AUES Job No.: TCS01137/20

 

 

 

 

 

 

 

 

 

Tuen Mun - Chek Lap Kok Link

Contract No. HMWSD 2/2020 (HY) ¡V

Establishment of Landscape Softworks for the Tuen Mun - Chek Lap Kok Link

 

 

 

 

 

 

 

 

 

 

Final Environmental Monitoring and Audit (EM&A) Report for Establishment Monitoring of Project¡¦s Boundary Area

(June 2020 to January 2023)

 

 

 

 

 

 

 

 

 

 

Prepared For

Hong Kong Landscaping Co., Ltd.

 

 

 

 

 

 

 

 

 

 

 

 

 

Date

Reference No.

Prepared By

Certified By

24 April 2023

TCS01137/20/600/R0091v1

My signature

Martin Li

(Environmental Consultant)

Ben Tam

 (Environmental Team Leader)

 

Version

Date

Remarks

1

24 April 2023

First Submission

 

 

 

 

 

 

 

 

 

 


 

 

 

 

EXECUTIVE SUMMARY

ES01       The TM-CLKL had been commissioning at the end of 2020 and the major construction works under the Project had been completed at the end of March 2021.  According to the Project EM&A Manual requirement, establishment monitoring works will be undertaken for a period of two years after the commission of the project

 

ES02       The planting area under TM-CLK Project was constructed by three different Contract - HY/2012/07, HY/2013/12 and HY/2017/10.

 

ES03       This is the Final EM&A report under the Contract HMWSD 2/2020 (HY) presenting the establishment monitoring results and inspection findings during the establishment period for TM-CLK Project¡¦s boundary from June 2020 to January 2023.

 

Summary of EM&A activities for the Reporting Period

ES04       During the establishment period, establishment inspection which supervised by the RLA was conducted quarterly. Total 8 inspections were conducted for the planting area under the Contract HY/2012/07, HY/2013/12 & HY/2017/10 respectively.

           

ES05       The 24-month establishment period for the planting area under the Contract HY/2012/07 and the Contract HY/2013/12 were completed at the end of May 2022. Furthermore, the 24-month establishment period for the planting area under the Contract HY/2017/10 was completed at the end of January 2023.

 

Environmental Complaint

ES06       In the Reporting Period, no environmental complaint was received. The statistical summary of environmental complaints is summarized in the following table.

 

Reporting Period

Environmental Complaint Statistics

Frequency

Cumulative

June 2020 to January 2023

0

0

 

Notification of Summons and Successful Prosecutions

ES07       No environmental summons or successful prosecutions were recorded in the Reporting Period.

 

Conclusion

ES08       The condition of the planted tree is satisfaction. Moreover, the species and quantity of tree planted in those areas are complied with the approved Landscape &Visual Plan / Planting Schedule.

 

ES09       The entire establishment monitoring for the planting area within the TMCLKL Project boundary was completed. The quantity of tree planting and the landscape planting area for the TM-CLKL Project fulfil with the EIA Report and EP requirement.

 

ES10       Reporting for those compensation tree planting areas outside the Project¡¦s boundary can be referred to the Monthly Report for the Contract HY/2021/13.

 

 

 


Table of Contents

1       Introduction                                                                                                                     1

1.1                Project Background                                                                                       1

1.2                Report Structure                                                                                             1

1.3                Contract Organization                                                                                 1

2       Summary of Monitoring Requirements for the Establishment Period         2

2.1                General                                                                                                                 2

2.2                Environmental Aspects                                                                                  2

3       Summary of Establishment Period Monitoring                                             3

3.1                General                                                                                                                 3

4       Compliance of Tree planting for TMCLK Project                                        5

4.1                Summary of the tree planting for the Project                                  5

5       Environmental Complaint and Non-compliance                                           6

5.1                Environmental Complaint, Summons and Prosecution                   6

6       Conclusions                                                                                                                       7

6.1                Conclusions                                                                                                        7


 

List of TABLES

Table 2-1      Summary of Establishment Period for the Project

Table 3-1      Summary of the Establishment inspection for the Planting Area under the Contract HY/2012/07

Table 3-2      Summary of the Establishment inspection for the Planting Area under the Contract HY/2012/07

Table 3-3      Summary of the Establishment inspection for the Planting Area under the Contract HY/2012/07

Table 4-1      Summary of Quantity Tree Planting for TM-CLKL Project

Table 4-2      Summary of Landscape Planting Area for TM-CLKL Project

Table 5-1      Statistical Summary of Environmental Complaints

Table 5-2      Statistical Summary of Environmental Summons

Table 5-3      Statistical Summary of Environmental Prosecution

 

 

 

List of Appendices

Appendix A  Project Layout Plan

Appendix B Zoning Plan for the Project

Appendix C  Organization of the Contract

Appendix D Event and Action Plan

Appendix E  Environmental Mitigation and Enhancement Measures Implementation Schedule (EMIS) 

Appendix F Minor Landscape Modification at Lung Fu Road, Lung Mun Road and in the Vicinit

Appendix G Tree Planting Summary for TMCLK Project

Appendix H Planting Area for the Project

 

 


1                    Introduction

1.1                       Project Background

1.1.1                 According to the findings of the Northwest New Territories (NWNT) Traffic and Infrastructure Review conducted by the Transport Department, Tuen Mun Road, Ting Kau Bridge, Lantau Link and North Lantau Highway would be operating beyond capacity after 2016. This forecast has been based on the estimated increase in cross boundary traffic, developments in the Northwest New Territories (NWNT), and possible developments in North Lantau, including the Airport developments, the Lantau Logistics Park (LLP) and the Hong Kong ¡V Zhuhai ¡V Macao Bridge (HZMB). In order to cope with the anticipated traffic demand, two new road sections between NWNT and North Lantau ¡V Tuen Mun ¡V Chek Lap Kok Link (TM-CLKL) and Tuen Mun Western Bypass (TMWB) are proposed. 

 

1.1.2                 Hong Kong Landscaping Co., Ltd. (hereafter ¡§HKL¡¨) is commissioned by the Highways Department (HyD) as the Main Contractor of the Contract No. HMWSD 2/2020 (HY) ¡VEstablishment of Landscape Softworks for the Tuen Mun - Chek Lap Kok Link ((hereafter ¡§the Contract¡¨) and this Contract is part of the Tuen Mun ¡V Chek Lap Kok Link (TM-CLK Link Project).TM-CLK Link Project is a Designated Project under Environmental Permit number EP-354/2009/D issued on 13 March 2015. 

 

1.1.3                 The TM-CLKL had been commissioning at the end of 2020 and the major construction works under the Project had been completed at the end of March 2021.  According to the Project EM&A Manual requirement, establishment monitoring works had been conducted for a period of two years after the commission of the project.

 

1.1.4                 The planting area under TM-CLK Project was constructed by three different Contract - HY/2012/07, HY/2013/12 and HY/2017/10. The layout Plan of the Project and the zoning plan for each Contract are showed in Appendix A and B respectively.

 

1.1.5                 The major works during the establishment period mainly include:-

a.              Maintenance the approx. 33ha planting area of the Project during the establishment period.

 

 

1.1.6                 This is the Final EM&A report under the Contract HMWSD 2/2020 (HY) presenting the establishment monitoring results and inspection findings during the establishment period for TM-CLK Project¡¦s boundary from June 2020 to January 2023.

 

1.2                       Report Structure

1.2.1                 The Monthly Environmental Monitoring and Audit (EM&A) Report is structured into the following sections:-

Section 1     Introduction

Section 2     Summary of Monitoring Requirements for the Establishment Period

Section 3     Summary of Establishment Period Monitoring

Section 4     Compliance of Tree planting for TMCLK Project

Section 5     Environmental Complaints and Non-Compliance

Section 6     Conclusions

 

1.3                       Contract Organization

1.3.1                 The Contract organization and contact details of key personnel are shown in Appendix C.

 


 

2                    Summary of Monitoring Requirements for the Establishment Period

2.1                       General

2.1.1                 In accordance with the Project EM&A Manual requirements, the environmental aspects under the Project shall be included air quality, ecological, cultural heritage, landscape and visual, landfill gas and site inspection. 

 

2.1.2                 In this report, it was only focus on the aspect ¡§landscape and visual¡¨ under the EM&A requirements during the establishment period. Should non-compliance of the environmental quality criteria occurs, remedial actions will be triggered according to the Event and Action Plan which presented in Appendix D.

 

2.2                       Environmental Aspects

Landscape and Visual

2.2.1                 Monitoring of the planting works during the 24-month Establishment period after completion of the construction works should be carried out. Establishment Works Inspection should be carried out once every 3 months to make sure the establishment planting works is complied with EMIS requirement.

 

2.2.2                 For the planting area under the Contract HY/2012/07, the first 6-month establishment period inspection and maintenance will be taken by the original Contract¡¦s ET and the main Contractor under the contract. For another Contract HY/2013/12 and HY/2017/10, the first 12-month establishment period inspection and maintenance was taken by the original Contract¡¦s ET and the main Contractor under the contract. After the first 6 month or year establishment period, the maintenance and inspection works had been handover to the contract HMWSD 2/2020 (HY) and the Contract HY/2021/13. The summary of establishment period for the Project is shown in Table 2-1.

 

Table 2-1    Summary of Establishment Period for the Project

Planting Area under the Contract

Establishment Period

Commenced

Completed

HY/2012/07

(Zone 1 ¡V 4)

June 2020

May 2022

HY/2013/12

(Zone 1 ¡V 5)

June 2020

May 2022

HY/2017/10

(Zone 1 ¡V 6)

February 2021

January 2023

 


 

3                    Summary of Establishment Period Monitoring 

3.1                       General

3.1.1                 According to the Project EM&A Manual requirement, monitoring for the planting works at a frequency of 3 months interval during the 24-month establishment period is required to make sure the establishment planting works is complied with EMIS requirement, and during the 12-month establishment period, the maintenance operations must be supervised by fully qualified Landscape Resident Site Staff (Registered Landscape Architect or Professional Member of the Hong Kong Institute of Landscape Architects).  Subsequent to the 12-month establishment period supervised by the qualified Landscape Resident Site Staff, the supervision from the 13th to the 24th month would be continued by other members of the Project. The EMIS for the Contract is shown in Appendix E.

 

3.1.2                 According to the contract arrangement, the establishment period under the planting area of the Contract HY/2012/07 and the Contract HY/2013/12 were commenced in June 2020. The establishment period under the planting area HY/2017/10 was commenced in February 2021.

 

3.1.3                 All the establishment inspection method including checklist and zoning plan under this Contract was follow the methodology prepared by original Contract¡¦s ET which approved by EPD.

 

3.1.4                 Total 8 establishment inspections were conducted for each planting area respectively. The details of Establishment inspection checklist for the Project during the establishment period can refer to the relative Monthly EM&A Reports and summary of the establishment inspection are shown in Table 3-1 to 3-3.

 

Table 3-1    Summary of the Establishment inspection for the Planting Area under the Contract HY/2012/07

 

Quarter of Establishment Inspection

Zoning

1st

(Jun to Aug 20)

2nd

(Sep to Nov 20)

3rd

(Dec 20 to Feb 21)

4th

(Mar to May 21)

5th

(Jun to Aug 21)

6th

(Sep to Nov 21)

7th

(Dec 21 to Feb 22)

8th

(Mar to May 22)

(Zone 1, 3 & 4)

16 & 21 Jun 20

8 & 9 Oct 20

26 Jan & 9 Feb 21

4 May 21

16 Aug 21

23 Nov 21

25 Feb 22

26 May 22

Respond Party

ET of the Contract HY/2012/07

ET of the Contract HMWSD 2/2020 (HY)

(Zone 2)

16 & 21 Jun 20

8 & 9 Oct 20

19 Feb 21

18 May 21

10 Aug 21

8 Nov 21

22 Dec 21

25 Apr 22

Respond Party

ET of the Contract HY/2012/07

ET of the Contract HY/2017/10

ET of the Contract HY/2021/13

 

 

Table 3-2    Summary of the Establishment inspection for the Planting Area under the Contract HY/2013/12

 

 

Quarter of Establishment Inspection

Zoning

1st

(Jun to Aug 20)

2nd

(Sep to Nov 20)

3rd

(Dec 20 to Feb 21)

4th

(Mar to May 21)

5th

(Jun to Aug 21)

6th

(Sep to Nov 21)

7th

(Dec 21 to Feb 22)

8th

(Mar to May 22)

(Zone 1 to 5)

17 & 26 Aug 20

30 Nov 20

25 Feb 21

14 May 21

18 Aug 21

16 Nov 21

24 Feb 22

31 May 22

Respond Party

ET of the Contract HY/2013/12

ET of the Contract HMWSD 2/2020 (HY)

 

 


Table 3-3         Summary of the Establishment inspection for the Planting Area under the Contract HY/2017/10

 

 

Quarter of Establishment Inspection

Zoning

1st

(Feb to Apr 21)

2nd

(May to Jul 21)

3rd

(Aug to Oct 21)

4th

(Nov 21 to Jan 22)

5th

(Feb to Apr 22)

6th

(May to Jul 22)

7th

(Aug to Oct 22)

8th

(Nov 22 to Jan 23)

(Zone 1 to 5)

4, 5 & 9 Mar 21

27 & 30 July 21

20 & 24 Sep 21

20 & 22 Dec 21

12 Apr 22

17 May 22

20 Oct 22

13 Jan 23

Respond Party

ET of the Contract HY/2017/10

ET of the Contract HMWSD 2/2020 (HY)

(Zone 6)

4, 5 & 9 Mar 21

27 & 30 July 21

20 & 24 Sep 21

20 & 22 Dec 21

25 Apr 22

21 Jul 22

20 Oct 22

13 Jan 23

Respond Party

ET of the Contract HY/2017/10

ET of the Contract HY/2021/13

 

3.1.5                 The 24-month establishment period for the planting area under the Contract HY/2012/07 and the Contract HY/2013/12 were completed at the end of May 2022. Furthermore, the 24-month establishment period for the planting area under the Contract HY/2017/10 was completed at the end of January 2023.

 

3.1.6                 Further to the TM-CLK ¡V Northern Connection opened to the public on 27 December 2020, road enhancement measures at the Lung Fu Road Roundabout were proposed by Transport Department (TD) and subsequently Leisure and Cultural Services Department (LCSD) reviewed the site condition at various locations and requested some landscape amendments for enhancement of safe work condition to be carried out during their routine maintenance of vegetation. Given that the quantity of tree planting remains unchanged and the landscape area in the vicinity would not be reduced, EPD reviewed the information and had no comment on the minor landscape modifications. The information on the landscape modifications at Lung Fu Road, Lung Mun Road and in the vicinity is shown in Appendix F.

 

3.1.7                 The entire establishment monitoring for the planting area within the TMCLKL Project boundary was completed. The condition of the planted tree is satisfaction. Moreover, the species and quantity of tree planted in those areas are complied with the approved Landscape &Visual Plan / Planting Schedule.


 

4                    Compliance of Tree planting for TMCLK Project

4.1                       Summary of the tree planting for the Project

4.1.1                 According to the requirements of the EIA Report and EP, the TM-CLKL Project shall carry out landscape softworks including planting of 6300 trees and provide at least 33 ha of landscape planting. All the planting works for the Project was completed. The compliance check for the quantity of tree planting and landscape planting area for the Project are summarized in Table 4-1 and Table 4-2 the tree planting summary and planting area for TM-CLKL Project is illustrated in Appendix G & H respectively.

 

Table 4-1          Summary of Quantity Tree Planting for TM-CLKL Project

Works Contract

Location

Total No. of Tree Planting  (light standard to heavy standard size)

EIA Requirement

HY/2012/07 (includes Entrusted Landscape Works to DC/2016/01)

Within TMCLK Project Boundary

1247

At least 6300 trees

(light standard to heavy standard size)

HY/2013/12

1109

HY/2017/10

2997

HY/2021/13

Outside TMCLK Project Boundary

1066

 

Total:

6419

Comply

 

Table 4-2          Summary of Landscape Planting Area for TM-CLKL Project

Works Contract

Location

Total Area of Landscape Planting

(ha)

EIA Requirement

HY/2012/07 (includes Entrusted Landscape Works to DC/2016/01)

Within TMCLK Project Boundary

14.3

At least 33 ha

HY/2013/12

5.3

HY/2017/10

14.4

HY/2021/13

Outside TMCLK Project Boundary

NA

 

Total:

33.9

Comply

 

4.1.2                 According to the above summary, the quantity of tree planting and the landscape planting area for the TM-CLKL Project fulfil with the EIA Report and EP requirement.

 

4.1.3                 Reporting for those compensation tree planting areas outside the Project¡¦s boundary can be referred to the Monthly Report for the Contract HY/2021/13.


 

5                    Environmental Complaint and Non-compliance

5.1                       Environmental Complaint, Summons and Prosecution

5.1.1                 In the Reporting Period, no environmental complaint, summons and prosecution under the EM&A Programme was lodged. 

 

5.1.2                 The statistical summary table of environmental complaint, summons and prosecution are presented in Tables 5-1, 5-2 and 5-3.

 

Table 5-1      Statistical Summary of Environmental Complaints

Reporting Period

Environmental Complaint Statistics

Frequency

Cumulative

Complaint Nature

Air

Noise

Water

Others

June 2020 to January 2023

0

0

NA

NA

NA

NA

 

Table 5-2      Statistical Summary of Environmental Summons

Reporting Period

Environmental Summons Statistics

Frequency

Cumulative

Complaint Nature

Air

Noise

Water

June 2020 to January 2023

0

0

NA

NA

NA

 

Table 5-3      Statistical Summary of Environmental Prosecution

Reporting Period

Environmental Prosecution Statistics

Frequency

Cumulative

Complaint Nature

Air

Noise

Water

June 2020 to January 2023

0

0

NA

NA

NA

 

5.1.3                 In the Reporting Period, no warning letter related to environmental issue was received from the EPD or HyD.

 

 


 

6                    Conclusions

6.1                       Conclusions

6.1.1                 This is the Final EM&A Report summarized the monitoring results and inspection findings for the establishment monitoring of Project¡¦s boundary area for the establishment period of June 2020 to January 2023.

 

6.1.2                 During the establishment period, establishment inspection which supervised by the RLA was conducted quarterly. Total 8 inspections were conducted for the planting area under the Contract HY/2012/07, HY/2013/12 & HY/2017/10 respectively.

 

6.1.3                 The 24-month establishment period for the planting area under the Contract HY/2012/07 and the Contract HY/2013/12 were completed at the end of May 2022. Furthermore, the 24-month establishment period for the planting area under the Contract HY/2017/10 was completed at the end of January 2023.

 

6.1.4                 The condition of the planted tree is satisfaction. Moreover, the species and quantity of tree planted in those areas are complied with the approved Landscape &Visual Plan / Planting Schedule.

 

6.1.5                 The entire establishment monitoring for the planting area within the TMCLKL Project boundary was completed. The quantity of tree planting and the landscape planting area for the TM-CLKL Project fulfil with the EIA Report and EP requirement.

 

6.1.6                 In the Reporting Period, no environmental complaint was received.

 

6.1.7                 No notifications of summons, or successful prosecution were received during the Reporting Period.