action Level

No

10 October 2018

ASR1

1Hr TSP

451 µg/m3

Action Level

No

31 October 2018

ASR1

1Hr TSP

371 µg/m3

Action Level

No

6 November 2018

ASR1

1Hr TSP

376 µg/m3

Action Level

No

12 November 2018

ASR1

1Hr TSP

395 µg/m3

Action Level

No

12 November 2018

ASR5

1Hr TSP

371 µg/m3

Action Level

No

12 November 2018

ASR5

1Hr TSP

425 µg/m3

Action Level

No

12 November 2018

ASR5

1Hr TSP

377 µg/m3

Action Level

No

12 November 2018

ASR6

1Hr TSP

343 µg/m3

Action Level

No

9 December 2018

ASR1

1Hr TSP

346 µg/m3

Action Level

No

12 December 2018

ASR1

1Hr TSP

414 µg/m3

Action Level

No

18 December 2018

ASR6

1Hr TSP

478 µg/m3

Action Level

No

8 January 2019

ASR5

1Hr TSP

354 µg/m3

Action Level

No

11 January 2019

ASR1

1Hr TSP

335 µg/m3

Action Level

No

11 January 2019

ASR5

1Hr TSP

398 µg/m3

Action Level

No

17 January 2019

ASR1

1Hr TSP

519 µg/m3

Limit Level

No

17 January 2019

ASR5

1Hr TSP

354 µg/m3

Action Level

No

26 January 2019

ASR5

1Hr TSP

399 µg/m3

Action Level

No

27 March 2019

ASR1

1Hr TSP

412 µg/m3

Action Level

No

30 March 2019

ASR1

1Hr TSP

374 µg/m3

Action Level

No

11 May 2019

ASR1

1Hr TSP

339 µg/m3

Action Level

No

23 May 2019

ASR1

1Hr TSP

408 µg/m3

Action Level

No

10 July 2019

ASR6

1Hr TSP

372 µg/m3

Action Level

No

28 July 2019

ASR1

1Hr TSP

646 µg/m3

Limit Level

No

28 July 2019

ASR5

1Hr TSP

410 µg/m3

Action Level

No

20 September 2019

ASR1

1Hr TSP

539 µg/m3

Limit Level

No

14 October 2019

ASR1

1Hr TSP

363 µg/m3

Action Level

No

17 October 2019

ASR1

1Hr TSP

354 µg/m3

Action Level

No

17 October 2019

ASR1

1Hr TSP

385 µg/m3

Action Level

No

4 November 2019

ASR1

1Hr TSP

626 µg/m3

Limit Level

No

4 November 2019

ASR5

1Hr TSP

398 µg/m3

Action Level

No

7 November 2019

ASR5

1Hr TSP

479 µg/m3

Action Level

No

28 November 2019

ASR1

1Hr TSP

577 µg/m3

Limit Level

No

28 November 2019

ASR1

1Hr TSP

452 µg/m3

Action Level

No

28 November 2019

ASR1

1Hr TSP

385 µg/m3

Action Level

No

28 November 2019

ASR5

1Hr TSP

534 µg/m3

Limit Level

No

28 November 2019

ASR5

1Hr TSP

500 µg/m3

Action Level

No

1 December 2019

ASR1

1Hr TSP

747 µg/m3

Limit Level

No

1 December 2019

ASR5

1Hr TSP

377 µg/m3

Action Level

No

1 December 2019

ASR10

1Hr TSP

407 µg/m3

Action Level

No

4 December 2019

ASR1

1Hr TSP

366 µg/m3

Action Level

No

4 December 2019

ASR5

1Hr TSP

380 µg/m3

Action Level

No

12 March 2020

ASR5

1Hr TSP

356 µg/m3

Action Level

No

8 April 2020

ASR1

1Hr TSP

357 µg/m3

Action Level

No

8 April 2020

ASR1

1Hr TSP

457 µg/m3

Action Level

No

8 April 2020

ASR5

1Hr TSP

384 µg/m3

Action Level

No

14 April 2020

ASR1

1Hr TSP

673 µg/m3

Limit Level

No

13 June 2020

ASR6

1Hr TSP

357 µg/m3

Action Level

No

13 August 2020

ASR1

1Hr TSP

352 µg/m3

Action Level

No

11 September 2020

ASR6

1Hr TSP

499 µg/m3

Action Level

No

11 September 2020

ASR6

1Hr TSP

1454 µg/m3

Limit Level

No

9 October 2020

ASR5

1Hr TSP

373 µg/m3

Action Level

No

21 October 2020

ASR1

1Hr TSP

494 µg/m3

Action Level

No

21 October 2020

ASR5

1Hr TSP

474 µg/m3

Action Level

No

21 October 2020

ASR6

1Hr TSP

352 µg/m3

Action Level

No

6 November 2020

ASR1

1Hr TSP

887 µg/m3

Limit Level

No

12 November 2020

ASR1

1Hr TSP

474 µg/m3

Action Level

No

12 November 2020

ASR5

1Hr TSP

433 µg/m3

Action Level

No

12 November 2020

ASR6

1Hr TSP

358 µg/m3

Action Level

No

10 December 2020

ASR5

1Hr TSP

348 µg/m3

Action Level

No

21 October 2017

ASR1

24Hr TSP

220 µg/m3

Action Level

No

8 December 2017

ASR1

24Hr TSP

328 µg/m3

Limit Level

No

8 December 2017

ASR5

24Hr TSP

279 µg/m3

Limit Level

No

11 December 2017

ASR1

24Hr TSP

218 µg/m3

Action Level

No

17 December 2017

ASR5

24Hr TSP

265 µg/m3

Limit Level

No

29 December 2017

ASR10

24Hr TSP

250µg/m3

Action Level

No

16 February 2019

ASR1

24Hr TSP

237 µg/m3

Action Level

No

23 May 2019

ASR1

24Hr TSP

217 µg/m3

Action Level

No

2 November 2020

ASR1

24Hr TSP

244 µg/m3

Action Level

No

6 November 2020

ASR1

24Hr TSP

214 µg/m3

Action Level

No

 

4.4                          Air Quality Exceedance Investigation

4.4.1                 Investigation for the 1-hour and 24-hour TSP exceedance was undertaken upon received the monitoring results by the ET.

 

4.4.2                 For the exceednances in the reporting period, the investigation reports were submitted to all relevant parties and concluded that those exceedances are unlikely related to the Contract work and no corrective action was required accordingly. The detailed investigation reports and findings can be referred to the Monthly EM&A Reports of the contract.

 

 


 

5                             Ecology Monitoring

5.1                          General

5.1.1                 According to the EM&A Manual requirements, regularly inspection for Pitcher Plants at least once every week to report it growth and protection measure situation shall be conducted during construction period.

 

5.1.2                 Permission for transplantation of Pitcher Plant was issued by the AFCD on 9th December 2014. 280 numbers of Pitcher Plant individuals located at Zones 1 - 7 were transplanted to the nursery site on 17th December 2014 by the accredited person and his assistant. The transplantation work was strictly followed to conditions on permit.

 

5.1.3                 Trial transplantation of pitcher plant from the nursery site to final receptor site which located near Zone 9 and Zone 10 was carried out on 15 April 2015 and a total of 5% pitcher plant was transplanted.  Transplantation of remaining 95% pitcher plant from the nursery site to final receptor site was completed on 10th September 2015. 

 

5.1.4                 Total 181 pitcher plants were transplanted to final receptor site and the rest of the Pitcher Plant individuals (certified dead by the specialist) were not transplanted and were treated as general refuse. All the transplantation of pitcher plant from the nursery site to final receptor site was completed on 10th September 2015. The layout plan for the final receptor site is illustrated in Appendix D.

 

5.2                          Pitcher Plants Inspection

5.2.1                 A total 322 occasions of inspection were carried out by the Contractor and ET during the Reporting Period.

 

5.2.2                 During weekly site inspection at the nursery zone before the transplantation to the receptor site, the transplanted Pitcher Plants in the nursery zone were observed in fair to poor condition.  At the final receptor site, all the transplanted Pitcher Plants were protected properly and the growth also was in fair to poor condition. 

 

5.2.3                 Establishment period for the pitcher plants was completed at the end of September 2016, the join site completion of Establishment period visit with AFCD was undertaken on 23 September 2016 and the final pitcher plants report was submitted to AFCD on early December 2016. Therefore after 23 September 2016, only the integrity of the protection fence was checked to fulfill the EIA requirement. During each inspection, the protection mitigation measures were checking at the final receptor area to make sure no site activities was undertaken inside the protection zone. Besides, no construction activities were observed to be carried out at the surrounding of the final receptor area.  The condition of chain link fence is good and no repair or maintenance is required.

 

5.2.4                 No matters the completion of establish period, the Contractor should properly maintain the fencing along the receptor area to avoid disturbance to the pitcher plants under the EIA requirement.

 

 


 

6                             CULTURAL HERITAGE

6.1                          General

6.1.1                 According to the EM&A Manual requirements, regular inspection for heritage resource Grave G1 shall be audited by the ET at least once every week to ensure recommended mitigation measures implemented during construction period.  The aim of the survey is prevention of any possible damage to the grave and to ensure that proposed mitigation measures are implemented. The broad scope of the audit will involve supervision of the following:

 

Ÿ   Non-contact effects of the engineering works, such as vibration from pneumatic drills which could cause damage, such as foundation or wall cracks and loosening of tiles or fixtures; and

Ÿ   Contact between the historic structures and equipment and materials associated with the engineering works.

 

6.1.2                 Specifically, the monitoring programme will entail the following tasks:

 

Ÿ   The extent of the agreed works areas should be regularly checked during the construction phase to ensure the buffer is being maintained; and

Ÿ   Ensure no stockpiling or equipment storage is affecting the structure.

 

6.1.3                 In the event of non-compliance the responsibilities of the relevant parties is detailed in the Event/ Action Plan in Appendix E.

 

6.2                          Grave Inspection

6.2.1                 In this Reporting Period, there are total 322 occasions to carry out the Grave G1 inspection.  During site inspection, buffer zone was observed between the working area and the Grave and no construction material or equipment was stored nearby the Grave throughout the construction period.

 

 

 


 

7                             LandscAPe and Visual

7.1                          General

7.1.1                 According to EM&A Manual requirements, monitoring of Contractor¡¦s operations during construction period to report on Contractor¡¦s compliance should be carried out on weekly basis.  Measure to mitigate landscape and visual impact during construction should be checked and monitored by a Registered Landscape Architect to ensure compliance with the intended aims of the mitigation measures.  Moreover, the progress of the engineering works shall be regularly reviewed on site to identify the earliest practical opportunities for the landscape works to be undertaken.

 

7.2                          Landscape and Visual Inspection (Construction Phase)

7.2.1                 In this Reporting Period, Registered Landscape Architect with the Contractor had undertaken a total of 291 occasions of inspection during construction phase.

 

7.2.2                 During the Reporting Period, existing trees on boundary of the project area were properly protected and no damage of the existing trees were record in this Reporting Period. Felled trees during construction were collected by a licensed collector for recycling.  The detailed inspection checklists can be referred to relevant Monthly EM&A Reports of the Contract.

 

7.2.3                 According to the approved planting plan, most of the planting works under the contract were completed and the substantial completion certificate had been issued by RE. Therefore, the establishment period monitoring for planting works was commenced on 1 June 2020 under the EM&A manual requirement.  The detailed inspection checklists can be referred to relevant Monthly EM&A Reports of the Contract.

 

7.3                          Establishment Works Inspection

7.3.1                 According to EM&A Manual requirements, monitoring of the planting works during the 24-month Establishment period after completion of the construction works should be carried out. Establishment Works Inspection should be carried out once every 3 months to make sure the establishment planting works is complied with EMIS requirement.

 

 

 


 

8                             Landfill Gas Hazard Monitoring

8.1                          General

8.1.1                 During EIA study, landfill gas hazards are likely to be generated from the Pillar Point Valley (PPV) Landfill. Hence, regular landfill gas monitoring is recommended during construction of the proposed toll plaza.

 

8.1.2                 During construction, a Safety Officer should be appointed to carry out the monitoring works. The monitoring frequency and areas to be monitored should be set down prior to commencement of ground-works either by the Safety Officer or an approved and appropriated qualified person. The routine monitoring should be carried out in all excavations, manholes, chambers, relocation of monitoring wells and any other confined spaces that may have been created. All measurements in excavations should be made with the extended monitoring tube located not more than 10 mm from the exposed ground surface. Monitoring should be performed properly to make sure that the area is free of landfill gas before any man enters in the area.

 

8.1.3                 For excavations deeper than 1m, measurements should be carried out:

Ÿ   at the ground surface before excavation commences;

Ÿ   immediately before any worker enters the excavation;

Ÿ   at the beginning of each working day for the entire period the excavation remains open; and

Ÿ   periodically through the working day whilst workers are in the excavation.

 

8.1.4                 For excavations between 300mm and 1m deep, measurements should be carried out:

Ÿ   directly after the excavation has been completed; and

Ÿ   periodically whilst the excavation remains open

 

8.1.5                 For excavations less than 300mm deep, monitoring may be omitted, at the discretion of the Safety Officer or other appropriately qualified person.

 

8.1.6                 To ensure the accuracy of the monitoring data, zeroing of the gas analyser shall be undertaken at the start of each day¡¦s monitoring.  As part of the QA/QC, calibration of the gas analyser shall be conducted at least once every two weeks according to the specification of the manufacturer¡¦s operation manual.

 

8.1.7                 The landfill consultation zone was divided into 6 monitoring zones. The landfill gas monitoring zones are summarized in Table 8-1 and the layout plan for the monitoring zone is illustrated in Appendix D.

Table 8-1      Landfill Gas Monitoring Zone

ID

Location

TD1

TD1, Retaining Wall A, Grave G1 and Subway

RW-B

Retaining Wall B

RW-F

Retaining Wall F

S&U

Slope and Underpass

BW

Bridge Works (G2, H1)

LMR

Lung Mun Road

 

 


 

8.2                          Landfill Gas Monitoring Result

8.2.1                 In the Reporting Period, total 1,403 monitoring days carried out by the Safety Officer or an approved and qualified persons.  Landfill gas measurement results throughout the construction period are summarized in Table 8-2.  Moreover, graphical plot are attached in Appendix F.

Table 8-2      Summary of Landfill Gas Measurement Results

Para.

Action Level

Limit Level

In Period

Retaining Wall B

In Period

Retaining Wall F

Min

Max

Min

Max

Methane

>10% LEL (>0.5% v/v)

>20% LEL (>1% v/v)

Nov 2014 to Sep 2016

0%

0.2%

Nov 2014 to Sep 2016

0%

0.2%

 

TD1

 

LMR

Min

Max

Min

Max

Oct 2016 to Oct 2018

0.1%

0.1%

Oct 2016 to Oct 2019

0.1%

0.1%

Oxygen

<19%

<18%

 

Retaining Wall B

 

Retaining Wall F

Min

Max

Min

Max

Nov 2014 to Sep 2016

20.9%

21.4%

Nov 2014 to Sep 2016

21.0%

21.3%

 

TD1

 

LMR

Min

Max

Min

Max

Oct 2016 to Oct 2018

19.2%

21.1%

Oct 2016 to Oct 2019

20.1%

21.1%

Carbon Dioxide

>0.5%

>1.5%

 

Retaining Wall B

 

Retaining Wall F

Min

Max

Min

Max

Nov 2014 to Sep 2016

0%

0.3%

Nov 2014 to Sep 2016

0%

0.3%

 

TD1

 

LMR

Min

Max

Min

Max

Oct 2016 to Oct 2018

0.1%

0.2%

Oct 2016 to Oct 2019

0.1%

0.2%

 

8.2.2                 Landfill gas monitoring at TD1 was temporary suspended in the period from 7 June 2018 to 10 July 2018 and LMR from 22 July 2017 to 2 April 2018 and 1 June 2019 to 30 June 2019 due to no excavation work were undertaken at those area.

 

8.2.3                 The measurement results shown that no monitoring parameter was trigger to the action / limit level throughout the construction period.


 

9                             Waste Management

9.1                          General Waste Management

9.1.1                 Waste management was carried out by an on-site Environmental Officer or an Environmental Supervisor from time to time. The effective management of waste arising during the construction phase will be monitored through the site audit programme. The aims of the waste audit are:

l  to ensure the waste arising from the works are handled, stored, collected, transferred and disposed of in an environmentally acceptable manner; and

l  to encourage the reuse and recycling of material.

 

9.1.2                 In addition to the site inspections, the ET shall review the documentation procedures prepared by the Waste Coordinator once a week to ensure proper records are being maintained and procedures undertaken in accordance with the Waste Management Plan.

 

9.2                          Records of Waste Quantities

9.2.1                 All types of waste arising from the construction work are classified into the following:

l  Construction & Demolition (C&D) Material;

l  Chemical Waste;

l  General Refuse; and

l  Excavated Soil.

 

9.2.2                 In the reporting periods, total quantities of waste disposal are summarized in Tables 9-1, 9-2 and the Waste Flow Table is presented in Appendix G.

Table 9-1      Summary of Quantities of Inert C&D Materials

Type of Waste

Quantity

Total

Disposal Location

Nov 14 ¡V Oct 15

Nov 15 ¡V Oct 16

Nov 16 ¡V Oct 17

Nov 17 ¡V Oct 18

Nov 18 ¡V Oct 19

Nov 19 ¡V Oct 20

Nov 20 ¡V Dec 20

Reused in this Contract (Inert) (`000m3)

158.692

121.699

30.492

2.201

0

0

0

313.084

-

Reused in other Projects (Inert) (`000m3)

161.308

125.501

81.074

4.770

0

0

0

372.653

    TM-CLKL C2 HY/2012/08

    Lam Tei Quarry

    Eco Park K.wah Recycle Facilities

    Lung Kwu Tan Tailor Recycled Aggregates

    Laintang BCP

Disposal as Public Fill (Inert) (`000m3)

159.021

7.618

15.508

29.501

26.861

11.985

0.662

251.156

Tuen Mum Area 38

 


 

Table 9-2      Summary of Quantities of C&D Wastes

Type of Waste

Quantity

Total

Disposal Location

Nov 14 ¡V Oct 15

Nov 15 ¡V Oct 16

Nov 16 ¡V Oct 17

Nov 17 ¡V Oct 18

Nov 18 ¡V Oct 19

Nov 19 ¡V Oct 20

Nov 20 ¡V Dec 20

Recycled Metal (`000kg)

0

0

0

0

0

0

0

0

-

Recycled Paper / Cardboard Packing (`000kg)

0.05

0.07

0

0

0

0

0

0.12

Recycle Collector

Recycled Plastic (`000kg)

0

0

0

0

0

0

0

0

-

Chemical Wastes (`000kg)

0

0

0.030

0.080

0

0

0

0.11

Licensed collector

General Refuses (`000m3)

0.374

1.250

2.267

3.259

2.598

1.291

0.115

11.154

WENT

 

9.2.3                 To control the site performance on waste management, the Contractor was ensured that all solid and liquid waste management works are fully in compliance with the relevant license/permit requirements, such as the effluent discharge license and the chemical waste producer registration.  The Contractor was also implemented the recommended environmental mitigation measures according to the Environmental Monitoring and Audit Manual.

 


 

10                         Inspection and Auditing

10.1                      Site Inspection

10.1.1             According to the approved EM&A Manual, the environmental site inspection shall be formulation by ET Leader.  Weekly environmental site inspections should carry out to confirm the environmental performance.

 

Findings / Deficiencies During Reporting Period

10.1.2             During the reporting period, total 322 events of joint site inspection to evaluate site environmental performance has been carried out by the RE, ET and the Contractor.  Moreover, IEC or ENPO attended total 84 occasion¡¦s joint site inspection.  

 

10.1.3             During the reporting period, there are no non-compliance recorded, however, 581 observations/ reminders were recorded during the site inspections.  The minor deficiencies found in the weekly site inspections were in general rectified within the specified deadlines.  The environmental performance of the Project was therefore considered satisfactory.

 

Inspection Checklist for Vulnerable to Contaminated Water Discharge

10.1.4             Following the complaint about discharge of milky water to Bufferfuly Beach on 2 September 2015, the Contractor proposed to carry out inspection of wastewater treatment facilities, concerned discharge points, drainage inlets and outlets daily during typhoon or wet season and once per week at dry season. 

 

10.1.5             In addition, specific inspections would also be conducted before and after adverse weather to ensure necessary remedial works would be carried out timely. Should incidental contaminated water discharge be found at the inlet of the associated drainage system, a specific inspection of the relevant drainage pipes would be conducted for traces of deposit, and follow up actions would be taken when necessary.

 

10.1.6             Following the EPD¡¦s site inspection on 22 February 2019, the contractor was advised to carry on the temporary drainage inspection until the completion of the construction of permanent drainage system. As the permanent drainage system was fully commissioned in July 2019, the temporary drainage inspection has been terminated since then.


 

11                         Environmental Complaint and Non-compliance

11.1                      Environmental Complaint, Summons and Prosecution

11.1.1             For the Contract, no environmental summons and prosecution was received throughout the construction period.  However, there are 117 exceedances of action / limit levels recorded and 11 complaints received during the Construction Period.  The statistical summary table of environmental exceedance, complaint, summons and prosecution is presented in Tables 11-1, 11-2, 11-3 and 11-4.

Table 11-1    Statistical Summary of Environmental Exceedance

Reporting Period

Environmental Aspect

Exceedance Statistics

Action

Limit

23 October 2014 ¡V

31 December 2020

Air Quality

1-hour TSP

94

13

24-hour TSP

7

3

Landfill Gas

Methane

0

0

Oxygen

0

0

Carbon Dioxide

0

0

Table 11-2    Statistical Summary of Environmental Complaints

Reporting Period

Complaint Nature*

Total Registered

Water Quality

Construction Dust

Construction Noise

Others

23 October 2014 ¡V

31 December 2020

6

4

1

2

11

         *Remarks: Some complaint related to more than one nature

 

Table 11-3    Statistical Summary of Environmental Summons

Reporting Period

Environmental Summons Statistics

Cumulative

Complaint Nature

Air

Noise

Water

23 October 2014 ¡V

31 December 2020

0

NA

NA

NA

 

Table 11-4    Statistical Summary of Environmental Prosecution

Reporting Period

Environmental Prosecution Statistics

Cumulative

Complaint Nature

Air

Noise

Water

23 October 2014 ¡V

31 December 2020

0

NA

NA

NA

 

11.2                      Summary record of all complaints, action and working procedures

11.2.1             During the complaint investigation work, the Contractor was co-operated with the ET in providing all the necessary information and assistance for completion of the investigation. Investigation reports for the complaints have completed by the ET and submitted to all relevant parties and they are summarized in below.

 

l   28 July 2015 - A complaint was received from the DSD on 28 July 2015. The complainant complained that milky water was observed from drainage outlet to Butterfly Beach. It was suspected that the milky water was come from the site under the Contractor. Joint inspection has been carried out by DSD, AECOM and CKJV immediately receipt the complaint and no milky/ muddy water was found. Moreover, EPD was conducted site inspection with AECOM and CKJV on 29 July 2015 to further investigation. No milky/ muddy water was observed during the inspection. However, EPD urged CKJV to enhance the mitigation measures for wastewater at Eastern Portal and MH7

 

l   3 August 2015 - A complaint was received via 1823 hotline on 3 August 2015.  The complainant complained that the frequent dump trucks running along Lung Mun Road from Tuen Mun Area 38 Fill Bank and carriageway near River Trade Terminal causing soil/ muddy water on the road surface. In our investigation, it was concluded that the complaint was not related to the works under the Contract.

 

l   2 September 2015 - A complaint was received from the LCSD on 2 September 2015 regarding milky water discharged from the drainage outlet near the Butterfly Beach, Tuen Mun.  It was suspected that the milky water was come from the site under the Contract. . In our investigation, it was concluded that the complaint was not related to the works under the Contract.

 

l   28 April 2016 - A complaint was received from the EPD on 28 April 2016.  The complainant complained that dust and smoke emission from a drilling rig was observed on the slope near Pillar Point, Tuen Mun.  It was suspected that the heavy dust was generated from the construction activities under the Contractor.

 

l   9 May 2016 - A complaint was received from the EPD on 9 May 2016.  The complainant complained that white color effluent discharging outfall behind sawmill at Ho Yeung Street, Tuen Mun.  It cannot confirm the source of the white color effluent therefore it considered that the above complaint is not related to the project.

 

l   7 June 2016 - A complaint was received from the EPD on 7 June 2016.  The complainant complained that white color effluent discharging outfall at storm outfall of No.33 Ho Yeung Street, Tuen Mun at around 18:00 and this is a follow up of the complaint EP/RW/0000368066 which received on 9 May 2016 and defecated as not project related complain. EPD visit the upstream area and open the cover of manhole at Ho Fuk Street on 21 June 2016. No water discharge was observed and the manhole was clean and dry in condition. During the joint investigation and inspection by EPD, Aecom and the Contractor, it was found that the white water might came from other facilities or site located at Ho Yeung Street which is not related to this project.

 

l   3 October 2016 - A complaint was received via EPD hotline on 3 October 2016, claimed that muddy water entering the drainage system near site entrance-Hand-key attendance system Pillar Point, Tuen Mun at around 03:00 to 04:00 after the rainstorm. Refer to tele-conversation with EPD and Contractor, the complaint was actually mentioning the muddy water entering the drainage system was occurred on 1 October 2016 03:00 to 04:00 at the bus station nearby the site entrance. According to the site record, the works carried out during the concerned time period was maintenance works of TTA include maintenances of flashlight, water barrier and road marking, there is no ponding water was observed nearby the concerned locations. Also during the weekly site inspection on 4 October 2016, no water discharged from site and ponding at the bus station nearby the site entrance was observed. Earth bund was also provided at the slope near the site entrance to divert the surface run-off to the de-silting system. Moreover, the record from the Hong Kong Observatory also stated there was no rainfall recorded at Tuen Mun between 30 September 2016 and 1 October 2016 04:45 a.m. Therefore for the above result, it is considered that the above complaint is not related to the project.

 

l   29 September 2017 - A complaint was received from the EPD on 29 September 2017.  The complainant complained that no water spraying for road works to cause construction dust emission at Lung Mun Road across from warehouse near Tuen Mun River Trade Terminal. After the investigation it was concluded that the complaint was project related, the improvement works for dust mitigation had been completed by contractor. The detailed investigation report can be referred to the Monthly EM&A Reports (October 2017) of the contract.

 

l   25 October 2017 - A complaint was received from the EPD on 24 October 2017 by District Councillor Mr. YAN Siu-nam.  The District Councillor represents the resident who living at Tuen Mun Ferry Pier area to complain that light nuisance created by Tuen Mun - Chek Lap Kok Link Project during mid-night to cause serious impact for their rest. Also, the complainant query the schedule for the construction works and the mitigation measures to avoid light nuisance affect to the resident. After the investigation it was concluded that the complaint was not project related. The detailed investigation report can be referred to the Monthly EM&A Reports (November 2017) of the contract.

 

l   30 January 2018 - A complaint was received from the EPD on 30 January 2018 to complaint that ¡§±ß¤W12ÂI©Î­â±á3ÂI¦Ü5ÂI¡AÂI¸Ñ¤ºªe½XÀYÁÙ¦³¤uµ{­n°µ¡A¤£¬O±ß¤W11ÂI«eÀ³¸Ó¤£¥iµo¥X¾¸­µ¶Ü¡H¦Ó¥B¥i¥HµL­­µo¥ú¡A¤w¸g¬O­â±á¤F¦³³o»Ý­n¶Ü? ¤w¸g¬O­â±á¤F¡A¬°¦ó¶}着Ëݦh¤j¥ú¿O¡H¦Ü©ó¦b¤éÀYÆ[¹î¡A¬°¦ó¤ºªe½XÀY¤Î´ä¯]¿D¤j¾ô¤uµ{¡A¤£¬OÀ³¸Ó§â¨F¥ÛÅx¤ôÁקKªÅ®ð¦Ã¬V¶Ü¡H¬°¦ó¨S¦³¨Ìµ{§ÇÅx¤ô¡A¥O¨F¹ÐÄƨì¤Ùªù½XÀY¡HÁÙ®e¤@²î²î¨F¥ÛÄÆ´­¡H¤Ùªù½XÀYªÅ®ð¦Ã¬V«ü¼Æ¬Æ°ª¡A³o´N¬O­ì¦].¡¨. After the investigation it was concluded that the complaint was project related, the improvement works for dust mitigation had been completed by contractor. The detailed investigation report can be referred to the Monthly EM&A Reports (January 2018) of the contract.

 

l   22 May 2019 - A complaint was received on 22 May 2019 to complaint that ¡§§ë¶D¦a½Lªº¤j¹Ð´þÂZ¡A¦a½L¦ì¸m¦b¤Ùªù¤ºªe½XÀY¤Î¯]¦¿­Ü®ÇÃä¡A¥¿¦b¿³«Ø¤@±ø¥Ñ¤Ùªù³q©¹¾÷³õªºÀG¹D¡A·Ð½Ð¸ò¶i¤Î¦^ÂС¨. After the investigation it was concluded that the complaint was not project related. The detailed investigation report can be referred to the Monthly EM&A Reports (May 2019) of the contract.

 


 

12                         Implementation Status of Mitigation Measures

12.1                      General Requirements

12.1.1             The environmental mitigation measures that recommended in the Environmental Mitigation Measures Implementation Schedule (EMMIS) in the Project EM&A Manual covered the issues of Air Quality, Cultural Heritage, Ecology, Landfill Gas Hazard, Landscape & Visual, Noise, Water and Waste and they are presented in Appendix H.

 

12.1.2             During the construction period, environmental mitigation measures generally implemented by the Contract are listed in Table 12-1.

Table 12-1    Environmental Mitigation Measures

Issues

Environmental Mitigation Measures

Air Quality

¡P       Maintain damp / wet surface on access road

¡P       Keep slow speed in the sites

¡P       All vehicles must use wheel washing facility before off site

¡P       Sprayed water during rock breaking works

¡P       During transportation by truck, materials loaded lower than the side and tail boards, and covered before transport

¡P       Compacted all soil stockpiles

¡P       Part of the exposed slopes covered geotextile net

Cultural Heritage

¡P       Set a buffer zone between the working area and the Grave

¡P       All construction materials and equipment store far from the Grave

¡P       Inspection the Grave to ensure provision mitigation measures effective

Ecology

¡P       Wire fencing provided for temporary protect Pitcher Plants

¡P       Undertake weekly inspection of Pitcher Plants

Landfill Gas Hazard

¡P       Landfill Gas measurement undertake during trench excavation

Water Quality

¡P       Temporary drainage system provide for surface runoff prevent discharge to public area

¡P       Wastewater to be treated by sedimentation tank before discharge.

Noise

¡P       No operation of powered mechanical equipment is allowed during restricted hours from 19:00 to 07:00 on the following day and whole day during Sunday and public holiday without construction noise permit (CNP)

¡P       Keep good maintenance of plants

¡P       The noisy plants or works provide mobile noise barriers

¡P       Shut down the plants when not in use

Waste and Chemical Management

¡P       On-site sorting prior to disposal

¡P       Follow requirements and procedures of the ¡§Trip-ticket System¡¨

¡P       Predict required quantity of concrete accurately

¡P       Collect the unused fresh concrete at designated locations in the sites for subsequent disposal

General

¡P       The site was generally kept tidy and clean.

 

 


13                         Conclusions and Recommendations

13.1                      Conclusions

13.1.1             This is Final EM&A Report summarized the monitoring results and inspection findings for the Reporting Period from 23 October 2014 to 31 December 2020.

 

13.1.2             The construction phase EM&A programme for the Contract commenced on 23 October 2014 and was terminated since 31 December 2020.

 

13.1.3             No environmental notifications of summons or successful prosecution were received during the Reporting Period.

 

13.1.4             The construction phase monitoring programme ensured that any environmental impact to the receivers would be readily detected and timely actions could be taken to rectify any non-compliance.  Assessment and analysis of monitoring results collected demonstrated the environmental acceptability of the Project.  The regular site inspection and waste audit ensured that all the mitigation measures on waste management were effectively implemented.

 

13.1.5             The EM&A programme effectively monitored the environmental impacts from the construction phase of the Project and no particular recommendation was advised for the improvement of the programme.

 

13.1.6             It is considered that the environmental acceptability of the Contract during the construction phase was satisfactory and acceptable. In general, the monitoring results were in line with EIA predictions.