AUES Job No.: TCS01137/20 |
|
|
||
|
|
|
|
|
||
|
|
Tuen Mun - Chek
Lap Kok Link Contract No. HMWSD 2/2020 (HY) ¡V Establishment of Landscape Softworks for the Tuen
Mun - Chek Lap Kok Link |
|
|
||
|
|
|
|
|
||
|
|
18th Monthly Environmental Monitoring and Audit (EM&A) Report¡V September
2022 |
|
|
||
|
|
|
|
|
||
|
|
Prepared
For Hong Kong Landscaping Co., Ltd. |
|
|
||
Date |
Reference No. |
Prepared By |
Certified By |
3 October 2022 |
TCS01137/20/600/R0067v1 |
Martin Li (Environmental Consultant) |
Ben Tam (Environmental
Team Leader) |
Version |
Date |
Remarks |
1 |
3 October 2022 |
First Submission |
|
|
|
|
|
|
|
|
|
EXECUTIVE
SUMMARY
ES01
This is the 18th Monthly
EM&A Report presenting the monitoring results and inspection findings under
the Contract HMWSD 2/2020 (HY) for the period from 1 to 30 September 2022
(hereinafter ¡¥the Reporting Period¡¦).
Summary of EM&A activities for the Reporting Period
ES02
The EM&A activities conducted
in the Reporting Period under this Contract are summary in below:-
Landscape & Visual Monitoring (Establishment
period) ¡V0 events
ES03 The
Establishment Period monitoring once per three months for planting works was
commenced on 1 June 2020 for the planting area under the contract HY/2012/07
& HY/2013/12 and commenced on 1 February 2021 for the planting area under
the contract HY/2017/10 according to the EM&A manual requirement. No
establishment period inspection was conducted by this contract or other
contract under TMCLK Project during this reporting period.
Environmental
Complaint
ES04
In the Reporting Period,
no environmental complaint was received.
ES05
The statistical summary
of environmental complaints is summarized in the following table.
Reporting Period |
Environmental
Complaint Statistics |
|
Frequency |
Cumulative |
|
Since the Contract commencement |
0 |
0 |
September 2022 |
0 |
0 |
Notification of Summons
and Successful Prosecutions
ES06
No environmental summons or successful
prosecutions were recorded in the Reporting Period.
Reporting Change
ES07
No reporting changes were made in the
Reporting Period.
Future Key Issues
ES08 The Project
TM-CLKL had been commissioning at the end of 2020 and the major construction
works under the Project had been completed at the end of March 2021. According to the Project EM&A Manual
requirement, operational phase EM&A works will be undertaken for a period
of two years after the commission of the project
ES09 According
to the Project EM&A Manual requirement, monitoring for the planting works
at a frequency of 3 months interval during the 24-month establishment period is
required to make sure the establishment planting works
is complied with EMIS requirement, and during the 12-month establishment
period, the maintenance operations must be supervised by fully qualified
Landscape Resident Site Staff (Registered Landscape Architect or Professional
Member of the Hong Kong Institute of Landscape Architects). Subsequent to the 12-month establishment
period supervised by the qualified Landscape Resident Site Staff, the
supervision from the 13th to the 24th month would be
continued by other members of the Project.
ES10
According to the
contract arrangement, the establishment
planting area under the Contract HY/2012/07 Zone 1, 3 & 4, the
Contract HY/2013/12 and the Contract HY/2017/10 Zone
1 to 5 were handover to this contract from December 2020, June 2021 and 27 May
2022. For the establishment planting area under the Contract HY/2012/07 Zone
2, it was handed over to the ET of Contact HY/2017/10 until 9 February 2022. Therefore, the establishment planting inspection and maintenance works for the
establishment planting area under the Contract HY/2012/07 Zone 1, 3 & 4, the Contract HY/2013/12 and the Contract HY/2017/10 Zone 1 to 5 responded by this Contract was commenced from December 2020, June 2021 and 27 May 2022.
ES11
After 10 February 2022,
the maintenance for the planting areas HY/2012/07 (zone 2)
and HY/2017/10 (Zone 6) was handed over to another contract HY/2021/13.
ES12
The 24-month
establishment period for the planting area under the Contract HY/2012/07 and
the Contract HY/2013/12 were completed at the end of May 2022. The condition of the planted tree
is satisfaction. Moreover, the species and quantity of tree planted in those
areas are complied with the approved Landscape &Visual Plan.
Table of Contents
1 Introduction 1
1.1 Project Background 1
1.2 Report Structure 1
1.3 Contract Organization 1
2 Summary of Monitoring Requirements Under the Contract 2
2.1 General 2
2.2 Environmental Aspects 2
2.3 Monitoring Schedule 4
3 LandscAPe and Visual 5
3.1 General 5
4 Environmental Complaint and Non-compliance 6
4.1 Environmental Complaint, Summons and
Prosecution 7
5 Conclusions and Recommendations 8
5.1 Conclusions 8
List
of TABLES
Table
2-1 Summary
of Establishment inspection for the Project
Table
3-1 Details
of Establishment Inspection for the Project during the Reporting Period
Table
4-1 Statistical
Summary of Environmental Complaints
Table
4-2 Statistical
Summary of Environmental Summons
Table
4-3 Statistical
Summary of Environmental Prosecution
List of Appendices
Appendix A Project
Layout Plan
Appendix B Layout Plan of the Contract
Appendix C Organization
of the Contract
Appendix D Event
and Action Plan
Appendix E Monitoring
Schedule
Appendix F Checklist for Establishment Works Monitoring
Appendix G Environmental Mitigation and Enhancement
Measures Implementation Schedule (EMIS)
Appendix H Cumulative Statistics on Exceedance and
Complaint
Appendix I Minor
Landscape Modification at Lung Fu Road, Lung Mun Road and in the Vicinity
1.1.1
According to the
findings of the Northwest New Territories (NWNT) Traffic and Infrastructure
Review conducted by the Transport Department, Tuen Mun Road, Ting Kau Bridge, Lantau
Link and North Lantau Highway would be operating beyond capacity after 2016.
This forecast has been based on the estimated increase in cross boundary
traffic, developments in the Northwest New Territories (NWNT), and possible
developments in North Lantau, including the Airport developments, the Lantau
Logistics Park (LLP) and the Hong Kong ¡V Zhuhai ¡V Macao Bridge (HZMB). In order
to cope with the anticipated traffic demand, two new road sections between NWNT
and North Lantau ¡V Tuen Mun
¡V Chek Lap Kok Link
(TM-CLKL) and Tuen Mun
Western Bypass (TMWB) are proposed.
1.1.2
Hong
Kong Landscaping Co., Ltd. (hereafter ¡§HKL¡¨) is
commissioned by the Highways Department (HyD) as the Main Contractor of the Contract No. HMWSD 2/2020 (HY) ¡VEstablishment
of Landscape Softworks for the Tuen
Mun - Chek Lap Kok Link ((hereafter ¡§the Contract¡¨) and this
Contract is part of the Tuen Mun
¡V Chek Lap Kok Link (TM-CLK
Link Project).TM-CLK Link Project is a Designated Project under Environmental
Permit number EP-354/2009/D issued on 13 March 2015. The layout Plan of the Project and the Contract
are showed in Appendix A and B respectively.
1.1.3
The construction works
of the Contract mainly include:-
a.
Maintenance the approx. 33ha planting area of
the Project during the establishment period.
1.1.4
The TM-CLKL had been commissioning at the end
of 2020 and the major construction works under the Project had been completed
at the end of March 2021. According
to the Project EM&A Manual requirement, operational phase EM&A works
will be undertaken for a period of two years after the commission of the
project.
1.1.5
This is 18th monthly
EM&A report under the Contract HMWSD 2/2020 (HY) presenting the monitoring
results and inspection findings for period from 1 to 30 September 2022.
1.2.1
The Monthly Environmental Monitoring and
Audit (EM&A) Report is structured into the following sections:-
Section 1 Introduction
Section 2 Summary of Monitoring
Requirements under the Contract
Section 3 Landscape and Visual
Section 4 Environmental
Complaints and Non-Compliance
Section 5 Conclusions and
Recommendations
1.3.1 The Contract organization and contact details of key personnel are shown in Appendix C.
2.1.1
In accordance with the
Project EM&A Manual requirements, the environmental aspects under the Project
shall be included air quality, ecological, cultural heritage, landscape
and visual, landfill gas and site
inspection.
2.1.2
A summary of EM&A requirements under the
contract are presented in the
sub-sections below. Should non-compliance of the environmental quality
criteria occurs, remedial actions will be triggered according to the Event and
Action Plan which presented in Appendix D.
Air
2.2.1
According to the
Contract nature is maintenance the planting area of the Project during the establishment period in the operational phase.
No specific EM&A requirement for air quality related to the establishment of landscape softworks
was identify.
2.2.2
The scopes of works
under this Contract do not involve any of works listed under Section 4.4.1.1 of
the approved EIA Report. Vehicles travel under this contract was carried out in
paved area. Therefore, fugitive dust emission from the contract would be
limited and no unacceptable air quality impact would be expected. No specific mitigation
measure and monitoring would be required.
Noise
2.2.3
According to the
Contract nature is maintenance the planting area of the Project during the establishment period in the operational phase.
No unacceptable noise impact would be expected from the contract. No
mitigation measure would be required under the approved EIA Report. No specific
EM&A requirement for noise impact related to the establishment of landscape softworks was
identify.
2.2.4
Most of the works under
this contract would be conducted manually, with limited use of PME for delivery
material on site and watering the planting area along the road side. Therefore,
no unacceptable noise impact would be expected. No specific mitigation measure
and monitoring would be required.
Water Quality
2.2.5
According to the
Contract nature is maintenance the planting area of the Project during the establishment period in the operational phase.
No specific EM&A requirement for water quality related to the establishment of landscape softworks
was identify.
2.2.6
All planting area under
this contract area are land-based, no major discharge would be expected from
the establishment planting
maintenance works. Therefore, no direct or indirect impact on marine water
quality would be expected. No specific mitigation measure and monitoring would
be required.
Ecology
2.2.7
According to the
Contract nature is maintenance the planting area of the Project during the
establishment period in the operational phase. No specific EM&A requirement
for ecology related to the establishment of landscape softworks
was identify.
2.2.8
No site clearance and
associated habitat loss would be required under this contract. Moreover, all
planting area under this contract area are land-based,
no direct or indirect impact on the marine ecology would be expected.
Therefore, no specific mitigation measure and monitoring would be required.
Landscape and Visual
2.2.9
Monitoring of the
planting works during the 24-month Establishment period after completion of the
construction works should be carried out. Establishment Works Inspection should
be carried out once every 3 months to make sure the establishment planting works
is complied with EMIS requirement. For the planting area under the Contract HY/2012/07, the first 6-month establishment period inspection and maintenance will
be taken by the original Contract¡¦s ET and the main Contractor under the
contract. For another Contract HY/2013/12 and HY/2017/10, the first
12-month establishment period inspection and maintenance will be taken by the
original Contract¡¦s ET and the main Contractor under the contract. After the
first 6 month or year establishment period, the maintenance and inspection
works will be handover to the contract HMWSD 2/2020 (HY) except the planting area
under the Contract HY/2012/07 Zone 2 and the planting area under the Contract
HY/2017/10 Zone 6. The summary of Establishment inspection for the Project is shown in Table 2-1.
Table 2-1 Summary
of Establishment
inspection for the Project
Contract Area |
Establishment Monitoring Commenced |
Inspection taken under the
contract HMWSD 2/2020 (HY) |
Next Quarter of Establishment
Monitoring |
HY/2012/07 (Zone 1, 3 & 4) |
June 2020 |
December
2020 |
Completed
(Last quarter inspection was taken on 26 May 2022) |
HY/2012/07 (Zone 2) |
June 2020 |
Responded
by Contract HY/2021/13 from 10 February 2022 |
Completed
(Last quarter inspection was taken on 25 April 2022) |
HY/2013/12 |
June 2020 |
June 2021 |
Completed
(Last quarter inspection was taken on 31 May 2022) |
HY/2017/10 (Zone 1-5) |
February 2021 |
27 May
2022 |
August
to October 2022 (7th Quarter) |
HY/2017/10 (Zone 6) |
February 2021 |
Responded
by Contract HY/2021/13 from 10 February 2022 |
August
to October 2022 (7th Quarter) |
Cultural Heritage
2.2.10
According to the
Contract nature is maintenance the planting area of the Project during the
establishment period in the operational phase. No specific EM&A requirement
for cultural heritage related to the establishment of landscape softworks was identify.
2.2.11
No major structural or
civil work would be conducted under this contract. Moreover, all planting area are set back from the cultural heritage zone Grave G1 more
than 10m. Therefore, no cultural heritage impact would be expected under this
contract. No mitigation measure and monitoring would be required.
Landfill
Gas
2.2.12
According to the
Contract nature is maintenance the planting area of the Project during the
establishment period in the operational phase. No specific EM&A requirement
for landfill gas related to the establishment of landscape softworks
was identify.
2.2.13
No major excavation work
would be conducted under this contract. Only minor hand digging works will be
conducted while tree replacement works. Therefore, no landfill gas hazard would
be expected under this contract. No mitigation measure and monitoring would be
required.
Waste Management
2.2.14
According to the
Contract nature is maintenance the planting area of the Project during the
establishment period in the operational phase. No specific EM&A requirement
for Waste Management related to the establishment of landscape softworks was identify.
2.2.15
All planting area under
this contract area are land-based, no dredged sediment, excavated C&D
material, C&D waste, chemical waste and sewage would be generated under
this Contract. Only limited level of dead plant would be generated from works
during maintenance of the planting area and would be easily controlled by
standard waste management practice. No specific mitigation measure would be
required.
Inspection and Audit
2.2.16
According to the
Contract nature is maintenance the planting area of the Project during the
establishment period in the operational phase. No construction works would be
taken under this contract. Moreover, no potential environmental issue had been
identified in the previous sections. No regular site inspections would be
required.
2.3.1
The monitoring schedule
for landscape &visual for the present reporting period is presented in Appendix E.
3.1.1
According to the Project EM&A Manual
requirement, monitoring for the planting works at a frequency of 3 months
interval during the 24-month establishment period is required to make sure the
establishment planting works is complied with EMIS requirement, and during the 12-month establishment
period, the maintenance operations must be supervised by fully qualified
Landscape Resident Site Staff (Registered Landscape Architect or Professional
Member of the Hong Kong Institute of Landscape Architects). Subsequent to the 12-month establishment
period supervised by the qualified Landscape Resident Site Staff, the supervision
from the 13th to the 24th month would be continued by
other members of the Project. The updated EMIS for
the Contract is shown in Appendix G.
3.1.2
According to the
contract arrangement, the establishment planting area under the Contract HY/2012/07 Zone 1, 3 & 4, the Contract HY/2013/12 and the Contract HY/2017/10 Zone 1 to 5 were
handover to this contract from December 2020, June 2021 and 27 May 2022. For the establishment planting area under the
Contract HY/2012/07 Zone 2, it was handed over to the ET of Contact HY/2017/10
until 9 February 2022. Therefore, the establishment
planting inspection and maintenance works for the establishment planting area under the
Contract HY/2012/07 Zone 1, 3 & 4, the Contract HY/2013/12 and the Contract HY/2017/10 Zone 1 to 5 responded by this
Contract was commenced from December 2020, June 2021 and 27 May 2022.
3.1.3
After 10 February 2022,
the maintenance for the planting areas HY/2012/07 (zone 2) and HY/2017/10 (Zone
6) was handed over to another contract HY/2021/13.
3.1.4
All the establishment
inspection method including checklist and zoning plan under this Contract was
follow the methodology prepared by original Contract¡¦s ET which approved by EPD
3.1.5
In the Reporting Period, no site inspection for landscape and visual mitigation
measures under establishment works was conducted by this contract or other contract under
TMCLK Project. The details of Establishment inspection for the Project during the reporting period are shown in Table 3-1 and the Establishment
inspection checklist is shown in Appendix F.
Table 3-1 Details of Establishment Inspection
for the Project during the Reporting Period
Planting Area |
Respond Party |
Quarter of Establishment Monitoring |
Inspection Date |
HY/2012/07 (Zone 1, 3 & 4) |
ET of the Contract HMWSD 2/2020
(HY) |
Nil |
NA |
HY/2012/07 (Zone 2) |
ET of the
Contract HY/2021/13 |
Nil |
NA |
HY/2013/12 |
ET of the Contract HMWSD 2/2020
(HY) |
Nil |
NA |
HY/2017/10 (Zone 1 to 5) |
ET of the Contract HMWSD 2/2020
(HY) |
Nil |
NA |
HY/2017/10 (Zone 6) |
ET of the
Contract HY/2021/13 |
Nil |
NA |
3.1.6
The 24-month
establishment period for the planting area under the Contract HY/2012/07 and
the Contract HY/2013/12 were completed at the
end of May 2022. The last quarter of joint establishment inspection were
summarized in Table 2-1, during the inspection the condition of the planted
tree is satisfaction. Moreover, the species and quantity of tree planted in those
areas are complied with the approved Landscape &Visual Plan.
3.1.7
Further to the TM-CLK ¡V
Northern Connection opened to the public on 27 December 2020, road enhancement
measures at the Lung Fu Road Roundabout were proposed by Transport Department
(TD) and subsequently Leisure and Cultural Services Department (LCSD) reviewed
the site condition at various locations and requested some landscape amendments
for enhancement of safe work condition to be carried out during their routine
maintenance of vegetation. Given that the quantity of tree planting remains
unchanged and the landscape area in the vicinity would not be reduced, EPD reviewed
the information and had no comment on the minor landscape modifications. The
information on the landscape modifications at Lung Fu Road, Lung Mun Road and in the vicinity is shown in Appendix I.
4.1.1
In the Reporting Period, no environmental
complaint, summons and prosecution under the EM&A Programme
was lodged.
4.1.2
The statistical summary table of environmental
complaint, summons and prosecution are presented in Tables 4-1, 4-2 and 4-3.
Table 4-1 Statistical
Summary of Environmental Complaints
Reporting Period |
Environmental Complaint Statistics |
|||||
Frequency |
Cumulative |
Complaint Nature |
||||
Air |
Noise |
Water |
Others |
|||
September
2022 |
0 |
0 |
NA |
NA |
NA |
NA |
Table 4-2 Statistical
Summary of Environmental Summons
Reporting Period |
Environmental Summons Statistics |
||||
Frequency |
Cumulative |
Complaint Nature |
|||
Air |
Noise |
Water |
|||
September
2022 |
0 |
0 |
NA |
NA |
NA |
Table 4-3 Statistical
Summary of Environmental Prosecution
Reporting Period |
Environmental Prosecution Statistics |
||||
Frequency |
Cumulative |
Complaint Nature |
|||
Air |
Noise |
Water |
|||
September
2022 |
0 |
0 |
NA |
NA |
NA |
4.1.3
In the
Reporting Period, no warning letter related to environmental issue was
received from the EPD or HyD.
5.1.1
This is 18th monthly
EM&A report presenting the monitoring results and inspection findings under
the Contract HMWSD 2/2020 (HY) for the period of 1 to 30 September 2022.
5.1.2
There is no air quality, noise, water
quality, ecology, cultural heritage and landfill gas monitoring was required for
the contract.
5.1.1
The Establishment Period
monitoring once per three months for planting works was commenced on 1 June
2020 for the planting area under the contract HY/2012/07 & HY/2013/12 and commenced on 1 February 2021 for the planting area under the contract HY/2017/10 according to the EM&A manual requirement. No establishment
period inspection was conducted by this contract or other contract under TMCLK
Project during this reporting period.
5.1.2
According to the
contract arrangement, the establishment
planting area under the Contract HY/2012/07 Zone 1, 3 & 4, the
Contract HY/2013/12 and the Contract HY/2017/10 Zone
1 to 5 were handover to this contract from December 2020, June 2021 and 27 May
2022. For the establishment planting area under the Contract HY/2012/07 Zone
2, it was handed over to the ET of Contact HY/2017/10 until 9 February 2022. Therefore, the establishment planting inspection and maintenance works for the
establishment planting area under the Contract HY/2012/07 Zone 1, 3 & 4, the Contract HY/2013/12 and the Contract HY/2017/10 Zone 1 to 5 responded by this Contract was commenced from December 2020, June 2021 and 27 May 2022.
5.1.3
After 10 February 2022,
the maintenance for the planting areas HY/2012/07 (zone 2)
and HY/2017/10 (Zone 6) was handed over to another contract HY/2021/13.
5.1.4
The 24-month
establishment period for the planting area under the Contract HY/2012/07 and
the Contract HY/2013/12 were completed at the end of May 2022. The condition of
the planted tree is satisfaction. Moreover, the species and quantity of tree
planted in those areas are complied with the approved Landscape &Visual
Plan.
5.1.5
In the
Reporting Period, no environmental complaint was received.
5.1.6
No notifications of summons, or
successful prosecution were received during the Reporting Period.