Executive Summary
1.1 Background
1.2 Scope of Report
1.3 Organization Structure
1.4 Summary of Construction Works
2.1 Air quality
2.2 EM&A Site Inspection
2.3 Waste Management Status
2.4 Environmental Licenses and
Permits
2.5 Implementation Status of
Environmental Mitigation Measures
2.6 Summary of Exceedances of the
Environmental Quality Performance Limit
2.7 Summary of Complaints,
Notification of Summons and Successful Prosecutions
3.1 Construction Activities for
the Coming Month
3.2 Key Issues for the Coming
Month
4 Conclusions and recommendations
4.1 Conclusions
List of Appendices
Appendix A Project Organization for Environmental Works
Appendix B Construction
Programmes
Appendix C Implementation
Schedule of Environmental Mitigation Measures (EMIS)
Appendix D Summary
of Action and Limit Levels
Appendix E Event
Action Plan
Appendix F Monthly
Summary of Waste Flow Table
Under Contract
No. HY/2017/10, Gammon Construction Limited (GCL) is commissioned by the
Highways Department (HyD) to undertake Northern Connection Tunnel Buildings,
Electrical and Mechanical Works of the Tuen Mun – Chek Lap Kok Link Project (TM-CLK
Link Project) while AECOM Asia Company Limited was appointed by HyD as the
Engineer. For implementation of the
environmental monitoring and audit (EM&A) programme under the Contract, ERM-Hong
Kong, Limited (ERM) has been appointed as the Environmental Team (ET) in
accordance with Environmental Permit No.
EP-354/2009/A. Ramboll Hong Kong Ltd. was employed by HyD as
the Independent Environmental Checker (IEC) and Environmental Project Office
(ENPO). Subsequent
applications for variation of environmental permits (VEP), EP-354/2009/B, EP-354/2009/C and
EP-354/2009/D, were granted on 28
January 2014, 10 December 2014 and 13 March 2015, respectively.
The construction phase of the Project commenced on 7
June 2018 and will tentatively be completed by 2021. The impact monitoring of the EM&A
programme, including air quality and environmental site inspections, were commenced
on 7 June 2018.
This is the Second Monthly EM&A report presenting
the EM&A works carried out during the period from 1 to 31 July 2018 for the
Contract No. HY/2017/10 Northern Connection Tunnel
Buildings, Electrical and Mechanical Works
(the “Project”) in accordance with the Updated EM&A Manual of the
TM-CLK Link Project. As informed by the Contractor, major
activities in the reporting period included:
Land-based Works
·
Bar bending and timber formwork at Toll Control
Building and Ventilation Plant Room;
·
ER’s and the Contractor’s site offices erection at
WA18; and
·
Additional land ground investigation (GI) at
Administration Building, trial pits and laboratory testing.
A summary of monitoring and audit activities conducted
in the reporting period is listed below:
24-hour TSP Monitoring 10
sessions
1-hour TSP Monitoring 10
sessions
Joint Environmental Site Inspection 4 sessions
Summary of Breaches of Action/Limit Levels
Breaches of
Action and Limit Levels for Air Quality
No exceedance of 1-hour and 24-hour TSP was recorded in
this reporting month.
Environmental Complaints, Non-compliance & Summons
There was no environmental complaint, notification of
summons or successful prosecution recorded in the reporting period.
Reporting Change
There was no reporting change in the reporting period.
Upcoming Works for the Next Reporting Month
Works to be undertaken in the next monitoring period of
August 2018 include the following:
Land-based Works
·
Bar bending, timber formwork and concreting at Toll
Control Building;
·
Architectual, Builder’s Work and Finishing at Ventilation
Plant Room;
·
ER’s and the Contractor’s site offices erection at
WA18; and
·
Socket H-pilling at Administration Building.
·
Additional land ground investigation (GI) at
Maintainence Depot, trial pits and laboratory testing.
Future Key
Issues
Potential environmental impacts arising from the above
upcoming construction activities in the next reporting month of August 2018 are
mainly associated with dust and waste management issues.
According to the findings of the Northwest New
Territories (NWNT) Traffic and Infrastructure Review conducted by the Transport
Department, Tuen Mun Road, Ting Kau Bridge, Lantau Link and North Lantau
Highway would be operating beyond capacity after 2016. This forecast has been based on the estimated
increase in cross boundary traffic, developments in the Northwest New Territories
(NWNT), and possible developments in North Lantau, including the Airport
developments, the Lantau Logistics Park (LLP) and the Hong Kong – Zhuhai –
Macao Bridge (HZMB). In order to cope
with the anticipated traffic demand, two new road sections between NWNT and
North Lantau – Tuen Mun – Chek Lap Kok Link (TM-CLKL) and Tuen Mun Western
Bypass (TMWB) are proposed.
An Environmental Impact Assessment (EIA) of TM-CLKL (the
Project) was prepared in accordance with the EIA Study Brief (No. ESB-175/2007)
and the Technical Memorandum of the
Environmental Impact Assessment Process (EIAO-TM). The EIA Report was
submitted under the Environmental Impact Assessment Ordinance (EIAO) in August
2009. Subsequent to the approval of the
EIA Report (EIAO Register Number AEIAR-146/2009), an Environmental Permit
(EP-354/2009) for TM-CLKL was granted by the Director of Environmental
Protection (DEP) on 4 November 2009, and EP variation (VEP) (EP-354/2009/A) was
issued on 8 December 2010. Subsequent
applications for variation of environmental permits (VEPs), EP-354/2009/B, EP-354/2009/C and EP-354/2009/D, were granted on 28
January 2014, 10 December 2014 and 13 March 2015, respectively.
Under Contract
No. HY/2017/10, Gammon Construction Limited (GCL) is commissioned by the Highways
Department (HyD) to undertake the Northern Connection Tunnel Buildings,
Electrical and Mechanical Works of TM-CLKL while AECOM Asia
Company Limited was appointed by HyD as the Engineer. For implementation of the environmental
monitoring and audit (EM&A) programme under the Contract, ERM-Hong Kong,
Limited (ERM) has been appointed as the Environmental Team (ET). Ramboll Hong
Kong Ltd. was employed by HyD as the Independent Environmental Checker (IEC)
and Environmental Project Office (ENPO).
The construction phase of the Contract commenced on 7
June 2018 and will be tentatively completed by 2021. The impact monitoring phase of the EM&A
programme, including air quality and environmental site inspections, commenced
on 7 June 2018.
The general layout plan of the Contract components is
presented in Figures 1.1 & 1.2a to c.
The organization structure of the Contract is shown in
Appendix A. The
key personnel contact names and contact details are summarized in Table 1.1 below.
Table 1.1 Contact Information of Key Personnel
Party |
Position |
Name |
Telephone |
Fax |
HyD (Highways
Department) |
Project
Coordinator |
Joseph Lee |
2762 4958 |
3188 6614 |
|
Senior
Engineer |
Cheng Pan |
2762 3383 |
3188 6614 |
ER (AECOM Asia
Company Limited) |
Principle
Resident Engineer |
S. W. Fok |
2293 6200 |
2293 6300 |
|
Resident
Engineer |
Desmond Fung |
2293 6200 |
2293 6300 |
ENPO / IEC (Ramboll Hong Kong Ltd.) |
ENPO Leader |
Y.H. Hui |
3465
2850 |
3465 2899 |
IEC |
Dr. F.C. Tsang |
3465
2851 |
3465 2899 |
|
Contractor (Gammon
Construction Limited) |
Site Agent |
Kenneth Tai |
9039 4723 |
- |
Environmental
Officer |
Max Poon |
9103 6303 |
- |
|
|
|
|
|
|
ET (ERM-HK) |
ET Leader |
Dr. Jasmine Ng |
2271 3311 |
2723 5660 |
The construction phase of the Contract commenced on 7
June 2018. The three-month rolling
construction programme is shown in Appendix B.
As informed by the Contractor, details of the major
works carried out in this reporting month are listed below:
Land-based Works
·
Bar bending and timber formwork at Toll Control
Building and Ventilation Plant Room;
·
ER’s and the Contractor’s site offices erection at
WA18; and
·
Additional land ground investigation (GI) at
Administration Building, trial pits and laboratory testing.
The
locations of the construction activities are shown in Figure 1.3.
The Environmental Sensitive Receivers in the vicinity of the Project are
shown in Figure 1.4.
Figure 1.3 Locations of Major Construction Activities in the
Reporting Month
|
The EM&A programme required environmental
monitoring for air quality and environmental site inspections for air quality, water
quality and waste management. The
EM&A requirements and related findings for each component are summarized in
the following sections
In accordance with the Updated EM&A Manual and the
Enhanced TSP Monitoring Plan, impact 1-hour TSP monitoring was conducted three
(3) times every six (6) days and impact 24-hour TSP monitoring was carried out once
every six (6) days when the highest dust impact was expected. 1-hr and 24-hr TSP monitoring frequency was
increased to three times per day every three days and daily every three days,
respectively, as excavation works for launching shaft under Contract No. HY/2012/08 Tuen Mun-Chek Lap
Kok Link – Northern Connection Sub-sea Tunnel Section commenced on 24
October 2014.
Results of air quality monitoring were adopted from
the published EM&A data of Contract
No. HY/2012/08 Tuen Mun-Chek Lap Kok Link – Northern Connection Sub-sea Tunnel
Section ([1]).
The locations of the monitoring stations overlapped
with Contract
No. HY/2012/08 are shown in Figure
2.1 and presented in Table
2.1.
Table
2.1 Locations of Impact Air Quality Monitoring Stations and and
its Corresponding Monitoring Requirements
Monitoring Station |
Monitoring Dates |
Location |
Description |
Parameters
& Frequency |
ASR1 |
3,
6, 9, 12, 15, 18, 21, 24, 27 and 30 July 2018 |
Tuen
Mun Fireboat Station |
Office |
TSP monitoring 1-hour Total Suspended Particulates (1-hour TSP, µg/m3), 3
times in every 6 days 24-hour Total Suspended Particulates (24-hour TSP, µg/m3),
daily for 24-hour in every 6 days Enhanced TSP monitoring
(commenced on 24 October 2014 under
Contract No. HY/2012/08) 1-hour Total Suspended Particulates (1-hour TSP, µg/m3), 3
times in every 3 days 24-hour Total Suspended Particulates (24-hour TSP, µg/m3),
daily for 24-hour in every 3 days |
ASR5 |
|
Pillar
Point Fire Station |
Office |
|
AQMS1 |
|
Previous
River Trade Golf |
Bare
ground |
|
ASR6 |
|
Butterfly
Beach Laundry |
Office |
|
ASR10 |
|
Butterfly
Beach Park |
Recreational
uses |
Neither Action nor Limit Levels exceedances was
recorded by the Environmental Team of Contract No. HY/2012/08 during the reporting period. No action is thus required to be undertaken
in accordance with the Event Action Plan presented in Appendix E.
Site inspections were carried out on a weekly basis to
monitor the implementation of proper environmental pollution control and mitigation
measures under the Contract. In the
reporting month, four (4) site inspections were carried out on 6, 13, 20 and 27
July 2018.
Key observations and recommendations during the site
inspections in this reporting period are summarized in Table 2.7.
Table 2.2 Specific Observations and Recommendations during the Weekly
Site Inspection in this Reporting Month
Inspection Date |
Observations |
Recommendations/ Remarks |
6 July 2018 |
Toll
Control Building Chemical
container was observed not placed in drip tray. Good
housekeeping should be maintained. |
Toll
Control Building The
Contractor was reminded to place chemical container in drip tray. The
Contractor was reminded to maintain good housekeeping. |
13
July 2018 |
Ventilation
Plant Room Accumulated
general refuse should be cleared. |
Ventilation
Plant Room The
Contractor was reminded to clear general refuse. |
20
July 2018 |
Ventilation
Plant Room General
refuse should be cleared. |
Ventilation
Plant Room The
Contractor was reminded to clear general refuse. |
27
July 2018 |
Maintenance
Depot NRMM
label should be displayed on piling rig. Toll
Control Building Stagnant
water was observed on the chemical container. Silt
removal should be carried out at the U-channel. |
Maintenance
Depot The
Contractor was reminded to display NRMM label on piling rig. Toll
Control Building The
Contractor was reminded to clear stagnant water on the chemical container. The
Contractor was reminded to install silt removal system at the U-channel. |
The Contractor has rectified all of the observations
as identified during environmental site inspections in the reporting month.
The Contractor had submitted application form for
registration as chemical waste producer under the Contract. Sufficient numbers of receptacles were
available for general refuse collection and sorting.
Wastes generated during this reporting period included
mainly construction wastes (inert and non-inert). Reference has been made to the waste flow
table prepared by the Contractor (Appendix F). The quantities of different types of wastes
are summarized in Table 2.8.
Table 2.3 Quantities of Different Waste Generated in the Reporting
Month
Month/Year |
Inert C&D Materials (a)
(m3) |
Inert Construction Waste Re-used (m3) |
Non-inert Construction Waste (b)
(kg) |
Imported
Fill (m3) |
Recyclable Materials (c) (kg) |
Chemical Wastes (kg) |
|||
|
|||||||||
July 2018 |
830 |
0 |
15,190 |
0 |
0 |
|
0 |
|
|
|
Notes: |
|
|||||||
|
(a) Inert
construction wastes include hard rock and large broken concrete, and
materials disposed as public fill. (b) Non-inert
construction wastes include general refuse disposed at landfill. (c) Recyclable
materials include metals, paper, cardboard, plastics, timber and others. |
|
|||||||
The Contractor was advised to properly maintain on
site C&D materials and waste collection, sorting and recording system,
dispose of C&D materials and wastes at designated ground and maximize reuse/
recycle of C&D materials and wastes.
The Contractor was also reminded to properly maintain the site tidiness
and dispose of the wastes accumulated on site regularly and properly.
For chemical
waste containers, the Contractor was reminded to treat properly and store temporarily
in designated chemical waste storage area on site in accordance with the Code of Practice on the Packaging, Labelling
and Storage of Chemical Wastes.
The status of
environmental licensing and permit is summarized in Table 2.9 below.
Table 2.4 Summary of Environmental Licensing and Permit Status
License/ Permit |
License or Permit No. |
Date of Issue |
Date of Expiry |
License/ Permit Holder |
Remarks |
Environmental
Permit |
EP-354/2009/D |
13
March 2015 |
N/A |
HyD |
Tuen
Mun- Chek Lap Kok Link |
APCO
Construction Dust Notification |
433493 |
14
May 2018 |
N/A |
GCL |
For Tuen Mun working area |
Construction
Waste Billing Account |
7030836 |
15 May 2018 |
N/A |
GCL |
N/A |
Chemical
Waste Producer Registration |
5213-422-G2827-01 |
13 June 2018 |
N/A |
GCL |
N/A |
WPCO
Licence for Buildings at C2 area |
|
|
|
GCL |
Submitted to EPD (Ref:434511, dated 11 June 2018) |
WPCO
Licence for Buildings at C3 area |
GCL |
Submitted to EPD (Ref:435029, dated 26 June 2018) |
|||
Construction
Noise Permit |
GW-RW0262-18 |
9
July 2018 |
9
Jan 2019 |
GCL |
For
Toll Control Building, Administration Building and WA18 |
|
In response to the site audit findings, the
Contractors carried out all corrective actions.
A summary of the Implementation Schedule of
Environmental Mitigation Measures (EMIS) is presented in Appendix C. The
necessary mitigation measures relevant to this Contract were implemented
properly.
No exceedance of 1-hour and 24-hour TSP was recorded in
this reporting month.
Cumulative statistics are provided in Appendix G.
The Environmental Complaint Handling Procedure is provided in Figure 2.2.
There was no environmental complaint, notification of
summons or successful prosecution recorded in the reporting period.
Statistics on complaints, notifications of summons,
successful prosecutions are summarized in Appendix G.
As informed by the Contractor, the major works for the
Project in August 2018 will be:
·
Bar bending, timber formwork and concreting at Toll
Control Building;
·
Architectual, Builder’s Work and Finishing at Ventilation
Plant Room;
·
ER’s and the Contractor’s site offices erection at
WA18; and
·
Socket H-pilling at Administration Building.
·
Additional land ground investigation (GI) at
Maintainence Depot, trial pits and laboratory testing.
Potential environmental impacts arising from the above
upcoming construction activities in the next reporting month of August 2018 are
mainly associated with dust and waste management issues.
This Second Monthly EM&A Report presents
the findings of the EM&A activities undertaken during the period from 1 to 31
July 2018, in accordance with the Updated EM&A Manual and the requirements
of EP-354/2009/D.
Air quality (including 1-hour TSP and 24-hour TSP) was
carried out in this reporting month.
No exceedance of 1-hour and 24-hour TSP was recorded in
this reporting month.
Environmental site inspection was carried out four (4)
times in July 2018. Remedial
actions recommended for the deficiencies identified during the site audits were
properly implemented by the Contractor.
There was no environmental complaint, notification of
summons or successful prosecution recorded in the reporting period.
The ET will keep track on the construction works to
confirm compliance of environmental requirements and the proper implementation
of all necessary mitigation measures.