AUES Job No.: TCS01230/21

 

 

 

 

 

 

 

 

 

Tuen Mun - Chek Lap Kok Link

Contract No. HY/2021/13¡V

Provision of Remaining Compensation Tree Planting for the Tuen Mun ¡V Chek Lap Kok Link Project

 

 

 

 

 

 

 

 

 

 

5th Monthly Environmental Monitoring and Audit (EM&A) Report¡V October 2022

 

 

 

 

 

 

 

 

 

 

Prepared For

Wing Ho Yuen Landscaping Co., Ltd

 

 

 

 

 

 

 

 

 

 

 

 

 

Date

Reference No.

Prepared By

Certified By

17 November 2022

TCS01230/21/600/R0043v1

My signature

Martin Li

(Environmental Consultant)

Ben Tam

 (Environmental Team Leader)

 

Version

Date

Remarks

1

17 November 2022

First Submission

 

 

 

 

 

 

 

 

 


 

 

 

 

 

 

EXECUTIVE SUMMARY

ES01       This is the 5th Monthly EM&A Report presenting the monitoring results and inspection findings for the period from 1 to 31 October 2022 (hereinafter ¡¥the Reporting Period¡¦).

 

Summary of EM&A activities for the Reporting Period

ES02       The EM&A activities conducted in the Reporting Period are summary in below:-

Ÿ     Environmental Site Inspection ¡V 4 events

Ÿ     Landscape & Visual Monitoring ¡V 4 events

 

ES03       According to the approved Landscape and Visual plan, the planting works under the contract was commended on 21 June 2022.

 

Site Inspection

ES04       In the Reporting Period, joint site inspection by the RE, ET and the Contractor was carried out on 7th, 14th, 21st and 28th October 2022 and the IEC has attended the joint site inspection on 28th October 2022.  No non-compliance and observation was recorded during the site inspection.

 

Environmental Complaint

ES05       In the Reporting Period, no environmental complaint was received.

 

ES06       The statistical summary of environmental complaints is summarized in the following table.

Reporting Period

Environmental Complaint Statistics

Frequency

Cumulative

Since the Contract commencement

0

0

October 2022

0

0

 

Notification of Summons and Successful Prosecutions

ES07       No environmental summons or successful prosecutions were recorded in the Reporting Period.

 

Reporting Change

ES08       No reporting changes were made in the Reporting Period.

 

Future Key Issues

ES09       During dry season, air quality mitigation measures such as watering of site area for at least 12 times per day and covering of exposed slopes should be fully implemented to reduce construction dust impact as recommended in the EMIS.

 

ES10       Moreover, muddy water or other water pollutants from site surface runoff into the public areas will be key environment issue.  Special attention should be paid on the water quality mitigation measures to prevent surface runoff flow to public area.

 

ES11       It was reminded that good housekeeping practice should be maintained.  Mosquito control measures should be properly implemented to prevent mosquito breeding on site especially after rain.

 


 

Table of Contents

1     Introduction                                                                                                                     1

1.1            Project Background                                                                                       1

1.2            Report Structure                                                                                             1

2     Contract Organization and Construction progress and Environmental Submissions                                                                                                                          2

2.1            Contract Organization                                                                                 2

2.2            Construction Progress                                                                                 2

2.3            Summary of Environmental Submissions                                               2

3     Summary of Impact Environmental Requirements Under the Contract      3

3.1            General                                                                                                                 3

3.2            Environmental Aspects                                                                                  3

4     LandscAPe and Visual                                                                                                    5

4.1            General                                                                                                                 5

4.2            Landscape and Visual Inspection                                                              5

5     Waste Management                                                                                                         6

5.1            General Waste Management                                                                        6

5.2            Records of Waste Quantities                                                                       6

6     Inspection and Audit                                                                                                      7

6.1            Site Inspection                                                                                                    7

7     Environmental Complaint and Non-compliance                                           8

7.1            Environmental Complaint, Summons and Prosecution                   8

8     Implementation Status of Mitigation Measures                                            9

8.1            General Requirements                                                                                   9

8.2            Tentative Construction Activities in the Coming Month               9

8.3            Key Environmental Issues for the Coming Month                           10

9     Conclusions and Recommendations                                                                   11

9.1            Conclusions                                                                                                      11

9.2            Recommendations                                                                                           11


 

List of TABLES

Table 2-1      Status of Environmental Licenses and Permits of the Contract

Table 4-1      Details of Provision of Remaining Compensation Tree Planting Works Areas

Table 5-1      Summary of Quantities of Inert C&D Materials

Table 5-2      Summary of Quantities of C&D Wastes

Table 6-1      Site Observations for the Contract

Table 6-2      Outstanding Items in Site Inspection of previous Reporting Period

Table 7-1      Statistical Summary of Environmental Complaints

Table 7-2      Statistical Summary of Environmental Summons

Table 7-3      Statistical Summary of Environmental Prosecution

Table 8-1      Environmental Mitigation Measures

 

 

List of Appendices

Appendix A  Project Layout Plan

Appendix B Layout Plan of the Contract

Appendix C  Organization of the Contract

Appendix D Three Months rolling Programme

Appendix E  Layout Plan for the Planting Zone

Appendix F Checklist for Landscape and Visual Monitoring

Appendix G Event and Action Plan

Appendix H Monthly Summary Waste Flow Table

Appendix I Environmental Mitigation and Enhancement Measures Implementation Schedule (EMIS)

Appendix J Cumulative Statistics of Complaint, Summon and Prosecution

Appendix K Investigation Report for the Complaint

 

 


1                    Introduction

1.1                       Project Background

1.1.1                 According to the findings of the Northwest New Territories (NWNT) Traffic and Infrastructure Review conducted by the Transport Department, Tuen Mun Road, Ting Kau Bridge, Lantau Link and North Lantau Highway would be operating beyond capacity after 2016. This forecast has been based on the estimated increase in cross boundary traffic, developments in the Northwest New Territories (NWNT), and possible developments in North Lantau, including the Airport developments, the Lantau Logistics Park (LLP) and the Hong Kong ¡V Zhuhai ¡V Macao Bridge (HZMB). In order to cope with the anticipated traffic demand, two new road sections between NWNT and North Lantau ¡V Tuen Mun ¡V Chek Lap Kok Link (TM-CLKL) and Tuen Mun Western Bypass (TMWB) are proposed.

 

1.1.2                 According to the requirements of the EIA Report, the TM-CLKL Project shall carry out landscape softworks including planting of 6300 trees within the project limits, amongst others. On completion of the planting works by the three other contracts, 5353 trees were accommodated within the project limits. The Landscape and Visual Plan (LVP) later prepared for this Project recommended the compensatory planting of remaining trees at locations outside the limits of the TM-CLKL Project.

 

1.1.3                 Wing Ho Yuen Landscaping Co., Ltd (hereafter ¡§WHY¡¨) is commissioned by the Highways Department (HyD) as the Main Contractor of the Contract No. HY/2021/13 ¡VProvision of Remaining Compensation Tree Planting for the Tuen Mun ¡V Chek Lap Kok Link Project ((hereafter ¡§the Contract¡¨) and this Contract is part of the Tuen Mun ¡V Chek Lap Kok Link (TM-CLK Link Project).TM-CLK Link Project is a Designated Project under Environmental Permit number EP-354/2009/D issued on 13 March 2015.  The layout Plan of the Project and the Contract are showed in Appendix A and B respectively.

 

1.1.4                 The planting works for the Contract No. HY/2021/13 was commenced on 21 June 2022.

 

1.1.5                 The construction works of the Contract mainly include:-

a.              Provision of Remaining Compensation Tree Planting at Tuen Mun and Lantau Island Area fulfil the quantity of compensation tree stated in the approved EIA Report.

 

1.1.6                 This is 5th monthly EM&A report presenting the inspection findings for period from 1 to 31 October 2022.

 

1.2                       Report Structure

1.2.1                 The Monthly Environmental Monitoring and Audit (EM&A) Report is structured into the following sections:-

Section 1     Introduction

Section 2     Contract Organization and Construction Progress and Environmental Submissions

Section 3     Summary of Environmental Requirements under the Contract

Section 4     Landscape and Visual

Section 5     Waste Management

Section 6     Inspections and Audit

Section 7     Environmental Complaints and Non-Compliance

Section 8     Implementation Status of Mitigation Measures

Section 9     Conclusions and Recommendations


2                    Contract Organization and Construction progress and Environmental Submissions

2.1                       Contract Organization

2.1.1                 The Contract organization and contact details of key personnel are shown in Appendix C. 

 

2.2                       Construction Progress

2.2.1                 In the Reporting Period, the major construction activity conducted under the Contract is summarized in below.  The three-months rolling programme of the Contract is enclosed in Appendix D.

Ÿ   Tree Planting Works at Slope 6SW-A/F25 Tseng Choi Street

Ÿ   Tree Planting Works at Slope 6NW-C/F153 Tuen Fu Road

Ÿ   Tree Planting Works at Slope 9SE-B/F56 Shun Tung Road

Ÿ   Tree Planting Works at Slope 9SE-B/F74 Tat Tung Road

Ÿ   Tree Planting Works at Slope 10NE-C/F6 Magic Road

Ÿ   Tree Planting Works at Slope 10NW-D/F93 Magic Road

 

2.3                       Summary of Environmental Submissions

2.3.1                 The environmental submissions under the EP requirement had been submitted to the EPD and they are listed in below:

Ÿ   Landscape and Visual Plan

Ÿ   Waste Management Plan

 

2.3.2                 Summary of environmental permits, licenses and notifications for the Contract is presented in Table 2-1.

Table 2-1      Status of Environmental Licenses and Permits of the Contract

No.

Type of Permit/ License

Reference/

License No.

Date of Issue

Date of Expiry

1

Air pollution Control (Construction Dust) Regulation

Nil

NA

NA

2

Chemical Waste Producer Registration - Waste Producers Number

Nil

NA

NA

3

Water Pollution Control Ordinance -Variation of Effluent Discharge License

Nil

NA

NA

4

Waste Disposal Regulation - Billing Account for Disposal of Construction Waste

7042684

24 December 2021

Nil


3                    Summary of Impact Environmental Requirements Under the Contract

3.1                       General

3.1.1                 The major construction activities under the Contract are land-based and no marine work will be involved.  In accordance with the Project EM&A Manual requirements, the environmental aspects under the Contract shall be included landscape and visual, site inspection during construction period.  In addition, audit of the contractor¡¦s implementation of the air quality, construction noise and land-based water quality pollution control measures are also required for the Contract.

 

3.1.2                 A summary of construction phase EM&A requirements are presented in the sub-sections below.

 

3.2                       Environmental Aspects

Air

3.2.1                 Considering that the construction activities under the Works Contract shall be a small scale works in a short period of time.  If properly dust mitigation measures are implemented, significant air quality impact generated from construction activities of the Works Contract is not anticipated. Therefore, no monitoring is required for the Contract.

 

3.2.2                 Regular site inspections and audits will be carried out during the construction phase in order to confirm compliance with the regulatory requirements and conformity of the Contractor with regard to air quality control and contract conditions.

 

Noise

3.2.3                 Considering that the construction activities under the Works Contract shall be a small scale works in a short period of time and no PME will be used during the planting works.  If properly noise mitigation measures are implemented, significant noise impact generated from construction activities of the Works Contract is not anticipated. Therefore, no monitoring is required for the Contract.

 

3.2.4                 Regular site inspections and audits will be carried out during the construction phase in order to confirm the construction works under the Contract comply with the regulatory noise requirements.

 

Water Quality

3.2.5                 No marine works will be undertaken under the Contract.  Therefore, no water quality monitoring is required for the construction phase of the Contract.

 

Ecology

3.2.6                 No marine works will be undertaken under the Contract and generated marine ecological impact, no dolphin monitoring is required for the construction phase of the Contract.

 

3.2.7                 According to the scope of works under the Contract, no identified ecology aspect was related to the Contract, therefore no land base ecology monitoring and mitigation measure would be required.

 

Landscape and Visual

3.2.8                 Measures to mitigate landscape and visual impact during construction should be checked and monitored to ensure compliance with the intended aims of the mitigation measures in accordance with the EM&A Manual.

 

Cultural Heritage

3.2.9                 According to the works area under the Contract, no cultural heritage zone is located. Therefore, no specific EM&A requirement for construction phase was identified.

 

Landfill Gas

3.2.10             According to work scope of the Contract, there is no works area lies within the 250m Consultation Zone around the closed Pillar Point Valley Landfill. Therefore, no landfill gas monitoring is required for the Contract.

 

 


 

4                    LandscAPe and Visual

4.1                       General

4.1.1                 According to EM&A Manual requirements, monitoring of Contractor¡¦s operations during construction period to report on Contractor¡¦s compliance should be carried out on weekly basis.  Measure to mitigate landscape and visual impact during construction should be checked and monitored by a Registered Landscape Architect to ensure compliance with the intended aims of the mitigation measures.  Moreover, the progress of the engineering works shall be regularly reviewed on site to identify the earliest practical opportunities for the landscape works to be undertaken.

 

4.2                       Landscape and Visual Inspection

4.2.1                 The planting works under the contract was commenced on 21 June 2022. According to the approved landscape and visual plan, the planting areas under the Contract are summarized in Table 4-1 and the layout plan for the planting zone is illustrated in Appendix E.

 

Table 4-1          Details of Provision of Remaining Compensation Tree Planting Works Areas

Works Area

Location

Proposed Use

Tuen Mun

Portion A1

Slope 6NW-C/F 153

Works area for compensation tree planting

Portion A2

Slope 6SW-A/F 25

Portion A3

Slope 5SE-B/F 89

Slope 5SE-B/F 70

Portion A4

Slope 5SE-D/F 73

Portion A5

Slope 6SW-C/FR 200

Portion A6

Slope 6SW-C/F 233

Slope 6SW-D/FR 279

Portion A7

Slope 6SW-D/FR 320

Lantau

Portion B

Slope 9SE-B/F 35

Slope 9SE-B/F 56

Slope 9SE-B/F 74

Works area for compensation tree planting

Portion C

Slope 10NW-D/F 86

Slope 10NW-D/F 88

Slope 10NW-D/FR 89

Slope 10NW-D/FR 90

Slope 10NW-D/F 93

Slope 10NE-C/F 4

Slope 10NE-C/F 5

Slope 10NE-C/F 6

Works area for compensation tree planting

Portion D

Southern Landfall

No additional tree planting works in this area, respond to maintenance the existing planting area from the Contract HY/2012/07 & HY/2017/10

 

4.2.2                 In the Reporting Period, site inspection for landscape and visual mitigation measures were undertaken on 7th, 14th, 21st and 28th October 2022 by the Registered Landscape Architect. The detailed inspection checklists were provided in Appendix F.

 

4.2.3                 In the event of non-compliance the responsibilities of the relevant parties is detailed in the Event/ Action Plan in Appendix G.


 

5                    Waste Management

5.1                       General Waste Management

5.1.1                 Waste management was carried out by an on-site Environmental Officer or an Environmental Supervisor from time to time. The effective management of waste arising during the construction phase will be monitored through the site audit programme. The aims of the waste audit are:

l  to ensure the waste arising from the works are handled, stored, collected, transferred and disposed of in an environmentally acceptable manner; and

l  to encourage the reuse and recycling of material.

 

5.1.2                 In addition to the site inspections, the ET shall review the documentation procedures prepared by the Waste Coordinator once a week to ensure proper records are being maintained and procedures undertaken in accordance with the Waste Management Plan.

 

5.2                       Records of Waste Quantities

5.2.1                 All types of waste arising from the construction work are classified into the following:

l  Construction & Demolition (C&D) Material;

l  Chemical Waste;

l  General Refuse; and

l  Excavated Soil.

 

5.2.2                 The quantities of wastes generated under the Contract in this Reporting Period are summarized in Tables 5-1 and 5-2 and the Monthly Summary Waste Flow Table is shown in Appendix H.  Whenever possible, materials were reused on-site as far as practicable.

Table 5-1      Summary of Quantities of Inert C&D Materials

Type of Waste

Quantity

Disposal Location

Reused in this Contract (Inert) (`000m3)

0.000

-

Reused in other Projects (Inert) (`000m3)

0.000

-

Disposal as Public Fill (Inert) (`000m3)

0.000

Tuen Mun Area 38

                                                                                                   

Table 5-2      Summary of Quantities of C&D Wastes

Type of Waste

Quantity

Disposal Location

Recycled Metal (`000kg)

0

-

Recycled Paper / Cardboard Packaging (`000kg)

0

-

Recycled Plastic (`000kg)

0

-

Chemical Wastes (`000kg)

0

-

General Refuses (`000m3)

0

-

 

 


 

6                    Inspection and Audit

6.1                       Site Inspection

6.1.1                 According to the approved EM&A Manual, the environmental site inspection shall be formulated by ET Leader on weekly basis to confirm the environmental performance of the construction site.

 

Findings / Deficiencies During Reporting Period

6.1.2                 In the Reporting Period, joint site inspections to evaluate site environmental performance were carried out by the RE, ET and the Contractor on 7th, 14th, 21st and 28th October 2022.  No non-compliance and observation were recorded during site inspection.  Moreover, ENPO/IEC has attended joint site inspection on 28th October 2022.

 

6.1.3                 The findings / deficiencies observed during the weekly site inspection in the Reporting Period are listed in Table 6-1.

Table 6-1      Site Observations for the Contract

Date

Findings / Deficiencies

Follow-Up Status

7 October 2022

Ÿ  Nil

Ÿ  NA

14 October 2022

Ÿ  Nil

Ÿ  NA

21 October 2022

Ÿ  Nil

Ÿ  NA

28 October 2022

Ÿ  Nil

Ÿ  NA

6.1.4                 No outstanding deficiency remained to be rectified in previous Reporting Period which presented in Table 6-2.

 

Table 6-2      Outstanding Items in Site Inspection of previous Reporting Period

Date

Findings / Deficiencies

Follow-Up Status

--

Ÿ  NA

Ÿ  NA

 

6.1.5                 Air quality mitigation measures such as watering of site area for at least 12 times per day and covering of exposed slopes should be implemented during the construciton period to reduce construction dust impact as recommended in the EMIS.

 

6.1.6                 Good site practice for daily housekeeping is reminded. In addition, stagnant water should be removed as soon as possible after rain to prevent mosquito breeding on site.

 

6.1.7                 Moreover, muddy water or other water pollutants from site surface runoff shall not be discharged into public areas.  Water quality mitigation measures to prevent surface runoff into the public areas should be paid on special attention.

 

 

 


7                    Environmental Complaint and Non-compliance

7.1                       Environmental Complaint, Summons and Prosecution

7.1.1                 In the Reporting Period, no environmental complaint, summons and prosecution under the EM&A Programme was lodged. 

 

7.1.2                 The statistical summary table of environmental complaint, summons and prosecution are presented in Tables 7-1, 7-2 and 7-3 and the cumulative statistics of complaint, summons and prosecution are illustrated in Appendix J.

 

Table 7-1      Statistical Summary of Environmental Complaints

Reporting Period

Environmental Complaint Statistics

Frequency

Cumulative

Complaint Nature

Air

Noise

Water

Others

October 2022

0

0

NA

NA

NA

NA

 

Table 7-2      Statistical Summary of Environmental Summons

Reporting Period

Environmental Summons Statistics

Frequency

Cumulative

Complaint Nature

Air

Noise

Water

October 2022

0

0

NA

NA

NA

 

Table 7-3      Statistical Summary of Environmental Prosecution

Reporting Period

Environmental Prosecution Statistics

Frequency

Cumulative

Complaint Nature

Air

Noise

Water

October 2022

0

0

NA

NA

NA

 

7.1.3                 In the Reporting Period, no warning letter related to environmental issue was received from the EPD or HyD.

 

 


 

8                    Implementation Status of Mitigation Measures

8.1                       General Requirements

8.1.1                 The environmental mitigation measures that recommended in the Environmental Mitigation and Enhancement Measures Implementation Schedule (EMIS) for in the Project EM&A Manual covered the issues of air quality, cultural heritage, ecology, landfill gas hazard, landscape & visual, noise, water and waste.  The EMIS for the Contract is shown in Appendix I.

 

8.1.2                 The Contractor shall implement the required environmental mitigation measures according to the EM&A Manual as subject to the site condition. The environmental mitigation measures implemented by the Contractor in this Reporting Period are summarized in Table 8-1 and Appendix I.

 

Table 8-1      Environmental Mitigation Measures

Issues

Environmental Mitigation Measures

Air Quality

¡P       Sprayed water for exposed area

¡P       During transportation by truck, materials loaded lower than the side and tail boards, and covered before transport

¡P       Compacted all soil stockpiles

Water Quality

¡P       Measures should be taken to prevent the washout of construction materials, soil, silt or debris into any drainage system.

¡P       Open stockpiles of construction materials (e.g. planting soil) on site should be covered with tarpaulin or similar fabric during rainstorms.

Noise

¡P       No operation of powered mechanical equipment is allowed during restricted hours from 19:00 to 07:00 on the following day and whole day during Sunday and public holiday without construction noise permit (CNP)

¡P       Keep good maintenance of plants

¡P       Shut down the plants when not in use

Landscape and Visual

¡P       Existing trees on boundary of the Project Area shall be carefully protected during construction.

¡P       Recycle/Reuse all felled trees and vegetation

¡P       Compensatory tree planting shall be provided to the satisfaction of relevant Government departments.

Waste and Chemical Management

¡P       On-site sorting prior to disposal

¡P       Follow requirements and procedures of the ¡§Trip-ticket System¡¨

¡P       Stockpiled material shall be covered by tarpaulin

General

¡P       The site was generally kept tidy and clean.

 

8.2                       Tentative Construction Activities in the Coming Month

8.2.1                 Construction activities as undertaken in the coming month for the Contract lists below:

Ÿ   Tree planting works at Tuen Mun Area.

Ÿ   Tree planting works at Lantau Island Area

 

 


 

8.3                       Key Environmental Issues for the Coming Month

8.3.1                 Key environmental issues to be considered in the coming month include:

Ÿ    Implementation of dust suppression measures at all times;

Ÿ    Potential wastewater quality impact due to surface runoff;

Ÿ    Potential fugitive dust impact due to the dry/loose/exposure soil surface/dusty material;

Ÿ    Ensure dust suppression measures are implemented properly;

Ÿ    Sediment catch-pits and silt removal facilities should be regularly maintained;

Ÿ    Protection of existing tress inside the works area

Ÿ    Follow-up of improvement on general waste management issues; and

Ÿ    Implementation of construction noise preventative control measures

 


9                    Conclusions and Recommendations

9.1                       Conclusions

9.1.1                 This is 5th monthly EM&A report presenting the inspection findings for the period of 1 to 31 October 2022.

 

9.1.2                 The planting works for the Contract No. HY/2021/13 was commenced on 21 June 2022.

 

9.1.3                 In the Reporting Period, no complaint was received by RE, the Contractor, ENPO or HyD. 

 

9.1.4                 No notifications of summons, or successful prosecution were received by the Contractor during the Reporting Period.

 

9.1.5                 In the Reporting Period, joint site inspection by the RE, ET and the Contractor was carried out on 7th, 14th, 21st and 28th October 2022 and the IEC has attended the joint site inspection on 28th October 2022.  No non-compliance and observation was recorded during the site inspection.

 

9.2                       Recommendations

9.2.1                 During dry season, air quality mitigation measures such as watering of site area for at least 12 times per day and covering of exposed slopes should be fully implemented to reduce construction dust impact as recommended in the EMIS.  

 

9.2.2                 Moreover, muddy water or other water pollutants from site surface runoff into the public areas will be key environment issue.  Special attention should be paid on the water quality mitigation measures to prevent surface runoff flow to public area.

 

9.2.3                 Stagnant water should be removed as soon as possible after rain to prevent mosquito breeding on site.